1. Materials Pricelist
Concreting Works
Concrete Amount (php)
Soil Poisoning – Termicide Liter 325.00
Gravel cu.m 1,310.00
Wash Sand cu.m 1,435.00
Portland Cement, 40kg Bag 259.00
Pozzolan Cement, 40kg Bag 261.00
#16 G.I. Tie Wire kg 16.00
Formworks
2 x 3 x 10′ Coco lumber pc 270.00
2 x 4 x 10 Coco lumber pc 270.00
1/2″ x 4′ x 8′ Plywood pc 656.00
6mm thk. Lawanit board pc 201.00
6mm thk. Ordinary Plywood pc 323.00
1″x2″x8′ Wood pc 75.00
2″x2″x8′ Wood pc 95.00
2″x3″x8′ Wood pc 105.00
2″x4″x8′ Wood pc 125.00
Deformed Reinforcing Bars Prices
Description Unit
REBAR, Gr 40, 12mm dia x 6m pc 187.13
REBAR, Gr 40, 12mm dia x 7.5m pc 233.92
REBAR, Gr 40, 12mm dia x 9m pc 280.69
REBAR, Gr 40, 12mm dia x 10.5m pc 327.47
REBAR, Gr 40, 12mm dia x 12m pc 374.26
REBAR, Gr 60, 16mm dia x 6m pc 334.42
REBAR, Gr 60, 16mm dia x 7.5m pc 418.02
REBAR, Gr 60, 16mm dia x 9m pc 501.62
REBAR, Gr 60, 16mm dia x 10.5m pc 585.23
REBAR, Gr 60, 16mm x 12m pc 668.83
REBAR, Gr 60, 20mm dia x 6.0m pc 522.60
REBAR, Gr 60, 20mm dia x 10.5m pc 914.56
REBAR, Gr 60, 25mm dia x 6.0m pc 816.55
REBAR, Gr 60, 25mm x 9.0m pc 1,224.82
REBAR, Gr 60, 25mm dia x 10.5m pc 1,428.97
REBAR, Gr 60, 25mm dia x 12m pc 1,633.10
Embankment (per)
Common Borrow cubic meter 384.40
Selected Borrow cubic meter 392.40
Mixed Sand & Gravel cubic meter 585.11
Rock cubic meter 602.56
Aggregate Subbase Course
Aggregate Subbase Course Material cubic meter 818.13
Aggregate Base Course cubic meter 934.89
Crushed Grading A cubic meter 839.13
Uncrushed Grading A cubic meter 926.00
Crushed Grading B cubic meter 831.63
Uncrushed Grading B cubic meter 837.00
Blended Weathered Limestone and Crush cubic meter
818.22
Stone
Filler Materials cubic meter 401.00
Crushed Aggregate Base (per cubic meter) cubic meter
Crushed Grading A cubic meter 921.63
Crushed Grading B cubic meter 875.43
Lime Stabilized Road Mx Base Course (per
cubic meter)
Lime Stabilized Mixed Soil Aggregate Base cubic meter
693.75
Course Crushed Grading A
Lime Stabilized Mixed Soil Aggregate Base cubic meter
662.78
Course Crushed Grading B
Lime Stabilized Mixed Soil Aggregate Base cubic meter
670.00
Course Uncrushed Grading A
Lime Stabilized Mixed Soil Aggregate Base cubic meter
641.11
Course Uncrushed Grading B
Aggregate Surface Course (per)
Crushed Grading A cubic meter 878.22
Crushed Grading B cubic meter 864.33
Crushed Grading C cubic meter 884.75
Crushed Grading D cubic meter 856.38
Uncrushed Grading A cubic meter 826.13
Uncrushed Grading B cubic meter 817.38
Uncrushed Grading C cubic meter 812.63
Uncrushed Grading D cubic meter 793.25
Painting Works
Paint Tinting Color Ltr 182.00
Paint Aluminum gal 664.00
Paint Enamel gal 660.00
Paint Latex Gloss gal 640.20
Paint Latex Semi-Gloss gal 650.00
Paint Red Lead gal 581.00
Thinner Lacquer gal 511.00
Paint Metal Epoxy gal 676.00
Paint Primer Solvent gal 635.00
Brush Paint (101mm) pc 72.00
Brush Roller (152mm) pc 84.00
Brush Steel (101mm) pc 36.00
Oil Paint Ltr 158.09
Spar Varnish Ltr 145.00
Lacquer Putty Ltr 167.00
Concrete neutralizer gal 422.00
Putty Knife pc 26.00
Roller paint # 9 w/ tray pc 153.00
Paint thinner gal 286.00
Sand paper #120 Dozen 123.00
2. Labor Rates