You are on page 1of 3

PROYEK : PEMBANGUNAN KANTOR DAN GUDANG

PEKERJAAN : PEMBANGUNAN KANTOR DAN GUDANG 2 LT


ALAMAT : JL SURATMO 76 SEMARANG

RENCANA ANGGARAN DAN BIAYA (RAB)


HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SATUAN (Rp.) (Rp.)
1 2 3 4 5 6
PEKERJAAN GUDANG
I. PEKERJAAN PERSIAPAN
1 Uitzet bouwplang 47.40 m' 30,000.00 1,422,000.00
2 Bongkar bang lama 1.00 ls 2,500,000.00 2,500,000.00
3 Brak kerja 0.00 m2 250,000.00 0.00
4 Pagar pengaman 18.65 m' 200,000.00 3,730,000.00
5 Alat kerja 1.00 ls 2,500,000.00 2,500,000.00
10,152,000.00
II. PEKERJAAN TANAH
1 Galian tanah pondasi 114.90 m3 95,000.00 10,915,500.00
2 Urug kembali 45.96 m3 25,000.00 1,149,000.00
3 Urug padas t=50cm 71.47 m3 90,000.00 6,432,525.00
4 Pemadatan tanah 142.95 m2 10,000.00 1,429,450.00
19,926,475.00
III. PEKERJAAN PONDASI
1 Pas batu belah pondasi 16.61 m3 725,000.00 12,040,437.50
2 Beraben 66.43 m2 30,000.00 1,992,900.00
14,033,337.50
IV. PEKERJAAN PASANGAN
1 Pas bata merah lt 1 169.80 m2 105,000.00 17,829,000.00
2 Plester dinding lt 1 339.60 m2 60,000.00 20,376,000.00
3 Acian dinding lt 1 339.60 m2 25,000.00 8,490,000.00
4 Sponengan lt 1 98.00 m' 25,000.00 2,450,000.00
5 Plester kolom lt 1 20.00 m' 80,000.00 1,600,000.00
6 Acian kolom lt 1 20.00 m' 35,000.00 700,000.00
7 Pas bata merah lt 2 200.13 m2 115,000.00 23,014,375.00
8 Plester dinding lt 2 400.26 m2 65,000.00 26,016,900.00
9 Acian dinding lt 2 400.26 m2 30,000.00 12,007,800.00
10 Sponengan lt 2 91.40 m' 25,000.00 2,285,000.00
114,769,075.00
V. PEK. KONSTRUKSI BETON
1 Cor lantai kerja 33.80 m2 65,000.00 2,197,000.00
2 Cor footplat 13.52 m3 3,750,000.00 50,700,000.00
3 Cor sloof 20/40 8.24 m3 3,750,000.00 30,885,000.00
4 Cor kolom pedestal 25/35 3.50 m3 4,250,000.00 14,875,000.00
5 Cor kolom praktis 90.00 m' 140,000.00 12,600,000.00
6 Cor ring balk praktis 70.70 m' 140,000.00 9,898,000.00
121,155,000.00
VI. PEKERJAAN ATAP
1 Pas galv 04 201.84 m2 105,000.00 21,193,046.88
2 Buble 4mm 201.84 m2 42,500.00 8,578,138.02
3 Nok galv 04 14.30 m' 75,000.00 1,072,500.00
4 Talang galv 04 28.60 m' 145,000.00 4,147,000.00
5 Wenfir galv 04 28.00 m' 65,000.00 1,820,000.00
36,810,684.90
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SATUAN (Rp.) (Rp.)
1 2 3 4 5 6

VII. PEKERJAAN KONST BAJA


1 Kolom IWF 250X125 1,776.00 kg 18,500.00 32,856,000.00
2 Balok IWF 250X125 1,709.40 kg 18,500.00 31,623,900.00
3 Balok IWF 200X100 1,684.83 kg 18,500.00 31,169,355.00
4 Terbil IWF 250X125 828.80 kg 18,500.00 15,332,800.00
5 Plat 10mm 737.10 kg 22,500.00 16,584,750.00
6 Mur baut+aval 673.61 kg 18,500.00 12,461,840.50
7 Cat konst baja dag 6,736.13 kg 2,500.00 16,840,325.00
8 Kolom IWF 200X100 426.00 kg 18,500.00 7,881,000.00
9 Portal IWF 200X100 1,281.33 kg 18,500.00 23,704,570.31
10 Regel IWF 150X75 316.40 kg 18,500.00 5,853,400.00
11 Konsul IWF 150X75 210.00 kg 18,500.00 3,885,000.00
12 Terbil IWF 200X100 213.00 kg 18,500.00 3,940,500.00
13 Plat 10mm 162.00 kg 22,500.00 3,645,000.00
14 Gording CNP 125X5X2,3 904.90 kg 17,500.00 15,835,820.00
15 Besi siku 70x70x7 sepatu gording 89.32 kg 17,500.00 1,563,100.00
16 Besi 12 jarum 24.92 kg 17,500.00 436,100.00
17 Besi 16 ikatan angin 94.80 kg 17,500.00 1,659,000.00
18 Besi siku 40x40x4 talang 146.40 kg 17,500.00 2,562,000.00
19 Mur baut+aval 386.91 kg 18,500.00 7,157,779.50
20 Cat konst baja atap 10,458.80 kg 2,500.00 26,147,005.31
21 Tangga baja 1.00 ls 16,500,000.00 16,500,000.00
277,639,245.63
VIII. PEKERJAAN LANTAI
1 Cor lantai 1 t 12cm 130.52 m2 190,000.00 24,797,850.00
2 Pas wire mesh M7 1 lapis 130.52 m2 45,000.00 5,873,175.00
3 Hardener 3kg/m2 130.52 m2 37,500.00 4,894,312.50
4 Pas bondex W 1000 lt 2 123.77 m2 155,000.00 19,183,575.00
5 Pas wire mesh M8 1 lapis 123.77 m2 65,000.00 8,044,725.00
6 Cor lantai 2 12cm 123.77 m2 190,000.00 23,515,350.00
7 Hardener 3kg/m2 123.77 m2 37,500.00 4,641,187.50
90,950,175.00
IX. PEKERJAAN LISTRIK
1 Titik lampu broco 26.00 titik 285,000.00 7,410,000.00
2 Stop kontak broco 12.00 titik 285,000.00 3,420,000.00
3 Pipa penggantung lampu+tutup 12.00 titik 375,000.00 4,500,000.00
4 Arde 1.00 set 850,000.00 850,000.00
5 Box sekring MCB 12.00 grup 450,000.00 5,400,000.00
6 Panel induk 1.00 set 5,500,000.00 5,500,000.00
27,080,000.00
X. PEKERJAAN FINISHING
1 Cat tembok Decolith 739.86 m2 32,500.00 24,045,450.00
2 Pas buis beton D 25 34.00 m' 175,000.00 5,950,000.00
3 Bak kontrol 6.00 buah 350,000.00 2,100,000.00
4 Pralon 4' talang 72.00 m' 75,000.00 5,400,000.00
37,495,450.00
PROYEK : PEMBANGUNAN KANTOR DAN GUDANG
PEKERJAAN : PEMBANGUNAN KANTOR DAN GUDANG 2 LT
ALAMAT : JL SURATMO 76 SEMARANG

REKAPITULASI
TOTAL HARGA
NO. URAIAN PEKERJAAN (Rp.)
1 2 3
PEKERJAAN GUDANG
I. PEKERJAAN PERSIAPAN 10,152,000.00
II. PEKERJAAN TANAH 19,926,475.00
III. PEKERJAAN PONDASI 14,033,337.50
IV. PEKERJAAN PASANGAN 114,769,075.00
V. PEK. KONSTRUKSI BETON 121,155,000.00
VI. PEKERJAAN ATAP 36,810,684.90
VII. PEKERJAAN KONST BAJA 277,639,245.63
VIII. PEKERJAAN LANTAI 90,950,175.00
IX. PEKERJAAN LISTRIK 27,080,000.00
X. PEKERJAAN FINISHING 37,495,450.00
JUMLAH ... Rp. 750,011,443.02

DIBULATKAN ... Rp, 750,000,000.00

Terbilang :
Tujuh ratus lima puluh juta rupiah.

NB : Biaya tersebut di atas BELUM termasuk :


- Pajak bangunan
- Pek pagar depan, r jaga
- Pek halaman gudang dan taman

Semarang, 29 November 2020

( Ir. Irwan Wiranto )