Professional Documents
Culture Documents
Sub-total for B -
C. Total (A+B) 31,429.70
D. Output / Day 8.00 mos. / day
NAME & SPECIFICATIONS QUANTITY UNIT UNIT COST AMOUNT
E. Materials
a. First Aid Kit 1.00 ls. 1,000.00 1,000.00
b. Safety Shoes 773.00 man-day 2.19 1,692.87
c. Working Gloves (Maong Material) 773.00 man-day 5.00 3,865.00
d. Reflectorized Vest 773.00 man-day 0.41 316.93
e. Safety Harness / Lanyard 773.00 man-day 4.79 3,702.67
f. Safety Helmet 773.00 man-day 0.48 371.04
g. PPE Signage (4' x 8') 1.00 set 960.00 960.00
h. Safety First (4' x 4') 1.00 set 480.00 480.00
i. Warning Signs (2' x 3') 4.00 sets 180.00 720.00
j. Caution Tape, 100ft 1.00 roll 800.00 800.00
Sub-total for B -
C. Total (A+B) 854.44
D. Output / Day 2.00 each / day
NAME & SPECIFICATIONS QUANTITY UNIT UNIT COST AMOUNT
E. Materials
Sub-total for E
F. Direct Cost (C + E) 21,338.11
G. Overhead, Contingencies and Miscellaneous (OCM) 15% 3,200.72
H. Contractor's Profit(CP) 10% 2,133.81
I. Value Added Tax (VAT) 5% 1,333.63
J. Total Cost (F+G+H+I) 28,006.27
K. Total Unit Cost 28,006.27
DETAILED UNIT PRICE ANALYSIS
Project:
CONSTRUCTION OF FARMERS MULTI PURPOSE BUILDING AT BRGY. PANTAY QUITIQUIT, CAOAYAN, ILOCOS SUR
Item No. / Description: 803(1)a / Structure Excavation(common soil)
Unit of Measurement: cu.m.
Output per hr.: 20.00 cu.m.
Quantity: 33.208 cu.m.
Sub-total for E -
F. Direct Cost (C + E) 7,723.06
G. Overhead, Contingencies and Miscellaneous (OCM) 15% 1,158.46
H. Contractor's Profit(CP) 10% 772.31
I. Value Added Tax (VAT) 5% 482.69
J. Total Cost (F+G+H+I) 10,136.52
K. Total Unit Cost 305.24
DETAILED UNIT PRICE ANALYSIS
Project:
CONSTRUCTION OF FARMERS MULTI PURPOSE BUILDING AT BRGY. PANTAY QUITIQUIT, CAOAYAN, ILOCOS SUR
Item No. / Description: 804(1)a /
Embankment from Structural Excavation
Unit of Measurement: cu.m.
Output per hr.: 9.84 cu.m.
Quantity: 9.714 cu.m.
Sub-total for E -
F. Direct Cost (C + E) 1,591.71
G. Overhead, Contingencies and Miscellaneous (OCM) 15% 238.76
H. Contractor's Profit(CP) 10% 159.17
I. Value Added Tax (VAT) 5% 99.48
J. Total Cost (F+G+H+I) 2,089.12
K. Total Unit Cost 215.06
DETAILED UNIT PRICE ANALYSIS
Project:
CONSTRUCTION OF FARMERS MULTI PURPOSE BUILDING AT BRGY. PANTAY QUITIQUIT, CAOAYAN, ILOCOS SUR
Item No. / Description: 804(1)b / Embankment from Common Borrow by
Unit of Measurement: cu.m. Equipment
Output per hr.: 9.84 cu.m.
Quantity: 42.930 cu.m.
62
80
80
558
Sub-total for B 21,204.48
C. Total (A+B) 35,382.62
D. Output / Day 3.60 m. / day
NAME & SPECIFICATIONS QUANTITY UNIT UNIT COST AMOUNT
E. Materials
a. 40 mm Ø stainless steel 4.00 pcs 2,000.00 8,000.00
Welding rod 1.20 kgs 150.00 180.00
Consumables (5% of Material Cost) 409.00