Professional Documents
Culture Documents
08028286991, 08114261696
9. Pipe (bits & bollard) 24” X 20ft (Schd 120) 1 pcs 1,200,000 1,200,000
SUBTOTAL 65,3400,000
12. Welding Glass Dark and Plain 100 pcs 400 40,000
SUBTOTAL 9,981,000
LABOUR
1. Welders For 70 days 4 Welders 10,000 2,800,000
2 Filters For 70 days 2 Fitters 10,000 2,800,000
3. Grinders For 70 days 2 Grinders 7,000 980,000
4. Helpers For 70 days 4 Helpers 5,000 1,400,000
SUBTOTAL 18,975,000
MECHANICAL
S/N ITEMS DESCRIPTION QTY RATE(N) AMOUNT (N)
1. China Engine 600 HP Pair 50,000,000 50,000,000
2. Propeller FPP with Shrouds 2 pcs 5,000,000 10,000,000
3. a) Generator 17.5KVA Auxiliary Engines Pair 9,600,000
c) 200amps Battery For Main engine 4 pieces 120,000 480,000
d) 100amps Battery For Auxiliary Engines 2 pieces 60,000 120,000
4. Plunger & Steering pump Steering 850,000
5. Anchor Windlass
6. Navigation &
Communication System 5,650,000
7. a) Machining of shaft,
Stern Tube & accessories 12,000,000
8. Alignment 4,830,000
9. Engine Room Installation Fire/Safety appliances 9,650,000
10. Documentation/Drawing 6,500,000
11. Towing Winch 2 pcs 850,000
12. Push-tool 2 pcs 450,000 900,000
SUBTOTAL 111,430,000
SUBTOTAL 38,570,000
TOTAL 243,956,000
COMPANY CHARGES 8,500,000
LAUNCHING/SLIPWAY 3,500,000
AMOUNT IN WORDS: Two hundred and twenty five million, nine hundred and fifty six thousand naira only
Yours Faithfully,