You are on page 1of 5

PROJECT MARSHALL SHP

Project Rating: 2 X 12.375 MW + 10% COL

Section: 2.0 (Volume – II, Section – C1)


Broad Scope of Supply & Services Page 1 of 7

S. NO. DESCRIPTION QTY UNIT


A SUPPLY OF SUPPLY
1.0 MECHANICAL
1.1 Turbine and Auxiliaries
1.1.1 Vertical Francis Turbine with full accessories (Cast Fabricated Runner of diameter
1370 mm)
Rated power = 12.757 MW, Continuous overload = 14.019 MW,
Rated discharge = 15.90 m3/s, Throat Diameter (Dth) = 1370 mm,
2 Sets
Rated speed = 500 rpm, Runaway speed = 1000 rpm,
Max. Net Head = 100.0 m, Rated Net Head = 88.0 m, Min. Net Head = 80.0 m,
Rated efficiency = 93.6%, Peak efficiency = 94.5%,
Turbine setting = (-) 2.4 m
1.1.2 Main Inlet Butterfly Valve with single soft service NBR seal and maintenance NBR
seal clamped on disc with movable Stainless-Steel seat (as per Sirmour project)
2 Sets
Interior diameter = 1900 mm, Design Pressure = 13 bars
Rated oil pressure = 10–12 MPa
1.1.3 Non-Redundant Digital Governor including Turbine Auxiliary cum Governor Panel
2 Sets
(TAGP) (as per Sirmour project)
1.1.4 Governor Oil pumping with accumulator sizing considering 3 strokes of guide vane
servomotor & 1 stroke of Main Inlet Valve opening, common for both Turbine and 2 Sets
Main Inlet Valve (OPU)
1.1.5 Common Cooling Water System comprising pump sets, valves, piping etc. (Open
loop, Tailrace Pumping)
1.1.5.1 Horizontal Centrifugal Pump 3 Nos.
1.1.5.2 Automatic duplex coarse filter 1 No.
1.1.5.3 Manual duplex fine filter 1 No.
1.1.5.4 ERW pipes and pipe fittings of various types (valve, pipe joint, etc.) 1 Lot
1.1.5.5 Measuring and monitoring instrument 1 Lot
1.1.5.6 Control equipment 1 Lot
1.1.6 Dewatering system (as per Sirmour project)
1.1.6.1 Centrifugal pumps (for dewatering in 6 hours) 2 Sets
1.1.6.2 ERW Pipes and fittings, valves, sensors, etc. 1 Lot
1.1.6.3 Electrical equipment and control equipment 1 Lot
1.1.7 Station Drainage system (as per Sirmour project)
1.1.7.1 Submersible pumps 2 Sets
1.1.7.2 ERW pipes and fittings, valves, sensors, etc. 1 Lot
1.1.7.3 Electrical equipment and control equipment 1 Lot
1.1.8a Instrumentation system for Turbine-Generator and auxiliaries
1.1.8a.1 Pressure measurement for head-water level (pressure transmitter) Part of 1.1.2 above
1.1.8a.2 Pressure measurement for tail-water level (level sensor) 1 Set
1.1.8b Control system for Turbine-Generator and Auxiliaries Part of 1.1.3 & 3.1.5
below
1.1.9 Runner Air Injection system Part of 1.1.1 above
1.2 EOT Crane of 55 / 10 Ton capacity – M3 class 1 Lot

© FLOVEL Energy Private Limited


www.flovel.net
PROJECT MARSHALL SHP

Project Rating: 2 X 12.375 MW + 10% COL

Section: 2.0 (Volume – II, Section – C1)


Broad Scope of Supply & Services Page 2 of 7

S. NO. DESCRIPTION QTY UNIT


1.3 Fire detection, alarm and protection System (Spray system for
transformer, Hydrant system and Portable extinguishers) as per
NFPA guidelines (as per Sirmour project)
1.3.1 Portable type fire extinguishers 1 Lot
1.3.2 HVWS system for Generator Transformers 2 Nos.
1.3.3 Hydrant system for Powerhouse and Switchyard 1 Lot
1.3.4 Fire detection and Alarm System 1 Lot
1.3.5 Other necessary materials and accessories Included in respective
items
1.4 Air conditioning system as per IS standard (as per Sirmour project)
1.4.1 Wall Mounted Split AC Units of rating 2 Ton each for Control Room 4 Nos.
1.5 Ventilation system as per IS standard (as per Sirmour project)
1.5.1 Exhaust Fans for Powerhouse 1 Lot
1.6 Emergency diesel generator set with acoustic enclosure of rating
1 Set
125 kVA and accessories including AMF Panel
1.7 Mandatory spares Part of 5 below
1.8 LP Compressed air system
1.8.1 Air compressor, 250 lpm 2 Nos.
1.8.2 Compressor Air vessel (1 for unit operation and 1 for service requirement) 2 Nos.
1.8.3 Control equipment 1 Lot
1.8.4 ERW Pipes and fittings of various types 1 Lot
1.8.5 Measuring and monitoring instrument 1 Set
1.9 Portable type Electrostatic oil filtration (ELC) machine 1 Set
1.10 Winter – Kennedy type Discharge Measuring System 2 Nos.
1.11 Vibration monitoring System Offered as Optional
2.0 Instrumentation and Control System
2.1 Instrumentation system for Turbine-Generator set Part of 1.1.8a & 1.10
above
2.2 Control system of the plant Part of 3.1.5, 3.1.6,
3.1.7 & 3.5 below
3.0 ELECTRICAL
3.1 Generator and auxiliaries
3.1.1a Vertical Synchronous Generator, Air-Water cooled, Self-lubricated bearings and
Hydraulic Brakes (considering GD2 requirement of 86 Tm2 with Speed Rise of
60% over the rated speed of 500 rpm and with cylindrical pole construction. 2 Sets
Capacity: 12.375 MW + 10% COL, Vrated = 11 kV, Freq = 50 Hz, cos = 0.85,
Effrated = 97.1%, nrated = 500 rpm, nrunaway = 1000 rpm,
3.1.1b Brushless Excitation System (Digital AVR (1A + 1M) channel 2 Sets
3.1.2 LAVT Panel Part of 3.2 below
3.1.3 NGT with NGR (Generator Neutral Grounding Cubicle) 2 Sets
3.1.4 PLC based Governing and Unit control system Part of 1.1.3 above
3.1.5 Control, metering and relay panel for the Generator and its auxiliary
2 Sets
system (GRMP)

© FLOVEL Energy Private Limited


www.flovel.net
PROJECT MARSHALL SHP

Project Rating: 2 X 12.375 MW + 10% COL

Section: 2.0 (Volume – II, Section – C1)


Broad Scope of Supply & Services Page 3 of 7

S. NO. DESCRIPTION QTY UNIT


3.1.6 Control, metering and relay panel for the Generator Transformer
2 Sets
and its auxiliary system (TRMP)
3.1.7 Control, metering and relay panel for Line (LRMP) 2 Sets
3.1.8 Auto synchronizer & manual synchronizing equipment for the
1 Set
complete Generator and its auxiliary system
3.1.9 Generator Bearing oil cooling system Part of 1.1.5 above
3.1.10 Generator Brake Part of 3.1.1 above
3.1.11 Generator Rotor Jacking System 2 Sets
3.2 11 kV Indoor Switchgear panel (Optimized scheme) 1 Set
3.3 415V Panel and AC Distribution board (LTAC panel) 1 Set
3.4 Auxiliary Service transformers
3.4.1 Service Transformer, ONAN, 250 kVA, 11/0.433 kV, OCTC, 50 Hz, 3 Phase, ±5% in
2 Sets
steps of 2.5%
3.5 SCADA for control and monitoring of Main plant and 33 kV 1 Lot
Switchyard including its UPS
3.6 Hardware & software for Remote monitoring facilities through Part of 3.5 above
PLC/SCADA
3.7 110V DC 1 x 100% Battery, 2 x 100% FCBC Battery charger and DC Distribution
1 Set
board for Powerhouse & Switchyard
3.8 Generator Transformer
3.8.1 Step up Transformer: 20/25 MVA, ONAN/ONAF type including RTCC panel, 11/33
2 Sets
kV, 3-Phase, ±10% OLTC in steps of 1.25%
3.9 33 kV Outdoor yard (for double circuit line)
3.9.1 Vacuum Circuit breaker 4 Nos.
3.9.2 Disconnector with single Earth Switch 6 Nos.
3.9.3 Single – phase, Current Transformers 18 Nos.
3.9.4 Single – phase, Voltage Transformers 15 Nos.
3.9.5 Metal oxide surge arrestors without gap, including lightning counter 12 Nos.
3.9.6 Steel structures with foundation bolts, insulators, clamps, connectors and 1 Lot
equipment connecting cables (ASCR conductors)
3.10 Cables (Power, Control & Instrumentation), cable accessories and 1 Lot
cabling system complete
3.11 Earthing and Lightning Protection for Powerhouse and switchyard 1 Lot
3.12 Indoor and Outdoor lighting system 1 Lot
3.13 Fire Alarm System for entire plant shall be as per NFPA guidelines & local 1 Lot
statutory regulations.
3.14 Telephone instruments for external communication 1 Lot
3.15 CCTV monitoring for powerhouse, switchyard including with UPS 1 Lot
4 Construction power supply arrangement Shall be in Employer’s
scope
5 Mandatory spares (As per the list enclosed in Section – 3.20 of our Offer) 1 Lot
6 Mandatory Tools as per Annexure – 1 enclosed below 1 Lot
B TECHNICAL SERVICES

© FLOVEL Energy Private Limited


www.flovel.net
PROJECT MARSHALL SHP

Project Rating: 2 X 12.375 MW + 10% COL

Section: 2.0 (Volume – II, Section – C1)


Broad Scope of Supply & Services Page 4 of 7

S. NO. DESCRIPTION QTY UNIT


1 Erection, Testing & Commissioning 1 Lot
2 Transportation & Transit Insurance up to the project site 1 Lot
C. OPTIONAL ITEMS AS PER TENDER REQUIREMENT
1.1.2 Additional price for Main Inlet Butterfly Valve with a diameter of 2000 mm, design
Pressure 13 bars, with single soft service NBR seal and maintenance NBR seal 2 Sets
clamped on disc with movable Stainless-Steel seat.
1.1.3 Additional price for Redundant Digital Governor including Turbine Auxiliary cum
2 Sets
Governor Panel (TAGP) (as per Tender)
1.1.5 Additional price for Separate Cooling Water System comprising pump sets,
valves, piping, etc. (Open loop, Tailrace Pumping) (as per Tender)
1.1.5.1 Horizontal Centrifugal Pump 4 Nos.
1.1.5.2 Automatic duplex coarse filters 2 Nos.
1.1.5.3 Automatic duplex fine filters 2 No.
1.1.5.4 ERW pipes and pipe fittings of various types (valve, pipe joint, etc.) 1 Lot
1.1.5.5 Measuring and monitoring instrument 1 Lot
1.1.5.6 Control equipment 1 Lot
1.1.6 Additional price for Drainage system (as per Tender)
1.1.6.1 Vertical Submersible pumps (for dewatering in 4 hours) 2 Sets
1.1.6.2 ERW Pipes and fittings, valves, sensors, etc. 1 Lot
1.1.6.3 Electrical equipment and control equipment 1 Lot
1.1.7 Additional price for Dewatering system (as per Tender)
1.1.7.1 Vertical Submersible pumps 2 Sets
1.1.7.2 ERW pipes and fittings, valves, sensors, etc. 1 Lot
1.1.7.3 Electrical equipment and control equipment 1 Lot
1.3 Additional price for Fire detection, alarm and protection System (Spray system
for transformer, Hydrant system and Portable extinguishers) as per
NFPA guidelines (as per Tender)
1.3.1 Portable type fire extinguishers 1 Lot
1.3.2 HVWS system for Generator Transformers 2 Nos.
1.3.3 Hydrant system for Powerhouse and Switchyard 1 Lot
1.3.4 Fire detection and Alarm System 1 Lot
1.3.5 Fire water tank storage filling pump station (Time – 8 hours) 1 Lot
1.3.7 Other necessary materials and accessories Included in respective
items
1.4 Additional price for Air conditioning system as per IS standard (as per Tender)
1.4.1 Local air conditioners and complete accessories 1 Lot
1.5 Additional price for Ventilation system as per IS standard (as per Tender)
1.5.1 Fans for turbine floor, MIV floor, service bay, switchgear room, and battery room 1 Lot
1.11 Vibration monitoring System (6 nos. sensors for each unit) 2 Nos.
3.1.1a Reduction in the price of Vertical Synchronous Generator with 86 Tm2 GD2
requirement, considering Speed Rise of 50% over the rated speed of 500 rpm 2 Sets
and with cylindrical pole construction

© FLOVEL Energy Private Limited


www.flovel.net
PROJECT MARSHALL SHP

Project Rating: 2 X 12.375 MW + 10% COL

Section: 2.0 (Volume – II, Section – C1)


Broad Scope of Supply & Services Page 5 of 7

S. NO. DESCRIPTION QTY UNIT


3.1.1a Reduction in the price of Vertical Synchronous Generator with 109 Tm2 GD2
requirement, considering Speed Rise of 60% over the rated speed of 500 rpm 2 Sets
and with cylindrical pole construction
3.1.1a Additional price of Vertical Synchronous Generator with 109 Tm2 GD2
requirement, considering Speed Rise of 60% over the rated speed of 500 rpm 2 Sets
and with salient pole construction
3.1.5 Rotor earth fault arrangement in GRMP panel (64R) 2 Nos.
3.2 Additional price for 11 kV Indoor Switchgear panel (as per tender) 1 Set
3.5 Additional price for Supervisory Control and Data Acquisition System (SCADA)
1 Set
(as per tender)
5. Additional price for Optional spare items as per tender's list enclosed in Section –
1 Lot
3.21 of our Offer

© FLOVEL Energy Private Limited


www.flovel.net

You might also like