You are on page 1of 34

RENCANA ANGGARAN BIAYA DOCKING BG.

Marine Power
A. Main Job Docking
No Description Duration Qty Satuan Harga Satuan indeks Price BOQ
1 SAFETY 4.0 1.0 OH 165,000 0.800 132,000 528,000
2 Daya Listrik 4.0 1.0 HM 795,655 1.000 795,655 3,182,620
3 Sewa Lahan dan Perairan 4.0 1.0 HM 1,317,015 5,268,059
4 Fitter 2.0 2.0 OH 165,000 0.800 132,000 528,000
4 Welder 2.0 2.0 OH 165,000 0.800 132,000 528,000
5 Mekanik & Mekanikal 4.0 4.0 HM 165,000 0.800 132,000 2,112,000
6 Elektrikal 2.0 2.0 OH 165,000 0.800 132,000 528,000
7 Plate thk 8 mm, H-Beam dan Siku 4.0 236.80 Kg 23,157 1.000 23,157 5,483,686
8 Scraping/Blasting 4.0 5,115.28 m2 - 1.000 - -
9 Painting 4.0 10,230.56 m2 - 1.000 - -
10 Total area Blasting dan Painting 4.0 15,345.84 m2 - 1.000 - -
11 Docking/Undocking 4.0 - Ls 55,546,177 1.000 55,546,177 -
1.000 - -
Total 30,928.5 Kg 18,158,364
Kapasitas kerja Fitter (232kg/Tk) 250 250.0 kg 1 Hari kerja fitter
Kapasitas kerja Welder (8mtr/Tk) 11 376.8 Kg 1 Hari kerja welder
Hari Kerja 2 Hari kerja
Tonase/Day Realisasi Kerja
Est Total Tenaga Kerja Fitter 2.0 TK 0 Hari kerja 500 0.5
Est Total Tenaga Kerja Welder 2.0 TK 0 Hari kerja 754 0.1
Est Total Tenaga Kerja (Blaster) 7 TK 15,345.0 m2 - Hari kerja -
Est Total Tenaga Kerja Docking/Undocking 10.0 TK 1 Hari kerja 1.0
B. Lain-lain/Comsumable 1.8 1.6
No Description Duration Qty Satuan Harga Satuan indeks Price BOQ
1 Kawat las 1 30.0 kg 35,000 1.000 35,000 1,050,000
2 Oksigen 1 4.0 tabung 80,000 1.000 350,000 1,400,000
3 LPG 12 Kg 1 2.0 tabung 225,000 1.000 200,000 400,000
4 Bearing 1 - pcs 500,000 1.000 500,000 -
5 Pillow Block 1 - pcs 1,500,000 1.000 1,500,000 -
5 roundbar 2 " 1 meter 1 1.0 Unit 560,000 1.000 560,000 560,000
Total 3,410,000
C. Equipment
No Description Duration Qty Satuan Harga Satuan indeks Price BOQ
1 Crane 0 3.0 HM 628,870 1.000 628,870 -
2 Excavator/loader 2 3.0 HM 616,870 1.000 616,870 3,701,220
3 Mesin Bubut 0 4.0 HM 48,280 1.000 48,280 -
4 Air Bag 0 13.0 PCS 331,878 1.000 331,878 -
5 Winch 0 8.0 HM 29,688 1.000 29,688 -
6 Airman 0 5.0 HM 488,782 1.000 488,782 -
Total 3,701,220
Total Bill of Quantity 25,269,584
Beban Biaya Replating per KG
Minimum Charge 50% 37,904,376
Gross Profit 12,634,792

Penawaran 55.0% 39,167,855


RENCANA ANGGARAN BIAYA DOCKING BG. Marine Power
A. Main Job Docking
No Description Duration Qty Satuan Harga Satuan indeks Price BOQ
1 SAFETY 2.0 1.0 OH 165,000 0.800 132,000 264,000
2 Daya Listrik 2.0 1.0 HM 795,655 1.000 795,655 1,591,310
3 Sewa Lahan dan Perairan 2.0 1.0 HM 1,317,015 2,634,029
4 Fitter 2.0 2.0 OH 165,000 0.800 132,000 528,000
4 Welder 2.0 2.0 OH 165,000 0.800 132,000 528,000
5 Mekanik & Mekanikal 4.0 - HM 165,000 0.800 132,000 -
6 Elektrikal 2.0 2.0 OH 165,000 0.800 132,000 528,000
7 Plate thk 8 mm, H-Beam dan Siku 2.0 48.00 Kg 23,157 1.000 23,157 1,111,558
8 Scraping/Blasting 2.0 5,115.28 m2 - 1.000 - -
9 Painting 2.0 10,230.56 m2 - 1.000 - -
10 Total area Blasting dan Painting 2.0 15,345.84 m2 - 1.000 - -
11 Docking/Undocking 2.0 - Ls 55,546,177 1.000 55,546,177 -
1.000 - -
Total 30,739.7 Kg 7,184,897
Kapasitas kerja Fitter (232kg/Tk) 250 250.0 kg 0 Hari kerja fitter
Kapasitas kerja Welder (8mtr/Tk) 11 376.8 Kg 0 Hari kerja welder
Hari Kerja 0 Hari kerja
Tonase/Day Realisasi Kerja
Est Total Tenaga Kerja Fitter 2.0 TK 0 Hari kerja 500 0.1
Est Total Tenaga Kerja Welder 2.0 TK 0 Hari kerja 754 0.0
Est Total Tenaga Kerja (Blaster) 7 TK 15,345.0 m2 - Hari kerja -
Est Total Tenaga Kerja Docking/Undocking 10.0 TK 1 Hari kerja 1.0
B. Lain-lain/Comsumable 1.2 1.1
No Description Duration Qty Satuan Harga Satuan indeks Price BOQ
1 Kawat las 1 10.0 kg 35,000 1.000 35,000 350,000
2 Oksigen 1 2.0 tabung 80,000 1.000 350,000 700,000
3 LPG 12 Kg 1 1.0 tabung 225,000 1.000 200,000 200,000
4 Bearing 1 - pcs 500,000 1.000 500,000 -
5 Pillow Block 1 - pcs 1,500,000 1.000 1,500,000 -
5 roundbar 2 " 1 meter 1 - Unit 560,000 1.000 560,000 -
Total 1,250,000
C. Equipment
No Description Duration Qty Satuan Harga Satuan indeks Price BOQ
1 Crane 0 3.0 HM 628,870 1.000 628,870 -
2 Excavator/loader 1 3.0 HM 616,870 1.000 616,870 1,850,610
3 Mesin Bubut 0 4.0 HM 48,280 1.000 48,280 -
4 Air Bag 0 13.0 PCS 331,878 1.000 331,878 -
5 Winch 0 8.0 HM 29,688 1.000 29,688 -
6 Airman 0 5.0 HM 488,782 1.000 488,782 -
Total 1,850,610
Total Bill of Quantity 10,285,507
Beban Biaya Replating per KG
Minimum Charge 50% 15,428,260
Gross Profit 5,142,753

Penawaran 60.0% 16,456,811


Formula est Biaya pembelian cat

Rp 272.00 Jumlah liter cat yg dibutuhkan


Rp 54,400,000.00 Biaya cat yg dikeluarkan
Rp 33,333.33 Biaya cat per m2 yg dikeluarkan
Rp 10,535.39 Biaya jasa cat per m2 yg dikeluarkan
Note :
1 Liter cat dibutuhkan untuk 6m area kapal

Biaya Sewa compressor ke client /hari 750,000 8


40 kg/m2 pasir blasting yg dibutuhkan per m2

Keterangan Area Luas Area Blasting

Bottom area sampai garis air 350.00


Topside ( Bootop ) 168.00
EXT BULWARK 123.00
350.00

291.00
641

Pengeluaran Painting Sewa/Jumlah ltr BBM


Pemakaian Alat Excavator 250,000 1
Biaya BBM Alat 18 12,500
Compressor 250,000 1
Tenaga Kerja 1,050,000 1

Pengeluaran Blasting Biaya/Jumlah ltr BBM/Volume


Pemakaian Alat Excavator 250,000 1
Biaya BBM Alat 18 12,500
Compressor 250,000 1
Tenaga Kerja 1,050,000 1
Pemakaian Pasir Blasting 1,000,000 16.03

Tota Pengeluaran Blasting & Painti

Sweep Full
63,000 73,000
16,000

Est Profit
Full Blast Standard dari Pak Rahmad :
(ditunggu hasilnya dari pak Rahmad Jenis jenis blastingnya dan material yg dipakai disetiap jenisnya)
Untuk penentuan tgl docking selain diskusi sama tim produksi diskusi juga dengan tim HE

ESTIMASI BIAYA TONGKANG

A. Jasa sandar kapal/docking/undocking


No Description (hari kerja)
1 Man Power Plan 3
2 Alat Berat/excavator (2 UNIT) 3
3 Winch 3
4 Air bag 1
5 kompresor (2 Unit) 3
6 Crane 35
Total
note : 2 hari kerja (docking dan undocking)
tongkang atau tugboat kondisi normal, kita berikan harga diatas
tongkang atau tugboat kondisi bottom pecah, kita berikan harga khusus (perhitungkan biaya repair kondisi plat yang peca
Jika sudah ada penawaran harga yang sudah ditanda tangani, penawaran tersebut tidak dapat dihilangkan dari RL (full cha
charge survey pekerjaan hanya berlaku di floating repair
Pemasangan kupingan memakan waktu 1,5 hari (2 hari)
Cleaning maks 1 tangki 6 orang cleaning
Keterangan per tahun per hari
Sewa Perairan 152,000,000 416,438
Sewa Lahan 720,000,000 1,972,603
Keterangan per tahun per hari
Sewa Perairan 152,000,000 416,438
Sewa Lahan 809,420,700 2,217,591
2,634,029

Keterangan HARGA beli + maintanance Pcs

Harga Ban 12mtr 9 layer 99,563,425 1

Keterangan KILO WATT Pcs

Winch Utama 64 Hp 570,000,000 1

Keterangan HARGA beli + maintanance COS PHI

WIRE ROPE

Note: 54.4 Konvert dari Hp ke KW (1 Hp = 0,85KW)


Keterangan HARGA beli + maintanance Pcs

Harga crane zoom lion 3,960,000,000 1

Keterangan HARGA beli + maintanance Pcs

Harga Compressor Atlas 685,440,000 1

Keterangan HARGA beli + maintanance Pcs

Harga Compressor Airman 228,000,000 1

Keterangan HARGA sewa + maintanance Pcs

Harga Compressor 22,500,000 1

Keterangan HARGA sewa + Maintenance+opr Pcs

Harga Excavator 38,850,000 1

Keterangan HARGA sewa + Maintenance+opr Pcs

Harga Whel loader 33,300,000 1

Keterangan HARGA beli + Maintenance+opr Pcs

Harga Mesin Bubut Swing 128,373,300 1

Keterangan HARGA beli + Maintenance+opr Pcs

Harga Mesin Bor Radial 98,400,000 1

Keterangan HARGA beli + Maintenance+opr Pcs

Harga Mesin Bending 390,000,000 1

Keterangan HARGA beli + Maintenance+opr Pcs

Harga Mesin Bubut Leblond 310,200,000 1

Keterangan HARGA beli + Maintenance+opr Pcs

Harga Mesin Airless 61,200,000 1

operator crane 175,000 24


BBm 18 20,000
Jeriken qty (liter) alat
6 35 compressor
9 35 excavator
7 35 loader
7 35 crane

salary/dy hours/day

Operator 250,000 8

85,000,000 26 8
3,269,231 408,654
93,750

30% 70%
Luas Area
Painting spot Sweep

1,050 105 245


336 50 118
246 37 86
192 449
-
-
1,632

Jam Hari Total Biaya


7 3 5,250,000
7 3 4,593,750
7 3 5,250,000
1 2 2,100,000
17,193,750 10,535 12,000

Jam Hari Total Biaya


7 4 7,000,000
7 4 6,125,000
7 4 7,000,000
1 4 4,200,000
1 1 16,025,000 3,000
40,350,000 62,949 55,000

Tota Pengeluaran Blasting & Painting 57,543,750

Blasting
Sweep Full
Tagihan Blasting 42,306,000 28,268,100 14,037,900
Tagihan Painting 26,112,000

rofit 10,874,250
tiap jenisnya)

MASI BIAYA TONGKANG

A. Jasa sandar kapal/docking/undockin


Qty Satuan Price BOQ No
10 HK 125,000 3,750,000 1
14 HM 616,870 25,908,540 2
8 HM 29,688 712,500 3
14 unit 331,878 4,646,293 4
14 HM 488,782 20,528,844 5
0 HM 628,870 - 6
55,546,177

biaya repair kondisi plat yang pecah)


k dapat dihilangkan dari RL (full charge)

25% 13,886,544 69,432,721


624,658 22% 12,220,159 67,766,336
2,389,041 15% 8,331,927 63,878,104

400
1,317,015

Satuan per Satuan Per hari


bulan(1 th) (25hk) Satuan per Jam
dp
8,296,952 331,878 pelunasan
baecukai
Satuan per Satuan Per hari
Satuan per Jam
bulan(8 th) (25hk)
5,937,500 237,500 29,688 pengursan jky

HARGA PER JUMLAH JAM JUMLAH BIAYA


KWH KERJA WINCH PER JAM

ert dari Hp ke KW (1 Hp = 0,85KW)


Satuan per Satuan Per hari
Satuan per Jam
bulan(5 th) (25hk)
41,250,000 1,650,000 206,250 628,870 200

Satuan per Satuan Per hari


Satuan per Jam
bulan(8 th) (25hk)
7,140,000 285,600 35,700

Satuan per Satuan Per hari


Satuan per Jam
bulan(8 th) (25hk)
2,375,000 95,000 11,875

Satuan per Satuan Per hari


bulan (25hk) Satuan per Jam

22,500,000 900,000 112,500 148,200 488,782

Satuan per Satuan Per hari


Satuan per Jam
bulan (25hk)
38,850,000 1,554,000 194,250 194,250 616,870 616,870

Satuan per Satuan Per hari Satuan per Jam


bulan (25hk)
33,300,000 1,332,000 166,500 166,500 589,120 589,120

Satuan per Satuan Per hari Satuan per Jam


bulan(8 th) (25hk)
1,337,222 53,489 6,686 6,686 6,686 6,686

Satuan per Satuan Per hari Satuan per Jam


bulan(8 th) (25hk)
1,025,000 41,000 5,125 5,125 5,125 5,125

Satuan per Satuan Per hari


Satuan per Jam
bulan(8 th) (25hk)
4,062,500 162,500 20,313 20,313 20,313 20,313

Satuan per Satuan Per hari


Satuan per Jam
bulan(8 th) (25hk)
3,231,250 129,250 16,156 16,156 16,156 16,156
48,280
Satuan per Satuan Per hari
bulan(8 th) (25hk) Satuan per Jam

637,500 25,500 3,188 3,188 3,188 3,188

4,200,000 616,870
350,000
Harga BBM
hari Kerja total qty BBM /JAM 65 113
1 210 16 dengan lembur 24,860
2 315 24 dengan lembur 24,860
3 245 19 dengan lembur 24,860
6 245 19 dengan lembur 24,860
41 78
20

Excavator TARIF BBM/JAM RATARATA 422,620


31,250 Comp Atlas TARIF BBM/JAM RATARATA 340,582
Crane TARIF BBM/JAM RATARATA 236,170
1150
220

1200
1600 12 1500
420
4,590 45,000 0.1020

165,000,000
- 7,949
ESTIMASI BIAYA TUGBOAT

sandar kapal/docking/undocking
Description Duration Qty Satuan
Man Power Plan 2 10 HK
Alat Berat/excavator 2 12 HM
Winch 2 8 HM
Air bag 1 7 unit
kompresor 2 12 HM
Crane 35 0 HM
Total

18,000 7,200,000

260,649,000
615,204,800 875,853,800
1,951,975

173,998,000
16,300,000
10,500,000

1,078,603,775 82,969,521 6,914,127


comp
1

2 200
3 105
4
178 32 5 120
401,585 6 105
602,377 7 120
468,515 8 120
468,515 9
10
11 120
12 890
13 89
17.0 LITER 14 11
13.7 LITER 15
9.5 LITER 16
17
18
19
20
21
22
6000 7.85 1000000 847.8
Price BOQ
125,000 2,500,000
616,870 14,804,880
29,688 475,000
331,878 2,323,147
488,782 11,730,768
- -
31,833,795

48% 15,280,221 47,114,016


29% 9,231,800 41,065,595
42% 13,370,194 45,203,988

total biaya biaya pengurusan per


pengurusan ban
- -

- -
- 7
- -

-
628,870 15,000,000 2,142,857
628,870

24,000,000 30 800,000

exca loader crane

240 240
140
245 175

210 120

240 240

160
335
120 24
1,055 3
66 175
8

240
1,155
55
7
- - -
note diskusi

114,286
536,906
1,000 600 12 7.85 ### 57 ###
600 300 8 7.85 ### 11 678,240
-

276,565
KET HARGA SATUAN JUMLAH PLAT (LBR) PANJANG (20') LEBAR1 LEBAR2 TEBAL
PLAT 12 14,437,500.00 1.00 6,096.00 1,524.00 12.00
PLAT 8 9,619,500.00 1.00 6,096.00 1,524.00 8.00
HBEAM 5,331,500.00 1.00 6,000.00 200.00 8.00 12.00
HBEAM 3,472,308.00 1.00 6,000.00 150.00 8.00 12.00
SIKU 895,400.00 1.00 6,000.00 100.00 100.00 8.00
SIKU 1,450,000.00 1.00 6,000.00 125.00 75.00 10.00

KET HARGA SATUAN JUMLAH PLAT (LBR) PANJANG LEBAR TEBAL


PLAT 12 14,787,500.00 15.00 6,096.00 1,524.00 12.00
PLAT 8 9,869,600.00 17.00 6,096.00 1,524.00 8.00

BEBAN REPLATING KETERANGAN HARGA SATUAN (KG)


1 TONASE PLAT 17,655.60 80.00 5.00
2 KAWAT LAS RD 4MM 1,925.00
3 WELDER 660.00
4 TRAFO LAS+STANG 109.59
5 LISTRIK 1,612.18
6 OKSIGEN 350.00
7 LPG 12kg 89.58
8 LPG 50kg 95.50
9 FITTER 660.00

10 23,157.46 9,610.34 42%


5,094.64 22.0000%

Note : 200kg adalah target replating per hari


128 adalah jumlah tenaga kerja langsung harian dan tetap

UPDATE HARGA 2023 FEBRUARI


KET HARGA SATUAN JUMLAH PLAT (LBR) PANJANG (20') LEBAR1 LEBAR2 TEBAL
PLAT 12 14,437,500.00 1.00 6,096.00 1,524.00 12.00
PLAT 8 9,619,500.00 1.00 6,096.00 1,524.00 8.00
HBEAM 5,331,500.00 1.00 6,000.00 200.00 8.00 12.00
HBEAM 3,472,308.00 1.00 6,000.00 150.00 8.00 12.00
SIKU 895,400.00 1.00 6,000.00 100.00 100.00 8.00
SIKU 1,450,000.00 1.00 6,000.00 125.00 75.00 10.00

KET HARGA SATUAN JUMLAH PLAT (LBR) PANJANG (20') LEBAR1 LEBAR2 TEBAL
PLAT 12 16,696,750.00 1.00 6,096.00 1,524.00 12.00
PLAT 8 11,124,806.00 1.00 6,096.00 1,524.00 8.00
HBEAM 5,502,414.00 1.00 6,000.00 200.00 8.00 12.00
HBEAM 3,472,308.00 1.00 6,000.00 150.00 8.00 12.00
SIKU 1,190,512.00 1.00 6,000.00 100.00 100.00 8.00
SIKU 1,568,784.00 1.00 6,000.00 125.00 75.00 10.00
BERAT JENIS TOTAL BERAT (KG) HARGA PER KG BIAYA EKSPEDISI TOTAL HARGA
7.85 875.15 16,497.24 585.80 17,083.03
7.85 583.43 16,487.81 585.80 17,073.61
0.26 299.52 17,800.15 585.80 18,385.94
0.22 188.99 18,372.84 585.80 18,958.64
0.15 73.97 12,105.23 585.80 12,691.03
0.16 90.00 16,111.11 585.80 16,696.91

KOEFISIEN TOTAL BERAT (KG) TOTAL KG BIAYA EKSPEDISI BIAYA EKSPEDISI/KG


7.85 875.15 13,127.20
7.85 583.43 9,918.33
23,045.53 13,500,000 585.796946809567

16.00

181,359.21

32,768 HULL 565.20 5,431,767


28,252 sideboard 565.20 2,879,491

BERAT JENIS TOTAL BERAT (KG) HARGA PER KG BIAYA EKSPEDISI TOTAL HARGA
7.85 875.15 16,497.24 585.80 17,083.03
7.85 583.43 16,487.81 585.80 17,073.61
0.26 299.52 17,800.15 585.80 18,385.94
0.22 188.99 18,372.84 585.80 18,958.64
0.15 73.97 12,105.23 585.80 12,691.03
0.16 90.00 16,111.11 585.80 16,696.91

BERAT JENIS TOTAL BERAT (KG) HARGA PER KG BIAYA EKSPEDISI TOTAL HARGA
7.85 875.15 19,078.80 - 19,078.80
7.85 583.43 19,067.90 - 19,067.90
0.26 299.52 18,370.77 - 18,370.77
0.22 188.99 18,372.84 - 18,372.84
0.15 73.97 16,094.96 - 16,094.96
0.16 90.00 17,430.93 - 17,430.93
UP RAB (2,5%)
17,937.18 105.00%
17,927.29 105.00%
19,305.24 105.00%
19,906.57 105.00%
13,325.58 105.00%
17,531.75 105.00%
105,933.62 KETERANGAN HARGA AWAL
17,655.60 Internal Tank HARGA AWAL
Replating Web, Frame, Bracket dan Roundbar 32000
Angle Bar 32000
Replating Bulkhead 32000
Replating Sideshell 32000
External Tank HARGA AWAL
Replating Side board 32000
Replating Sideshell 32000
Angle Bar 32000
5,995,730,000 H-Beam Standhion 32000
4,294,593,000
1,701,137,000
28%
KETERANGAN HARGA AWAL
Full Blasting Rp 65,000.00
Sweeep Blasting Rp 58,000.00

Painting 11000

UP RAB (2,5%)
17,937.18 105.00%
17,927.29 105.00%
19,305.24 105.00%
19,906.57 105.00%
13,325.58 105.00%
17,531.75 105.00%
105,933.62
17,655.60 123,942,330.51
UP RAB (2,5%)
20,032.74 105.00%
20,021.30 105.00%
19,289.31 105.00%
19,291.48 105.00%
16,899.71 105.00%
18,302.48 105.00%
113,837.02
18,972.84
HARGA UPDATE
HARGA UPDATE
40000
32000
32000
32000
HARGA UPDATE
32000
32000
32000
32000

HARGA UPDATE 1 HARGA UPDATE 2 (Aft Disc)


Rp 81,250.00 Rp 76,500.00 Rp 4,750.00 Rp 16,250.00
Rp 78,000.00 Rp 68,000.00 Rp 10,000.00 Rp 20,000.00

19000 16000
Formula est Biaya pembelian cat

Rp 852.55 Jumlah liter cat yg dibutuhkan


Rp 127,882,000.00 Biaya cat yg dikeluarkan
Rp 25,000.00 Biaya cat per m2 yg dikeluarkan
Note :
1 Liter cat dibutuhkan untuk 6m area kapal

Biaya Sewa compressor ke client /hari 750,000 8 93,750 22,500,000


40 kg/m2 pasir blasting yg dibutuhkan per m2

Luas Area Luas Area


Keterangan Area
Blasting Painting
Bottom area sampai garis air 2,768.62 5,537
Topside ( Bootop ) 1,110.14 1,110 PRIMER
3,878.76 1,110 2ND COAT
External main deck dan winch house 400.60 801
External sideboard 835.92 1,236.52 1,672
5,115 10,231

Pengeluaran Painting Sewa/Jumlah ltr QTY Jam Hari


Pemakaian Alat Excavator 616,870 1 8 6
Compressor 488,782 2 8 6
Air less 3,188 1 8 2
Tenaga Kerja 125,000 8 1 6

Pengeluaran Blasting Biaya/Jumlah ltr QTY Jam Hari


Pemakaian Alat Excavator 616,870 1 8 8
Compressor 488,782 2 8 8
Tenaga Kerja 125,000 8 1 8
Pemakaian Pasir Blasting 1,220,000 102 1 1

Tota Pengeluaran Blasting & Painting

Sweep Full
minimum charge 60,000 60,000 Tagihan Blasting
15,000 Tagihan Painting

Est Profit
Full Blast Standard dari Pak Rahmad :
(ditunggu hasilnya dari pak Rahmad Jenis jenis blastingnya dan material yg dipakai disetiap jenisnya)
Untuk penentuan tgl docking selain diskusi sama tim produksi diskusi juga dengan tim HE
1.2 3 3.6

Total Biaya
29,609,760
46,923,072
51,008
6,000,000
- -

Total Biaya
39,479,680
62,564,096
8,000,000
124,812,832 -
- full blast 28 hari
spot weep 30% dan 70% 14 hari kerja
-

Blasting
Sweep Full
306,916,800 74,191,200 232,725,600 55,000 60,000
153,458,400 15,500

460,375,200
73,000
68,000
5,000
Tagihan Blasting -
Tagihan Painting -
CATATAN UMUM KERJA BG. NAUTICA 12
1 Pekerjaan cleaning 23 Hari kerja untuk 23 tangki (setelah proses cleaning di
satu tengki selesai maka tidak ada proses cleaning ulang)

2 Pekerjaan air test dilakukan keseluruhan 23 tangki dikerjakan parallel (mana yang selesai langsung
di test)

3 Pekerjaan Blasting est 8-10 hari 1. Bottom (Blasting area disesuaikan bagian mana saja
yang korosinya parah, est 600m2 dari owner 30% dari
2000m2 2.
(Aplikasi Primer Painting area disesuaikan bagian mana
saja yang korosinya parah, est 1000m2 dari owner 50%
dari 2000m2

2. Blasting area top side(area disesuaikan bagian mana


saja yang korosinya parah, est 360m2 dari owner 30%
dari 1200m2
2. (Aplikasi Primer Painting area disesuaikan
bagian mana saja yang korosinya parah, est 600m2 dari
owner 50% dari 1200m2

3. Blasting area external deck full 100% dari 390m 2

Note :
Aplikasi 2nd coat painting bottom : 1000m2 atau 50% dari area bottom 2000m2 (area disesuaikan)
Aplikasi AF painting bottom : 300-600m2 atau 15-30% dari area bottom 2000m2 (area disesuaikan)
Aplikasi 2nd coat painting top side : 1200m2 atau 100% dari area
Aplikasi 2nd coat painting external deck : 390m2 atau 100% dari area

4 Bongkar pasang zinc anode 60 pcs


5 Waktu pekerjaan selama 25 hari

You might also like