You are on page 1of 5

RENCANA ANGGARAN BIAYA PEKERJAAN KANDANG AYAM (CLOSE HOUSE)

Luas : 14 x 95 (2 Lantai)
Lokasi : cineam-tasikmalaya

Harga Satuan Total Harga


No. Item Pekerjaan Volume Satuan
( Rp) ( Rp)
I BIAYA UMUM DAN PERSIAPAN
2 Air Kerja dan Listrik Kerja 1.00 ls 10,000,000.00 10,000,000.00
3 Pengukuran dan Bouwplank 1,330.00 m² 10,000.00 13,300,000.00
4 Koordinasi, Keamanan, dll 1.00 ls 25,000,000.00 25,000,000.00
SUB TOTAL 48,300,000.00
II PEKERJAAN TANAH DAN PONDASI
1 Pondasi Tapak Cakar Ayam 45.00 bh 425,000.00 19,125,000.00
2 Sloop Beton 246.00 m¹ 145,000.00 35,670,000.00
3 Pedestal 45.00 ttk 175,000.00 7,875,000.00
SUB TOTAL 62,670,000.00
III. PEKERJAAN BESI BAJA
1 Pasangan Base Plate, Angkur dan Skoor 452.00 kg 19,000.00 8,588,000.00
2 Pasangan Kolom Tiang Kandang 4m WF-250 3,808.00 kg 19,000.00 72,352,000.00
3 Pasangan Kolom Tiang Tengah Kandang 2m WF-250 952.00 kg 19,000.00 18,088,000.00
4 Pasangan Balok Tengah Tarikan Tiang Kolom 14m WF-250 6,664.00 kg 19,000.00 126,616,000.00
5 Pasangan Balok Tengah dudukan bambu 14m WF 250 6,272.00 kg 19,000.00 119,168,000.00
6 Pasangan Balok Kuda-kuda WF - 250 7,616.00 kg 19,000.00 144,704,000.00
7 Pasangan Balok Tengah sambungan antar tiang WF 250, P= 95 2,660.00 kg 19,000.00 50,540,000.00
8 Pasangan Balok Samping Tiang Kandang WF 250, P= 95 5,320.00 kg 19,000.00 101,080,000.00
9 Pasangan Balok Samping Tiang Atas holo 5 x 10 x 2,1 190.00 m¹ 145,000.00 27,550,000.00
10 Pasangan Gordeng holo 5 x 10 x 2,1 1,552.00 m¹ 145,000.00 225,040,000.00
11 Pasangan Baseplate 8 mm u/Pasangan Gordeng 326.00 kg 19,000.00 6,194,000.00
12 Mur 5/8 180.00 Pcs 2,500.00 450,000.00
13 Pasangan Dudukan Mesin 216.00 m¹ 35,000.00 7,560,000.00
14 Pasangan Trekstang + Spandskrup 240.00 m¹ 35,000.00 8,400,000.00
15 Pasangan Tusuk Jarum gordeng behel ɸ 12 544.00 m¹ 17,500.00 9,520,000.00
16 Pengecatan 1.00 ls 17,000,000.00 17,000,000.00
SUB TOTAL 942,850,000.00
IV PEKERJAAN PASANGAN ATAP DAN PLAPOND
1 Pasangan Atap Zinc alum + peredam t = 0.5 1,414.00 m² 225,000.00 318,150,000.00
2 Pasangan Nok Atap 97.00 m 78,500.00 7,614,500.00
3 Pek. Plapond rangka holo 40 x 60 1,260.00 m² 90,000.00 113,400,000.00
SUB TOTAL 439,164,500.00
V PEKERJAAN DINDING
1 Pasangan Dinding Bata Hebel T= 50 cm Keliling Kandang 116.00 m² 250,000.00 29,000,000.00
2 Pek. Dinding Kandang Kawat Harmonika 426.00 m² 125,000.00 53,250,000.00
3 Pekerjaan Dinding Gudang 162.00 m² 125,000.00 20,250,000.00
SUB TOTAL 102,500,000.00
VI PEKERJAAN LANTAI KANDANG
1 Pek. Lantai 1 t= 10 cm 1,330.00 m² 175,000.00 232,750,000.00
2 Pekerjaan Rabat tinggi 5 cm Keliling Kandang 114.00 m² 95,000.00 10,830,000.00
3 Pekerjaan (Lantai 2) 1,295.00 m² 125,000.00 161,875,000.00
SUB TOTAL 405,455,000.00
VII PEKERJAAN COLLING PAD
1 Pekerjaan Rangka Dudukan Celdek 120.00 m² 115,000.00 13,800,000.00
2 Pekerjaan Plester Lantai Colling Pad 60.00 m² 90,000.00 5,400,000.00
3 Pekerjaan Bak Pembuangan Air Colling Pad 16.00 m² 345,000.00 5,520,000.00
SUB TOTAL 24,720,000.00

VIII PEKERJAAN PENUNJANG KANDANG…


VIII PEKERJAAN PENUNJANG KANDANG
1 Pek. Dudukan Blower 138.00 m¹ 40,000.00 5,520,000.00
2 Pekerjaan Pasang Pintu Besi Double Swing 2.00 bh 3,250,000.00 6,500,000.00
3 Pekerjaan Pasangan Pintu Besi Kandang 4.00 bh 1,150,000.00 4,600,000.00
4 Pekerjaan Pintu Besi Kecil 4.00 bh 800,000.00 3,200,000.00
5 Pekerjaan Tangga Besi 3.00 bh 1,750,000.00 5,250,000.00
6 Pasangan Bata Merah Saluran pembuangan air 144.00 m² 275,000.00 39,600,000.00
7 Pekerjaan Instalasi PVC Pembuangan Air Dalam Kandang 60.00 m¹ 25,000.00 1,500,000.00
SUB TOTAL 66,170,000.00
IX PEKERJAAAN TAMBAHAN
1 Konsol Blower 30.00 m² 115,000.00 3,450,000.00
2 Konsol Pintu dan Tangga 27.00 m² 115,000.00 3,105,000.00
3 Pek. Dudukan Jalur Kabel Kandang 640.00 m 75,000.00 48,000,000.00
4 Pek. Dudukan Torn Dalam Kandang 60.00 m 75,000.00 4,500,000.00
5 Pek. pemasangan gardu listrik pln + pemasangan genset 1.00 unit 300,000,000.00 300,000,000.00
6 Pembuatan perijinan 1.00 ls 100,000,000.00 100,000,000.00
SUB TOTAL 459,055,000.00
GRAND TOTAL 2,550,884,500.00
1,913,163,375.0
RENCANA ANGGARAN BIAYA PEKERJAAN KANDANG AYAM (CLOSE HOUSE)

Luas : 14 x 95 (2 Lantai)
Lokasi : cineam-tasikmalaya

Harga Satuan Total Harga


No. Item Pekerjaan Volume Satuan
( Rp) ( Rp)
I BIAYA UMUM DAN PERSIAPAN
2 Air Kerja dan Listrik Kerja 1.00 ls 10,000,000.00 10,000,000.00
3 Pengukuran dan Bouwplank 1,140.00 m² 10,000.00 11,400,000.00
4 Koordinasi, Keamanan, dll 1.00 ls 25,000,000.00 25,000,000.00
SUB TOTAL 46,400,000.00
II PEKERJAAN TANAH DAN PONDASI
1 Pondasi Tapak Cakar Ayam 45.00 bh 425,000.00 19,125,000.00
2 Sloop Beton 238.00 m¹ 145,000.00 34,510,000.00
3 Pedestal 45.00 ttk 175,000.00 7,875,000.00
SUB TOTAL 61,510,000.00
III. PEKERJAAN BESI BAJA
1 Pasangan Base Plate, Angkur dan Skoor 452.00 kg 19,000.00 8,588,000.00
2 Pasangan Kolom Tiang Kandang 4m WF-250 3,808.00 kg 19,000.00 72,352,000.00
3 Pasangan Kolom Tiang Tengah Kandang 2m WF-250 952.00 kg 19,000.00 18,088,000.00
4 Pasangan Balok Tengah Tarikan Tiang Kolom 14m WF-250 2,856.00 kg 19,000.00 54,264,000.00
5 Pasangan Balok Tengah dudukan bambu 14m WF 250 2,688.00 kg 19,000.00 51,072,000.00
6 Pasangan Balok Kuda-kuda WF - 250 3,808.00 kg 19,000.00 72,352,000.00
7 Pasangan Balok Tengah sambungan antar tiang WF 250, P= 95 2,660.00 kg 19,000.00 50,540,000.00
8 Pasangan Balok Samping Tiang Kandang WF 250, P= 95 2,660.00 kg 19,000.00 50,540,000.00
9 Pasangan Balok Samping Tiang Atas holo 5 x 10 x 2,1 190.00 m¹ 145,000.00 27,550,000.00
10 Pasangan Gordeng holo 5 x 10 x 2,1 1,552.00 m¹ 145,000.00 225,040,000.00
11 Pasangan Baseplate 8 mm u/Pasangan Gordeng 326.00 kg 19,000.00 6,194,000.00
12 Mur 5/8 180.00 Pcs 2,500.00 450,000.00
13 Pasangan Dudukan Mesin 216.00 m¹ 35,000.00 7,560,000.00
14 Pasangan Trekstang + Spandskrup 240.00 m¹ 35,000.00 8,400,000.00
15 Pasangan Tusuk Jarum gordeng behel ɸ 12 544.00 m¹ 17,500.00 9,520,000.00
16 Pengecatan 1.00 ls 17,000,000.00 17,000,000.00
SUB TOTAL 679,510,000.00
IV PEKERJAAN PASANGAN ATAP DAN PLAPOND
1 Pasangan Atap Zinc alum + peredam t = 0.5 1,414.00 m² 225,000.00 318,150,000.00
2 Pasangan Nok Atap 97.00 m 78,500.00 7,614,500.00
3 Pek. Plapond rangka holo 40 x 60 1,260.00 m² 90,000.00 113,400,000.00
SUB TOTAL 439,164,500.00
V PEKERJAAN DINDING
1 Pasangan Dinding Bata Hebel T= 50 cm Keliling Kandang 113.00 m² 250,000.00 28,250,000.00
2 Pek. Dinding Kandang Kawat Harmonika 426.00 m² 125,000.00 53,250,000.00
3 Pekerjaan Dinding Gudang 146.00 m² 125,000.00 18,250,000.00
SUB TOTAL 99,750,000.00
VI PEKERJAAN LANTAI KANDANG
1 Pek. Lantai 1 t= 10 cm 1,140.00 m² 175,000.00 199,500,000.00
2 Pekerjaan Rabat tinggi 5 cm Keliling Kandang 114.00 m² 95,000.00 10,830,000.00
3 Pekerjaan (Lantai 2) 755.00 m² 125,000.00 94,375,000.00
SUB TOTAL 304,705,000.00
VII PEKERJAAN COLLING PAD
1 Pekerjaan Rangka Dudukan Celdek 120.00 m² 115,000.00 13,800,000.00
2 Pekerjaan Plester Lantai Colling Pad 60.00 m² 90,000.00 5,400,000.00
3 Pekerjaan Bak Pembuangan Air Colling Pad 16.00 m² 345,000.00 5,520,000.00
SUB TOTAL 24,720,000.00

VIII PEKERJAAN PENUNJANG KANDANG…


VIII PEKERJAAN PENUNJANG KANDANG
1 Pek. Dudukan Blower 138.00 m¹ 40,000.00 5,520,000.00
2 Pekerjaan Pasang Pintu Besi Double Swing 2.00 bh 3,250,000.00 6,500,000.00
3 Pekerjaan Pasangan Pintu Besi Kandang 4.00 bh 1,150,000.00 4,600,000.00
4 Pekerjaan Pintu Besi Kecil 4.00 bh 800,000.00 3,200,000.00
5 Pekerjaan Tangga Besi 3.00 bh 1,750,000.00 5,250,000.00
6 Pasangan Bata Merah Saluran pembuangan air 144.00 m² 275,000.00 39,600,000.00
7 Pekerjaan Instalasi PVC Pembuangan Air Dalam Kandang 60.00 m¹ 25,000.00 1,500,000.00
SUB TOTAL 66,170,000.00
IX PEKERJAAAN TAMBAHAN
1 Konsol Blower 30.00 m² 115,000.00 3,450,000.00
2 Konsol Pintu dan Tangga 27.00 m² 115,000.00 3,105,000.00
3 Pek. Dudukan Jalur Kabel Kandang 320.00 m 75,000.00 24,000,000.00
4 Pek. Dudukan Torn Dalam Kandang 60.00 m 75,000.00 4,500,000.00
5 Pek. pemasangan gardu listrik pln + pemasangan genset 1.00 unit 150,000,000.00 150,000,000.00
6 Pembuatan perijinan 1.00 ls 50,000,000.00 50,000,000.00
SUB TOTAL 235,055,000.00
GRAND TOTAL 1,956,984,500.00