You are on page 1of 8

Doc. No. : CE-02.00.

00 COST ESTIMATE SHEET/SHEETS : - -

Design Data

1 Project Name / Area : KIP-3

2 Unit Name : Slide Gate - Motorize

3 Dimension/Capacity : 2.0 x 2.0 m

4 Type : Slide Gate (Manual)

5 Specification : Welded Steel Gate

No. Descriptions Qty / Unit Price/Units Total Prices Remarks

A Constructions

1.1 Gate Leaf 1 Set 47,710,000 47,710,000

1.2 Guide Frame 1 Set 363,350,000 363,350,000

1.3

1.4

1.5

1.6

1.7

1.8 Sliding Shoes 8 Set 2,860,000 22,880,000

B Hoists System

2.1 Driven Gear 1 Set 130,000,000 130,000,000 Motorize

2.2 Lifting Gear 2 Set 139,100,000 278,200,000 Gearbox

2.3 Spindle Shaft 2 Set 10,790,000 21,580,000

2.4 Connecting Shaft 1 Set 18,590,000 18,590,000

C Delivery

3.1 Land 1 Lot 5,000,000 5,000,000

3.2 Plant 1 Lot

3.3 Shipping 1 Lot 10,000,000 10,000,000

D Installation

4.1 Material 1 Lot 2,250,000 2,250,000 Cement and Sand

4.2 Tools 1 Lot 1,500,000 1,500,000 Cement and Sand

4.3 Manpower 1 Lot 6,000,000 6,000,000 Bricklayer

E Others

5.1 Local Control Panel 1 Lot 25,400,000 25,400,000 Electrical

TOTAL COST 932,460,000


Doc. No. : CE-02.01.00 BREAKDOWN UNIT PRICES SHEET/SHEETS : - -

1.1 - Gate Leaf

No. Descriptions Units Quantity Price/Unit Total Prices

A Manpower

1 Engineer Man/Day 1 1 300,000 300,000

2 Supervisor Man/Day 1 1 250,000 250,000

3 Foreman Man/Day 1 1 250,000 250,000

4 Technisian Man/Day 200,000

5 Welder (F2) Man/Day 1 5 250,000 1,250,000

6 Welder (G6) Man/Day 300,000

7 Mechanic Man/Day 225,000

8 Fitter Man/Day 1 5 200,000 1,000,000

9 Helper Man/Day 1 5 155,000 775,000

10 Operator Man/Day 195,000

11 Bricklayer Man/Day 175,000

12 Others Man/Day 110,000

B Material

1 SS400,#10mm Kg 588.75 22,000 12,952,500

2 SS400,#10mm Kg 47.1 22,000 1,036,200

3 UNP - 250 Kg 61.5 2 22,000 2,706,000

4 UNP - 250 Kg 61.5 1 22,000 1,353,000

5 UNP - 250 Kg 85 3 22,000 5,610,000

C Consumable

1 Grinding Stone 4" Pcs 50 10,000 500,000

2 Sandblast M2 0 120,000 0

3 Painting M2 843.85 10,000 8,438,500

D Machine and Tools

1 Cutting Machine Machine/Hour 1 2 40,000 80,000

2 Grinding Machine Machine/Hour 1 1 30,000 30,000

3 Compressore Machine/Hour 1 3 35,000 105,000

Total Production Cost 36,636,200

Roundup Cost 36,700,000

OverHead 10% 3,670,000

Profit 20% 7,340,000

Total Prices/Unit 47,710,000


Doc. No. : CE-02.02.00 BREAKDOWN UNIT PRICES SHEET/SHEETS : - -

1.2 - Guide frame

No. Descriptions Units Quantity Price/Unit Total Prices

A Manpower

1 Engineer Man/Day 1 1 300,000 300,000

2 Supervisor Man/Day 250,000

3 Foreman Man/Day 1 1 250,000 250,000

4 Technisian Man/Day 200,000

5 Welder (F2) Man/Day 1 5 250,000 1,250,000

6 Welder (G6) Man/Day 300,000

7 Mechanic Man/Day 225,000

8 Fitter Man/Day 1 5 200,000 1,000,000

9 Helper Man/Day 2 5 155,000 1,550,000

10 Operator Man/Day 195,000

11 Bricklayer Man/Day 175,000

12 Others Man/Day 110,000

B Material

1 UNP - 250 Kg 622.8 1 22,000 13,701,600

2 SS400 200x200x12mm Kg 3.768 22,000 82,896

3 Roundbar Dia.10 Kg 0.157 16 27,000 67,824

4 SUS304 40x20x1000 Kg 7.2 2 105,000 1,512,000

5 Hex.Bolts M10x50 Set 14 10,000 140,000

C Consumable

1 Grinding Stone 4" Pcs 20 10,000 200,000

2 Sandblast M2 0 120,000 0

3 Painting (3-Layers) M2 647.925 400,000 259,170,000

4 Galvanized M2 0 10,000 0

D Machine and Tools

1 Cutting Machine Machine/Hour 1 2 40,000 80,000

2 Grinding Machine Machine/Hour 1 2 30,000 60,000

3 Compressore Machine/Hour 1 2 35,000 70,000

Total Production Cost 279,434,320

Roundup Cost 279,500,000

OverHead 10% 27,950,000

Profit 20% 55,900,000

Total Prices/Unit 363,350,000


Doc. No. : CE-02.03.00 BREAKDOWN UNIT PRICES SHEET/SHEETS : - -

1.8 - Slinding Shoes

No. Descriptions Units Quantity Price/Unit Total Prices

A Manpower

1 Engineer Man/Day 1 0.5 300,000 150,000

2 Supervisor Man/Day 250,000

3 Foreman Man/Day 1 0.5 250,000 125,000

4 Technisian Man/Day 200,000

5 Welder (F2) Man/Day 1 0.5 250,000 125,000

6 Welder (G6) Man/Day 300,000

7 Mechanic Man/Day 225,000

8 Fitter Man/Day 1 0.5 200,000 100,000

9 Helper Man/Day 1 1 155,000 155,000

10 Operator Man/Day 1 2 195,000 390,000

11 Bricklayer Man/Day 175,000

12 Others Man/Day 110,000

B Material

1 Teflon Kg 2.4625 1 10,000 24,625

2 Hex.Bolt M12x150 Set 4 1 15,000 60,000

3 S45C Kg

4 Cylinder Kg

5 S45C Kg

C Consumable

1 Grinding Stone 4" Pcs 0.5 10,000 5,000

2 Sandblast M2 0.5 120,000 60,000

3 Painting (3-Layers) M2 0.5 400,000 200,000

D Machine and Tools

1 Cutting Machine Machine/Hour 1 1 40,000 40,000

2 Grinding Machine Machine/Hour 1 0.5 30,000 15,000

3 Milling Machine Machine/Hour 1 8 88,000 704,000

Total Production Cost 2,153,625

Roundup Cost 2,200,000

OverHead 10% 220,000

Profit 20% 440,000

Total Prices/Unit 2,860,000


Doc. No. : CE-02.04.00 BREAKDOWN UNIT PRICES SHEET/SHEETS : - -

2.1 - Driven Gear

No. Descriptions Units Quantity Price/Unit Total Prices

A Manpower

1 Engineer Man/Day 1 1 300,000 300,000

2 Supervisor Man/Day 1 1 250,000 250,000

3 Foreman Man/Day 1 1 250,000 250,000

4 Technisian Man/Day 1 1 200,000 200,000

5 Welder (F2) Man/Day 1 1 250,000 250,000

6 Welder (G6) Man/Day 1 1 300,000 300,000

7 Mechanic Man/Day 1 1 225,000 225,000

8 Fitter Man/Day 1 3 200,000 600,000

9 Helper Man/Day 1 3 155,000 465,000

10 Operator Man/Day 1 7 195,000 1,365,000

11 Bricklayer Man/Day 175,000

12 Others Man/Day 110,000

B Material

1 S45C Kg 3 1 35,000 105,000

2 Bronze Kg 2 1 200,000 400,000

3 SS400 Kg 3 1 22,000 66,000

4 SS400 Kg 3 1 22,000 66,000

5 Actuator 1 86,800,000 86,800,000

C Consumable

1 Grinding Stone 4" Pcs 5 10,000 50,000

2 Sandblast M2 0.5 120,000 60,000

3 Painting (3-Layers) M2 0.5 400,000 200,000

D Machine and Tools

1 Lathe Machine Machine/Hour 1 18 50,000 900,000

2 Grinding Machine Machine/Hour 1 0.5 50,000 25,000

3 Milling Machine Machine/Hour 1 80 88,000 7,040,000

Total Production Cost 99,917,000

Roundup Cost 100,000,000

OverHead 10% 10,000,000

Profit 20% 20,000,000

Total Prices/Unit 130,000,000


Doc. No. : CE-02.05.00 BREAKDOWN UNIT PRICES SHEET/SHEETS : - -

2.2 - Lifting Gear

No. Descriptions Units Quantity Price/Unit Total Prices

A Manpower

1 Engineer Man/Day 1 1 300,000 300,000

2 Supervisor Man/Day 1 1 250,000 250,000

3 Foreman Man/Day 1 5 250,000 1,250,000

4 Technisian Man/Day 1 0 200,000 0

5 Welder (F2) Man/Day 1 2 250,000 500,000

6 Welder (G6) Man/Day 1 2 300,000 600,000

7 Mechanic Man/Day 1 5 225,000 1,125,000

8 Fitter Man/Day 1 8 200,000 1,600,000

9 Helper Man/Day 1 8 155,000 1,240,000

10 Operator Man/Day 1 7 195,000 1,365,000

11 Bricklayer Man/Day 175,000

12 Others Man/Day 110,000

B Material

1 S45C Kg 5 1 35,000 175,000

2 Bronze Kg 2 1 200,000 400,000

3 SS400 Kg 8 1 22,000 176,000

4 SS400 Kg 6 1 22,000 132,000

5 Bevel Gearbox 2 44,800,000 89,600,000

C Consumable

1 Grinding Stone 4" Pcs 5 10,000 50,000

2 Sandblast M2 0.5 120,000 60,000

3 Painting (3-Layers) M2 0.5 400,000 200,000

D Machine and Tools

1 Lathe Machine Machine/Hour 1 18 50,000 900,000

2 Grinding Machine Machine/Hour 1 0.5 50,000 25,000

3 Milling Machine Machine/Hour 1 80 88,000 7,040,000

Total Production Cost 106,988,000

Roundup Cost 107,000,000

OverHead 10% 10,700,000

Profit 20% 21,400,000

Total Prices/Unit 139,100,000


Doc. No. : CE-02.06.00 BREAKDOWN UNIT PRICES SHEET/SHEETS : - -

2.3 - Spindle Shaft

No. Descriptions Units Quantity Price/Unit Total Prices

A Manpower

1 Engineer Man/Day 1 0.2 300,000 60,000

2 Supervisor Man/Day 250,000

3 Foreman Man/Day 1 0.2 250,000 50,000

4 Technisian Man/Day 200,000

5 Welder (F2) Man/Day 250,000

6 Welder (G6) Man/Day 300,000

7 Mechanic Man/Day 225,000

8 Fitter Man/Day 200,000

9 Helper Man/Day 1 2 155,000 310,000

10 Operator Man/Day 1 2 195,000 390,000

11 Bricklayer Man/Day 175,000

12 Others Man/Day 110,000

B Material

1 ST60-Dia2" Kg 49.0625 1 80,200 3,934,813

2 Hex.Bolt M24x150 Set 1 1 35,000 35,000

C Consumable

1 Lathe Machine Machine/Hour 1 16 75,000 1,200,000

2 Sandblast M2 0.2 120,000 24,000

3 Painting (3-Layers) M2 0.2 400,000 80,000

D Machine and Tools

1 Cutting Machine Machine/Hour 1 1 40,000 40,000

2 Grinding Machine Machine/Hour 1 0.2 30,000 6,000

3 Milling Macjine Machine/Hour 1 24 88,000 2,112,000

Total Production Cost 8,241,813

Roundup Cost 8,300,000

OverHead 10% 830,000

Profit 20% 1,660,000

Total Prices/Unit 10,790,000


Doc. No. : CE-02.07.00 BREAKDOWN UNIT PRICES SHEET/SHEETS : - -

2.4 - Connecting Shaft

No. Descriptions Units Quantity Price/Unit Total Prices

A Manpower

1 Engineer Man/Day 1 2 300,000 600,000

2 Supervisor Man/Day 250,000

3 Foreman Man/Day 1 2 250,000 500,000

4 Technisian Man/Day 200,000

5 Welder (F2) Man/Day 250,000

6 Welder (G6) Man/Day 300,000

7 Mechanic Man/Day 225,000

8 Fitter Man/Day 200,000

9 Helper Man/Day 1 5 155,000 775,000

10 Operator Man/Day 1 5 195,000 975,000

11 Bricklayer Man/Day 175,000

12 Others Man/Day 110,000

B Material

1 ST60-Dia2" Kg 49.0625 2 80,200 7,869,625

2 Hex.Bolt M24x150 Set 1 1 35,000 35,000

C Consumable

1 Lathe Machine Machine/Hour 1 16 75,000 1,200,000

2 Sandblast M2 0.2 120,000 24,000

3 Painting (3-Layers) M2 0.2 400,000 80,000

D Machine and Tools

1 Cutting Machine Machine/Hour 1 1 40,000 40,000

2 Grinding Machine Machine/Hour 1 0.2 30,000 6,000

3 Milling Macjine Machine/Hour 1 24 88,000 2,112,000

Total Production Cost 14,216,625

Roundup Cost 14,300,000

OverHead 10% 1,430,000

Profit 20% 2,860,000

Total Prices/Unit 18,590,000

You might also like