You are on page 1of 2

RAB POS SECURITY

BILL OFF QUANTITY (BOQ)


Nama :Reginald Nashirudin (142016033)
Pekerjaan : FASUM
Jenis Pek. : POS SECURTY
VOLUME HARGA JMLH HARGA

NO. URAIAN PEKERJAAN SAT SATUAN TUNGGAL


1. 2. 3. TUNGGAL ( Rp. ) ( Rp. )

5. 6. 8.
I PEKERJAAN PERSIAPAN : 313.540,00

1 Direksikeet / Bouwkeet Ls 1,000 - -


2 Air Kerja + Listrik Kerja Ls 1,000 - -
3 Pengukuran, Pemat.& Pembers. Lapangan. Ls 1,000 200.000,00 200.000,00
4 Pemasangan Bouwplank M' 14,000 8.110,00 113.540,00
5 Keamanan Ls 0,000 50.000,00 -
II PEKERJAAN PONDASI : 1.381.053,76

1 Galian tanah pondasi M³ 3,970 18.200,00 72.254,00


2 Urugan tanah kembali & pemadatan bekas galian pondasi M³ 1,390 4.180,00 5.808,11
3 Urugan tanah bawah lantai M³ 1,454 4.180,00 6.077,72
4 Urugan pasir bwh pondasi & lantai. M³ 0,364 108.550,00 39.457,93
5 Pondasi Umpak batu kali camp 1 Pc : 4 pasir M³ 2,760 455.600,00 1.257.456,00
III PEKERJAAN LANTAI I 35.183.807,48
A. DINDING MASIF 17.654.818,56
1 Pasangan Dinding Bata merah ad. 1Pc : 3 Kpr M² 40,390 82.240,00 3.321.673,60
2 Pasangan beton bertulang ad. 1 Pc: 2 Ps : 3 Krl
- Sloof beton S2 15/20 cm 4d10, d6 - 150/200 M³ 0,420 2.702.700,00 1.135.134,00
- Kolom K1 15/25 cm 4d12, 2d10, d8-150/200 M³ 0,550 3.259.480,00 1.792.714,00
- Kolom K2 15/15 cm 4d10, d8-150/200 M³ 0,340 2.742.920,00 932.592,80
- Balok beton B2 15/15 cm 4d10, 2d10, d8-150/200 M³ 0,140 2.468.628,00 345.607,92
- Balok beton B2 15/20 cm 4d12, 2d10, d8-150/200 M³ 0,660 2.742.920,00 1.810.327,20
- Plat Atap t = 10 cm M³ 1,460 2.860.890,00 4.176.899,40
- Ban jendela M³ 0,110 879.850,00 96.783,50
3 Pekerjaan Plesteran ad. 1 Pc : 5 Psr
- Plesteran dinding luar M² 30,710 24.940,00 765.907,40
- Plesteran dinding dalam M² 29,300 24.040,00 704.372,00
- Pas. Batu andesit 10/30 M² 7,390 225.000,00 1.662.750,00
4 Acian M² 60,010 9.200,00 552.092,00
5 Dinding KM / WC ,Keramik ex. Mulia/setara 20x20 M² 7,620 46.977,00 357.964,74
B. DINDING KOMPONEN 2.990.809,00
1 Pekerjaan Pintu & Jendela
Pas. Kusen Alumunium
- Kusen Type P1 (2,00x 0,75) M' 5,500 75.000,00 412.500,00
- Kusen Type J1 (1 x 1,2) M' 10,800 75.000,00 810.000,00
- Kusen Type V1 (0,55 x 0,5) M' 2,100 75.000,00 157.500,00
2 Pas. Daun Pintu & jendela
- Type P1 Pintu Frame Kaca BH 1,000 500.000,00 500.000,00
- Type J1 Jendela Frame Kaca BH 2,000 300.000,00 600.000,00
3 Pas. Kaca Polos T = 5 mm
- Type P1 M² 0,860 76.000,00 65.360,00
- Type J1 M² 1,640 76.000,00 124.640,00
- Type V1 M² 0,190 76.000,00 14.440,00
4 Pas. Kunci tanam 2 slaag BH 1,000 95.481,00 95.481,00
5 Pas. Kusen & daun pintu PVC lengkap (KM/WC) BH 1,000 210.888,00 210.888,00
C. PEKERJAAN LANTAI 457.430,48

1 Pas. Lantai Keramik uk. 40 x 40 cm ex. Mulia KW-1 / setara :

1/2
RAB POS SECURITY.xls.pdf

HARGA JMLH HARGA


NO. URAIAN PEKERJAAN SAT VOLUME SATUAN TUNGGAL
TUNGGAL ( Rp. ) ( Rp. )
1. 2. 3. 5. 6. 8.
- R. Jaga + teras M² 2,900 66.573,00 193.061,70
2 Teras depan uk. 30 x 30 ex Mulia KW-1 / Setara hitam unpolish M² 2,300 73.970,00 170.131,00
3 Lantai KM / WC ,Keramik ex. Mulia/setara 20x20 M² 1,820 51.779,00 94.237,78
D. PEKERJAAN SANITAIR 11.828.940,00

1 Pas. Pipa Leiding PVC dia 3/4" + Accessories M' 6,000 11.680,00 70.080,00
2 Pas. Kran Leiding 0 1/2" BH 1,000 39.340,00 39.340,00
4 Pas. Pipa pembuangan :
- Sal Tinja pipa PVC dia 4" M' 6,000 38.840,00 233.040,00
- Sal air kotor bawah lantai PVC dia 3" M' 8,000 33.310,00 266.480,00
5 Pas. Closet Jongkok ex INA BH 1,000 125.000,00 125.000,00
6 Pas. septiktank lengkap BH 1,000 1.000.000,00 1.000.000,00
7 Pas. Sumur resapan BH 1,000 750.000,00 750.000,00
8 Pas. Floor Drain Bh 1,000 45.000,00 45.000,00
9 Water torn 1 m3 BH 1,000 1.300.000,00 1.300.000,00
10 Sumur bor + casing + pompa Bh 1,000 8.000.000,00 8.000.000,00
E. PEKERJAAN PENGECATAN 1.463.209,44

1 Pengecatan Metrolite pada dinding luar M² 30,710 18.172,00 558.062,12


2 Pengecatan Metrolite pada dinding dalam M² 29,300 18.172,00 532.439,60
3 Pengecatan Metrolite pada dinding KM/WC M² 6,900 18.172,00 125.386,80
4 Pengecatan Metrolite pada Plafond M131 13,610 18.172,00 247.320,92
F. PEKERJAAN INSTALASI LISTRIK 788.600,00

1 Titik lampu TtK 3,000 99.800,00 299.400,00


2 Titik stop kontak TtK 1,000 99.800,00 99.800,00
3 Titik outlet TV TtK 1,000 115.000,00 115.000,00
4 Box panel MCB outbow Presto ( 4 MCB) unit 1,000 85.750,00 85.750,00
5 MCB (1200 Watt) TtK 2,000 94.325,00 188.650,00
V PEKERJAAN ATAP. 283.200,00

1 Water proofing Dak Atap M² 7,080 40.000,00 283.200,00

2/2