You are on page 1of 1

BILL OF QUANTITY

ACTIVITY : SWIMMING POOL (3,5 x9 m)


NAME OF WORK : VILLA 3 MAWUN
FISCAL YEAR : 2023

Unit Price Total Price


No. Descriptions Volume Unit
Rp. Rp.
1 2 3 4 5 6
I SWIMMING POOL WORK
1 Measurement and Installation of Bouwplank 27,55 m' 43.000,00 1.184.650,00
2 Soil excavation 71,67 m3 58.944,00 4.224.516,48
3 Swimming pool foundation 4,07 m3 1.250.000,00 5.085.937,50
4 250 mm thick concrete floor 8,96 m3 4.200.000,00 37.626.750,00
5 300 mm thick concrete wall 16,53 m3 4.200.000,00 69.426.000,00
6 Plaster Wall 1 Pc:3 Ps 155,00 m2 75.000,00 11.625.000,00
7 Waterproofing floor and wall 25,49 m2 300.000,00 7.646.625,00
8 green palimanan stone 20 x 40 90,94 m2 450.000,00 40.920.750,00
9 Pump room 2 X 2 1,00 Ls 25.000.000,00 25.000.000,00
10 Circulation pump ( Hayward Pump 2 PK ) 1,00 Bh 27.000.000,00 27.000.000,00
11 Filter pump 1,00 Bh 30.000.000,00 30.000.000,00
12 Piping system installation 1,00 Unit 25.000.000,00 25.000.000,00
TOTAL 284.740.228,98