BILL OF QUANTITIES

PROJECT: RENOVATION OF WAREHOUSE


LOCATION: MARULAS, VALENZUELA CITY
OWNER: GOTACO PROPERTIES

PARTICULARS/ ITEM/ DESCRIPTION QUANTITY UNIT UNIT PRICE COST


1 GENERAL REQUIREMENTS
(MOBILIZATION)
Site Cleaning & Layout lot 2,000.00
Tempacil lot 1,500.00
3,500.00
2 EARTHWORKS
Excavation 150 Cu.m. 30,000.00
Filling Materials Cu.m.
Hauling Cu.m.
30,000.00
3 CONCRETE WORKS
Concrete Powering Cu.m.
Job Mixed Cu.m.
Portland Cement 1,090 Bags 223,450.00
Sand 49 Cu.m. 58,800.00
Gravel (6-3/4) 25 Cu.m. 55,000.00
Reinforcing Bars
10 mm x 6.0 m 60 Pcs. 9,000.00
12 mm x 6.0 m 595 Pcs. 121,975.00
16 mm x 6.0 m 272 Pcs. 142,000.00
Form Works
Plywood 10 mm THK Ordinary 30 Pcs. 13,500.00
Form Lumber 980 B.F. 24,500.00
Nails Asst’d 50 Kgs. 7,500.00
G.I. Wires #16 Tie Wires 50 Kgs. 8,500.00
664,225.00
4 MASONRY WORKS
C.H.B Laying
5” C.H.B. 8,350 Pcs. 100,200.00
4” C.H.B. 500 Pcs. 5,000.00
10 mm Steel Bars Dowels 150 Pcs. 22,500.00
Plastering
Cement 30 Pcs. 6,150.00
Sand Shield 25 Cu.m. 22,500.00
156,350.00
5 METALS
Angular Bar 3/16 x 2 ½ x 3/16 70 Set 55,850.00
G.A. 1.5 mm x 50 x 100 G.I. PURLINS 60 Pcs. 52,450.00
108,300.00
6 CARPENTRY WORKS
Plywood 6 mm (1/4”) THK Marine Pcs. 41,250.00
Metal Furring (Frame) Pcs. 48,800.00
90,050.00
7 ROOFING ACCESORIES
Pre-formed Color Roof Sheet 45 Pcs. 84,000.00
Plain G.I. Sheet GA. #26 (Ridge Roll) 20 Pcs. 28,000.00
STD. G.I. Sheet Gutter GA. #26 30 Pcs. 42,000.00
Roof Sealant (Vulcaseal) 5 Pcs. 2,800.00
Rivets/ Accessories 30 Kgs. 3,000.00
Plain G.I. Flushing GA. #26 20 Pcs. 7,000.00
166,800.00
8 DOORS AND WINDOWS
Wood Flush Type Door (ord.) 2 Sets 5,000.00
Wood Flush Type Door (marine) 3 Sets 10,500.00
PVC Flush Type Door 3 Sets 6,000.00
Panel Solid Door 1 Sets 700.00
Door Jambs 9 Rel 1,500.00
Alum-Frame Door 3 Sets 13,500.00
Alum-Frame Window (Sliding) 6 Sets 28,800.00
Clear Glass Steel Grills 6 Sets 7,200.00
62,800.00
FINISHING HARDWARE
Door Hinges (butt type loose pin) 36 2,880.00
Main Ent. Door Lock Set (Schlage) 1 1,500.00
Door Lock Set 9 5,400.00
Consealed Hinges 2,880.00
148,660.00
9 FLOOR FINISHES
Plain Cement Finish 506 m2
Portland Cement 10 Bags 2,050.00
Shieved Sand 6 Cu.m. 10,800.00
12,850.00
PLUMBING WORKS
H2O Closet 3 Sets 7,500.00
Kitchen Sink 1 Set 3,500.00
Floor Drain 3 Pcs. 150.00
H2O Faucet 5 Pcs. 150.00
Gate Valve 4 Pcs. 500.00
Check Value 4 Pcs. 500.00
12,300.00
10 WATER LINE
½ DIA x 20’ PVC Pipe 5 Pcs. 13,750.00
½ DIA x 10’ PVC Pipe 6 Pcs. 2,400.00
¾” DIA G.I. Pipe
¾” DIA PVC Pipe
Fittings (Elbow, Tee, Bushing, Etc.) 4,500.00
H2O Tank 1 Set 15,650.00
36,300.00
11 ELECTRICAL WORKS
Conduits/ Fittings/ Accessories 165,000.00

SUMMARY
MATERIAL COST 1,614,675.00
CONTINGENCIES 70,000.00
LABOR COST 726,585.00

TOTAL COST OF LABOR AND 2,411,260.00


MATERIALS