ID Task Task Name Duration Start Finish November December January February

Mode 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6
1 Clearing 3 days Mon 11/15/21 Wed 11/17/21
2 Excavation 2 days Thu 11/18/21 Fri 11/19/21
3 Gravel Bedding 2 days Sat 11/20/21 Mon 11/22/21
4 Placing of Pre-Cast Footing Pedestal 3 days Tue 11/23/21 Thu 11/25/21
Columns for Health Facility

5 Reinforcement Works (Footing, 8 days Fri 11/26/21 Sat 12/4/21


Footing Tie Beam, Wall Footing,
Columns) for Toilet Facility
6 Concreting Works (Footing, 5 days Mon 12/6/21 Fri 12/10/21
Foooting Tie Beam, Wall Footing,
Columns) for Toilet Facility
7 Handback filling and compaction 9 days Sat 12/11/21 Tue 12/21/21
8 Plumbing Works 3 days Wed 12/22/21 Mon 12/27/21
9 Construction of Health Facility 18 days Tue 12/28/21 Wed 1/19/22
10 Concreting of Slabs 5 days Tue 12/28/21 Tue 1/4/22
11 Installation of Steel (Columns and 10 days Wed 1/5/22 Sat 1/15/22
Trusses)
12 Installation of Double PVC Coated 3 days Mon 1/17/22 Wed 1/19/22
Textile
13 For Toilet Facility 24 days Tue 12/28/21 Wed 1/26/22
14 Concreting of Slabs 1 day Tue 12/28/21 Tue 12/28/21
15 Masonry 2 days Wed 12/29/21 Thu 12/30/21
16 Roof Beam 4 days Mon 1/3/22 Thu 1/6/22
17 Plastering Works 5 days Fri 1/7/22 Wed 1/12/22
18 Truss Installation 3 days Thu 1/13/22 Sat 1/15/22
19 Roof Installation 1 day Mon 1/17/22 Mon 1/17/22
20 Electrical Installation 6 days Tue 1/18/22 Mon 1/24/22
21 Finishing Works 8 days Tue 1/25/22 Wed 2/2/22
22 Ceiling Works 1 day Tue 1/25/22 Tue 1/25/22
23 Floor Tiling 2 days Wed 1/26/22 Thu 1/27/22
24 Finishing Tiles (Wall and Sink) 4 days Fri 1/28/22 Tue 2/1/22
25 Painting Works 1 day Wed 2/2/22 Wed 2/2/22
26 For Septic Tanks 3 days Thu 2/3/22 Sat 2/5/22
27 Reinforcement Works 2 days Thu 2/3/22 Fri 2/4/22
28 Concreting Works 1 day Wed 1/5/22 Wed 1/5/22

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project1 Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 11/17/21 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 1