SKIM - Build - Upgrading Parking Area

Volume Total Amount


No Description Vol Cargill Contractor Unit Price (Rp) (Rp) Remark
A Preliminaries
1 Mob-Demob Manpower 1.0 Lot 1.0 Lot 7,500,000 7,500,000
2 Mob-Demob Tools 1.0 Lot 1.0 Lot 30,000,000 30,000,000
3 Lighting & Safety 1.0 Lot 1.0 Lot 35,000,000 35,000,000
4 Slump test 1.0 Lot 1.0 Lot 6,000,000 6,000,000
5 Pembobokan Joint Beton dan Halte 1.0 Lot 5,000,000 5,000,000
6 Barak Kerja 1.0 Lot 6,000,000 6,000,000

B STRUCTURAL WORK
1 Excavation / Clearing Area 428.25 m3 428.25 m3 130,000 55,672,500 Excavator by contractor
2 Concrete Work Include mixer truck, excavator, concrete vibro, slump test
- Concrete K-250 thickness 150 mm 127.05 m3 128.48 m3 2,375,175 305,150,608 c/w begisting, plastic cor
- Wire Mesh A-8 ; 2 layer 1694.00 m2 1713.00 m2 118,242 202,549,060 c/w dacking
- Asphalt/Sterofoam 1.0 Lot 1.0 Lot 5,000,000 5,000,000 detail material refer to drawing
- Joint Beton Besi Ø16 - 450mm 435.5 Kg 19,087 8,313,104
- Rebar cover PVC 1"- 450mm 261.0 m' 21,000 5,481,000
- Cansteen 3.38 m3 4.22 m3 2,375,175 10,020,270 detail material refer to drawing
- Bekisting 54.00 m2 183,540 9,911,160
3 Walk Way
- Concrete 1:3:5 thickness 100 mm 5.88 m3 6.44 m3 2,173,144 13,984,178 detail material refer to drawing
- Wire Mesh A-6 ; 1 layer 58.80 m2 64.35 m3 57,329 3,689,102
- Bekisting 35.10 m2 183,540 6,442,254
4 Smoking Area/Waiting Area
As per drawing 2.0 Lot 2.0 Lot 40,000,000 80,000,000
5 Lampu Penerangan Jalan
As per reference 4.0 Lot 4.0 Lot - c/w tiang, kabel, lampu 100 watt

Total >>> 795,713,236


795,714,000
USD 53,000

25,000,000
30,714,000
740,000,000
49,000

nego1

No Description Vol Cargill Volume Unit Price (Rp) Total Amount Remark
Contractor (Rp)
A Preliminaries
1 Mob-Demob Manpower 1.0 Lot 1.0 Lot 7,500,000 7,500,000
2 Mob-Demob Tools 1.0 Lot 1.0 Lot 30,000,000 30,000,000
3 Lighting & Safety 1.0 Lot 1.0 Lot 35,000,000 35,000,000
4 Slump test 1.0 Lot 1.0 Lot 6,000,000 6,000,000
5 Pembobokan Joint Beton dan Halte 1.0 Lot 5,000,000 5,000,000
6 Barak Kerja 1.0 Lot 6,000,000 6,000,000

B STRUCTURAL WORK
1 Excavation / Clearing Area 428.25 m3 428.25 m3 130,000 55,672,500 Excavator by contractor
2 Concrete Work Include mixer truck, excavator, concrete vibro, slump test
- Concrete K-250 thickness 150 mm 127.05 m3 128.48 m3 2,310,398 296,828,319 c/w begisting, plastic cor
- Wire Mesh A-8 ; 2 layer 1694.00 m2 1713.00 m2 115,018 197,024,995 c/w dacking
- Asphalt/Sterofoam 1.0 Lot 1.0 Lot 5,000,000 5,000,000 detail material refer to drawing
- Joint Beton Besi Ø16 - 450mm 435.5 Kg 19,087 8,313,104
- Rebar cover PVC 1"- 450mm 261.0 m' 21,000 5,481,000
- Cansteen 3.38 m3 4.22 m3 2,375,175 10,020,270 detail material refer to drawing
- Bekisting 54.00 m2 183,540 9,911,160
3 Walk Way
- Concrete 1:3:5 thickness 100 mm 5.88 m3 6.44 m3 2,113,876 13,602,792 detail material refer to drawing
- Wire Mesh A-6 ; 1 layer 58.80 m2 64.35 m3 55,765 3,588,490
- Bekisting 35.10 m2 183,540 6,442,254
4 Smoking Area/Waiting Area
As per drawing 2.0 Lot 2.0 Lot 35,000,000 70,000,000
5 Lampu Penerangan Jalan
As per reference 4.0 Lot 4.0 Lot - c/w tiang, kabel, lampu 100 watt

Total >>> 771,384,882


771,385,000
USD 51,000

830,920,000
20,773,000
810,147,000
nego 2

No Description Vol Cargill Volume Unit Price (Rp) Total Amount Remark
Contractor (Rp)
A Preliminaries
1 Mob-Demob Manpower 1.0 Lot 1.0 Lot 7,500,000 7,500,000
2 Mob-Demob Tools 1.0 Lot 1.0 Lot 30,000,000 30,000,000
3 Lighting & Safety 1.0 Lot 1.0 Lot 35,000,000 35,000,000
4 Slump test 1.0 Lot 1.0 Lot 6,000,000 6,000,000
5 Pembobokan Joint Beton dan Halte 1.0 Lot 5,000,000 5,000,000
6 Barak Kerja 1.0 Lot 6,000,000 6,000,000

B STRUCTURAL WORK
1 Excavation / Clearing Area 428.25 m3 428.25 m3 130,000 55,672,500 Excavator by contractor
2 Concrete Work Include mixer truck, excavator, concrete vibro, slump test
- Concrete K-250 thickness 150 mm 127.05 m3 128.48 m3 2,267,213 291,280,126 c/w begisting, plastic cor
- Wire Mesh A-8 ; 2 layer 1694.00 m2 1713.00 m2 112,868 193,342,284 c/w dacking
- Asphalt/Sterofoam 1.0 Lot 1.0 Lot 5,000,000 5,000,000 detail material refer to drawing
- Joint Beton Besi Ø16 - 450mm 435.5 Kg 19,087 8,313,104
- Rebar cover PVC 1"- 450mm 261.0 m' 21,000 5,481,000
- Cansteen 3.38 m3 4.22 m3 2,375,175 10,020,270 detail material refer to drawing
- Bekisting 54.00 m2 183,540 9,911,160
3 Walk Way
- Concrete 1:3:5 thickness 100 mm 5.88 m3 6.44 m3 2,074,364 13,348,534 detail material refer to drawing
- Wire Mesh A-6 ; 1 layer 58.80 m2 64.35 m3 54,723 3,521,415
- Bekisting 35.10 m2 183,540 6,442,254
4 Smoking Area/Waiting Area
As per drawing 2.0 Lot 2.0 Lot 35,000,000 70,000,000
5 Lampu Penerangan Jalan
As per reference 4.0 Lot 4.0 Lot - c/w tiang, kabel, lampu 100 watt

Total >>> 761,832,647


761,833,000
USD 50,000

830,920,000
20,773,000
810,147,000

nego 3
Volume Total Amount
No Description Vol Cargill Contractor Unit Price (Rp) (Rp) Remark
A Preliminaries
1 Mob-Demob Manpower 1.0 Lot 1.0 Lot 7,500,000 7,500,000
2 Mob-Demob Tools 1.0 Lot 1.0 Lot 30,000,000 30,000,000
3 Lighting & Safety 1.0 Lot 1.0 Lot 35,000,000 35,000,000
4 Slump test 1.0 Lot 1.0 Lot 6,000,000 6,000,000
5 Pembobokan Joint Beton dan Halte 1.0 Lot 5,000,000 5,000,000
6 Barak Kerja 1.0 Lot 6,000,000 6,000,000

B STRUCTURAL WORK
1 Excavation / Clearing Area 428.25 m3 428.25 m3 130,000 55,672,500 Excavator by contractor
2 Concrete Work Include mixer truck, excavator, concrete vibro, slump test
- Concrete K-250 thickness 150 mm 127.05 m3 128.48 m3 1,943,325 249,668,679 c/w begisting, plastic cor
- Wire Mesh A-8 ; 2 layer 1694.00 m2 1713.00 m2 102,118 174,928,734 c/w dacking
- Asphalt/Sterofoam 1.0 Lot 1.0 Lot 5,000,000 5,000,000 detail material refer to drawing
- Joint Beton Besi Ø16 - 450mm 435.5 Kg 19,087 8,313,104
- Rebar cover PVC 1"- 450mm 261.0 m' 21,000 5,481,000
- Cansteen 3.38 m3 4.22 m3 2,375,175 10,020,270 detail material refer to drawing
- Bekisting 54.00 m2 183,540 9,911,160
3 Walk Way
- Concrete 1:3:5 thickness 100 mm 5.88 m3 6.44 m3 1,876,806 12,077,245 detail material refer to drawing
- Wire Mesh A-6 ; 1 layer 58.80 m2 64.35 m3 49,511 3,186,043
- Bekisting 35.10 m2 183,540 6,442,254
4 Smoking Area/Waiting Area
As per drawing 2.0 Lot 2.0 Lot 35,000,000 70,000,000
5 Lampu Penerangan Jalan
As per reference 4.0 Lot 4.0 Lot - c/w tiang, kabel, lampu 100 watt

Total >>> 700,200,988


700,201,000
USD 46,000

830,920,000
20,773,000
810,147,000

nego revisi

No Description Vol Cargill Volume Unit Price (Rp) Total Amount Remark
Contractor (Rp)
A Preliminaries
1 Mob-Demob Manpower 1.0 Lot 1.0 Lot 7,500,000 7,500,000
2 Mob-Demob Tools 1.0 Lot 1.0 Lot 30,000,000 30,000,000
3 Lighting & Safety 1.0 Lot 1.0 Lot 35,000,000 35,000,000
4 Slump test 1.0 Lot 1.0 Lot 6,000,000 6,000,000
5 Pembobokan Joint Beton dan Halte 1.0 Lot 5,000,000 5,000,000
6 Barak Kerja 1.0 Lot 6,000,000 6,000,000

B STRUCTURAL WORK
1 Excavation / Clearing Area 428.25 m3 428.25 m3 130,000 55,672,500 Excavator by contractor
2 Concrete Work Include mixer truck, excavator, concrete vibro, slump test
- Concrete K-250 thickness 150 mm 127.05 m3 128.48 m3 2,159,250 277,409,644 c/w begisting, plastic cor
- Wire Mesh A-8 ; 2 layer 1694.00 m2 1713.00 m2 107,493 184,135,509 c/w dacking
- Asphalt/Sterofoam 1.0 Lot 1.0 Lot 5,000,000 5,000,000 detail material refer to drawing
- Joint Beton Besi Ø16 - 450mm 435.5 Kg 19,087 8,313,104
- Rebar cover PVC 1"- 450mm 261.0 m' 21,000 5,481,000
- Cansteen 3.38 m3 4.22 m3 2,159,250 9,109,336 detail material refer to drawing
- Bekisting 54.00 m2 183,540 9,911,160
3 Walk Way
- Concrete 1:3:5 thickness 100 mm 5.88 m3 6.44 m3 1,975,585 12,712,889 detail material refer to drawing
- Wire Mesh A-6 ; 1 layer 58.80 m2 64.35 m3 52,117 3,353,729
- Bekisting 35.10 m2 183,540 6,442,254
4 Smoking Area/Waiting Area
As per drawing 2.0 Lot 2.0 Lot 35,000,000 70,000,000
5 Lampu Penerangan Jalan
As per reference 4.0 Lot 4.0 Lot - c/w tiang, kabel, lampu 100 watt

Total >>> 737,041,125


737,042,000
USD 49,000

830,920,000
20,773,000
810,147,000
PT. KARYA RAGAM INDOAGUNG
Jl. Brigjen Katamso
Kelurahan Sukaharja Kecamatan Delta Pawan
KETAPANG
JADWAL PELAKSANAAN PEKERJAAN
RENCANA PELAKSANAAN (MINGGU)
No. LOKASI URAIAN UNIT SAT MAN POWER BOBOT I II III
1 2 3 4 5 6 7 8 9 10 11 12
100
90
PEKERJAAN PERSIAPAN 16.2 5.42 5.42 5.42 80
70
Civil = 7 Orang 60
PEKERJAAN PENGECORAN 66.9 11.15 11.15 11.15 11.15 11.15 11.15
50
1 SKIM 1 unit ME = 3 40
PEKERJAAN SMOKING AREA/WAITING AREA Orang 9.6 4.81 4.81
30
20
PEKERJAAN LAMPU JALAN 7.2 3.61 3.61
10
0

Jumlah nilai pekerjaan 100.0


5.4 5.4 16.6 11.2 11.2 11.2 11.2 11.2 4.8 4.8 3.6 3.6

Kemajuan pekerjaan kumulatif 5.4 10.8 27.4 38.5 49.7 60.9 72.0 83.2 88.0 92.8 96.4 100.0

Kemajuan pekerjaan Aktual


Deviasi (Kontrak - Aktual) - - - - - - - - - - - -