You are on page 1of 2

RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : RUMAH KOS 2 LANTAI


LOKASI : SABAK
TAHUN : 2023

RINCIAN RENCANA ANGGARAN BIAYA

NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA


(RP) (RP)

A PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi sebelum dan sesudah 540.00 m² 13,250.00 7,155,000.00
2 Bownplank 66.00 m³ 75,000.00 4,950,000.00
3 Pembuatan Gudang, Sewa Air, dll 1.00 Ls 4,000,000.00 4,000,000.00
Sub Jumlah 16,105,000.00
B PEKERJAAN TANAH DAN PASIR
1 Galian Tanah 540.00 m³ 502,500.00 271,350,000.00
2 Urug Pasir bawah lantai dan bawah pondasi 41.11 m³ 26,520.00 1,090,237.20
3 Urugan Tanah Kembali 35.84 m³ 28,640.00 1,026,457.60
Sub Jumlah 273,466,694.80
C PEKERJAAN STRUKTUR BETON BERTULANG
1 Pondasi Footplat 1.2 x 1.2 m kedalaman 2 m 18.28 m³ 3,406,095.56 62,263,426.84
2 Beton sloof SL 15x20cm 2.61 m³ 4,790,918.33 12,504,296.84
3 Beton sloof SL 20x30cm 5.43 m³ 3,728,993.33 20,248,433.78
4 Beton kolom praktis 15x15cm 4.07 m³ 6,650,121.11 27,065,992.92
5 Beton kolom K1 25x40 12.77 m³ 7,238,647.20 92,437,524.74
6 Beton kolom K2 25x30 1.49 m³ 6,366,673.33 9,486,343.26
7 Beton balok B1 20x40 5.34 m³ 5,821,170.00 31,085,047.80
8 Beton balok B2 20x30 6.18 m³ 6,396,411.67 39,529,824.12
9 Ring Balok RB 15x20 5.63 m³ 5,740,918.33 32,321,370.20
11 Pelat lantai bondek 0.75 tandon 2.23 m³ 4,502,350.00 10,040,240.50
12 Dak talang beton 1.74 m³ 7,238,647.20 12,595,246.13
Sub Jumlah 349,577,747.13
D PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasangan Dinding Bata 709.90 m² 238,010.00 168,963,299.00
2 Plasteran Dinding Bata 1365.60 m² 74,200.00 101,327,520.00
3 Acian Dinding Bata 1360.60 m² 42,250.00 57,485,350.00
Sub Jumlah 327,776,169.00
E PEKERJAAN LANTAI, DINDING, PLAFOUND DAN ATAP
1 Keramik Lantai 60x60 270.00 m² 181,700.00 49,059,000.00
2 Keramik KM 25x25 24.00 m² 161,200.00 3,868,800.00
3 Keramik KM 20x25 136.00 m² 161,200.00 21,923,200.00
4 List plank GRC Motif Kayu 32.90 m' 39,110.80 1,286,745.32
5 Rangka Baja Ringan 130.04 m² 91,800.00 11,937,672.00
6 Seng Metal + accessories 130.04 m² 42,260.00 5,495,490.40
7 Pekerjaan Plafon Gypsum dan Rangka 294.00 m² 86,320.00 25,378,080.00
Sub Jumlah 118,948,987.72
F PEKERJAAN CAT, FINISHING
1 Cat dinding 1,365.60 m² 37,636.00 51,395,721.60
2 Railing Teras dan Balkon 23.95 m² 400,000.00 9,580,000.00
3 Tangga Beton 1.00 Ls 5,000,000.00 5,000,000.00
Sub Jumlah 65,975,721.60
G PEKERJAAN PINTU
1 Pintu Jendela P1 Kayu + Kaca + Finishing Melamin 28.00 unit 4,000,000.00 112,000,000.00
2 Pintu P2 Kamar Mandi Fiber 28.00 unit 2,000,000.00 56,000,000.00
3 Perlengkapan Pintu Handel, engsel dll 28.00 Ls 200,000.00 5,600,000.00
Sub Jumlah 173,600,000.00
H PEKERJAAN KELISTRIKAN
1 Instalasi Lampu 66.00 unit 212,520.00 14,026,320.00
2 MCB + MCB Box 2.00 unit 384,800.00 769,600.00
3 Memasang Stop Kontak 66.00 unit 49,800.00 3,286,800.00
4 Memasang Lampu dan Fitting 62.00 unit 69,800.00 4,327,600.00
5 Memasang Saklar Ganda 64.00 unit 74,600.00 4,774,400.00
Sub Jumlah 27,184,720.00
I PEKERJAAN SANITASI AIR HUJAN DAN TEMPAT JEMUR
1 Memasang floor drain 28.00 unit 66,400.00 1,859,200.00
2 Memasang Pipa PVC 4' 140.00 m' 306,497.00 42,909,580.00
3 Memasang Pipa PVC 3' 160.00 m' 73,172.00 11,707,520.00
5 Memasang Pipa 3/4' 84.05 m' 18,396.00 1,546,183.80
6 Memasang kran 56.00 unit 46,475.00 2,602,600.00
7 Membuat Septictank 1.00 unit 3,500,000.00 3,500,000.00
8 Membuat Sumur Resapan 3.00 unit 1,500,000.00 4,500,000.00
9 Memasang Kloset Duduk 28.00 unit 2,982,300.00 83,504,400.00
10 Tandon 6.00 unit 1,250,000.00 7,500,000.00
Sub Jumlah 159,629,483.80
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA
(RP) (RP)

I PEKERJAAN INTERIOR KAMAR


1 Backdrop TV Hpl Triplek Tb.16mm 28.00 unit 1,500,000.00 42,000,000.00
2 Lemari Hpl Triplek Tb.16mm/18mm 28.00 unit 4,500,000.00 126,000,000.00
3 Meja Hpl Triplek Tb.16mm 28.00 unit 2,050,000.00 57,400,000.00
4 Tempat Tidur Hpl Triplek Tb.18mm 28.00 unit 3,412,000.00 95,536,000.00
Sub Jumlah 320,936,000.00
TOTAL 1,833,200,524.05