Sub-Total
Volume 4 – Bill of Quantities for Package -1
and Price Schedules for Package-2 Works
Part A – Bill of Quantities for Package-1
IDR IDR
PIU - DGWR - MPWH
Warsamson Dam Porject - West Papua
Bidding Documents
Bill No. 13 - GATE CONTROL SYSTEM, ELECTRICAL AND TELECOMUNICATION SYSTEM
Design, Furnishing and Installation, Testing, Commissioning and Maintenance of Gate Control S
installations, lighting, power and telecommunication for the following, all in accordance with Sec
Specification Section 16 (permamnent electrical installations and telecommunication) of the Spe
shown on the Drawings
Sub-Total
a) Private Zone
b) Public Zone
c) Control Bulidings
13.13 KELUAR sign inclusive of bracket, support, wiring from nearest
lighting point and all associated works for the following :-
Lot
a) Private Zone
b) Public Zone
13.14 ABC 9kg dry powder fire extinguisher inclusive of bracket,
support and necessary works for the followings :-
Lot
a) Private Zone
b) Public Zone
c) Control Bulidings
13.15 CO2 2.27 kg dry powder fire extinguisher inclusive of bracket,
support and necessary works for the followings :-
Lot
a) Private Zone
b) Public Zone
c) Control Bulidings
13.16 Carbon Dioxide Total Flooding system complete with storage
cylinders, gas, detectors, schedule 80 of pipeworks, discharge
nozzles, valve assembly, pilot cylinder, solenoid valve, control Lot
panel and cablings, bell, battery, warning lights and all
associated works for the following:-
a) Private Zone
b) Public Zone
c) Control Bulidings
13.17 Provisional Sum
In the event the works are carried out directly by the relevant
Agencies or Authorities, the following Provisional Sum items may
be substantially or entirely omitted and the Contractor shall not
be entitled to any claim for profit and attendance and
compensations
a) Allow provisional sum for the installation of coming cable, PS
transformers, switchgears and other works as may be directed by
Engineer.
b) Allow provisional sum for connecting to Telekom's manhole PS
c) Allow provisional sum of for security ligthing PS
13.18 Any other works not described but contingently and necessary to L.S
complete the works as per Specification and Tender Drawings
( Tendere to itemised the works below )
TOTAL FOR
(Carried to summary of BOQ FO
Volume 4 – Bill of Quantities for Package -1
and Price Schedules for Package-2 Works
Part A – Bill of Quantities for Package-1
ICATION SYSTEM
1
1
Sub-Total
1
1
Sub-Total
1
1
Sub-Total
1
1
1
Sub-Total
1
1
1
1
Sub-Total
1
1
1
1
Sub-Total
1
1
1
1
Sub-Total
1
1
1
Sub-Total
unication
1
1
1
1
1
Sub-Total
1
1
1
Sub-Total
1
1
1
1
1
1
Sub-Total
26
8
4
35
2
1
Sub-Total
1
1
1
TOTAL FOR BILL NO.13
ed to summary of BOQ FOR Package-13