Professional Documents
Culture Documents
MONITORING SYSTEM
1.0 SCOPE
2.0 EXPERIENCE
1/15
including at least 2 (two) No. of similar system in a hydro power
plant any where in India & working satisfactorily for at least one
year as on date of submission of bid. Bidders shall have to
furnish performance certificate from the purchaser. Other
contractual/financial criteria as per CVC guidelines. Th e bidder
shall give a brief detail of at least 2 (two) on line condition
monitoring system of hydro generators along with labyrinth gap
measurement system of Francis Turbine installed by them and
working satisfactorily for period of one year and above.
2/15
6. Stator winding connection : Star
7. Generator earthing : Star point earthed through
a distribution T/F
8. Inertia constant (H) : 4 MW-Sec/MVA
9. Stator and Rotor winding insulation: F
10. Bearing type : a) 2 (Two) Guide Bearing
pivoted pad located above
and below rotor
b) 1 (One) Thrust
Bearing below rotor, Spring
plate type
11. Air Gap at center of pole : 30 mm
12. Rotor Diameter : 5940 mm
13. Shaft Diameter : 1010 mm
14. Active height of stator :3M
3/15
4.1 MEASUREMENT OF AIR GAP :
4.1.1 INTRODUCTION
4/15
4.1.3 AIR GAP SENSORS AND CABLE LEADS
The wall mounted enclosure shall meet the oil and dust tight
requirement of EEMAC/NEMA standard. Its dimensions shall
be sized to accommodate on line air gap monitoring system
with all cable leads. Protective conduits for sensor leads,
synchronization leads and the AC power line shall be rigidly
5/15
fixed to the metallic housing. The sensor cable lead shall be
labeled to show the associated sensor. A 14 gauge copper
wire shall be connected between the ground lug on the air
gap monitoring system and the generator ground bus. The
location of the wall mounted enclosure shall not interfere with
normal operation and maintenance of the generator.
6/15
AGMS on the generator shall be provided by the supplier with
a complete installation report. Semiskilled and unskilled
manpower will be provided by SJVNL. Supplier shall indicate
the no. of persons required in the offer. Highly
skilled/specialist required for field installation will be provided
by the supplier.
Installation criteria:-
4.1.7 COMMISSIONING
7/15
humidity and present noise level normally of the order of 90
db and available vibration level of normally 100 to 200
microns and the present disturbances beyond the above limits
in power house. Temperature in the vicinity of sensors will
approx. 125 degree centigrade (max absolute).
4.2.1 INTRODUCTION
8/15
• Orbit • Shaft • Waveform
Centerline
• Shaft • Bode • Spectrum
centerline
• Polar • Polar • Orbit
• Trend • Multi Polar • Polar
• Waterfall • Long waveform
9/15
The details of scope shall be as follows:
Software:
10/15
4.3 ON LINE LABYRINTH CLEARANCE MONITORING
11/15
• Permit continuous alarm monitoring capability with user
defined dual level threshold input.
• Accepts analogue signal sources as required.
12/15
6.0 DOCUMENTS TO BE SUBMITTED ALONG WITH QUOTATION
8.0 SPARES
13/15
9.0 WARRANTY
10.0 TRAINING
11.2 The owner or his representative shall have the right to witness
inspection and/or testing of the goods to confirm their
conformity to the contract and relevant standards. The supplier
shall inform the testing programme to the purchaser with at
least 15 days prior notice. The Owner may notify the Supplier in
writing, in a timely manner, the identity of any representative(s)
deputed for these purposes.
11.3 The inspection and tests and witnessing (if done) by purchaser,
may be conducted on the premises of the Supplier or at point of
delivery and/or at the goods’ final destination. If the inspection
and/or tests to be conducted on the premises of the Supplier are
14/15
to be carried out in the presence of SJVNL’s representative, all
reasonable facilities and assistance, including access to drawings
and production data, shall be furnished to the inspector. For the
cost of traveling, boarding, lodging and local traveling on
account of SJVNL’s representative shall be borne by SJVNL.
11.5 The Owner’s right to inspect, test and where necessary, reject
the Goods after the Good’s arrival in India, shall in no way be
limited or waived by reason of the Goods having previously been
inspected, tested and passed by the Owner or its representative
prior to the Goods’ shipment from the country of origin.
11.6 The supplier will furnish the test/compliance certificates for the
goods to be supplied to the Owner as per the Contract. The
test/compliance certificate shall be sent by the Supplier for
approval along with the request to issue MDCC required for
shipment/invoicing. MDCC will be issued by SJVNL within 14
days after receipt of such request from the Supplier provided the
test/compliance certificates are in order. However, if inspection
at manufacturer’s work is required by SJVNL, the Supplier shall
give 3 weeks notice for attending the same. The Supplier shall
dispatch the material only after receipt of MDCC from Purchaser
unless the requirement of MDCC has been explicitly waived off in
writing by the Owner.
12.0 Drawings
15/15