NO URAIAN PEKERJAAN VOLUME SAT HARGA SAT JUMLAH TOTAL

(Rp) HARGA

V KOLAM PENERIMA ( UTK BOOMERANG SLIDE )

Luas : 8 x 16 = 128 m 2
Kedalaman : 1 m
Keliling : 48 m
Volume air : 128 m3
a PEKERJAAN GALIAN, URUGAN & BEKISTING
1 Galian tanah kolam renang 196,35 M3 150.000 29.452.500
2 Buang tanah bekas galian 196,35 M3 100.000 19.635.000
3 Urugan tanah kembali 60,25 M3 150.000 9.037.500
4 Bekisting dinding luar bata merah 1:4 109,67 M2 350.000 38.384.500
5 Bekisting dinding dlm triplek 6 mm+rangka kaso 43,05 M2 350.000 15.067.500
6 Urugan pasir tebal 5 cm 6,22 M3 260.000 1.617.200
7 Pemadatan tanah dengan stamper 118,45 M2 50.000 5.922.500
119.116.700
b PEKARJAAN KONSTRUKSI BETON
1 Lantai kerja t = 5 cm 6,40 M3 2.625.000 16.800.000
2 Cor lantai beton tebal 17 cm, besi 8mm - 20 cm, 22,40 M3 4.250.000 95.200.000
2 lapis Readymix K 225
3 Cor dinding beton tebal 17cm, besi 8mm - 20cm, 8,40 M3 3.250.000 27.300.000
2 lapis Readymix K 225
4 Balok beton 17/35 penyangga kolam tul. pokok, 3,60 M3 3.575.000 12.870.000
6 dia. 10 mm; beugel dia. 8 mm - 20 cm
5 Balok beton 17/35 keliling kolam tulangan pokok, 3,07 M3 3.575.000 10.975.250
6 dia. 10 mm; beugel dia. 8 mm - 20 cm
5 Cor gutter overflow 5,40 M3 3.250.000 17.550.000
6 Grill / tutup gutter 48,00 M' 550.000 26.400.000
207.095.250
c PEK. WATER PROOFING,PLESTERAN & FINISHING
1 Water proofing lantai,dinding,gutter & bibir kolam 258,00 M2 95.500 24.639.000
2 Plesteran lantai,dinding,gutter & bibir kolam 258,00 M2 150.000 38.700.000
3 Keramik lantai,dinding,gutter,bibir kolam uk. 20/20cm 258,00 M2 175.500 45.279.000
ex. Masterina/setara + Chemical Additive
4 Nat khusus keramik 258,00 M2 22.750 5.869.500
114.487.500
d PEK. INSTALASI PLUMBING & TREATMENT AIR
1 Instalasi plumbing system 140,00 M3 350.000 49.000.000
2 Treatment air & Chemical pool 140,00 M3 90.000 12.600.000

61.600.000
e EQUIPMENT
Filter dia. 32" merk. Emaux / setara 2,00 Unit 15.000.000 30.000.000
Pompa sirkulasi 2 HP merk. Emaux / setara 2,00 Unit 12.000.000 24.000.000
Inlet Fitting 4,00 Bh 850.000 3.400.000
Maindrain frame & grate 9" x 9" 1,00 Bh 2.750.000 2.750.000
Vaccum Fitting 4,00 Bh 550.000 2.200.000
Pool Ladder 3 steep stainless steel 1,00 Bh 1.850.000 1.850.000
64.200.000
f RUANG MESIN DAN BALANCING TANK
Ruang mesin uk. 4 m x 3 m x 2 m 12,00 M2 3.500.000 42.000.000
Balancing tank uk. 4 m x 3 m x 2 m 24,00 M3 3.000.000 72.000.000
Sumpit pump + instalasi 1,00 Unit 7.500.000 7.500.000
Atap dark,cor beton t = 15 cm, K 175 + sloof 20/35 7,20 M3 3.000.000 21.600.000
143.100.000

TOTAL KOLAM 709.599.450


Hal. 5
N URAIAN PEKERJAAN VOLUM SAT HARGA SAT JUMLAH TOTAL
O E (Rp) HARGA
(Rp)
C POOL DECK DAN JALAN SETAPAK

( Pada area Kolam Renang )


Luas : 1500m2 (750m x 2m)
1 Pemadatan tanah dasar pakai stamper 1.500,00 M2 50.000 75.000.000
2 Pasir urug t = 10 cm 192,50 M3 150.000 28.875.000
3 Paving Blok Type Persegi tebal 8 cm ( abu-abu ) 1.500,00 m2 300.000 450.000.000
4 Gutter keliling lebar 10 cm 375,00 M' 125.000 46.875.000
5 Pembatas pasangan bata taman dan parit 375,00 M' 125.000 46.875.000
TOTAL C 647.625.000
D ORNAMENT dan MAINAN
1 Patung Semprot
a Patung Semprot ( kuda laut ) 4,00 Unit 17.500.000 70.000.000
b patung Semprott (Walrus) 1,00 Unit 18.000.000 18.000.000
c Patung semprot (dolphine) 1,00 Unit 18.500.000 18.500.000
b Pompa sirkulasi 3 HP merk.Emaux / setara 2,00 Unit 13.250.000 26.500.000
c Instalasi plumbing 6,00 Unit 5.050.000 30.300.000
163.300.000
2 Aqua Umbrella ( pada kolam baby )
a Aqua Umbrella 1,00 Unit 19.500.000 19.500.000
b Pompa 1 HP merk. Emaux / setara 1,00 Unit 7.750.000 7.750.000
c Instalasi plumbing 1,00 Unit 8.500.000 8.500.000
35.750.000
3 Aqua Spray / Tirai air ( pada kolam baby )
a Tirai air 3,00 Unit 19.500.000 58.500.000
b Pompa 3 HP merk. Emaux / setara 1,00 Unit 12.250.000 12.250.000
c Instalasi plumbing 3,00 Unit 3.500.000 10.500.000
81.250.000
6 Goa
a Goa air ( pada kolam arus ) (p = 10m) 1,00 Unit 95.000.000 95.000.000
b Patung gurita 1,00 Unit 25.500.000 25.500.000
c Pompa sirkulasi 3 HP merk.Emaux / setara 2,00 Unit 13.250.000 26.500.000
d Instalasi plumbing 1,00 Unit 10.000.000 10.000.000
157.000.000
7 Jembatan ( pada kolam arus ) 1,00 Unit 95.000.000 95.000.000
a Tirai air + plumbing dibawah jembatan 1,00 Unit 25.000.000 25.000.000
b Pompa 3 HP merk. Emaux / setara 1,00 Unit 13.250.000 13.250.000
133.250.000
8 Outdoor shower
a Pek. sipil outdoor shower + 6 titik shower 1,00 Unit 70.000.000 70.000.000
b Pompa sirkulasi 3 HP merk.Emaux / setara 1,00 Unit 13.250.000 13.250.000
c Instalasi plumbing 1,00 Unit 10.000.000 10.000.000
93.250.000

TOTAL D 663.800.000