LABOR / LABOR/EQUIP.
MATERIAL MATERIAL
ITEM DESCRIPTION QTY UNIT EQUIP. TOTAL TOTAL REMARKS
UNIT COST TOTAL AMOUNT
UNIT COST AMOUNT
A. GENERAL REQUIRMENTS
A.1 Mobilization and Demobilization (Tools and Equipment 1.00 lot 16,000.00 0.00 16,000.00 16,000.00
A.2 Occupational Safety & Health includes PPEs 1.00 lot 6,000.00 6,000.00 6,000.00 6,000.00 12,000.00
A.3 Engineering Supervision 1.00 lot 14,000.00 0.00 14,000.00 14,000.00
A.4 Scaffoldings and Bracings Flat forms 1.00 lot 12,000.00 12,000.00 12,000.00 12,000.00 24,000.00
SUB-TOTAL 18,000.00 48,000.00 66,000.00
B. DISMANTLING WORKS
Dismantling of Existing Roof sheets including
B.1 152.00 sm 250.00 0.00 38,000.00 38,000.00
all existing tinsmithry (spare all roofing sheets)
Hauling of all dismantled roof sheets from
B.2 1.00 lot 20,000.00 0.00 20,000.00 20,000.00
roof area to designated storage room
SUB-TOTAL 0.00 58,000.00 58,000.00
D. RE-ROOFING WORKS
Rib-type roofing sheets @ 0.50mm thickness
D.1 180.50 sm 800.00 480.00 144,400.00 86,640.00 231,040.00
includes accessories and hardwares
Tinsmithry works: Outside and Inside Gutter,
D.2 1.00 all 40,000.00 24,000.00 40,000.00 24,000.00 64,000.00
Ridgeroll, Flashings
D.3 Down-spouts:100.00mm Ø 1.00 all 22,000.00 13,200.00 22,000.00 13,200.00 35,200.00
SUB-TOTAL 206,400.00 123,840.00 330,240.00
E OTHERS
E.1 Consumables, Miscellaneous and Overhead 1.00 lot 15,000.00 15,000.00 15,000.00 15,000.00 30,000.00