Professional Documents
Culture Documents
Jumlah 1,618,300.00
Profit 10 % 161,830.00
Total 1,780,130.00
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH NIECE
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL. PANTAI KUTA BALI
Jumlah 140,750.00
Profit 10 % 14,075.00
Total 154,825.00
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I. PEKERJAAN CIVIL
1 Demolish Pump Room existing ls 1.000 800,000.00 800,000.00
2 Galian tanah m3 3.000 22,900.00 68,700.00
3 Pasang batako m2 - 35,970.00 -
4 Rabatan m3 0.078 298,320.00 23,268.96
5 Concrete roof plat m3 0.203 1,136,971.00 230,805.11
6 Concrete dinding m3 1.150 1,136,971.00 1,307,516.65
7 Concrete lantai m3 0.214 637,748.00 136,478.07
8 Waterprofing m2 11.410 62,500.00 713,125.00
9 Plaster smooth plaster m2 15.410 24,667.00 380,118.47
10 Additional pondasi m3 2.000 178,200.00 356,400.00
11 Box Sumpit bh 1.000 225,000.00 225,000.00
12 Box manhole plat aluminium 60x120 bh 1.000 1,100,000.00 1,100,000.00
Jumlah I 5,341,412.27
TOTAL I + II 6,264,992.27
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I. PEKERJAAN CIVIL
1 Demolish Pump Room existing ls 1.000 800,000.00 800,000.00
2 Galian tanah m3 2.730 22,900.00 62,517.00
3 Rabatan m3 0.078 282,150.00 22,007.70
4 Concrete roof plat m3 0.084 1,136,971.00 95,505.56
5 Concrete lantai dan dinding m3 1.547 635,745.00 983,179.64
6 Waterprofing m2 11.880 62,500.00 742,500.00
7 Plaster smooth plaster m2 11.880 24,667.00 293,043.96
8 Additional pondasi m3 1.000 178,200.00 178,200.00
9 Box manhole plat aluminium 60x120 bh 1.000 1,100,000.00 1,100,000.00
Jumlah I 4,276,953.87
TOTAL I + II 5,200,533.87
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I. PEKERJAAN CIVIL
1 Galian tanah m3 3.000 22,900.00 68,700.00
2 Concrete wall m3 1.150 1,136,971.00 1,307,516.65
3 Concrete flooring m3 0.214 637,748.00 136,478.07
4 Waterprofing m2 11.410 62,500.00 713,125.00
5 Plaster smooth plaster m2 11.410 24,667.00 281,450.47
6 Box manhole plat ( aluminium ) bh 1.000 1,100,000.00 1,100,000.00
Jumlah I 3,607,270.19
TOTAL I + II 4,530,850.19
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN KURANG
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I. PEKERJAAN CIVIL
1 Galian tanah pondasi m3 1.680 22,900.00 38,472.00
2 Urugan pasir bawah pondasi 10 cm m3 0.220 72,600.00 15,972.00
3 Polyethelene sheet damp proof m3 2.200 10,500.00 23,100.00
4 Concrete floor m3 0.220 635,745.00 139,863.90
5 Concrete 175 tie beam 15/20 m3 0.126 1,709,950.00 215,453.70
6 Concrete 175 column 11/11 m3 0.077 1,727,880.00 133,807.03
7 Concrete 175 ring beam 15/15 m3 0.095 1,786,730.00 168,845.99
8 Concrete 225 roof plate m3 0.220 1,136,971.00 250,133.62
9 Waterproofing m2 2.200 62,500.00 137,500.00
10 Loose river stone masonry dia. 20 m3 0.420 96,250.00 40,425.00
11 Pondasi batu kali m3 1.155 96,250.00 111,168.75
12 Pas. Bata m2 6.720 37,860.90 254,425.25
13 Plaster m2 13.440 24,667.00 331,524.48
Jumlah I 1,860,691.71
TOTAL I 1,860,691.71
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH / KURANG
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I. PEKERJAAN CIVIL
1 Galian tanah pondasi m3 1.68 22,900.00 38,472.00 2.73 22,900.00 62,517.00
2 Urugan pasir bawah pondasi 10 cm m3 0.22 72,600.00 15,972.00 - 72,600.00 -
3 Polyethelene sheet damp proof m3 2.20 10,500.00 23,100.00 - 10,500.00 -
4 Rabat beton 5 cm m3 - 282,150.00 - 0.08 282,150.00 22,007.70
5 Concrete 175 lantai tebal 10 m3 0.22 635,745.00 139,863.90 - 635,745.00 -
6 Concrete 175 tie beam 15/20 m3 0.13 1,709,950.00 215,453.70 - 1,709,950.00 -
7 Concrete 175 column 11/11 m3 0.08 1,727,880.00 133,807.03 - 1,727,880.00 -
8 Concrete 175 ring beam 15/15 m3 0.09 1,786,730.00 168,845.99 - 1,786,730.00 -
9 Concrete 225 lantai dan dinding tebal 15 cm m3 - 635,745.00 - 1.55 635,745.00 983,179.64
10 Concrete 225 roof plate m3 0.22 1,136,971.00 250,133.62 0.08 1,136,971.00 95,505.56
11 Waterproofing m2 2.20 62,500.00 137,500.00 11.88 62,500.00 742,500.00
12 Loose river stone masonry dia. 20 m3 0.42 96,250.00 40,425.00 - 96,250.00 -
13 Pondasi batu kali m3 1.16 96,250.00 111,168.75 - 96,250.00 -
14 Pas. Bata m2 6.72 37,860.90 254,425.25 - 37,860.90 -
15 Plaster m2 13.44 24,667.00 331,524.48 11.88 24,667.00 293,043.96
16 Tutup manhole (aluminium) bh - - - 1.00 1,100,000.00 1,100,000.00
Jumlah I 1,860,691.71 Jumlah I 3,298,753.87
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
9 M/E:
- Lighting instalation ttk 5.000 115,000.00
- One gang two way switch ex legrand ttk 1.000 59,100.00
TOTAL
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
AMOUNT
6,595.20
164,155.20
216,153.30
15,427.50
44,625.00
582,411.50
144,000.00
225,000.00
325,000.00
585,000.00
680,000.00
754,000.00
3,012,900.00
3,472,000.00
250,000.00
825,000.00
575,000.00
59,100.00
11,936,367.70
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
TOTAL 3,827,303.83
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
Jumlah I 792,508.75
Jumlah II 450,000.00
T O T A L I + II 1,242,508.75
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
Jumlah I 9,603,688.28
TOTAL I 9,603,688.28
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
Jumlah I 17,492,341.56
Jumlah II 17,422,494.73
T O T A L I + II 34,914,836.29
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
Jumlah I 529,123.75
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
Jumlah I 607,123.75
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
Masonry Work
Jumlah I 2,767,025.51
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
Masonry Work
Jumlah I 862,331.63
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH / KURANG
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I Concrete work
1 Bongkar concrete bathtub existing Ls - 150,000.00 - 1.00 150,000.00 150,000.00
2 Add Concrete untuk dinding & lantai bathtub M3 - 1,136,971.00 - 0.15 1,136,971.00 165,179.15
3 Waterproofing M2 - 62,500.00 - 1.82 62,500.00 113,500.00
Jumlah I - Jumlah I 428,679.15
II Finished work
1 Tumbled marble and polished marble slab Unit 1.00 1,486,996.60 1,486,996.60 - 1,486,996.60 -
coping/façade as indicated in drawing to
Sunken Tub
2 Polished marble floor & wall M2 - 301,521.00 - 4.58 301,521.00 1,380,966.18
3 Polished marble slab capping M2 - 401,521.00 - 1.65 401,521.00 662,509.65
Jumlah II 1,486,996.60 Jumlah II 2,043,475.83
IV Progreess work
Tumbled marble material only according already M2 - 95,000.00 - 3.20 95,000.00 304,000.00
1 stock
Jumlah IV - Jumlah IV 304,000.00
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH / KURANG
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I Concrete work
1 Chipping concrete bathtub existing Ls - 150,000.00 - 1.00 150,000.00 150,000.00
2 Waterproofing M2 - 62,500.00 - 4.50 62,500.00 281,250.00
Jumlah I - Jumlah I 431,250.00
II Finished work
1 Tumbled marble and polished marble slab Unit 1.00 1,486,996.60 1,486,996.60 - 1,486,996.60 -
coping/façade as indicated in drawing to
Sunken Tub
2 Polished marble floor & wall M2 - 301,521.00 - 3.50 301,521.00 1,055,323.50
3 Polished marble slab capping M2 - 401,521.00 - 1.50 401,521.00 602,281.50
Jumlah II 1,486,996.60 Jumlah II 1,657,605.00
IV Progreess work
1 Tumbled marble material only according already M2 - 95,000.00 - 3.20 95,000.00 304,000.00
stock
Jumlah IV - Jumlah IV 304,000.00
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH / KURANG
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
BATHTUB ROOM :
102,104,105,106,107,109,110,111,112,116,
117,118,119
I Concrete work
1 Chipping concrete bathtub existing Ls - 150,000.00 - - 150,000.00 -
2 Waterproofing M2 - 62,500.00 - - 62,500.00 -
Jumlah I - Jumlah I -
II Finished work
1 Tumbled marble and polished marble slab Unit 1.00 1,486,996.60 1,486,996.60 - 1,486,996.60 -
coping/façade as indicated in drawing to
Sunken Tub
2 Polished marble floor & wall M2 - 301,521.00 - 3.50 301,521.00 1,055,323.50
3 Polished marble slab capping M2 - 401,521.00 - 1.50 401,521.00 602,281.50
Jumlah II 1,486,996.60 Jumlah II 1,657,605.00
IV Progreess work
1 Tumbled marble material only according already M2 - 95,000.00 - 3.20 95,000.00 304,000.00
stock
Jumlah IV - Jumlah IV 304,000.00
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
FINISHED WORK
Jumlah I 2,138,508.84
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
FINISHED WORK
Jumlah 12,148,570.67
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
Jumlah 124,018.75
Total 16 Unit 1,984,300.00
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I Wardrobe
4 Papan bingkirai dan plat stainless steel Unit 1.00 250,000.00 250,000.00
(luggage)
II Small Table
1 Bongkar dan pasang marmer termasuk geser Unit 1.00 175,785.50 175,785.50
pintu kaca
TOTAL 28,214,787.96
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
1 Chusion tenun ikat pada kursi make up Unit 1.00 (90,000.00) (90,000.00)
TOTAL 291,088.95
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I Resapan
1 Resapan termasuk bak kontrol, buis beton, ijuk, Unit 1.00 285,714.29 285,714.29
batu bata, galian dan buang tanah pada Resort
Standard
II Floor work
1 Peninggian posisi palmet pada Java Villa, Unit 1.00 150,000.00 150,000.00
Resort Standard dan Resort Villa
TOTAL -27,317,768.75
Dibuat oleh
( Ketut Ludrayasa )
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
II Electrical work
1 Saklar kartu Legrand Mozaic 45, 744 45 Unit 1.00 450,000.00 450,000.00
termasuk pemasangan
1 Installasi kabel NYY pada lampu wardrobe 113 Point 2.00 115,000.00 230,000.00
2 Lampu small E - 14 c/w fittings, lampu dan micro Point 2.00 72,000.00 144,000.00
switch pada wardrobe 113
TOTAL 14,399,000.00
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
AREA : GATE & WALL FENCE WORK (Villa 101)
1 Wall
- Excavation c/ back fill M3 17.46 15,400.00 268,871.68
- Sand fill 10 cm to foundation M3 2.18 72,600.00 158,442.24
- Loose foundation M3 4.36 96,250.00 420,112.00
- River stone foundation M3 9.00 178,200.00 1,604,227.68
- Concrete tie beam 12/12 M3 0.39 1,727,880.00 678,766.56
- Concrete column 11/11 M3 0.31 1,727,880.00 535,228.11
- Concrete beam 12/12 M3 0.39 1,727,880.00 678,766.56
- Bataco wall M2 65.16 35,970.00 2,343,733.26
- Rought plaster M2 164.64 24,667.00 4,061,076.21
- Wall finish paint M2 164.64 23,347.50 3,843,839.01
- Pilah stone finished M2 2.72 325,211.26 884,574.63
- Paras Kerobokan stone copping M1 46.08 90,000.00 4,147,200.00
- Paras Kerobokan stone cansteen 40x15x10 cm M1 5.25 150,000.00 787,500.00
- Palimanan Room number Unit 2.00 150,000.00 300,000.00
2 Floor
- Demolish floor existing M2 19.00 15,000.00 285,000.00
- Demolish concrete pad existing Ls 1.00 50,000.00 50,000.00
- Take out tree existing Ls 1.00 200,000.00 200,000.00
- Removal rubbish Ls 1.00 1,000,000.00 1,000,000.00
- Excavation soil 20 cm to Garden floor M3 11.70 15,400.00 180,180.00
- Sand bed 5 cm to Entry floor M3 0.95 72,600.00 68,970.00
- Sand bed 5 cm to Garden floor M3 2.93 72,600.00 212,355.00
- Polyethelene sheet damp proof 0.6 mm to Entry floor M2 19.00 10,500.00 199,500.00
- Polyethelene sheet damp proof 0.6 mm to Garden floor M2 58.50 10,500.00 614,250.00
- Concrete K175 slab 8 cm w/ bars 8 - 200 mm to Entry floor M3 1.52 635,745.00 966,332.40
- Concrete K175 slab 8 cm w/ bars 8 - 200 mm to Garden floor M3 4.68 635,745.00 2,975,286.60
- Peble wash to Entry floor M2 19.00 137,038.00 2,603,722.00
- Peble wash to Garden floor M2 15.21 137,038.00 2,084,347.98
- Loose peble to Garden floor dia. 2 cm M2 43.29 93,750.00 4,058,437.50
1 Wall
- Excavation c/ back fill M3 17.46 15,400.00 268,871.68
- Sand fill 10 cm to foundation M3 2.18 72,600.00 158,442.24
- Loose foundation M3 5.70 96,250.00 548,702.00
- River stone foundation M3 11.76 178,200.00 2,095,257.78
- Concrete tie beam 12/12 M3 0.51 1,727,880.00 886,526.85
- Concrete column 11/11 M3 0.50 1,727,880.00 869,745.68
- Concrete beam 12/12 M3 0.51 1,727,880.00 886,526.85
- Bataco wall M2 78.52 35,970.00 2,824,292.46
- Rought plaster M2 191.36 24,667.00 4,720,178.45
- Wall finish paint M2 191.36 23,347.50 4,467,684.21
- Pilah stone finished M2 2.72 325,211.26 884,574.63
- Paras Kerobokan stone copping M1 54.43 90,000.00 4,898,700.00
- Paras Kerobokan stone cansteen 40x15x10 cm M1 5.25 150,000.00 787,500.00
- Palimanan Room number Unit 2.00 150,000.00 300,000.00
- Demolish wall partition existing M2 6.84 25,000.00 171,000.00
- Concrete roof nieche M3 0.68 1,727,880.00 1,174,958.40
2 Floor
- Demolish floor existing M2 22.75 15,000.00 341,250.00
- Demolish concrete pad existing Ls 1.00 50,000.00 50,000.00
- Take out tree existing Ls 1.00 200,000.00 200,000.00
- Removal rubbish Ls 1.00 1,000,000.00 1,000,000.00
- Excavation soil 20 cm to Garden floor M3 11.70 15,400.00 180,180.00
- Sand bed 5 cm to Entry floor M3 1.14 72,600.00 82,582.50
- Sand bed 5 cm to Garden floor M3 2.93 72,600.00 212,355.00
- Polyethelene sheet damp proof 0.6 mm to Entry floor M2 22.75 10,500.00 238,875.00
- Polyethelene sheet damp proof 0.6 mm to Garden floor M2 47.25 10,500.00 496,125.00
- Concrete K175 slab 8 cm w/ bars 8 - 200 mm to Entry floor M3 1.82 635,745.00 1,157,055.90
- Concrete K175 slab 8 cm w/ bars 8 - 200 mm to Garden floor M3 3.78 635,745.00 2,403,116.10
- Peble wash to Entry floor M2 22.75 137,038.00 3,117,614.50
- Peble wash to Garden floor M2 15.21 137,038.00 2,084,347.98
- Loose peble to Garden floor dia. 2 cm M2 32.04 93,750.00 3,003,750.00
Dibuat Oleh
( Ketut Ludrayasa )
Dibuat Oleh
( Ketut Ludrayasa )
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
I Nieche
I Vanity Table
TOTAL 5,289,900.00
Dibuat oleh
( Ketut Ludrayasa )
Site Manager
PEKERJAAN TAMBAH
PROYEK : ALAM KUL KUL RESORT
LOKASI : JL PANTAI KUTA - BALI
( Ketut Ludrayasa )
Site Manager
PEKERJAAN FLOOR LANDSCAPE 101 - 102
PROYEK : ALAM KUL - KUL RESORT
LOKASI : JL. PANTAI KUTA - BALI
1 Floor
- Excavation soil 20 cm to Garden floor M3 12.87 15,400.00 198,198.00
- Sand bed 5 cm to Entry floor M3 2.85 72,600.00 206,910.00
- Sand bed 5 cm to Garden floor M3 3.95 72,600.00 286,770.00
- Polyethelene sheet damp proof 0.6 mm to Entry floor M2 33.66 10,500.00 353,430.00
- Polyethelene sheet damp proof 0.6 mm to Garden floor M2 47.25 10,500.00 496,125.00
- Concrete K175 slab 8 cm w/ bars 8 - 200 mm to Entry floor M3 2.84 635,745.00 1,805,515.80
- Concrete K175 slab 8 cm w/ bars 8 - 200 mm to Garden floor M3 3.98 635,745.00 2,530,265.10
- Peble wash to Entry floor M2 33.66 137,038.00 4,612,699.08
- Peble wash to Garden floor M2 47.25 137,038.00 6,475,045.50
- Removal rubbish Ls 1.00 1,000,000.00 1,000,000.00
Dibuat Oleh
( Ketut Ludrayasa )
Dibuat Oleh
( Ketut Ludrayasa )
ROOF GLASS :
I Room 121
1 Change design laminated glass 5 + 5 mm with
clear glass 10 mm w/ film sand blasting to Entry
M2 3.00 750,000.00 2,250,000.00 3.00 380,400.00 1,141,200.00
II Room 122
1 Change design laminated glass 5 + 5 mm with 3.00 750,000.00 2,250,000.00 3.00 380,400.00 1,141,200.00
clear glass 10 mm w/ film sand blasting to Entry
M2
Dibuat oleh
( Ketut Ludrayasa )
Site Manager