2 Field Personnel
2.1 Project Manager man-mos (3) 1.00 22,285 66855 66855
2.2 Site Engineer man-mos (3) 1.00 20216 60648 60648
2.3 QA/QC Engineer man-mos (3) 1.00 22178 66534 66534
2.4 Safety Engineer man-mos (3) 1.00 25544 76632 76632
5 Construction Aids
5.1 Personal Protective Equipment
a. Safety Boots/Shoes pcs 20.00 470 9400 9400
b. Gloves pcs 20.00 350 7000 7000
c. Hard Hats pcs 20.00 490 9800 9800
d. Safety Goggles pcs 20.00 250 5000 5000
5 Hand Backfilling and Compaction cu.m 579.86 75 43489.5 25944 25944 69433.5
DIVISION 3: CONCRETE
For Health Facility
1 Pre-Cast Concrete
1.1 Pedestal Column Base pcs 60.00 3300 198000 4800 4800 202800
2 100mm THK Concrete Slab on Fill cu.m 45.00 3482.5 156712.5 156712.5
7 100mm THK Concrete Slab on Fill cu.m 3.50 3482.5 12188.75 12188.75
Laborers days 2.18 1040 2267.2 2267.2
Productivity rate of 5 man-hour/cu.m
Septic Tank
8 Concrete cu.m 1.08 3482.5 3761.1 3761.1
Laborers days 1.00 960 960 960
Productivity rate of 5 man-hour/cu.m
DIVISION 5: METALS
For Health Facility
Column
1 1.1 HSSP 5x0.5x3.85m pcs/6m 34.65 4500 155925 155925
Truss
2 2.1 T-1
a. HSSP 3x0.25x5.22m pcs/6m 20.88 3500 73080 73080
b. HSSP 3x0.25x5m pcs/6m 20.00 3500 70000 70000
c. HSSP 3x0.25x1.5m pcs/6m 3.00 3500 10500 10500
d. HSSP 2.5x0.23x0.75m pcs/6m 3.00 2500 7500 7500
e. HSSP 2.5x0.23x2.61m pcs/6m 10.44 2500 26100 26100
2.2 T-2
a. HSSP 3x0.25x3m pcs/6m 9.00 3500 31500 31500
b. HSSP 2.5x0.23x2.12 m pcs/6m 6.36 2500 15900 15900
c. HSSP 2.5x0.23x1.5m pcs/6m 2.25 2500 5625 5625
2.3 T-3
a. HSSP 3x0.25x3m pcs/6m 13.00 3500 45500 45500
b. HSSP 2.5x0.23x0.75m pcs/6m 2.25 2500 5625 5625
c. HSSP 2.5x0.23x1.68m pcs/6m 10.08 2500 25200 25200
2.4 HT-1
a. HSSP 3x0.25x3m pcs/6m 3.00 3500 10500 10500
b.HSSP 3x0.25x3.35m pcs/6m 3.35 3500 11725 11725
c. HSSP 2.5x0.23x0.712m pcs/6m 6.00 2500 15000 15000
d. HSSP 2.5x0.23x2.12m pcs/6m 6.00 2500 15000 15000
2.5 HT-2
a. HSSP 3x0.25x5.831m pcs/6m 11.66 3500 40817 40817
b. HSSP 3x0.25x6.021m pcs/6m 12.04 3500 42147 42147
c. HSSP 2.5x0.23x0.707m pcs/6m 1.41 2500 3535 3535
d. HSSP 2.5x0.23x3m pcs/6m 6.00 2500 15000 15000
e. Ø16mm Bolt with STD Nuts and pcs 1536.00 12.44 19107.84 19107.84
Washer
T-4
3 3.1 HSSP 3x0.25 (5m) pcs/6m 4.00 3500 14000 14000
3.2 HSSP 3x0.25 (1.48m) pcs/6m 2.00 3500 7000 7000
3.3 HSSP 3x0.25 (5.22m) pcs/6m 4.00 3500 14000 14000
3.4 HSSP 2.5x0.23 (1m) pcs/6m 4.00 2500 10000 10000
3.5 HSSP 2.5x0.23 (500mm) pcs/6m 4.00 2500 10000 10000
3.5 HSSP 2.5x0.23 (2.25m) pcs/6m 4.00 2500 10000 10000
3.6 HSSP 2.5x0.23 (1.95m) pcs/6m 4.00 2500 10000 10000
3.7 Ø16x300mm Anchor Bolts with STD nuts pcs 1536.00 12.44 19107.84 19107.84
and Washer
Footing
5 5.1 Ø20mm Reinforcing Bar kgs 94.69 43.6 4128.571 4128.5712
Laborers days 0.80 2250 1800 1800
Productivity Rate of 117.6 kg/man-day
Roof Beam
6 6.1 Ø20mm Reinforcing Bar kgs 297.88 43.6 12987.7424 12987.7424
6.2 Ø12mm Reinforcing Bar kgs 53.64 44 2360.336 2360.336
6.3 Ø10mm Reinforcing Bar kgs 141.45 44 6223.888 6223.888
Laborers days 4.19 2250 9427.5 9427.5
Productivity Rate of 117.6 kg/man-day
Wall Footing
8 8.1 Ø10mm Reinforcing Bar kgs 17.47 44 768.68 768.68
Laborers days 0.15 2250 337.5 337.5
Productivity Rate of 117.6 kg/man-day
Septic Tank
9 Reinforcing Bars
9.1 Ø12mm Reinforcing Bar kgs 64.80 44 2851.2 2851.2
9.2 Ø16mm Reinforcing Bar kgs 111.60 44 4910.4 4910.4
Laborers days 2.45 2250 5512.5 5512.5
Productivity Rate of 117.6kg/man-day
2 Roof
2.1 8mm THK Roof Insulation sq.m 35.00 1050 36750 36750
2.2 150x150mm GA 24 Pre-formed Pre- lm 8.20 351 2878.2 2878.2
painted Gutter Sheet
2.3 0.40mm THK (Base Metal Thickness) with
Total Thickness of 0.43 - 0.45mm THK (with sq.m 45.92 423 19424.16 19424.16
Paint) Corrugated G.I. Sheet
2.4 0.40mm THK (Base Metal Thickness) with
Total Thickness of 0.43 - 0.45mm THK (with lm 8.20 261 2140.2 2140.2
Paint) G.I. Sheet Ridge Roll
2.5 GA 26 Preformed Pre-Painted G.I. Flashing
lm 11.20 323 3617.6 3617.6
Sheet
2.6 LC100x50x15x3mm THK Purlins pcs 23.00 1100 25300 25300
2.7 10mmØ Sagrods kgs 15.00 45 675 675
2 Floor Finishes
2.1 300x300mm Vitrified Unglazed Floor Tile
sq.m 30.69 708 21728.52 21728.52
Finish
Laborers days 1.02 1400 1428 1428
3 Wall Finishes
3.1 300x300mm Vitrified Glazed Tile Wall
sq.m 81.33 749 60916.17 60916.17
Finish
3.2 Lavatory
a. 3mm THK Facial Mirror in Aluminum
Framing
b. 300x300mm Vitrified Glazed Tiles
sq.m 4.29 749 3213.21 3213.21
Counter Sink Finish
3.2 Handwashing Counter
a. 300x300mm Vitrified Glazed Tiles
sq.m 1.53 749 1145.97 1145.97
Handwashing Back Flash Finish
b. 300x300mm Vitrified Glazed Tiles
sq.m 3.51 749 2630.488 2630.488
Handwashing Counter Top Finish
Laborers days 3.39 1400 4746 4746