Department of Public Works and Highways

Davao City 1st District Engineering Office


Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 78 Calendar Days


ABC: 2,970,000.00
Part No. Part Description Total Amount
PART B OTHER GENERAL REQUIREMENTS
B.3 Permits and Clearances 12,768.00
B.5 Project Billboard/Signboard (4"x8" DPWH/8"x8" COA Billboard) 5,644.80
B.7 (2) Occupational Safety and Health Program 32,928.00
B.9 Mobilization/Demobilization 30,240.00
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMB
PART A EARTHWORKS
803 STRUCTURE EXCAVATION
803 (1) a Structure Excavation (Common Soil) 31,449.60
804 EMBANKMENT
804 (4) Gravel Fill 26,006.40
PART B PLAIN AND REINFORCED CONCRETE WORKS
900 REINFORCED CONCRETE
900 (1) b2 Structural Concrete (Footing and Slab on Fill) (Class A,14 days) 153,183.74
900 (1) c3 Structural Concrete (Footing Tie beam) (Class A,28 days ) 40,150.66
900 (1) c4 Structural Concrete (Columns) ( Class A,28 days ) 12,165.89
902 REINFORCING STEEL
902 (1) a Reinforcing Steel(Deformed) - Grade 40 111,650.92
902 (1) b Reinforcing Steel(Deformed) - Grade 60 84,704.90
903 FORMWORKS AND FALSEWORKS
903 (2) Formworks and Falseworks 9,664.70
PART C FINISHINGS AND OTHER CIVIL WORKS
1000 TERMITE CONTROL WORK
1000 (1) Soil Poisoning 6,096.38
TOTAL OF THIS PAGE 556,654.00

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 78 Calendar Days


ABC: 2,970,000.00
Part No. Part Description Total Amount
1001 STORM DRAINAGE AND SEWERAGE SYSTEM
1001 (5) a Catch Basin (Concrete) 8,064.00
1001 (9) Storm Drainage and Downspout 36,288.00
1013 CORRUGATED METAL ROOFING
1013 (2) a2 Fabricated Metal Roofing Accessory (Flashings) (Gauge 26) 18,811.70
1013 (2) b1 Fabricated Metal Roofing Accessory (Gutter) Gauge 24 29,262.64
1014 PREPAINTED METAL SHEETS
1014 (1) b2 Prepainted Metal Sheets (Rib T ype-Long Span,above 0.427mm thk) 485,341.84
1021 CEMENT FLOOR FINISH
1021(3)a Floor Topping (Plain) (With mesh wire) 81,139.97
1021 (1) c Cement Floor Finish (with Floor Hardener) 150,474.24
1027 CEMENT PLASTER FINISH/DECORATIVE STONE
1027 (1) Cement Plaster Finish 2,564.35
1032 PAINTING, VARNISHING AND OTHER RELATED WORKS
411 (2) Paint (Rubberize Paint) 77,220.86
1032 (1) a Painting Works (Masonry/Concrete) 16,921.50
1032 (1) c Painting Works (Steel) 155,645.95
1047 METAL STRUCTURES
403(4)a1 Structural Steel, Furnished, and Fabricated (Grade 36) (Steel Bleachers) 193,835.98
1047(1) Structural Steel (Hanging Goal) 32,256.00
1047 (2) a Structural Steel (trusses) 345,177.18
1047 (2) b Structural Steel (Purlins) 220,445.57
1047 (7) b Metal Structure Accessories (Sagrods) 17,369.86
1047 (3) c Metal Structure Accessories (Turnbuckle) 4,644.86
1047 (4) Metal Structure Accessories (Cross Bracing) 10,994.54
1047 (6) Metal Structure Accessories (Steel Plates) 12,521.30
1047 (7) a Metal Structure Accessories (Bolts) 8,534.94
1048 GLASS FIBER
1048 Glass Fiber (Basketball Goal Board and Its Accessories) 56,448.00
TOTAL OF THIS PAGE 1,963,963.28

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 78 Calendar Days


ABC: 2,970,000.00
Part No. Part Description Total Amount
PART D ELECTRICAL
1100 CONDUITS,BOXES & FITTINGS (CONDUIT WORKS/CONDUIT ROUGH-IN)
1100 (10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in) 145,152.00
1101 WIRESAND WIRING DEVICES
1101 (33) Wires and Wiring Devices 137,733.12
1103 LIGHTING FIXTURES AND LAMPS
1103 (1) Lighting Fixtures and Lamps 37,900.80
1103 POWER LOAD CENTER, SWITCHGEAR AND PANELBOARDS,
1102 (1) Panelboard with Main & Branch Breakers 14,515.20
TOTAL OF THIS PAGE 335,301.12
Total of All Amounts in Words: GRAND TOTAL 2,855,918.39

Two Million Eight Hundred Fifty Five Thousand Nine Hundred Eighteen and Thirty Nine Cents

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item
PART II Description Unit Quantity Unit Price Amount
No.
(1) (2) (3) (4) (Pesos)
(5) (Pesos)
(6)
OTHER GENERAL REQUIREMENTS
In words: Pesos In words: Pesos
B.3
Twelve Thousand Seven Twelve Thousand Seven
B.3 Permits and Clearances l.s 1.00 Hundred Sixty-Eight Hundred Sixty-Eight

In figures: PhP In figures: PhP

12,768.00 12,768.00
In words: Pesos In words: Pesos
Five Thousand Six
Hundred Forty-Four and Eleven Thousand Two
Project Billboard/Signboard (4"x8" DPWH/8"x8" COA Eighty Cents Hundred Eight-Nine and
B.5 each 2.00 Sixty Cents
Billboard)
In figures: PhP In figures: PhP
5,644.80 11,289.60

In words: Pesos In words: Pesos


Thirty-Two Thousand
Nine Hundred Twenty- Thirty-Two Thousand Nine
Occupational Safety and Health Eight Hundred Twenty-Eight
B.7 (2) l.s 1.00
Program
In figures: PhP In figures: PhP
32,928.00 32,928.00

In words: Pesos In words: Pesos

Thirty Thousand Two Thirty Thousand and Two


B.9 Mobilization/Demobilization l.s 1.00 Hundred Forty Hundred Forty

In figures: PhP In figures: PhP


30,240.00 30,240.00

SUB TOTAL FOR THIS PAGE 81,580.80 87,225.60

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


No. Description Unit Quantity (Pesos) (Pesos)

PART
(1) III (2) (3) (4) (5) (6)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART
803 (1)Aa EARTHWORKS
803 STRUCTURE EXCAVATION In words: Pesos In words: Pesos

One Thousand Seven Thirty-One Thousand Four


17.70 Hundred seventy-Six and Hundred Forty-Nine and
803 (1)
(1) aa Structure Excavation (Common Soil) Eighty-One Cents fifty-Four Cents
803 cu.m

In figures: PhP In figures: PhP

1,776.81 31,449.54
804 EMBANKMENT In words: Pesos In words: Pesos

One Thousand Two Sixty Thousand Four


Hundred Nine and Sixty Hundred Nineteen and Fifty-
21.50 Cents Two Cents
804 (4) Gravel Fill In figures: PhP In figures: PhP
cu.m
1,209.60 26,006.40

PART B PLAIN AND REINFORCED CONCRETE WORKS In words: Pesos In words: Pesos
900 REINFORCED CONCRETE One Hundred Fifty-Three
Seven Thousand Twenty- Thousand One Hundred
Three and Fifty-Six Cents Eighty-Three and Eighty-Four
21.81 Cents
Structural Concrete (Footing and Slab on Fill) (Class cu.m In figures: PhP In figures: PhP
900 (1) b2 A,14 days)
7,023.56 153,183.84
In words: Pesos In words: Pesos
Seven Thousand One
Forty Thousand One Hundred
Structural Concrete (Footing Tie beam) (Class A,28 days Hundred Sixty-Nine and
900 (1) c3 cu.m 5.60 Fifty and Sixty-Six Cents
) Seventy-Six Cents
In figures: PhP
In figures: PhP In figures: PhP
7,169.76 40,150.66

SUB TOTAL FOR THIS PAGE 17,179.73 250,790.44

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit
No. (Pesos) (Pesos)
(1) (2) (3) (5) (6)
In words: Pesos In words: Pesos
Seven Thousand Three Twelve Thousand One
Structural Concrete (Columns) ( Class Hundred Twenty-Eight Hundred Sixty-Five and
900 (1) c4 cu.m 1.66 and Eighty-Five Cents Eighty-Nine Cents
A,28 days ) In figures: PhP
In figures: PhP In figures: PhP
7,328.85 12,165.89

902 REINFORCING STEEL In words: Pesos In words: Pesos

One Hundred Eleven


Seventy-Six and Seventy
Thousand Six Hundred Fifty-
1,455.70 Cents
902 (1) a Reinforcing Steel(Deformed) - Grade kgs Two and Nineteen Cents
40 In figures: PhP In figures: PhP
76.70 111,652.19
In words: Pesos In words: Pesos
Eighty-Four Thousand Seven
Eighty-One and Sixty
Reinforcing Steel(Deformed) - Grade Hundred One and Sixty-Two
902 (1) b 1,038.01 Cents
60 kgs Cents
In figures: PhP
In figures: PhP In figures: PhP
81.60 84,701.62

903 FORMWORKS AND FALSEWORKS In words: Pesos In words: Pesos

Nine Thousand Six Hundred


Six Hundred Fifty-Four
Sixty-Four and Seventy
sq.m 14.76 and Seventy-Nine Cents
903 (2) Formworks and Falseworks Cents

In figures: PhP In figures: PhP


654.79 9,664.70

PART C FINISHING AND OTHER CIVIL WORKS In words: Pesos In words: Pesos
1000 TERMITE CONTROL WORK
One Thousand Sixteen Six Thousand Ninety-Six and
and Six Cents Thirty-Six Cents
1000 (1)
1000 (1) Soil Poisoning Liters 6.00
In figures: PhP In figures: PhP

1,016.06 6,096.36

SUB TOTAL FOR THIS PAGE 9,158.00 224,280.76

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
1001 STORM DRAINAGE AND SEWERAGE SYSTEM In words: Pesos In words: Pesos

Two Thousand Sixteen Eight Thousand Sixty-Four

1001 (5) a 4.00


Catch Basin (Concrete) each
In figures: PhP In figures: PhP
2,016.00 8,064.00

In words: Pesos In words: Pesos

Thirty-Six Thousand Two Thirty-Six Thousand Two


1001 (9) Storm Drainage and Downspout l.s 1.00 Hundred Eighty-Eight Hundred Eighty-Eight

In figures: PhP
In figures: PhP In figures: PhP
36,288.00 36,288.00

1013 CORRUGATED METAL ROOFING In words: Pesos In words: Pesos

Eighteen Thousand Eight


Two Hundred Ninety and
Hundred Eleven and forty-
64.80 Thirty Cents
Four Cents
Fabricated Metal Roofing Accessory lin.m
1013 (2) a2 (Flashings) (Gauge 26)
In figures: PhP In figures: PhP
290.30 18,811.44

In words: Pesos In words: Pesos

Twenty-Nine Thousand Two


Four Hundred Fifty-One
Fabricated Metal Roofing Accessory hundred Sixty-Two and
1013 (2) b1 lin.m 64.80 and Fifty-Eight Cents
(Gutter) Gauge 24 Thirty-Eight Cents
In figures: PhP
In figures: PhP In figures: PhP
451.58 29,262.38

1014 PREPAINTED METAL SHEETS In words: Pesos In words: Pesos

Four Hundred Eighty-Five


Seven Hundred Seventy- Thousand Three Hundred
626.94 Four and Fourteen Cents Thirty-Nine and thirty-Three
Prepainted Metal Sheets (Rib T ype- Long Span,above Cents
sq.m
1014 (1) b2 0.427mm thk)
In figures: PhP In figures: PhP
774.14 485,339.33

SUB TOTAL FOR THIS PAGE 39,820.02 577,765.16

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
1021 CEMENT FLOOR FINISH In words: Pesos In words: Pesos

Eighty Thousand Nine


Two Hundred Ninety
Hundred Ninety-Three and
279.00 and Thirty Cents
1021 (3) a Floor Topping (Plain) (With Mesh Wire) sq.m Seventy Cents

In figures: PhP In figures: PhP


290.30 80,993.70
In words: Pesos In words: Pesos

Three Hundred One Hundred Fifty Thousand


Twenty-Two and Four Hundred Seventy-Four
1021 (1) c Cement Floor Finish (with Floor 466.50 Fifty-Six Cents and Twenty-Four Cents
sq.m
Hardener)

In figures: PhP In figures: PhP


322.56 150,474.24
1027 CEMENT PLASTER FINISH/DECORATIVE STONE In words: Pesos In words: Pesos

One Hundred Fifty-


Two Thousand Five Hundred
Six and Thirty-Six
Sixty-Four and Thirty Cents
1027 (1) Cents
Cement Plaster Finish sq.m 16.40

In figures: PhP In figures: PhP


156.36 2,564.30
1032 PAINTING, VARNISHING AND OTHER RELATED WORKS In words: Pesos In words: Pesos

One Hundred Sixty- Seventy-Seven Thousand


Five and Fifty-Three Two Hundred Nineteen and
Cents Seventy-Five Cents
466.50
411 (2)
Paint (Rubberize Paint) sq.m
In figures: PhP In figures: PhP
165.53 77,219.75
In words: Pesos In words: Pesos

One Thousand Four Sixteen Thousand Nine


Hundred Ten and Hundred Twenty-One and
1032 (1) a Painting Works (Masonry/Concrete) sq.m 12.00 Twelve Cents Forty-Four Cents

In figures: PhP In figures: PhP


1,410.12 16,921.44
SUB TOTAL FOR THIS PAGE 2,388.88 333,344.81

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos

One Hundred Fifty-Five


Three Hundred Sixty-Six
Thousand Six Hundred Forty-
1032 (1) c Painting Works (Steel) sq.m 424.60 and Fifty-Seven Cents
Five and Sixty-Two Cents

In figures: PhP In figures: PhP


366.57 155,645.62

1047 METAL STRUCTURES In words: Pesos In words: Pesos

One Hundred Ninety-Three


Two Hundred Ninety and Thousand and Eight Hundred
667.70 Thirty Cents Thirty-Three and Thirty-One
403(4)a1 Structural Steel, Furnished, and Fabricated Cents
kgs
(Grade 36) (Steel Bleachers)
In figures: PhP In figures: PhP
290.30 193,833.31
In words: Pesos In words: Pesos

Thirty-Two Thousand Thirty-Two Thousand Two


1047 (1) Structural Steel (Hanging Goal) l.s 1.00 Two Hundred Fifty-Six Hundred Fifty-Six

In figures: PhP In figures: PhP


In figures: PhP In figures: PhP
32,256.00 32,256.00
In words: Pesos In words: Pesos

Three Hundred Forty-Fivr


One Hundred Four and
One Thousand One Hundred
1047 (2) a Structural Steel (Trusses) 3,292.67 Eighty-Three Cents
kgs Seventy and Sxity Cents
In figures: PhP In figures: PhP
In figures: PhP In figures: PhP
104.83 345,170.60
SUB TOTAL FOR THIS PAGE 1,000.29 447,296.10

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos
Two Hundred Twenty
One Hundred Five and Thousand Four hundred
1047 (2) b Structural Steel (Purlins) 2,095.76 Nineteen Cents Fifty-Two and Ninety-Nine
kgs Cents
In figures: PhP In figures: PhP
In figures: PhP In figures: PhP
105.19 220,452.99
In words: Pesos In words: Pesos

Seventeen Thousand Three


Two Hundred Forty-One
Metal Structure Accessories Hundred sixty-Nine and
1047 (7) b each 71.80 and Ninety-Two Cents
(Sagrods) Eighty-Six Cents
In figures: PhP In figures: PhP
In figures: PhP In figures: PhP
241.92 17,369.86
In words: Pesos In words: Pesos

Two Hundred Ninety and Four Thousand Six hundred


Metal Structure Accessories Thirty Cents Forty-Four and Eighty Cents
1047 (3) c each 16.00
(Turnbuckle)
In figures: PhP In figures: PhP
In figures: PhP In figures: PhP
290.30 4,644.80
In words: Pesos In words: Pesos

Ten Thousand Nine Hundred


Seventy-Two and Fifty-
Metal Structure Accessories (Cross Ninety-Five and Fourteen
1047 (4) kgs 151.49 Eight Cents
Bracing) Cents
In figures: PhP
In figures: PhP In figures: PhP
72.57
72.58 10,995.14
In words: Pesos In words: Pesos

Twelve Thousand Five


Ninety-One and Thirty-
Metal Structure Accessories (Steel Hundred Twenty-One and
1047 (6) kgs 137.06 Six Cents
Plates) Eighty Cents

In figures: PhP In figures: PhP


91.36 12,521.80
SUB TOTAL FOR THIS PAGE 145,474.28 166,208.60

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos

Two Hundred Thirty and Eight Thousand Five Hundred


1047 (7) a Metal Structure Accessories (Bolts) kgs 36.96 Ninety-Two Cents Thirty-Four and Eighty Cents

In figures: PhP In figures: PhP


230.92 8,534.80
In words: Pesos In words: Pesos

Fifty-Six Thousand Four Fifty-Six Thousand Four


1048 Glass Fiber(Basketball Goal Board and Its Accessories) l.s 1.00 Hundred Forty-Eight Hundred Forty-Eight

In figures: PhP In figures: PhP


56,448.00 56,448.00
PART D ELECTRICAL
1100 CONDUITS,BOXES & FITTINGS (CONDUIT WORKS/CONDUIT ROUGH-IN)
In words: Pesos In words: Pesos

One Hundred Forty-Five One Hundred Forty-Five


Thousand One Hundred Thousand One Hundred Fifty-
l.s 1.00 Fifty-Two Two
1100 (10) Conduits, Boxes & Fittings (Conduit
Works/Conduit Rough-in) In figures: PhP In figures: PhP
In figures: PhP In figures: PhP
145,152.00 145,152.00
SUB TOTAL FOR THIS PAGE 201,830.92 210,134.80

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
1101 WIRESAND WIRING DEVICES In words: Pesos In words: Pesos
One Hundred Thirty-
Seven Thousand Seven One Hundred Thirty-Seven
Hundred Thirty-Three Thousand Seven Hundred
1.00 and Twelve Cents Thirty-Three and Twelve
Cents
1101 (33) Wires and Wiring Devices l.s
In figures: PhP In figures: PhP
137,733.12 137,733.12
1103 LIGHTING FIXTURES AND LAMPS In words: Pesos In words: Pesos

Thirty-Seven Thousand
Thirty-Seven Thousand Nine
Nine Hundred and Eighty
1.00 Hundred and Eighty Cents
Cents
1103 (1) Lighting Fixtures and Lamps l.s In figures: PhP In figures: PhP

In figures: PhP In figures: PhP


37,900.80 37,900.80
1103 POWER LOAD CENTER, SWITCHGEAR AND PANELBOARDS, AND OTHER OVERCURRENT
PROTECTION DEVICES In words: Pesos In words: Pesos

Fourteen Thousand Five Fourteen Thousand Five


Hundred Fifteen and Hundred Fifteen and Twenty
1.00 Twenty Cents Cents
1102 (1) Panelboard with Main & Branch l.s
In figures: PhP In figures: PhP
Breakers In figures: PhP In figures: PhP
14,515.20 14,515.20
SUB TOTAL FOR THIS PAGE 190,149.12 190,149.12

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

Part B
B.3 Permits and Clearances
Qty: 1.0 l.s

1.00 l.s Permits and Clearances 9,500.00 / l.s P 9,500.00

Direct Cost P 9,500.00


Indirect Cost (20%) 1,900.00
VAT (12%) 1,368.00
Total Cost P 12,768.00
Unit Cost P 12,768.00
Adjusted Cost 12,768.00

B.5 Projects Billboard/Signboard (4'x8' DPWH Billboard/8'x8' COA Billboard)


Qty: 2.0 each
Projects
2.00 each Billboard/Signboard 4,200.00 / each P 8,400.00
(4'x8' DPWH
Billboard/8'x8' COA Direct Cost P 8,400.00
Billboard) Indirect Cost (20%) 1,680.00
VAT (12%) 1,209.60
Total Cost P 11,289.60
Unit Cost P 5,644.80
Adjusted Cost 5,644.80

B.7 (2) Occupational Health and Safety


Qty: 1.0 l.s

1.00 l.s 24,500.00 / l.s P 24,500.00


Occupational Health and
Safety
Direct Cost P 24,500.00
Indirect Cost (20%) 4,900.00
VAT (12%) 3,528.00
Total Cost P 32,928.00
Unit Cost P 32,928.00
Adjusted Cost 32,928.00

B.9 Mobilization/Demobilization
Qty: 1.0 l.s

1.00 l.s 22,500.0 / l.s P 22,500.00


Mobilization/Demobilization
Direct Cost P 22,500.00
Indirect Cost (20%) 4,500.00
VAT (12%) 3,240.00
Total Cost P 30,240.00
Unit Cost P 30,240.00
Adjusted Cost 30,240.00
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

EARTHWORKS

803 (1) a Structure Excavation (Common Soil)


Qty: 17.70 cu.m

Equipment
1.00 unit 1 day Dump Truck @ 7,500.00 / unit P 7,500.00
1.00 unit 1 day Backhoe @ 12,000.00 / unit P 12,000.00

Labor (20% of Equipment) P 3,900.00

Direct Cost P 23,400.00


Indirect Cost (20%) 4,680.00
VAT (12%) 3,369.60
Total Cost 31,449.60
Unit Cost 1,776.81
Adjusted Cost 31,449.60
804 (4) Gravel Fill
Qty: 21.50 cu.m

Materials
21.50 cu.m Fill Materials @ 750.00 / cu.m P 16,125.00

Labor (20% of Equipment) P 3,225.00

Direct Cost P 19,350.00


Indirect Cost (20%) 3,870.00
VAT (12%) 2,786.40
Total Cost 26,006.40
Unit Cost 1,209.60
Adjusted Cost 26,006.40

PART B PLAIN AND REINFORCED CONCRETE WORKS


REINFORCED CONCRETE
900 (1) b2 Structural Concrete (Footings and Slab on Fill)(Class A-14days)
Qty: 21.81 cu.m

Materials
21.81 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 76,335.00
359.00 kg Reinforcing Steel Bar @ 40.00 / kg P 14,360.00
4.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 256.00
59.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 3,186.00
10.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 1,000.00
of Steel)
2.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 700.00
95,837.00

Labor (20% of Equipment) P 18,139.00

Direct Cost P 113,976.00


Indirect Cost (20%) 22,795.20
VAT (12%) 16,412.54
Total Cost 153,183.74
Unit Cost 7,023.56
Adjusted Cost 153,183.74
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

900 (1) b2 Structural Concrete (Footing Tie Beam)(Class A-28days)


Qty: 5.60 cu.m

Materials
5.60 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 19,600.00
92.00 kg Reinforcing Steel Bar @ 40.00 / kg P 3,680.00
2.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 128.00
15.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 810.00
3.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 300.00
of Steel)
2.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 700.00
25,218.00

Labor (20% of Equipment) P 4,656.00

Direct Cost P 29,874.00


Indirect Cost (20%) 5,974.80
VAT (12%) 4,301.86
Total Cost 40,150.66
Unit Cost 7,169.76
Adjusted Cost 40,150.66

900 (1) b2 Structural Concrete (Columns)(Class A-28days)


Qty: 1.66 cu.m

Materials
1.66 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 5,810.00
27.00 kg Reinforcing Steel Bar @ 40.00 / kg P 1,080.00
1.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 64.00
5.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 270.00
1.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 100.00
of Steel)
1.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 350.00
7,674.00

Labor (20% of Equipment) P 1,378.00

Direct Cost P 9,052.00


Indirect Cost (20%) 1,810.40
VAT (12%) 1,303.49
Total Cost 12,165.89
Unit Cost 7,328.85
Adjusted Cost 12,165.89
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

REINFORCING STEEL
REINFORCED CONCRETE
902 (1) a Reinforcing Steel (Deformed) Grade 40
Qty: 1,455.70 kgs

Materials
1.00 unit 5 day Bar Bender @ 2,200.00 / unit P 11,000.00
11,000.00

Materials
1,455.70 kgs Reinforming Steel @ 40.00 / kgs P 58,228.00
Deformed (Grade 40) 58,228.00

Labor (20% of Equipment) P 13,845.60

Direct Cost P 83,073.60


Indirect Cost (20%) 16,614.72
VAT (12%) 11,962.60
Total Cost 111,650.92
Unit Cost 76.70
Adjusted Cost 111,650.92

902 (1) a Reinforcing Steel (Deformed) Grade 60


Qty: 1,038.01 kgs

Materials
1.00 unit 5 day Bar Bender @ 2,200.00 / unit P 11,000.00
11,000.00

Materials
1,038.01 kgs Reinforming Steel @ 40.00 / kgs P 41,520.40
Deformed (Grade 40) 41,520.40

Labor (20% of Equipment) P 10,504.08

Direct Cost P 63,024.48


Indirect Cost (20%) 12,604.90
VAT (12%) 9,075.53
Total Cost 84,704.90
Unit Cost 81.60
Adjusted Cost 84,704.90

FORMWORKS AND FALSEWORKS


903 (2) Formworks and Falseworks
Qty: 14.76 cu.m

Materials
5.00 pc Fiber Cement Board @ 450.00 / pc P 2,250.00
82.00 bd.ft Wood Frame @ 45.00 / bd.ft P 3,690.00
1.00 kg Nails @ 63.00 / kg P 63.00
6,003.00

P 1,188.00

Direct Cost P 7,191.00


Indirect Cost (20%) 1,438.20
Labor (20% of Equipment) VAT (12%) 1,035.50
Total Cost 9,664.70
Unit Cost 654.79
Adjusted Cost 9,664.70
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

PART C FINISHING AND OTHER CIVIL WORKS


1000 TERMITE CONTROL WORK
Qty: 6.00 Liters

Materials
6.00 Liters Soil poisoning @ 630.00 / Liters P 3,780.00
3,780.00

Labor (20% of Equipment) P 756.00

Direct Cost P 4,536.00


Indirect Cost (20%) 907.20
VAT (12%) 653.18
Total Cost 6,096.38
Unit Cost 1,016.06
Adjusted Cost 6,096.38

STORM DRAINAGE AND SEWERAGE SYSTEM


1001 (5) a Catch Basin (Concrete)
Qty: 4.00 each

Materials
4.00 each Catch Basin (CHB) @ 1,250.00 / each P 5,000.00
5,000.00

Labor (20% of Equipment) P 1,000.00

Direct Cost P 6,000.00


Indirect Cost (20%) 1,200.00
VAT (12%) 864.00
Total Cost 8,064.00
Unit Cost 2,016.00
Adjusted Cost 8,064.00

1001 (9) Storm Drainage and Downspout


Qty: 1.00 l.s

Materials
1.00 l.s Storm Draiange & Downspout @ 22,500.00 / l.s P 22,500.00
22,500.00

Labor (20% of Equipment) P 4,500.00

Direct Cost P 27,000.00


Indirect Cost (20%) 5,400.00
VAT (12%) 3,888.00
Total Cost 36,288.00
Unit Cost 36,288.00
Adjusted Cost 36,288.00
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

CORRUGATED METAL ROOFING


1013 (2) a2 Fabricated Metal Roofing Accessory (Flashing) (Gauge 26)
Qty: 64.80 lin.m

Materials
64.80 lin.m Flashing @ 180.00 / lin.m P 11,664.00
324.00 pc Rivets @ 0.70 / pc 226.80
11,664.00

Labor (20% of Equipment) P 2,332.80

Direct Cost P 13,996.80


Indirect Cost (20%) 2,799.36
VAT (12%) 2,015.54
Total Cost 18,811.70
Unit Cost 290.30
Adjusted Cost 18,811.70

1013 (2) b1 Fabricated Metal Roofing Accessory (Gutter) (Gauge 24)


Qty: 64.80 lin.m

Materials
64.80 lin.m Gutter @ 280.00 / lin.m P 18,144.00
320.00 pc Rivets @ 0.70 / pc 224.00
18,144.00

Labor (20% of Equipment) P 3,628.80

Direct Cost P 21,772.80


Indirect Cost (20%) 4,354.56
VAT (12%) 3,135.28
Total Cost 29,262.64
Unit Cost 451.58
Adjusted Cost 29,262.64

PREPAINTED METAL SHEETS


1014 (1) b2 Prepainted Metal Sheet (above 0.427mm/Rib Type/Long Span)
Qty: 626.94 lin.m

Materials
626.94 lin.m Prepainted Metal Sheet @ 480.00 / lin.m P 300,931.20
(above 0.427mm/Rib Type/Long Span)
300,931.20

Labor (20% of Equipment) P 60,186.24

Direct Cost P 361,117.44


Indirect Cost (20%) 72,223.49
VAT (12%) 52,000.91
Total Cost 485,341.84
Unit Cost 774.14
Adjusted Cost 485,341.84
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

CEMENT FLOOR FINISH


1021 (3) a Floor Topping (Plain) (with Mesh Wire)
Qty: 279.50 sq.m

Materials
279.50 sq.m Floor Topping (Plain) @ 180.00 / sq.m P 50,310.00
(with Mesh Wire)
50,310.00

Labor (20% of Equipment) P 10,062.00

Direct Cost P 60,372.00


Indirect Cost (20%) 12,074.40
VAT (12%) 8,693.57
Total Cost 81,139.97
Unit Cost 290.30
Adjusted Cost 81,139.97

1021 (1) c Cement Floor Finish (with Floor Hardener)


Qty: 466.50 sq.m

Materials
466.50 sq.m Cement Floor Finish @ 200.00 / sq.m P 93,300.00
(with Floor Hardener)
93,300.00

Labor (20% of Equipment) P 18,660.00

Direct Cost P 111,960.00


Indirect Cost (20%) 22,392.00
VAT (12%) 16,122.24
Total Cost 150,474.24
Unit Cost 322.56
Adjusted Cost 150,474.24

CEMENT PLASTER FINISH/DECORATIVE STONE


1027 (1) Cement Plaster Finish
Qty: 16.40 sq.m

Materials
6.00 bag Cement @ 265.00 / bag P 1,590.00
1.00 cu.m Sand @ 850.00 / cu.m 850.00
1,590.00

Labor (20% of Equipment) P 318.00

Direct Cost P 1,908.00


Indirect Cost (20%) 381.60
VAT (12%) 274.75
Total Cost P 2,564.35
Unit Cost P 156.36
Adjusted Cost 2,564.35
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

PAINTING, VARNISHING AND OTHER RELATED WORKS


411(2) Paint (Rubberized Paint)
Qty: 466.50 sq.m

Materials
76.00 gal Rubberized Paint @ 630.00 / gal P 47,880.00
47,880.00

Labor (20% of Equipment) P 9,576.00

Direct Cost P 57,456.00


Indirect Cost (20%) 11,491.20
VAT (12%) 8,273.66
Total Cost P 77,220.86
Unit Cost P 165.53
Adjusted Cost 77,220.86

1032 (1) a Painting Works (Masonry/Concrete)


Qty: 12.00 sq.m

Materials
2.00 ltr Concrete Neutralizer @ 105.00 / ltr P 210.00
14.00 gal Latex, Flat @ 578.00 / gal P 8,092.00
2.00 gal Masonry Putty @ 420.00 / gal P 840.00
2.00 gal Latex,Semi Gloss @ 578.00 / gal P 1,156.00
2.00 gal Acri Color @ 90.00 / gal P 180.00
1.00 qrt Paint Thinner @ 362.00 / qrt 362.00
1.00 pc Paint roller with Tray @ 90.00 / pc P 90.00
10,930.00

Labor (20% of Equipment) P 1,660.40

Direct Cost P 12,590.40


Indirect Cost (20%) 2,518.08
VAT (12%) 1,813.02
Total Cost 16,921.50
Unit Cost 1,410.12
Adjusted Cost 16,921.50

1032 (1) c Painting Works (Steel)


Qty: 424.60 lin.m

Materials
72.00 ltr Epoxy Paint @ 550.00 / ltr P 39,600.00
64.00 gal Red Oxide @ 580.00 / gal P 37,120.00
49.00 gal Roofing Paint @ 420.00 / gal P 20,580.00
7.00 gal Paint Thinner @ 362.00 / gal P 2,534.00
7.00 pc Paint Roller with Tray @ 90.00 / pc P 630.00
100,464.00

P 15,344.00

Labor (20% of Equipment) Direct Cost P 115,808.00


Indirect Cost (20%) 23,161.60
VAT (12%) 16,676.35
Total Cost 155,645.95
Unit Cost 366.57
Adjusted Cost 155,645.95
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

METAL STRUCTURES
403(4)a1 Structural Steel Furnished, Fabricated (Grade 36) (Steel Bleachers)
Qty: 667.70 kgs

Materials
667.70 kgs Steel Bleachers @ 180.00 / kgs P 120,186.00
120,186.00

Labor (20% of Equipment) P 24,037.20

Direct Cost P 144,223.20


Indirect Cost (20%) 28,844.64
VAT (12%) 20,768.14
Total Cost P 193,835.98
Unit Cost P 290.30
Adjusted Cost 193,835.98

1047 (1) Structural Steel (Hanging Goal)


Qty: 1.00 l.s

Materials
1.00 l.s Structural Steel (Hanging Goal) @ 20,000.00 / l.s P 20,000.00
20,000.00

Labor (20% of Equipment) P 4,000.00

Direct Cost P 24,000.00


Indirect Cost (20%) 4,800.00
VAT (12%) 3,456.00
Total Cost P 32,256.00
Unit Cost P 32,256.00
Adjusted Cost 32,256.00

1047 (2) a Structural Steel (Trusses)


Qty: 3292.67 kgs

Materials
3292.67 kgs Structural Steel (Trusses) @ 65.00 / kgs P 214,023.55
214,023.55

Labor (20% of Equipment) P 42,804.71

Direct Cost P 256,828.26


Indirect Cost (20%) 51,365.65
VAT (12%) 36,983.27
Total Cost P 345,177.18
Unit Cost P 104.83
Adjusted Cost 345,177.18
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

1047 (2) b Structural Steel (Purlins)


Qty: 2,095.76 kgs

Materials
2095.76 kgs 150x50x20x2.0mm @ 75.00 / kgs P 157,182.00
27.00 gal Red Lead @ 200.00 / gal P 5,400.00
12.00 gal Welding Rod @ 100.00 / gal P 1,200.00
163,782.00

Labor (20% of Equipment) P 240.00

Direct Cost P 164,022.00


Indirect Cost (20%) 32,804.40
VAT (12%) 23,619.17
Total Cost P 220,445.57
Unit Cost P 105.19
Adjusted Cost 220,445.57

1047 (7) b Structural Steel Accessories (Sagrods)


Qty: 71.80 each

Materials
71.80 each Metal Structure Accessories @ 150.00 / each P 10,770.00
(Sagrods) 10,770.00

Labor (20% of Equipment) P 2,154.00

Direct Cost P 12,924.00


Indirect Cost (20%) 2,584.80
VAT (12%) 1,861.06
Total Cost P 17,369.86
Unit Cost P 241.92
Adjusted Cost 17,369.86

1047 (3) c Structural Steel Accessories (Turnbuckle)


Qty: 16.00 each

Materials
16.00 each Standard Turnbuckle @ 180.00 / each P 2,880.00
(Sagrods) 2,880.00

Labor (20% of Equipment) P 576.00

Direct Cost P 3,456.00


Indirect Cost (20%) 691.20
VAT (12%) 497.66
Total Cost P 4,644.86
Unit Cost P 290.30
Adjusted Cost 4,644.86
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

1047 (4) Structural Steel Accessories (Cross Bracing)


Qty: 151.49 kgs

Materials
151.49 kgs Cross Bracing 16mmØ @ 45.00 / kgs P 6,817.05
6,817.05

Labor (20% of Equipment) P 1,363.41

Direct Cost P 8,180.46


Indirect Cost (20%) 1,636.09
VAT (12%) 1,177.99
Total Cost P 10,994.54
Unit Cost P 72.58
Adjusted Cost 10,994.54

1047 (6) Metal Structure Accessories (Steel Plates)


Qty: 137.06 kgs

Materials
137.06 kgs Steel Plate @ 45.00 / kgs P 6,167.70
4.00 gal Red Lead @ 399.00 / gal P 1,596.00
7,763.70

Labor (20% of Equipment) P 1,552.74

Direct Cost P 9,316.44


Indirect Cost (20%) 1,863.29
VAT (12%) 1,341.57
Total Cost P 12,521.30
Unit Cost P 91.36
Adjusted Cost 12,521.30
1047 (7) a Metal Structure Accessories (Bolts)
Qty: 36.96 each

Materials
36.96 each Bolts @ 100.00 / each P 3,696.00
4.00 gal Red Lead @ 399.00 / gal P 1,596.00
5,292.00

Labor (20% of Equipment) P 1,058.40

Direct Cost P 6,350.40


Indirect Cost (20%) 1,270.08
VAT (12%) 914.46
Total Cost P 8,534.94
Unit Cost P 230.92
Adjusted Cost 8,534.94
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

1048 Glass Fiber (Basketball Goal Board and Its Accessories)


Qty: 1.00 l.s

Materials
1.00 l.s Glass Fiber (Basketball Goal @ 35,000.00 / l.s P 35,000.00
Board and Its 35,000.00
Accessories
Labor (20% of Equipment) P 7,000.00

Direct Cost P 42,000.00


Indirect Cost (20%) 8,400.00
VAT (12%) 6,048.00
Total Cost P 56,448.00
Unit Cost P 56,448.00
Adjusted Cost 56,448.00
PART D ELECTRICAL
CONDUITS, BOXES & FITTINGS (CONDUIT WORKS/ CONDUIT ROUGH-IN)
1100 (10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in)
Qty: 1.00 l.s

Materials
1.00 l.s Conduits, Boxes & Fittings @ 90,000.00 / l.s P 90,000.00
(Conduit Works/Conduit Rough-in) 90,000.00

Labor (20% of Equipment) P 18,000.00

Direct Cost P 108,000.00


Indirect Cost (20%) 21,600.00
VAT (12%) 15,552.00
Total Cost P 145,152.00
Unit Cost P 145,152.00
Adjusted Cost 145,152.00

WIRES AND WIRING DEVICES


1101 (33) Wires and Wiring Devices
Qty: 1.00 l.s

Materials
1.00 l.s Wires and Wiring Devices @ 85,400.00 / l.s P 85,400.00
85,400.00

Labor (20% of Equipment) P 17,080.00

Direct Cost P 102,480.00


Indirect Cost (20%) 20,496.00
VAT (12%) 14,757.12
Total Cost P 137,733.12
Unit Cost P 137,733.12
Adjusted Cost 137,733.12
DETAILED ESTIMATES
Contact I.D: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00
Contractor: Bill Hill Construction & Supply

LIGHTING FIXTURES AND LAMPS


1101 (1) Lighting Fixtures and Lamps
Qty: 1.00 l.s

Materials
1.00 l.s Lighting Fixtures and Lamps @ 23,500.00 / l.s P 23,500.00
23,500.00

Labor (20% of Equipment) P 4,700.00

Direct Cost P 28,200.00


Indirect Cost (20%) 5,640.00
VAT (12%) 4,060.80
Total Cost P 37,900.80
Unit Cost P 37,900.80
Adjusted Cost 37,900.80

POWER LOAD CENTER, DWITCHGEAR AND PANELBOARDS,


AND OTHER OVERCURRENT PROTECTION DEVICES
1102(1) Panelboard with Main & Branch Breakers
Qty: 1.00 l.s

Materials
1.00 l.s Panelboard with Main @ 9,000.00 / l.s P 9,000.00
and Branch Breakers 9,000.00

Labor (20% of Equipment) P 1,800.00

Direct Cost P 10,800.00


Indirect Cost (20%) 2,160.00
VAT (12%) 1,555.20
Total Cost P 14,515.20
Unit Cost P 14,515.20
Adjusted Cost 14,515.20

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0211
Contract Name: Construction of Multi-Purpose Building,
Mudiang ES, Brgy. Mudiang, Davao City
ABC: Php. 3,960,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 117 Calendar Days


ABC: 3,960,000.00
Part No. Part Description Total Amount
PART II OTHER GENERAL REQUIREMENTS
PART B OTHER GENERAL REQUIREMENTS
B.3 Permits and Clearances 12,768.00
B.5 Project Billboard/Signboard (4"x8" DPWH/8"x8" COA Billboard) 11,289.60
B.7 (2) Occupational Safety and Health Program 32,928.00
B.9 Mobilization/Demobilization 30,240.00
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMB
PART A EARTHWORKS
803 STRUCTURE EXCAVATION
803 (1) a Structure Excavation (Common Soil) 29,837.00
804 EMBANKMENT
804 (4) Gravel Fill 60,419.52
PART B PLAIN AND REINFORCED CONCRETE WORKS
900 REINFORCED CONCRETE
900 (1) b2 Structural Concrete (Footing and Slab on Fill) (Class A,14 days) 381,462.00
900 (1) c3 Structural Concrete (Footing Tie beam) (Class A,28 days ) 58,877.91
900 (1) c4 Structural Concrete (Columns) ( Class A,28 days ) 92,136.59
902 REINFORCING STEEL
902 (1) a Reinforcing Steel(Deformed) - Grade 40 307,574.38
902 (1) b Reinforcing Steel(Deformed) - Grade 60 101,467.00
903 FORMWORKS AND FALSEWORKS
903 (2) Formworks and Falseworks 112,360.14
PART C FINISHINGS AND OTHER CIVIL WORKS
1000 TERMITE CONTROL WORK
1000 (1) Soil Poisoning 4,838.40
TOTAL OF THIS PAGE 1,236,198.54

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0211
Contract Name: Construction of Multi-Purpose Building,
Mudiang ES, Brgy. Mudiang, Davao City
ABC: Php. 3,960,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 117 Calendar Days


ABC: 3,960,000.00
Part No. Part Description Total Amount
1001 STORM DRAINAGE AND SEWERAGE SYSTEM
1001 (5) a Catch Basin (Concrete) 49,351.68
1001 (9) Storm Drainage and Downspout 40,320.00
1013 CORRUGATED METAL ROOFING
1013 (2) a2 Fabricated Metal Roofing Accessory (Flashings) (Gauge 26) 29,378.36
1013 (2) b1 Fabricated Metal Roofing Accessory (Gutter) Gauge 24 28,901.12
1014 PREPAINTED METAL SHEETS
1014 (1) b2 Prepainted Metal Sheets (Rib T ype-Long Span,above 0.427mm thk) 506,117.25
1021 CEMENT FLOOR FINISH
1021 (1) c Cement Floor Finish (with Floor Hardener) 145,152.00
1027 CEMENT PLASTER FINISH/DECORATIVE STONE
1027 (1) Cement Plaster Finish 13,249.44
1032 PAINTING, VARNISHING AND OTHER RELATED WORKS
411 (2) Paint (Rubberize Paint) 74,173.50
1032 (1) a Painting Works (Masonry/Concrete) 31,003.78
1032 (1) c Painting Works (Steel) 123,319.18
1047 METAL STRUCTURES
1047 (2) a Structural Steel (trusses) 673,753.94
1047 (2) b Structural Steel (Purlins) 376,251.76
1047 (7) b Metal Structure Accessories (Sagrods) 26,998.27
1047 (3) c Metal Structure Accessories (Turnbuckle) 5,806.00
1047 (4) Metal Structure Accessories (Cross Bracing) 20,615.62
1047 (6) Metal Structure Accessories (Steel Plates) 48,080.04
1047 (7) a Metal Structure Accessories (Bolts) 48,080.04
1,048.00 Glass Fiber (Basketball Goal Board and Its Accessories) 154,828.80
TOTAL OF THIS PAGE 2,395,380.78

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0211
Contract Name: Construction of Multi-Purpose Building,
Mudiang ES, Brgy. Mudiang, Davao City
ABC: Php. 3,960,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 117 Calendar Days


ABC: 3,960,000.00
Part No. Part Description Total Amount
PART D ELECTRICAL
1,100.00 CONDUITS,BOXES & FITTINGS (CONDUIT WORKS/CONDUIT ROUG
1100 (10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in) 101,283.84
1,101.00 WIRESAND WIRING DEVICES
1101 (33) Wires and Wiring Devices 137,733.12
1,103.00 LIGHTING FIXTURES AND LAMPS
1103 (1) Lighting Fixtures and Lamps 36,288.00
1,103.00 POWER LOAD CENTER, SWITCHGEAR AND PANELBOARDS,
1102 (1) Panelboard with Main & Branch Breakers 13,870.08
TOTAL OF THIS PAGE 289,175.04
Total of All Amounts in Words: GRAND TOTAL 3,920,754.36

Three Million Nine Hundred Twenty Thousand Seven Hundred Fifty Four and Thirty Six Cents

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Description Unit Quantity Unit Price Amount


No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
OTHER GENERAL REQUIREMENTS
In words: Pesos In words: Pesos
Twelve Thousand Twelve Thousand
Seven Hundred Seven Hundred Sixty-
B.3 Permits and Clearances l.s 1.00 Sixty-Eight Eight

In figures: PhP In figures: PhP


12,768.00 12,768.00
In words: Pesos In words: Pesos
Five Thousand Six Eleven Thousand Two
Project Billboard/Signboard (4"x8" Hundred Forty-Four Hundred Eight-Nine and
B.5 each 2.00 and Eighty Cents Sixty Cents
DPWH/8"x8" COA Billboard)
In figures: PhP In figures: PhP
5,644.80 11,289.60
In words: Pesos In words: Pesos
Thirty-Two Thousand
Nine Hundred Twenty- Thirty-Two Thousand
Occupational Safety and Health Eight Nine Hundred Twenty-
B.7 (2) l.s 1.00 Eight
Program
In figures: PhP In figures: PhP
32,928.00 32,928.00
In words: Pesos In words: Pesos
Thirty Thousand
Thirty Thousand and
Two Hundred
B.9 Mobilization/Demobilization l.s 1.00 Two Hundred Forty
Forty

In figures: PhP In figures: PhP


30,240.00 30,240.00
SUB TOTAL FOR THIS PAGE 81,580.80 87,225.60

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
803 STRUCTURE EXCAVATION In words: Pesos In words: Pesos
Twenty-Nine
Four Hundred
Thousand Eight
65.70 Fifty-Four and
Hundred Thirty-
803 (1) a Structure Excavation (Common Soil) Fourteen Cents
cu.m Seven

In figures: PhP In figures: PhP


454.14 29,837.00
804 EMBANKMENT In words: Pesos In words: Pesos
One Thousand Two Sixty Thousand Four
Hundred Nine and Hundred Nineteen
49.95 Sixty Cents and Fifty-Two Cents

cu.m In figures: PhP In figures: PhP


804 (4) Gravel Fill 1,209.60 60,419.52
PART B PLAIN AND REINFORCED CONCRETE WORKS In words: Pesos In words: Pesos
900 REINFORCED CONCRETE Seven Thousand Three Hundred Eighty-
Five and Seventy- One Four Hundred Sixty-
Three Cents Two
54.45
cu.m In figures: PhP In figures: PhP
Structural Concrete (Footing and Slab 7,005.73 381,462.00
900 (1) b2 on Fill) (Class A,14 days)
In words: Pesos In words: Pesos
Six Thousand Five Fifty-Eight Thousand
Hundred Forty-One Eight Hundred Seventy-
Structural Concrete (Footing Tie and ninety-Nine Seven and Ninety-One
900 (1) c3 cu.m 9.00
beam) (Class A,28 days ) Cents Cents

In figures: PhP In figures: PhP


6,541.99 58,877.91
SUB TOTAL FOR THIS PAGE 15,211.46 530,596.43

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit
No. (Pesos) (Pesos)
(1) (2) (3) (5) (6)
In words: Pesos In words: Pesos
Seven Thousand Eighty- Ninety-Two Thousand One
Seven and Forty-Three Hundred Thirty-Six and
Structural Concrete (Columns) ( Class Cents Fifty-Nine Cents
900 (1) c4 cu.m 13.00
A,28 days ) In figures: PhP In figures: PhP
7,087.43 92,136.59
902 REINFORCING STEEL In words: Pesos In words: Pesos
Three Hundred Seven
Seventy and Thousand Five Hundred
4,382.65 Eighteen Cents Seventy-Four and Thirty-
kgs Eight Cents
902 (1) a Reinforcing Steel(Deformed) - Grade
40 In figures: PhP In figures: PhP
70.18 307,574.38
In words: Pesos In words: Pesos
Eighty-Five and One Hundred One Thousand
Reinforcing Steel(Deformed) - Grade Forty-Two Cents four Hundred Sixty-Seven
902 (1) b 1,187.86
60 kgs In figures: PhP In figures: PhP
85.42 101,467.00
903 FORMWORKS AND FALSEWORKS In words: Pesos In words: Pesos
One Hundred Twelve
Nine Hundred
Thousand Three
Seventy-Two and
sq.m 115.56 Thirty-One Cents
Hundred Sixty and
Fourteen Cents
903 (2) Formworks and Falseworks
In figures: PhP In figures: PhP
972.31 112,360.14
PART C FINISHING AND OTHER CIVIL WORKS In words: Pesos In words: Pesos
1000 TERMITE CONTROL WORK Four Thousand Eight
Eight Hundred Six
Hundred Thirty-Eight
and Forty Cents
Liters 6.00 and Forty Cents
1000 (1) Soil Poisoning In figures: PhP In figures: PhP
806.40 4,838.40
SUB TOTAL FOR THIS PAGE 9,021.74 618,376.51

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
1001 STORM DRAINAGE AND SEWERAGE SYSTEM In words: Pesos In words: Pesos
Four Thousand Forty-Nine Thousand
One Hundred Three Hundred Fifty-
Twelve and Sixty- One and Sixty-Eight
12.00 Four Cents Cents
Catch Basin (Concrete) each
1001 (5) a In figures: PhP In figures: PhP
4,112.64 49,351.68
In words: Pesos In words: Pesos
Forty Thousand Forty Thousand and
and Three Three Hundred
1001 (9) Storm Drainage and Downspout l.s 1.00 Hundred Twenty Twenty

In figures: PhP In figures: PhP


40,320.00 40,320.00
1013 CORRUGATED METAL ROOFING In words: Pesos In words: Pesos
Twenty Nine Thousand
Two Hundred Ninety Three Hundred Seventy
101.20 and Thirty Cents Eight and Thirty-Six
Cents
lin.m
Fabricated Metal Roofing Accessory In figures: PhP In figures: PhP
1013 (2) a2 (Flashings) (Gauge 26)
290.30 29,378.36
SUB TOTAL FOR THIS PAGE 45,948.66 654,068.41

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos
Four Hundred Twenty-Eight Thousand
Fabricated Metal Roofing Accessory Fifty-One and Nine Hundred One and
1013 (2) b1 lin.m 64.00 Fifty-Eight Cents Twelve Cents
(Gutter) Gauge 24
In figures: PhP In figures: PhP
451.58 28,901.12
1014 PREPAINTED METAL SHEETS In words: Pesos In words: Pesos
Five Hundred Six
Seven Hundred
Thousand One Hundred
Seventy-Four and
653.78 Seventeen and Twenty-
Fourteen Cents Five Cents
sq.m
Prepainted Metal Sheets (Rib T ype- In figures: PhP In figures: PhP
1014 (1) b2 Long Span,above 0.427mm thk)
774.14 506,117.25
1021 CEMENT FLOOR FINISH In words: Pesos In words: Pesos
Twenty-Seven
Three Hundred
Thousand Eight
Twenty-Two and
450.00 Hundred Sixty-Nine
Fifty-Six Cents
and Eighteen Cents
sq.m
1021 (1) c Cement Floor Finish (with Floor
In figures: PhP In figures: PhP
Hardener)
322.56 145,152.00
1027 CEMENT PLASTER FINISH/DECORATIVE STONE In words: Pesos In words: Pesos
Thirteen Thousand
One Hundred Fifty-
Two Hundred Forty-
Three and thirty-
Nine and Forty-Four
Five Cents
Cement Plaster Finish sq.m 86.40 Cents
1027 (1)
In figures: PhP In figures: PhP
153.35 13,249.44
SUB TOTAL FOR THIS PAGE 1,362.70 386,897.90

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
1032 PAINTING, VARNISHING AND OTHER RELATED WORIn words: Pesos In words: Pesos
Seventy-Four
One Hundred Sixty
Thousand One
Four and Eighty-
Hundred Seventy-
Three Cents
450.00 Three and Fifty Cents
Paint (Rubberize Paint) sq.m
In figures: PhP In figures: PhP
411 (2)
164.83 74,173.50
In words: Pesos In words: Pesos

Three Hundred Thirty-One Thousand


Fifty-Eight and Three and Seventy-
1032 (1) a Painting Works (Masonry/Concrete) 86.40 Eighty-Four Cents Eight Cents
sq.m
In figures: PhP In figures: PhP
358.84 31,003.78
In words: Pesos In words: Pesos
Three Hundred One Hundred Twenty-Three
Thousand Three Hundred
Sixty-Three and Nineteen and Eighteen
Painting Works (Steel) sq.m 339.61 Twelve Cents Cents

In figures: PhP In figures: PhP


363.12 123,319.18
1047 METAL STRUCTURES In words: Pesos In words: Pesos
Six Hundred Seventy-
One Hundred Four
Three Thousand Seven
and Eighty-Three
6,427.11 Hundred Fity-Three and
Cents
Ninety-Four Cents
kgs
1047 (2) a Structural Steel (trusses) In figures: PhP In figures: PhP
104.83 673,753.94
SUB TOTAL FOR THIS PAGE 814.74 1,103,425.59

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos
Three Hundred Seventy-
One Hundred Five Six Thousand Two
and Eleven Cents Hundred Fifty-One and
1047 (2) b Structural Steel (Purlins) 3,579.60
kgs Seventy-Six Cents

In figures: PhP In figures: PhP


105.11 376,251.76
In words: Pesos In words: Pesos
Twenty-Six Thousand
Two Hundred Forty-
Nine Hundred Ninety-
Metal Structure Accessories One and Ninety-Two
Eight and Twenty-Seven
1047 (7) b each 111.60 Cents
(Sagrods) Cents
In figures: PhP In figures: PhP
241.92 26,998.27
In words: Pesos In words: Pesos
Two Hundred
Five Thousand Eight
Metal Structure Accessories Ninety and Thirty
Hundred Six
1047 (3) c each 20.00 Cents
(Turnbuckle)
In figures: PhP In figures: PhP
290.30 5,806.00
In words: Pesos In words: Pesos
Twenty Thousand Six
Seventy-Two and
Metal Structure Accessories (Cross Fifty-Eight Cents
Hundred Fifteen and
1047 (4) kgs 284.04 Sixty-Two Cents
Bracing)
In figures: PhP In figures: PhP
72.58 20,615.62
SUB TOTAL FOR THIS PAGE 101,590.88 164,256.61

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos
Eighty-Nine and Forty-Eight Thousand
Metal Structure Accessories (Steel thirty-One Cents Eighty and Four Cents
1047 (6) Plates) kgs 538.35
In figures: PhP In figures: PhP
89.31 48,080.04
In words: Pesos In words: Pesos
Two Hundred Fourteen Thousand
Seventeen and Eight Hundred
1047 (7) a Metal Structure Accessories (Bolts) kgs 68.40 Seventy-Three Ninety_Two and
Cents Seventy-Three Cents

In figures: PhP In figures: PhP


217.73 14,892.73
In words: Pesos In words: Pesos
One Hundred Fifty-Four One Hundred Fifty-Four
Thousand eight hundred Thousand eight hundred
Glass Fiber(Basketball Goal Board and Twenty-Eight and Eighty Twenty-Eight and Eighty
1048 l.s 1.00 Cents
Its Accessories) Cents

In figures: PhP In figures: PhP


154,828.80 154,828.80
PART D ELECTRICAL
1100 CONDUITS,BOXES & FITTINGS (CONDUIT WORKS/CONDUIT ROUGH-IN)
In words: Pesos In words: Pesos
One Hundred One One Hundred One
Thousand Two Hundred Thousand Two Hundred
Eighty-Three and Eighty-Three and Eighty-
l.s 1.00
Conduits, Boxes & Fittings (Conduit Eighty-Four Cents Four Cents
Works/Conduit Rough-in) In figures: PhP In figures: PhP
1100 (10)
101,283.84 101,283.84
SUB TOTAL FOR THIS PAGE 256,419.68 319,085.41

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 192LB0210
Contract Name: Construction/Completion of Multi-Purpose Building,
Cabantian ES, Brgy. Cabantian, Davao City
ABC: Php. 2,970,000.00
Location of the Contract: Davao City
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
1101 WIRESAND WIRING DEVICES In words: Pesos In words: Pesos
One Hundred Thirty- One Hundred Thirty-
Seven Thousand Seven Seven Thousand Seven
Hundred Thirty-Three Hundred Thirty-Three
1.00 and Twelve Cents and Twelve Cents

l.s In figures: PhP In figures: PhP


1101 (33) Wires and Wiring Devices 137,733.12 137,733.12
1103 LIGHTING FIXTURES AND LAMPS In words: Pesos In words: Pesos
Thirty-Six
Thirty-Six Thousand
Thousand Two
Two Hundred Eighty-
1.00 Hundred Eighty-
Eight
Eight
Lighting Fixtures and Lamps l.s
1103 (1) In figures: PhP In figures: PhP
36,288.00 36,288.00
1103 POWER LOAD CENTER, SWITCHGEAR AND PANELBOARDS, AND OTHER OVERCURRENT
In words: Pesos In words: Pesos
Thirteen Thousand
Thirteen Thousand Eight
Eight Hundred
Hundred Seventy and
1.00 Seventy and Eight
Eight Cents
Cents
Panelboard with Main & Branch l.s
In figures: PhP In figures: PhP
1102 (1) Breakers In 13,870.08
figures: PhP In 13,870.08
figures: PhP
SUB TOTAL FOR THIS PAGE 187,891.20 187,891.20

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

Part B
B.3 Permits and Clearances
Qty: 1.0 l.s

1.00 l.s Permits and Clearances 9,500.00 / l.s P 9,500.00

Direct Cost P 9,500.00


Indirect Cost (20%) 1,900.00
VAT (12%) 1,368.00
Total Cost P 12,768.00
Unit Cost P 12,768.00
Adjusted Cost 12,768.00

B.5 Projects Billboard/Signboard (4'x8' DPWH Billboard/8'x8' COA Billboard)


Qty: 2.0 each
Projects
2.00 each Billboard/Signboard 4,200.00 / each P 8,400.00
(4'x8' DPWH
Billboard/8'x8' COA Direct Cost P 8,400.00
Billboard) Indirect Cost (20%) 1,680.00
VAT (12%) 1,209.60
Total Cost P 11,289.60
Unit Cost P 5,644.80
Adjusted Cost 5,644.80

B.7 (2) Occupational Health and Safety


Qty: 1.0 l.s

1.00 l.s 24,500.00 / l.s P 24,500.00


Occupational Health and
Safety
Direct Cost P 24,500.00
Indirect Cost (20%) 4,900.00
VAT (12%) 3,528.00
Total Cost P 32,928.00
Unit Cost P 32,928.00
Adjusted Cost 32,928.00
B.9 Mobilization/Demobilization
Qty: 1.0 l.s

1.00 l.s 22,400.00 / l.s P 22,400.00


Mobilization/Demobilization
Direct Cost P 22,400.00
Indirect Cost (20%) 4,480.00
VAT (12%) 3,225.60
Total Cost P 30,105.60
Unit Cost P 30,105.60
Adjusted Cost 30,105.60
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

EARTHWORKS

803 (1) a Structure Excavation (Common Soil)


Qty: 65.70 cu.m

Equipment
1.00 unit 1 day Dump Truck @ 7,500.00 / unit P 7,500.00
1.00 unit 1 day Backhoe @ 11,000.00 / unit P 11,000.00

Labor (20% of Equipment) P 3,700.00

Direct Cost P 22,200.00


Indirect Cost (20%) 4,440.00
VAT (12%) 3,196.80
Total Cost 29,836.80
Unit Cost 454.14
Adjusted Cost 29,836.80
804 (4) Gravel Fill
Qty: 10.85 cu.m

Materials
10.85 cu.m Fill Materials @ 750.00 / cu.m P 8,137.50

Labor (20% of Equipment) P 1,627.50

Direct Cost P 9,765.00


Indirect Cost (20%) 1,953.00
VAT (12%) 1,406.16
Total Cost 13,124.16
Unit Cost 1,209.60
Adjusted Cost 13,124.16

PART B PLAIN AND REINFORCED CONCRETE WORKS


REINFORCED CONCRETE
900 (1) b2 Structural Concrete (Footings and Slab on Fill)(Class A-14days)
Qty: 54.45 cu.m

Materials
54.45 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 190,575.00
894.00 kg Reinforcing Steel Bar @ 40.00 / kg P 35,760.00
10.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 640.00
146.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 7,884.00
23.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 2,300.00
of Steel)
4.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 1,400.00
238,559.00

Labor (20% of Equipment) P 45,267.00

Direct Cost P 283,826.00


Indirect Cost (20%) 56,765.20
VAT (12%) 40,870.94
Total Cost 381,462.14
Unit Cost 7,005.73
Adjusted Cost 381,462.14
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

900 (1) b2 Structural Concrete (Footing Tie Beam)(Class A-28days)


Qty: 9.00 cu.m

Materials
9.00 cu.m Pre-Mix Concrete 3000Psi @ 3,100.00 / cu.m P 27,900.00
148.00 kg Reinforcing Steel Bar @ 40.00 / kg P 5,920.00
2.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 128.00
24.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 1,296.00
4.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 400.00
of Steel)
4.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 1,400.00
37,044.00

Labor (20% of Equipment) P 6,764.00

Direct Cost P 43,808.00


Indirect Cost (20%) 8,761.60
VAT (12%) 6,308.35
Total Cost 58,877.95
Unit Cost 6,541.99
Adjusted Cost 58,877.95

900 (1) b2 Structural Concrete (Columns)(Class A-28days)


Qty: 13.00 cu.m

Materials
13.00 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 45,500.00
214.00 kg Reinforcing Steel Bar @ 40.00 / kg P 8,560.00
3.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 192.00
35.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 1,890.00
5.50 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 550.00
of Steel)
3.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 1,050.00
57,742.00

Labor (20% of Equipment) P 10,812.00

Direct Cost P 68,554.00


Indirect Cost (20%) 13,710.80
VAT (12%) 9,871.78
Total Cost 92,136.58
Unit Cost 7,087.43
Adjusted Cost 92,136.58
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

REINFORCING STEEL
REINFORCED CONCRETE
902 (1) a Reinforcing Steel (Deformed) Grade 40
Qty: 4,382.65 kgs

Materials
1.00 unit 7 day Bar Bender @ 2,200.00 / unit P 15,400.00
15,400.00

Materials
4,382.65 kgs Reinforming Steel @ 40.00 / kgs P 175,306.00
Deformed (Grade 40) 175,306.00

Labor (20% of Equipment) P 38,141.20

Direct Cost P 228,847.20


Indirect Cost (20%) 45,769.44
VAT (12%) 32,954.00
Total Cost 307,570.64
Unit Cost 70.18
Adjusted Cost 307,570.64

902 (1) a Reinforcing Steel (Deformed) Grade 60


Qty: 1,187.86 kgs

Materials
1.00 unit 7 day Bar Bender @ 2,200.00 / unit P 15,400.00
15,400.00

Materials
1,187.86 kgs Reinforming Steel @ 40.00 / kgs P 47,514.40
Deformed (Grade 40) 47,514.40

Labor (20% of Equipment) P 12,582.88

Direct Cost P 75,497.28


Indirect Cost (20%) 15,099.46
VAT (12%) 10,871.61
Total Cost 101,468.34
Unit Cost 85.42
Adjusted Cost 101,468.34

FORMWORKS AND FALSEWORKS


903 (2) Formworks and Falseworks
Qty: 115.56 cu.m

Materials
111.00 pc Fiber Cement Board @ 450.00 / pc P 49,950.00
423.00 bd.ft Wood Frame @ 45.00 / bd.ft P 19,035.00
13.00 kg Nails @ 63.00 / kg P 819.00
69,804.00

P 13,797.00

Direct Cost P 83,601.00


Indirect Cost (20%) 16,720.20
Labor (20% of Equipment) VAT (12%) 12,038.54
Total Cost 112,359.74
Unit Cost 972.31
Adjusted Cost 112,359.74
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

PART C FINISHING AND OTHER CIVIL WORKS


1000 TERMITE CONTROL WORK
Qty: 6.00 Liters

Materials
6.00 Liters Soil poisoning @ 500.00 / Liters P 3,000.00
3,000.00

Labor (20% of Equipment) P 600.00

Direct Cost P 3,600.00


Indirect Cost (20%) 720.00
VAT (12%) 518.40
Total Cost 4,838.40
Unit Cost 806.40
Adjusted Cost 4,838.40

STORM DRAINAGE AND SEWERAGE SYSTEM


1001 (5) b Catch Basin (Concrete)
Qty: 12.00 each

Materials
12.00 each Catch Basin (CHB) @ 2,550.00 / each P 30,600.00
30,600.00

Labor (20% of Equipment) P 6,120.00

Direct Cost P 36,720.00


Indirect Cost (20%) 7,344.00
VAT (12%) 5,287.68
Total Cost 49,351.68
Unit Cost 4,112.64
Adjusted Cost 49,351.68

1001 (9) Storm Drainage and Downspout


Qty: 1.00 l.s

Materials
1.00 l.s Storm Draiange & Downspout @ 25,000.00 / l.s P 25,000.00
25,000.00

Labor (20% of Equipment) P 5,000.00

Direct Cost P 30,000.00


Indirect Cost (20%) 6,000.00
VAT (12%) 4,320.00
Total Cost 40,320.00
Unit Cost 40,320.00
Adjusted Cost 40,320.00
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

CORRUGATED METAL ROOFING


1013 (2) a2 Fabricated Metal Roofing Accessory (Flashing) (Gauge 26)
Qty: 101.20 lin.m

Materials
101.20 lin.m Flashing @ 180.00 / lin.m P 18,216.00
506.00 pc Rivets @ 0.70 / pc 354.20
18,216.00

Labor (20% of Equipment) P 3,643.20

Direct Cost P 21,859.20


Indirect Cost (20%) 4,371.84
VAT (12%) 3,147.72
Total Cost 29,378.76
Unit Cost 290.30
Adjusted Cost 29,378.76

1013 (2) b1 Fabricated Metal Roofing Accessory (Gutter) (Gauge 24)


Qty: 64.00 lin.m

Materials
64.00 lin.m Gutter @ 280.00 / lin.m P 17,920.00
320.00 pc Rivets @ 0.70 / pc 224.00
17,920.00

Labor (20% of Equipment) P 3,584.00

Direct Cost P 21,504.00


Indirect Cost (20%) 4,300.80
VAT (12%) 3,096.58
Total Cost 28,901.38
Unit Cost 451.58
Adjusted Cost 28,901.38

PREPAINTED METAL SHEETS


1014 (1) b2 Prepainted Metal Sheet (above 0.427mm/Rib Type/Long Span)
Qty: 653.78 lin.m

Materials
653.78 lin.m Prepainted Metal Sheet @ 480.00 / lin.m P 313,814.40
(above 0.427mm/Rib Type/Long Span)
313,814.40

Labor (20% of Equipment) P 62,762.88

Direct Cost P 376,577.28


Indirect Cost (20%) 75,315.46
VAT (12%) 54,227.13
Total Cost 506,119.86
Unit Cost 774.14
Adjusted Cost 506,119.86
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

CEMENT FLOOR FINISH


1021 (1) c Cement Floor Finish (with Floor Hardener)
Qty: 450.00 sq.m

Materials
450.00 sq.m Prepainted Metal Sheet @ 200.00 / sq.m P 90,000.00
(above 0.427mm/Rib Type/Long Span)
90,000.00

Labor (20% of Equipment) P 18,000.00

Direct Cost P 108,000.00


Indirect Cost (20%) 21,600.00
VAT (12%) 15,552.00
Total Cost 145,152.00
Unit Cost 322.56
Adjusted Cost 145,152.00

CEMENT PLASTER FINISH/DECORATIVE STONE


1027 (1) Cement Plaster Finish
Qty: 86.40 sq.m

Materials
31.00 bag Cement @ 265.00 / bag P 8,215.00
4.50 cu.m Sand @ 850.00 / cu.m 3,825.00
8,215.00

Labor (20% of Equipment) P 1,643.00

Direct Cost P 9,858.00


Indirect Cost (20%) 1,971.60
VAT (12%) 1,419.55
Total Cost P 13,249.15
Unit Cost P 153.35
Adjusted Cost 13,249.15

PAINTING, VARNISHING AND OTHER RELATED WORKS


411(2) Paint (Rubberized Paint)
Qty: 450.00 sq.m

Materials
73.00 gal Rubberized Paint @ 630.00 / gal P 45,990.00
45,990.00

Labor (20% of Equipment) P 9,198.00

Direct Cost P 55,188.00


Indirect Cost (20%) 11,037.60
VAT (12%) 7,947.07
Total Cost P 74,172.67
Unit Cost P 164.83
Adjusted Cost 74,172.67
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

1032 (1) a Painting Works (Masonry/Concrete)


Qty: 86.40 sq.m

Materials
13.00 ltr Concrete Neutralizer @ 105.00 / ltr P 1,365.00
14.00 gal Latex, Flat @ 578.00 / gal P 8,092.00
12.00 gal Masonry Putty @ 420.00 / gal P 5,040.00
10.00 gal Latex,Semi Gloss @ 578.00 / gal P 5,780.00
9.00 gal Acri Color @ 90.00 / gal P 810.00
2 qrt Paint Thinner @ 362.00 / qrt 724.00
1.00 pc Paint roller with Tray @ 90.00 / pc P 90.00
21,901.00

Labor (20% of Equipment) P 1,891.40

Direct Cost P 23,792.40


Indirect Cost (20%) 4,758.48
VAT (12%) 3,426.11
Total Cost 31,976.99
Unit Cost 370.10
Adjusted Cost 31,976.99

1032 (1) c Painting Works (Steel)


Qty: 339.61 lin.m

Materials
57.00 ltr Epoxy Paint @ 550.00 / ltr P 31,350.00
51.00 gal Red Oxide @ 580.00 / gal P 29,580.00
39.00 gal Roofing Paint @ 420.00 / gal P 16,380.00
5.00 gal Paint Thinner @ 362.00 / gal P 1,810.00
5.00 pc Paint Roller with Tray @ 90.00 / pc P 450.00
79,570.00

P 12,186.00

Labor (20% of Equipment) Direct Cost P 91,756.00


Indirect Cost (20%) 18,351.20
VAT (12%) 13,212.86
Total Cost 123,320.06
Unit Cost 363.12
Adjusted Cost 123,320.06

METAL STRUCTURES
1047 (2) a Structural Steel (Trusses)
Qty: 6427.11 kgs

Materials
6427.11 kgs Structural Steel (Trusses) @ 65.00 / kgs P 417,762.15
417,762.15

Labor (20% of Equipment) P 83,552.43

Direct Cost P 501,314.58


Indirect Cost (20%) 100,262.92
VAT (12%) 72,189.30
Total Cost P 673,766.80
Unit Cost P 104.83
Adjusted Cost 673,766.80
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

1047 (2) b Structural Steel (Purlins)


Qty: 3,579.60 kgs

Materials
3579.60 kgs 150x50x20x2.0mm @ 75.00 / kgs P 268,470.00
46.00 gal Red Lead @ 200.00 / gal P 9,200.00
19.00 gal Welding Rod @ 100.00 / gal P 1,900.00
279,570.00

Labor (20% of Equipment) P 380.00

Direct Cost P 279,950.00


Indirect Cost (20%) 55,990.00
VAT (12%) 40,312.80
Total Cost P 376,252.80
Unit Cost P 105.11
Adjusted Cost 376,252.80

1047 (7) b Structural Steel Accessories (Sagrods)


Qty: 111.60 each

Materials
111.60 each Metal Structure Accessories @ 150.00 / each P 16,740.00
(Sagrods) 16,740.00

Labor (20% of Equipment) P 3,348.00

Direct Cost P 20,088.00


Indirect Cost (20%) 4,017.60
VAT (12%) 2,892.67
Total Cost P 26,998.27
Unit Cost P 241.92
Adjusted Cost 26,998.27

1047 (3) c Structural Steel Accessories (Turnbuckle)


Qty: 20.00 each

Materials
20.00 each Standard Turnbuckle @ 180.00 / each P 3,600.00
(Sagrods) 3,600.00

Labor (20% of Equipment) P 720.00

Direct Cost P 4,320.00


Indirect Cost (20%) 864.00
VAT (12%) 622.08
Total Cost P 5,806.08
Unit Cost P 290.30
Adjusted Cost 5,806.08
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

1047 (4) Structural Steel Accessories (Cross Bracing)


Qty: 284.04 kgs

Materials
284.04 kgs Cross Bracing 16mmØ @ 45.00 / kgs P 12,781.80
12,781.80

Labor (20% of Equipment) P 2,556.36

Direct Cost P 15,338.16


Indirect Cost (20%) 3,067.63
VAT (12%) 2,208.70
Total Cost P 20,614.49
Unit Cost P 72.58
Adjusted Cost 20,614.49

1047 (6) Metal Structure Accessories (Steel Plates)


Qty: 538.35 kgs

Materials
538.35 kgs Steel Plate @ 45.00 / kgs P 24,225.75
14.00 gal Red Lead @ 399.00 / gal P 5,586.00
29,811.75

Labor (20% of Equipment) P 5,962.35

Direct Cost P 35,774.10


Indirect Cost (20%) 7,154.82
VAT (12%) 5,151.47
Total Cost P 48,080.39
Unit Cost P 89.31
Adjusted Cost 48,080.39
1047 (7) a Metal Structure Accessories (Bolts)
Qty: 68.40 each

Materials
68.40 each Bolts @ 100.00 / each P 6,840.00
6.00 gal Red Lead @ 399.00 / gal P 2,394.00
9,234.00

Labor (20% of Equipment) P 1,846.80

Direct Cost P 11,080.80


Indirect Cost (20%) 2,216.16
VAT (12%) 1,595.64
Total Cost P 14,892.60
Unit Cost P 217.73
Adjusted Cost 14,892.60
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

1048 Glass Fiber (Basketball Goal Board and Its Accessories)


Qty: 1.00 l.s

Materials
1.00 l.s Glass Fiber (Basketball Goal @ 96,000.00 / l.s P 96,000.00
Board and Its 96,000.00
Accessories
Labor (20% of Equipment) P 19,200.00

Direct Cost P 115,200.00


Indirect Cost (20%) 23,040.00
VAT (12%) 16,588.80
Total Cost P 154,828.80
Unit Cost P 154,828.80
Adjusted Cost 154,828.80
PART D ELECTRICAL
CONDUITS, BOXES & FITTINGS (CONDUIT WORKS/ CONDUIT ROUGH-IN)
1100 (10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in)
Qty: 1.00 l.s

Materials
1.00 l.s Conduits, Boxes & Fittings @ 62,800.00 / l.s P 62,800.00
(Conduit Works/Conduit Rough-in) 62,800.00

Labor (20% of Equipment) P 12,560.00

Direct Cost P 75,360.00


Indirect Cost (20%) 15,072.00
VAT (12%) 10,851.84
Total Cost P 101,283.84
Unit Cost P 101,283.84
Adjusted Cost 101,283.84

WIRES AND WIRING DEVICES


1101 (33) Wires and Wiring Devices
Qty: 1.00 l.s

Materials
1.00 l.s Wires and Wiring Devices @ 85,400.00 / l.s P 85,400.00
85,400.00

Labor (20% of Equipment) P 17,080.00

Direct Cost P 102,480.00


Indirect Cost (20%) 20,496.00
VAT (12%) 14,757.12
Total Cost P 137,733.12
Unit Cost P 137,733.12
Adjusted Cost 137,733.12
DETAILED ESTIMATES
Contact I.D: 19LB0211
Contract Name Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00
Contractor: Bill Hill Construction & Supply

LIGHTING FIXTURES AND LAMPS


1101 (1) Lighting Fixtures and Lamps
Qty: 1.00 l.s

Materials
1.00 l.s Lighting Fixtures and Lamps @ 22,500.00 / l.s P 22,500.00
22,500.00

Labor (20% of Equipment) P 4,500.00

Direct Cost P 27,000.00


Indirect Cost (20%) 5,400.00
VAT (12%) 3,888.00
Total Cost P 36,288.00
Unit Cost P 36,288.00
Adjusted Cost 36,288.00

POWER LOAD CENTER, DWITCHGEAR AND PANELBOARDS,


AND OTHER OVERCURRENT PROTECTION DEVICES
1102(1) Panelboard with Main & Branch Breakers
Qty: 1.00 l.s

Materials
1.00 l.s Panelboard with Main @ 8,600.00 / l.s P 8,600.00
and Branch Breakers 8,600.00

Labor (20% of Equipment) P 1,720.00

Direct Cost P 10,320.00


Indirect Cost (20%) 2,064.00
VAT (12%) 1,486.08
Total Cost P 13,870.08
Unit Cost P 13,870.08
Adjusted Cost 13,870.08
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

Part B
B.3 Permits and Clearances
Qty: 1.0 l.s

1.00 l.s Permits and Clearances 9,500.00 / l.s P 9,500.00

Direct Cost P 9,500.00


Indirect Cost (20%) 1,900.00
VAT (12%) 1,368.00
Total Cost P 12,768.00
Unit Cost P 12,768.00
Adjusted Cost 12,768.00

B.5 Projects Billboard/Signboard (4'x8' DPWH Billboard/8'x8' COA Billboard)


Qty: 2.0 each

2.00 each Projects Billboard/Signboard 4,200.00 / each P 8,400.00


(4'x8' DPWH Billboard/8'x8'
COA Billboard) Direct Cost P 8,400.00
Indirect Cost (20%) 1,680.00
VAT (12%) 1,209.60
Total Cost P 11,289.60
Unit Cost P 5,644.80
Adjusted Cost 5,644.80

B.7 (2) Occupational Health and Safety


Qty: 1.0 l.s

1.00 l.s 24,500.0 / l.s P 24,500.00


Occupational Health and
Safety
Direct Cost P 24,500.00
Indirect Cost (20%) 4,900.00
VAT (12%) 3,528.00
Total Cost P 32,928.00
Unit Cost P 32,928.00
Adjusted Cost 32,928.00
B.9 Mobilization/Demobilization
Qty: 1.0 l.s

1.00 l.s 22,500.0 / l.s P 22,500.00


Mobilization/Demobilization
Direct Cost P 22,500.00
Indirect Cost (20%) 4,500.00
VAT (12%) 3,240.00
Total Cost P 30,240.00
Unit Cost P 30,240.00
Adjusted Cost 30,240.00
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


PART A EARTHWORKS
Removal of Structures and Obstructions
Qty: 1.00 l.s

Equipment
1.00 unit 1 day Dump Truck @ 7,500.00 / unit P 7,500.00
1.00 unit 1 day Backhoe @ 12,000.00 / unit P 12,000.00
19,500.00

Labor (20% of Equipment) P 3,900.00

Direct Cost P 23,400.00


Indirect Cost (20%) 4,680.00
VAT (12%) 3,369.60
Total Cost 31,449.60
Unit Cost 31,449.60
Adjusted Cost 31,449.60
803 (1) a Structure Excavation (Common Soil)
Qty: 70.80 cu.m

Equipment
1.00 unit 1 day Dump Truck @ 7,500.00 / unit P 7,500.00
1.00 unit 1 day Backhoe @ 12,000.00 / unit P 12,000.00
19,500.00

Labor (20% of Equipment) P 3,900.00

Direct Cost P 23,400.00


Indirect Cost (20%) 4,680.00
VAT (12%) 3,369.60
Total Cost 31,449.60
Unit Cost 444.20
Adjusted Cost 31,449.60
804 (1) b Embankment (from Borrow)
Qty: 61.59 cu.m

Equipment
1.00 unit 1 day Motorized Road Grader, G71 @ 13,000.00 / unit P 13,000.00
1.00 unit 1 day Vibratory Roller (10m.t.), SP @ 10,000.00 / unit P 10,000.00
1.00 unit 1 day Water Truck @ 8,000.00 / unit P 8,000.00
1.00 unit 1 day Backhoe @ 11,000.00 / unit P 11,000.00
42,000.00

Labor (20% of Equipment) P 8,400.00

Direct Cost P 31,400.00


Indirect Cost (20%) 6,280.00
VAT (12%) 4,521.60
Total Cost 42,201.60
Unit Cost 685.20
Adjusted Cost 42,201.60
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

804 (4) Gravel Fill


Qty: 11.16 cu.m

Materials
11.16 cu.m Fill Materials @ 750.00 / cu.m P 8,370.00

Labor (20% of Equipment) P 1,674.00

Direct Cost P 10,044.00


Indirect Cost (20%) 2,008.80
VAT (12%) 1,446.34
Total Cost 13,499.14
Unit Cost 1,209.60
Adjusted Cost 13,499.14

PART B PLAIN AND REINFORCED CONCRETE WORKS


REINFORCED CONCRETE
900 (1) b2 Structural Concrete (Footings and Slab on Fill)(Class A-14days)
Qty: 18.51 cu.m

Materials
18.51 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 64,785.00
304.00 kg Reinforcing Steel Bar @ 40.00 / kg P 12,160.00
4.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 256.00
50.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 2,700.00
8.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 800.00
of Steel)
5.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 1,750.00
82,451.00

Labor (20% of Equipment) P 15,389.00

Direct Cost P 97,840.00


Indirect Cost (20%) 19,568.00
VAT (12%) 14,088.96
Total Cost 131,496.96
Unit Cost 7,104.10
Adjusted Cost 131,496.96
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

900 (1) b2 Structural Concrete (Footing Tie Beam)(Class A-28days)


Qty: 3.36 cu.m

Materials
3.36 cu.m Pre-Mix Concrete 3000Psi @ 3,100.00 / cu.m P 10,416.00
19.00 kg Reinforcing Steel Bar @ 40.00 / kg P 760.00
1.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 64.00
10.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 540.00
2.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 200.00
of Steel)
1.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 350.00
12,330.00

Labor (20% of Equipment) P 2,235.20

Direct Cost P 14,565.20


Indirect Cost (20%) 2,913.04
VAT (12%) 2,097.39
Total Cost 19,575.63
Unit Cost 5,826.08
Adjusted Cost 19,575.63

900 (1) b2 Structural Concrete (Suspended Slab)(Class A-28days)


Qty: 14.27 cu.m

Materials
14.27 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 49,945.00
325.00 kg Reinforcing Steel Bar @ 40.00 / kg P 13,000.00
4.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 256.00
20.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 1,080.00
5.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 500.00
of Steel)
4.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 1,400.00
66,181.00

Labor (20% of Equipment) P 12,589.00

Direct Cost P 78,770.00


Indirect Cost (20%) 15,754.00
VAT (12%) 11,342.88
Total Cost 105,866.88
Unit Cost 7,418.84
Adjusted Cost 105,866.88
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

900 (1) b2 Structural Concrete (Beam/Girders)(Class A-28days)


Qty: 21.24 cu.m

Materials
21.24 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 74,340.00
365.00 kg Reinforcing Steel Bar @ 40.00 / kg P 14,600.00
8.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 512.00
223.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 12,042.00
15.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 1,500.00
of Steel)
15.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 5,250.00
108,244.00

Labor (20% of Equipment) P 17,788.00

Direct Cost P 126,032.00


Indirect Cost (20%) 25,206.40
VAT (12%) 18,148.61
Total Cost 169,387.01
Unit Cost 7,974.91
Adjusted Cost 169,387.01

900 (1) b2 Structural Concrete (Columns)(Class A-28days)


Qty: 6.98 cu.m

Materials
6.98 cu.m Pre-Mix Concrete 3000Psi @ 3,500.00 / cu.m P 24,430.00
79.00 kg Reinforcing Steel Bar @ 40.00 / kg P 3,160.00
3.00 kg #16 G.I Wire (2% of RSB) @ 64.00 / kg P 192.00
18.00 kg 100 x 100 x 6mm Angle Bar @ 54.00 / kg P 972.00
5.00 kg Welding Rod (1 kg./2000kg. @ 100.00 / kg P 500.00
of Steel)
3.00 pc 1/4" Ordinary Plywood @ 350.00 / pc P 1,050.00
30,304.00

Labor (20% of Equipment) P 5,518.00

Direct Cost P 35,822.00


Indirect Cost (20%) 7,164.40
VAT (12%) 5,158.37
Total Cost 48,144.77
Unit Cost 6,897.53
Adjusted Cost 48,144.77
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

REINFORCING STEEL
902 (1) a Reinforcing Steel (Deformed) Grade 40
Qty: 7,454.65 kgs

Materials
1.00 unit 12 day Bar Bender @ 2,200.00 / unit P 26,400.00

Materials
7,454.65 kgs Reinforming Steel @ 40.00 / kgs P 298,186.00
Deformed (Grade 40) 324,586.00

Labor (20% of Equipment) P 64,917.20

Direct Cost P 389,503.20


Indirect Cost (20%) 77,900.64
VAT (12%) 56,088.46
Total Cost 523,492.30
Unit Cost 70.22
Adjusted Cost 523,492.30

902 (1) a Reinforcing Steel (Deformed) Grade 60


Qty: 1,466.97 kgs

Materials
1.00 unit 5 day Bar Bender @ 2,200.00 / unit P 11,000.00

Materials
1,466.97 kgs Reinforming Steel @ 40.00 / kgs P 58,678.80
Deformed (Grade 40) 69,678.80

Labor (20% of Equipment) P 13,935.76

Direct Cost P 83,614.56


Indirect Cost (20%) 16,722.91
VAT (12%) 12,040.50
Total Cost 112,377.97
Unit Cost 76.61
Adjusted Cost 112,377.97

FORMWORKS AND FALSEWORKS


903 (2) Formworks and Falseworks
Qty: 429.24 sq.m

Materials
413.00 pc Fiber Cement Board @ 450.00 / pc P 185,850.00
1571.00 bd.ft Wood Frame @ 45.00 / bd.ft P 70,695.00
48.00 kg Nails @ 63.00 / kg P 3,024.00
259,569.00

P 51,309.00

Direct Cost P 310,878.00


Indirect Cost (20%) 62,175.60
Labor (20% of Equipment) VAT (12%) 44,766.43
Total Cost 417,820.03
Unit Cost 973.39
Adjusted Cost 417,820.03
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

PART C FINISHING AND OTHER CIVIL WORKS


1000 TERMITE CONTROL WORK
Qty: 6.00 Liters

Materials
6.00 Liters Soil poisoning @ 680.00 / Liters P 4,080.00
4,080.00

Labor (20% of Equipment) P 816.00

Direct Cost P 4,896.00


Indirect Cost (20%) 979.20
VAT (12%) 705.02
Total Cost 6,580.22
Unit Cost 1,096.70
Adjusted Cost 6,580.22

MASONRY WORKS
1046 (2) a2 CHB Non Load Bearing (including Reinforcing Steel/150mm thickness)
Qty: 363.45 sq.m

Materials
363.45 kgs 10mmØ x 6m @ 40.00 / kgs P 14,538.00
292.00 bags Portland Cement @ 265.00 / bags P 77,380.00
59.00 cu.m Coarse Aggregate @ 620.00 / cu.m P 36,580.00
4246.00 pc CHB - 4" x 8" x 16" @ 24.00 / pc P 101,904.00
(load bearing)
35.00 kgs Tire wire #16 @ 43.00 / kgs P 1,505.00
231,907.00

Labor (20% of Equipment) P 46,381.40

Direct Cost P 148,285.40


Indirect Cost (20%) 29,657.08
VAT (12%) 21,353.10
Total Cost 199,295.58
Unit Cost 548.34
Adjusted Cost 199,295.58
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

1046 (2) a1 CHB Non Load Bearing (including Reinforcing Steel/100mm thickness)
Qty: 49.72 sq.m

Materials
49.72 kgs 10mmØ x 6m @ 40.00 / kgs P 1,988.80
23.00 bags Portland Cement @ 265.00 / bags P 6,095.00
8.00 cu.m Coarse Aggregate @ 620.00 / cu.m P 4,960.00
227.00 pc CHB - 4" x 8" x 16" @ 24.00 / pc P 5,448.00
(load bearing)
3.00 kgs Tire wire #16 @ 43.00 / kgs P 129.00
18,620.80

Labor (20% of Equipment) P 3,724.16

Direct Cost P 9,172.16


Indirect Cost (20%) 1,834.43
VAT (12%) 1,320.79
Total Cost 12,327.38
Unit Cost 247.94
Adjusted Cost 12,327.38

CEMENT PLASTER FINISH/DECORATIVE STONE


1027 (1) Cement Plaster Finish
Qty: 1390.92 sq.m

Materials
498.00 bag Cement @ 265.00 / bag P 131,970.00
72.00 cu.m Sand @ 850.00 / cu.m 61,200.00
131,970.00

Labor (20% of Equipment) P 26,394.00

Direct Cost P 158,364.00


Indirect Cost (20%) 31,672.80
VAT (12%) 22,804.42
Total Cost P 212,841.22
Unit Cost P 153.02
Adjusted Cost 212,841.22

1018 (2) Unglazed Tiles


Qty: 360.33 sq.m

Materials
360.33 sq.m Unglazed Tiles @ 600.00 / sq.m P 216,198.00
41.00 bag Cement @ 265.00 / bag P 10,865.00
21.00 cu.m Sand @ 850.00 / cu.m P 17,850.00
244,913.00

Labor (20% of Equipment) P 2,173.00

Direct Cost P 247,086.00


Indirect Cost (20%) 49,417.20
VAT (12%) 35,580.38
Total Cost P 332,083.58
Unit Cost P 921.61
Adjusted Cost 332,083.58
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

PAINTING, VARNISHING AND OTHER RELATED WORKS


1032 (1) a Painting Works (Masonry/Concrete)
Qty: 1278.93 sq.m

Materials
181.00 ltr Concrete Neutralizer @ 105.00 / ltr P 19,005.00
207.00 gal Latex, Flat @ 578.00 / gal P 119,646.00
170.00 gal Masonry Putty @ 420.00 / gal P 71,400.00
143.00 gal Latex,Semi Gloss @ 578.00 / gal P 82,654.00
121.00 gal Acri Color @ 90.00 / gal P 10,890.00
25 qrt Paint Thinner @ 362.00 / qrt 9,050.00
10.00 pc Paint roller with Tray @ 90.00 / pc P 900.00
313,545.00

Labor (20% of Equipment) P 27,730.20

Direct Cost P 341,275.20


Indirect Cost (20%) 68,255.04
VAT (12%) 49,143.63
Total Cost 458,673.87
Unit Cost 358.64
Adjusted Cost 458,673.87
CARPENTRY AND JOINERY WORKS
1003 (1) a1 Ceiling (4.5mm thickness/Metal Frame/Fiber Cement Board
Qty: 174.60 sq.m

Materials
174.60 sq.m Ceiling (4.5mm Metal @ 700.00 / sq.m P 122,220.00
Frame/Fiber Cement Board) 122,220.00

Labor (20% of Equipment) P 24,444.00

Direct Cost P 146,664.00


Indirect Cost (20%) P 29,332.80
VAT (12%) 21,119.62
Total Cost P 197,116.42
Unit Cost 1,128.96
Adjusted Cost P 197,116.42

PREPAINTED METAL SHEETS


1014 (1) b2 Prepainted Metal Sheet (above 0.427mm/Rib Type/Long Span)
Qty: 122.40 sq.m

Materials
122.40 lin.m Prepainted Metal Sheet @ 480.00 / lin.m P 58,752.00
(above 0.427mm/Rib Type/Long Span)
58,752.00

Labor (20% of Equipment) P 11,750.40

Direct Cost P 70,502.40


Indirect Cost (20%) 14,100.48
VAT (12%) 10,152.35
Total Cost 94,755.23
Unit Cost 774.14
Adjusted Cost 94,755.23
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

CORRUGATED METAL ROOFING


1013 (2) a2 Fabricated Metal Roofing Accessory (Gauge 26/Ridge/Hip Rolls)
Qty: 10.20 lin.m

Materials
10.20 lin.m Ridge/Hip Rolls @ 180.00 / lin.m P 1,836.00
51.00 pc Rivets @ 0.70 / pc 35.70
1,836.00

Labor (20% of Equipment) P 367.20

Direct Cost P 2,203.20


Indirect Cost (20%) 440.64
VAT (12%) 317.26
Total Cost 2,961.10
Unit Cost 290.30
Adjusted Cost 2,961.10

1013 (2) b1 Fabricated Metal Roofing Accessory (Flashing) (Gauge 26)


Qty: 34.20 lin.m

Materials
34.20 lin.m Flashing @ 320.00 / lin.m P 10,944.00
171.00 pc Rivets @ 0.70 / pc 119.70
10,944.00

Labor (20% of Equipment) P 2,188.80

Direct Cost P 13,132.80


Indirect Cost (20%) 2,626.56
VAT (12%) 1,891.12
Total Cost 17,650.48
Unit Cost 516.10
Adjusted Cost 17,650.48

METAL STRUCTURES
1047 (2) a Structural Steel (Trusses)
Qty: 867.09 kgs

Materials
867.09 kgs Structural Steel (Trusses) @ 65.00 / kgs P 56,360.85
56,360.85

Labor (20% of Equipment) P 11,272.17

Direct Cost P 67,633.02


Indirect Cost (20%) 13,526.60
VAT (12%) 9,739.15
Total Cost P 90,898.78
Unit Cost P 104.83
Adjusted Cost 90,898.78
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

1047 (2) b Structural Steel (Purlins)


Qty: 582.04 kgs

Materials
582.04 kgs 150x50x20x2.0mm @ 54.00 / kgs P 31,430.16
8.00 gal Red Lead @ 200.00 / gal P 1,600.00
4.00 gal Welding Rod @ 100.00 / gal P 400.00
33,430.16

Labor (20% of Equipment) P 80.00

Direct Cost P 33,510.16


Indirect Cost (20%) 6,702.03
VAT (12%) 4,825.46
Total Cost P 45,037.66
Unit Cost P 77.38
Adjusted Cost 45,037.66

1047 (7) b Metal Structure Accessories (Sagrods)


Qty: 46.85 each

Materials
46.85 each Metal Structure Accessories @ 150.00 / each P 7,027.50
(Sagrods) 7,027.50

Labor (20% of Equipment) P 1,405.50

Direct Cost P 8,433.00


Indirect Cost (20%) 1,686.60
VAT (12%) 1,214.35
Total Cost P 11,333.95
Unit Cost P 241.92
Adjusted Cost 11,333.95

1047 (3) c Metal Structure Accessories (Turnbuckle)


Qty: 8.00 each

Materials
8.00 each Standard Turnbuckle @ 180.00 / each P 1,440.00
(Sagrods) 1,440.00

Labor (20% of Equipment) P 288.00

Direct Cost P 1,728.00


Indirect Cost (20%) 345.60
VAT (12%) 248.83
Total Cost P 2,322.43
Unit Cost P 290.30
Adjusted Cost 2,322.43
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

1047 (4) Metal Structure Accessories (Cross Bracing)


Qty: 173.53 kgs

Materials
173.53 kgs Cross Bracing 16mmØ @ 45.00 / kgs P 7,808.85
7,808.85

Labor (20% of Equipment) P 1,561.77

Direct Cost P 9,370.62


Indirect Cost (20%) 1,874.12
VAT (12%) 1,349.37
Total Cost P 12,594.11
Unit Cost P 72.58
Adjusted Cost 12,594.11

1047 (6) Metal Structure Accessories (Steel Plates)


Qty: 204.74 kgs

Materials
204.74 kgs Steel Plate @ 45.00 / kgs P 9,213.30
6.00 gal Red Lead @ 399.00 / gal P 2,394.00
11,607.30

Labor (20% of Equipment) P 2,321.46

Direct Cost P 13,928.76


Indirect Cost (20%) 2,785.75
VAT (12%) 2,005.74
Total Cost P 18,720.25
Unit Cost P 91.43
Adjusted Cost 18,720.25
1047 (7) a Metal Structure Accessories (Bolts)
Qty: 15.81 each

Materials
15.81 each Bolts @ 100.00 / each P 1,581.00
6.00 gal Red Lead @ 399.00 / gal P 2,394.00
3,975.00

Labor (20% of Equipment) P 795.00

Direct Cost P 4,770.00


Indirect Cost (20%) 954.00
VAT (12%) 686.88
Total Cost P 6,410.88
Unit Cost P 405.50
Adjusted Cost 6,410.88
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

RAILINGS
1051 (5) Metal Railing
Qty: 17.94 m

Materials
17.94 m Metal Railing @ 2,500.00 / m P 44,850.00
44,850.00

Labor (20% of Equipment) P 8,970.00

Direct Cost P 53,820.00


Indirect Cost (20%) 10,764.00
VAT (12%) 7,750.08
Total Cost P 72,334.08
Unit Cost P 4,032.00
Adjusted Cost 72,334.08

STEEL DOORS AND FRAMES


1006 (3) Grille Door
Qty: 22.89 sq.m

Materials
22.89 sq.m Grille Door @ 3,200.00 / sq.m P 73,248.00
73,248.00

Labor (20% of Equipment) P 14,649.60

Direct Cost P 87,897.60


Indirect Cost (20%) 17,579.52
VAT (12%) 12,657.25
Total Cost P 118,134.37
Unit Cost P 5,160.96
Adjusted Cost 118,134.37

1044(1)a Folding Door (Wooden)


Qty: 46.40 sq.m

Materials
46.40 sq.m Folding Door (Wooden) @ 1,800.00 / sq.m P 83,520.00
83,520.00

Labor (20% of Equipment) P 16,704.00

Direct Cost P 100,224.00


Indirect Cost (20%) 20,044.80
VAT (12%) 14,432.26
Total Cost P 134,701.06
Unit Cost P 2,903.04
Adjusted Cost 134,701.06
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

1008 (1) a Aluminum Glass Windows (Sliding Type)


Qty: 15.36 sq.m

Materials
15.36 sq.m Aluminum Glass Windows @ 5,000.00 / sq.m P 76,800.00
(Sliding Type) 76,800.00

Labor (20% of Equipment) P 15,360.00

Direct Cost P 92,160.00


Indirect Cost (20%) 18,432.00
VAT (12%) 13,271.04
Total Cost P 123,863.04
Unit Cost P 8,064.00
Adjusted Cost 123,863.04

1008 (1) c Aluminum Glass Windows (Awning Type)


Qty: 11.01 sq.m

Materials
11.01 sq.m Aluminum Glass Windows @ 4,500.00 / sq.m P 49,545.00
(Awning Type) 49,545.00

Labor (20% of Equipment) P 9,909.00

Direct Cost P 59,454.00


Indirect Cost (20%) 11,890.80
VAT (12%) 8,561.38
Total Cost P 79,906.18
Unit Cost P 7,257.60
Adjusted Cost 79,906.18

1043 (2) PVC Doors and Frames


Qty: 3.00 set

Materials
3.00 set PVC Doors and Frames @ 3,500.00 / set P 10,500.00
10,500.00

Labor (20% of Equipment) P 2,100.00

Direct Cost P 12,600.00


Indirect Cost (20%) 2,520.00
VAT (12%) 1,814.40
Total Cost P 16,934.40
Unit Cost P 5,644.80
Adjusted Cost 16,934.40
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

WOODEN DOORS AND WINDOWS


1010 (2) b Door (Wood Panel)
Qty: 8.60 sq.m

Materials
8.60 sq.m Doors (Wood Panel) @ 3,000.00 / sq.m P 25,800.00
25,800.00

Labor (20% of Equipment) P 5,160.00

Direct Cost P 30,960.00


Indirect Cost (20%) 6,192.00
VAT (12%) 4,458.24
Total Cost P 41,610.24
Unit Cost P 4,838.40
Adjusted Cost 41,610.24

1010 (1) Frames (Jambs, Sills, Head, Transoms and Mullions)


Qty: 4.00 set

Materials
4.00 set Frames (Jambs, Sills, Head, @ 2,000.00 / set P 8,000.00
Transoms and Mullions) 8,000.00

Labor (20% of Equipment) P 1,600.00

Direct Cost P 9,600.00


Indirect Cost (20%) 1,920.00
VAT (12%) 1,382.40
Total Cost P 12,902.40
Unit Cost P 3,225.60
Adjusted Cost 12,902.40

HARDWARE
1004 (2) Finishing Hardware (Lockset & Hinges)
Qty: 1.00 l.s

Materials
1.00 l.s Finishing Hardware (Lockset & @ 17,000.00 / l.s P 17,000.00
Hinges) 17,000.00

Labor (20% of Equipment) P 3,400.00

Direct Cost P 20,400.00


Indirect Cost (20%) 4,080.00
VAT (12%) 2,937.60
Total Cost P 27,417.60
Unit Cost P 27,417.60
Adjusted Cost 27,417.60
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

STORM DRAINAGE AND SEWERAGE SYSTEM


1001 (8) Sewer Line Works
Qty: 1.00 l.s

Materials
1.00 l.s Sewer line Works @ 25,000.00 / l.s P 25,000.00
25,000.00

Labor (20% of Equipment) P 5,000.00

Direct Cost P 30,000.00


Indirect Cost (20%) 6,000.00
VAT (12%) 4,320.00
Total Cost 40,320.00
Unit Cost 40,320.00
Adjusted Cost 40,320.00

1001 (5) b Catch Basin (CHB)


Qty: 3.00 each

Materials
3.00 each Catch Basin (CHB) @ 2,550.00 / each P 7,650.00
7,650.00

Labor (20% of Equipment) P 1,530.00

Direct Cost P 9,180.00


Indirect Cost (20%) 1,836.00
VAT (12%) 1,321.92
Total Cost 12,337.92
Unit Cost 4,112.64
Adjusted Cost 12,337.92

1001 (9) Storm Drainage and Downspout


Qty: 1.00 l.s

Materials
1.00 l.s Storm Draiange & Downspout @ 25,000.00 / l.s P 25,000.00
25,000.00

Labor (20% of Equipment) P 5,000.00

Direct Cost P 30,000.00


Indirect Cost (20%) 6,000.00
VAT (12%) 4,320.00
Total Cost 40,320.00
Unit Cost 40,320.00
Adjusted Cost 40,320.00
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

1001 (11) Septic Vault (Concrete/CHB)


Qty: 1.00 l.s

Materials
1.00 l.s Septic Vault (Concrete/CHB) @ 34,500.00 / l.s P 34,500.00
34,500.00

Labor (20% of Equipment) P 6,900.00

Direct Cost P 41,400.00


Indirect Cost (20%) 8,280.00
VAT (12%) 5,961.60
Total Cost 55,641.60
Unit Cost 55,641.60
Adjusted Cost 55,641.60

WATERPROOFING
1016 (1) b Waterproofing (Liquid)
Qty: 14.60 sq.m

Materials
14.60 sq.m Waterproofing (Liquid) @ 4,800.00 / sq.m P 70,080.00
70,080.00

Labor (20% of Equipment) P 14,016.00

Direct Cost P 84,096.00


Indirect Cost (20%) 16,819.20
VAT (12%) 12,109.82
Total Cost 113,025.02
Unit Cost 7,741.44
Adjusted Cost 113,025.02

PLUMBING WORKS
1002 (5) b Water Closet, Elongated, Complete (Flush Type)
Qty: 3.00 set

Materials
3.00 set Water Closet, Elongated, @ 32,000.00 / set P 96,000.00
Complete (Flush Type) 96,000.00

Labor (20% of Equipment) P 19,200.00

Direct Cost P 115,200.00


Indirect Cost (20%) 23,040.00
VAT (12%) 16,588.80
Total Cost 154,828.80
Unit Cost 51,609.60
Adjusted Cost 154,828.80
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

1002 (14) a Lavatory, Wall Hung, Complete (Manually Operated)


Qty: 3.00 set

Materials
3.00 set Lavatory, Wall Hung @ 15,000.00 / set P 45,000.00
Complete (Manually Operated) 45,000.00

Labor (20% of Equipment) P 9,000.00

Direct Cost P 54,000.00


Indirect Cost (20%) 10,800.00
VAT (12%) 7,776.00
Total Cost 72,576.00
Unit Cost 24,192.00
Adjusted Cost 72,576.00

1002 (24) Cold Water Lines


Qty: 1.00 l.s

Materials
1.00 l.s Cold Water Lines @ 15,500.00 / l.s P 15,500.00
15,500.00

Labor (20% of Equipment) P 3,100.00

Direct Cost P 18,600.00


Indirect Cost (20%) 3,720.00
VAT (12%) 2,678.40
Total Cost 24,998.40
Unit Cost 24,998.40
Adjusted Cost 24,998.40
WATER PUMPING SYSTEM
1201 (8) Water Tank
Qty: 1.00 set

Materials
1.00 set Water Tank @ 42,000.00 / set P 42,000.00
42,000.00

Labor (20% of Equipment) P 8,400.00

Direct Cost P 50,400.00


Indirect Cost (20%) 10,080.00
VAT (12%) 7,257.60
Total Cost 67,737.60
Unit Cost 67,737.60
Adjusted Cost 67,737.60
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

PART D ELECTRICAL
CONDUITS, BOXES & FITTINGS (CONDUIT WORKS/ CONDUIT ROUGH-IN)
1100 (10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in)
Qty: 1.00 l.s

Materials
1.00 l.s Conduits, Boxes & Fittings @ 90,000.00 / l.s P 90,000.00
(Conduit Works/Conduit Rough-in) 90,000.00

Labor (20% of Equipment) P 18,000.00

Direct Cost P 108,000.00


Indirect Cost (20%) 21,600.00
VAT (12%) 15,552.00
Total Cost P 145,152.00
Unit Cost P 145,152.00
Adjusted Cost 145,152.00

WIRES AND WIRING DEVICES


1101 (33) Wires and Wiring Devices
Qty: 1.00 l.s

Materials
1.00 l.s Wires and Wiring Devices @ 85,400.00 / l.s P 85,400.00
85,400.00

Labor (20% of Equipment) P 17,080.00

Direct Cost P 102,480.00


Indirect Cost (20%) 20,496.00
VAT (12%) 14,757.12
Total Cost P 137,733.12
Unit Cost P 137,733.12
Adjusted Cost 137,733.12

LIGHTING FIXTURES AND LAMPS


1101 (1) Lighting Fixtures and Lamps
Qty: 1.00 l.s

Materials
1.00 l.s Lighting Fixtures and Lamps @ 290,000.00 / l.s P 290,000.00
290,000.00

Labor (20% of Equipment) P 58,000.00

Direct Cost P 348,000.00


Indirect Cost (20%) 69,600.00
VAT (12%) 50,112.00
Total Cost P 467,712.00
Unit Cost P 467,712.00
Adjusted Cost 467,712.00
DETAILED ESTIMATES
Contact I.D: 19LB0193
Contract Name Repair/Improvement of DOTr Buidling, Philippine Coast Guard Office
Building 2, Sasa, Davao City
Location of ContractDavao City
ABC: 5,135,200.00
Contractor: Bill Hill Construction & Supply

POWER LOAD CENTER, DWITCHGEAR AND PANELBOARDS,


AND OTHER OVERCURRENT PROTECTION DEVICES
1102(1) Panelboard with Main & Branch Breakers
Qty: 1.00 l.s

Materials
1.00 l.s Panelboard with Main @ 9,000.00 / l.s P 9,000.00
and Branch Breakers 9,000.00

Labor (20% of Equipment) P 1,800.00

Direct Cost P 10,800.00


Indirect Cost (20%) 2,160.00
VAT (12%) 1,555.20
Total Cost P 14,515.20
Unit Cost P 14,515.20
Adjusted Cost 14,515.20

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 215 Calendar Days


ABC: 5,135,200.00
Part No. Part Description Total Amount
PART II OTHER GENERAL REQUIREMENTS
PART B OTHER GENERAL REQUIREMENTS
B.3 Permits and Clearances 12,768.00
B.5 Project Billboard/Signboard (4"x8" DPWH/8"x8" COA Billboard) 5,644.80
B.7 (2) Occupational Safety and Health Program 32,928.00
B.9 Mobilization/Demobilization 30,240.00
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMB
PART A EARTHWORKS
803.00 REMOVAL OF STRUCTURES AND OBSTRUCTION
803 (1) Removal of Structure and Obstruction 31,449.60
803.00 STRUCTURE EXCAVATION
803 (1) a Structure Excavation (Common Soil) 31,449.60
804.00 EMBANKMENT
804 (1)b Embankment (From Borrow) 42,201.60
804 (4) Gravel Fill 13,499.14
PART B PLAIN AND REINFORCED CONCRETE WORKS
900.00 REINFORCED CONCRETE
900 (1) c2 Structural Concrete (Footing and Slab on Fill) (Class A,28 days) 131,496.96
900 (1) c3 Structural Concrete (Footing Tie beam) (Class A,28 days ) 19,575.63
900 (1) c5 Structural Concrete (Suspended Slab/Class A-28 days ) 105,866.88
900 (1) c6 Structural Concrete (Beams/Girders/Class A-28 days ) 169,387.01
900 (1) c4 Structural Concrete (Suspended Slab/Class A-28 days ) 48,144.77
902.00 REINFORCING STEEL
902 (1) a Reinforcing Steel(Deformed) - Grade 40 523,492.30
902 (1) b Reinforcing Steel(Deformed) - Grade 60 112,377.97
903.00 FORMWORKS AND FALSEWORKS
903 (2) Formworks and Falseworks 417,820.03
TOTAL OF THIS PAGE 1,734,922.51

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 215 Calendar Days


ABC: 5,135,200.00
Part No. Part Description Total Amount
PART C FINISHINGS AND OTHER CIVIL WORKS
1,000.00 TERMITE CONTROL WORK
1000 (1) Soil Poisoning 6,580.22
MASONRY WORKS
1046 (1) a2 CHB Load Bearing (including Reinforcing Steel/150mm thickness) 199,295.58
1046 (1) a1 CHB Load Bearing (including Reinforcing Steel/100mm thickness) 12,327.38
1027 CEMENT PLASTER FINISH/DECORATIVE STONE
1027 (1) Cement Plaster Finish 212,841.22
1018 (2) Unglazed Tiles
1032 PAINTING, VARNISHING AND OTHER RELATED WORKS
1032 (1) a Painting Works (Masonry/Concrete) 458,673.87
CARPENTRY AND JOINERY WORKS
1003 (1) a1 Ceiling (4.5mm thickness/Metal Frame/Fiber Cement Board) 197,116.42
1,014.00 PREPAINTED METAL SHEETS
1014 (1) b2 Prepainted Metal Sheets (Rib T ype-Long Span,above 0.427mm thk) 94,755.23
1013 CORRUGATED METAL ROOFING
1013 (2) a2 Fabricated Metal Roofing Accessory (Flashings) (Gauge 26) 2,961.10
1013 (2) b1 Fabricated Metal Roofing Accessory (Gutter) Gauge 24 17,650.48
1,047.00 METAL STRUCTURES
1047 (2) a Structural Steel (trusses) 90,898.78
1047 (2) b Structural Steel (Purlins) 45,037.66
1047 (7) b Metal Structure Accessories (Sagrods) 11,333.95
1047 (3) c Metal Structure Accessories (T urnbuckle) 2,322.43
1047 (4) Metal Structure Accessories (Cross Bracing) 12,594.11
1047 (6) Metal Structure Accessories (Steel Plates) 18,720.25
1047 (7) a Metal Structure Accessories (Bolts) 6,410.88
TOTAL OF THIS PAGE 1,382,939.34

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 215 Calendar Days


ABC: 5,135,200.00
Part No. Part Description Total Amount
RAILINGS
1051 (1) Railing 72,334.08
STEEL DOORS AND FRAMES
1006 (3) Grille Door 118,134.37
FOLDING DOOR/PARTITION
1044(1)a Foldong Door (Wooden) 134,701.06
ALUMINUM GLASS WINDOWS
1008 (1) a Aluminum Glass Windows (Sliding Type) 123,863.04
1008 (1) c Aluminum Glass Windows (Awning Type) 79,906.18
PVC DOORS AND FRAMES
1043 (2) PVC Doors and Frames 16,934.40
WOODEN DOORS AND WINDOWS
1010 (2) b Door (Wood Panel) 41,610.24
1010 (1) Frames (Jambs, Sills, Head, Transoms and Mullions) 12,902.40
HARDWARE
1004 (2) Finishing Hardware (Locksets and Hinges) 27,417.60
1001 STORM DRAINAGE AND SEWERAGE SYSTEM
1001 (8) Sewer Line Works 40,320.00
1001 (5)b Catch Basin, CHB 12,337.92
1001 (5) a Storm Drainage and Downspout 40,320.00
1001 (9) Septic Vault (Concrete/CHB) 55,641.60
WATERPROOFING
1016 (1) b Waterproofing (Liquid) 113,025.02
TOTAL OF THIS PAGE 889,447.91

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
ABC: Php. 5,135,200.00
Location of the Contract: Davao City

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities or BOQ)

Duration: 215 Calendar Days


ABC: 5,135,200.00
Part No. Part Description Total Amount
PLUMBING WORKS
1002 (5) b Water Closet, elongated, Complete (Flush Type) 154,828.80
1002 (14) a Lavatory, Wall Hung, Complete (Manually Operated) 72,576.00
1002 (24) Cold Water Lines 24,998.40
WATER PUMPING STATION
1201 (8) Water Tank 67,737.60
PART D ELECTRICAL
CONDUITS, BOXES & FITTINGS (CONDUIT WORKS/CONDUIT ROUGH-IN
1100 (10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in) 145,152.00
WIRES AND WIRING DEVICES
1101 (33) Wires and Wiring Devices 137,733.12
LIGHTING FIXTURES AND LAMPS
1103 (1) LIGHTING Fixtures and Lamps 467,712.00
TOTAL OF THIS PAGE 1,070,737.92
Total of All Amounts in Words: GRAND TOTAL 5,078,047.67

Five Million Seventy Eight Thousand Forty Seven and Sixty Seven Cents

Name MELINDA L. TIU in capacity of GENERAL MANAGER


Signed Date MARCH 21,2019

Duly authrorized to sign the Bid for and on behalf of:


BILL HILL CONSTRUCTION AND SUPPLY
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Description Unit Quantity Unit Price Amount


(1) (2) (3) (4) (5) (6)
OTHER GENERAL REQUIREMENTS
In words: Pesos In words: Pesos
Twelve Thousand Twelve Thousand
Seven Hundred Seven Hundred Sixty-
B.3 Permits and Clearances l.s 1.00 Sixty-Eight Eight

In figures: PhP In figures: PhP


12,768.00 12,768.00
In words: Pesos In words: Pesos
Five Thousand Six Eleven Thousand Two
Hundred Forty-
Project Billboard/Signboard (4"x8" Hundred Eight-Nine
B.5 each 2.00 Four and Eighty and Sixty Cents
DPWH/8"x8" COA Billboard) Cents
In figures: PhP In figures: PhP
5,644.80 11,289.60
In words: Pesos In words: Pesos
Thirty-Two Thousand
Thirty-Two Thousand
Nine Hundred
Occupational Safety and Health Twenty-Eight Nine Hundred
B.7 (2) l.s 1.00 Twenty-Eight
Program
In figures: PhP In figures: PhP
32,928.00 32,928.00
In words: Pesos In words: Pesos
Thirty Thousand
Thirty Thousand and
Two Hundred
B.9 Mobilization/Demobilization l.s 1.00 Two Hundred Forty
Forty

In figures: PhP In figures: PhP


30,240.00 30,240.00
SUB TOTAL FOR THIS PAGE 81,580.80 87,225.60

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
803 REMOVAL OF STRUCTURES AND OBSTRUCTION In words: Pesos In words: Pesos
Thirty-One
Thousand Four Thirty-One Thousand
Hundred Forty- Four Hundred Forty-
801 (1) Removal of Structures and Obstruction l.s 1.00 Nine and Sixty Nine and Sixty Cents
Cents
In figures: PhP In figures: PhP
31,449.60 31,449.60
STRUCTURE EXCAVATION In words: Pesos In words: Pesos
Four Hundred Twnety-Nine Thousand
Twenty-One and Eight Hundred Thirty-Six
70.80 Forty-Two Cents and Fifty-Four Cents

cu.m In figures: PhP In figures: PhP


804 (4) Structure Excavation (Common Soil) 421.42 29,836.54
804 EMBANKMENT In words: Pesos In words: Pesos
Six Hundred Forty-Two Thousand
Eighty-Five and Two Hundred One and
61.59 Twenty Cents Forty-Seven Cents

cu.m In figures: PhP In figures: PhP


804 (1) b Embankment (from Borrow) 685.20 42,201.47
Thirteen Thousand
One Thousand Two
Four Hundred Ninety-
Hundred Nine and
Nine and Fourteen
804 (4) Gravel Fill cu.m 11.16 Sixty Cents
Cents

In figures: PhP In figures: PhP


1,209.60 13,499.14
SUB TOTAL FOR THIS PAGE 40,869.92 248,483.63

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit
No. (Pesos) (Pesos)
(1) (2) (3) (5) (6)
PART B PLAIN AND REINFORCED CONCRETE WORKS In words: Pesos In words: Pesos
900 REINFORCED CONCRETE Seven Thousand One One Hundred Thirty-One
Hundred Four and Four Hundred Ninety-Six
Ten Cents and Eighty-Nine Cents
18.51
Structural Concrete (Footing and Slab cu.m In figures: PhP In figures: PhP
900 (1) c2 on Fill) (Class A,28 days) 7,104.10 131,496.89
In words: Pesos In words: Pesos
Five Thousand Eight Nineteen Thousand Five
Structural Concrete (Footing Tie Hundred Twenty-Six Hundred Seventy-Five
900 (1) c3 cu.m 3.36 and Eight Cents and Sixty-Three Cents
beam) (Class A,28 days )
In figures: PhP In figures: PhP
5,826.08 19,575.63
In words: Pesos In words: Pesos
Seven Thousand Four One Hundred Five
Structural Concrete (Suspended Slab) Hundred Eighteen Thousand Eight Hundred
900 (1) c5 ( Class cu.m 14.27 and Eighty-Four Sixty-Six and Eighty-
Cents Five Cents
A,28 days )
In figures: PhP In figures: PhP
7,418.84 105,866.85
In words: Pesos In words: Pesos
Seven Thousand Nine
One Hundred Sixty Nine
Hundred Seventy-
Structural Concrete (Beam/Girders) Four and Ninety-One
Three Hundred Eighty-
900 (1) c6 cu.m 21.24 Seven and Nine Cents
(Class A,28 days ) Cents
In figures: PhP
7,974.91 169,387.09
In words: Pesos In words: Pesos
Six Thousand Eight
Forty-Eight Thouasand
Hundred Ninety
Structural Concrete (Columns) ( Class Seven and Fifty-
One Hundred Forty-Four
900 (1) c4 cu.m 6.98 and Seventy-Six Cents
A,28 days ) Three Cents
In figures: PhP In figures: PhP
6,897.53 48,144.76
SUB TOTAL FOR THIS PAGE 7,044.36 683,994.85

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
902 REINFORCING STEEL In words: Pesos In words: Pesos
Five Hundred Twenty-
Seventy and Three Four Hundred
7,454.7 Twenty-Two Cents Sixty-Five and Fifty-Two
kgs Cents
902 (1) a Reinforcing Steel(Deformed) - Grade In figures: PhP In figures: PhP
40 70.22 523,465.52
In words: Pesos In words: Pesos
One Hundred Twelve
Seventy-Six and Thousand Three Hundred
Reinforcing Steel(Deformed) - Grade Sixty-One Cents Eighty-Four and Fifty-
902 (1) b 1,467.0
60 kgs Seven Cents

In figures: PhP In figures: PhP


76.61 112,384.57
903 FORMWORKS AND FALSEWORKS In words: Pesos In words: Pesos
Four Hundred
Nine Hundred
Seventeen Thousand
Seventy-Three and
sq.m 429.24 Seven Hundred Seventy-
twenty-Nine Cents
Five
903 (2) Formworks and Falseworks In figures: PhP In figures: PhP
973.29 417,775.00
PART C FINISHING AND OTHER CIVIL WORKS In words: Pesos In words: Pesos
1000 TERMITE CONTROL WORK One Thousand Six Thousand Five
Ninety-Six and Hundred Eighty and
Liters 6.00 Seventy Cents Twenty Cents
1000 (1) Soil Poisoning In figures: PhP In figures: PhP
1,096.70 6,580.20
SUB TOTAL FOR THIS PAGE 3,940.90 1,180,899.26

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
MASONRY WORKS
In words: Pesos In words: Pesos
Five Hundred One Hundred Ninety-
Forty-Eight and Nine Thousand Two
CHB Load Bearing (including Thirty-Four Hundred Ninety-Four
1046(1)a2 sq.m 363.45 Cents and Seventeen Cents
Reinforcing Steel)-150mm
1 In
In figures: PhP
figures: PhP In
In figures: PhP
figures: PhP
0
548.34 199,294.17
4
In words: Pesos In words: Pesos
6(
1) Two Hundred
Twelve Thpousand
a Three Hundred
Forty-Seven and
Twenty-Seven and
21046(2)a1 CHB Load Bearing (including sq.m 49.72 Ninety-Four Cents
Fifty-Eight Cents
Reinforcing Steel)-100mm
In figures: PhP In figures: PhP
247.94 12,327.58
CEMENT PLASTER FINISH/DECORATIVE STONE
In words: Pesos In words: Pesos
Two Hundred Twelve
One Hundred Fifty-
Thousand Eight
Three and Two
Hundred Thirty-Eight
1027 (1) Cement Plaster Finish sq.m 1,390.9 Cents
and Fifty-Eight Cents
1 In
In figures: PhP
figures: PhP In
In figures: PhP
figures: PhP
0
153.02 212,838.58
4
SUB TOTAL FOR THIS PAGE
6(
1)
a Submitted by:
2
Melinda L. Tiu Date: March 21,2019
Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos
Three Hundred
Nine Hundred
Thirty-Two Thousand
Twenty-One and
Eighty-Three and
1018 (2) Unglazed Tiles sq.m 360.33 Sixty-One Cents
Seventy-Three Cents

In figures: PhP In figures: PhP


921.61 332,083.73
1032 PAINTING, VARNISHING AND OTHER RELATED WORKS In words: Pesos In words: Pesos
Four Hundred Fifty-
Three Hundred
Eight Thousand Six
Fifty-Eight and
hundred Seventy-Five
Sixty-Four Cents
1032 (1) a Painting Works (Masonry/Concrete) 1,278.9 and Forty-Six Cents
sq.m
In figures: PhP In figures: PhP
1032 (1) a
358.64 458,675.46
CARPENTRY AND JOINERY WORKS In words: Pesos In words: Pesos
One Thousand One One Hundred ninety-
Hundred Twenty- Seven Thousand One
Ceiling (4.5mm thickness/Metal Eight and Ninety- Hundred Sixteen and
1003 (1) a1 174.60 Six Cents Forty-Two Cents
Frame/Fiber Cement Board)
sq.m
In figures: PhP In figures: PhP
1,128.96 197,116.42
SUB TOTAL FOR THIS PAGE 787.01 162,186.46

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PREPAINTED METAL SHEETS In words: Pesos In words: Pesos
Ninety-Four
Seven Hundred Thousadn Seven
Seventy-Four and Hundred Fifty-Four
Prepainted Metal Sheets (above Fourteen Cents and Seventy-Four
1014 (1) b2 sq.m 122.40
0.427mm/Rib Type/Long Span) Cents
In figures: PhP In figures: PhP
774.14 94,754.74
CORRUGATED METAL ROOFING In words: Pesos In words: Pesos

Two Hundred Two Thousand Nine


ninety and Thirty Hundred Sixty-One
Fabricated Metal Roofing Accessory Cents and Six Cents
1013 (2) a1 lin.m 10.20
(Gauge 26/Ridge/Hip Rolls)
In figures: PhP In figures: PhP
290.30 2,961.06
In words: Pesos In words: Pesos
Seventeen
Five Hundred
Thousand Six
Sixteen and Ten
Fabricated Metal Roofing Accessory Hundred Fifty and
1013 (2) a2 lin.m 34.20 Cents
(Gauge 26/Flashing) Sxty-Two Cents
In figures: PhP In figures: PhP
516.10 17,650.62
1047 METAL STRUCTURES In words: Pesos In words: Pesos
Ninety Thousand
One Hundred
Eight Hundred
Four and Eighty-
867.09 Ninety-Seven and
Three Cents
kgs Four Cents
1047 (2) a Structural Steel (trusses) In figures: PhP In figures: PhP
104.83 90,897.04
SUB TOTAL FOR THIS PAGE 5,657.89 143,264.71

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos
Forty-Five
Seventy-Seven
Thousand Thirty-
and Thirty-Eight
1047 (2) b Structural Steel (Purlins) 582.04 Eight and Twenty-
kgs Cents
Six Cents
In figures: PhP In figures: PhP
77.38 45,038.26
In words: Pesos In words: Pesos
Two Hundred
Eleven Thousand Three
Forty-One and
Metal Structure Accessories Ninety-Two
Hundred Thirty-Three
1047 (7) b kgs 46.85 and Ninety-Five Cents
(Sagrods) Cents
In figures: PhP In figures: PhP
241.92 11,333.95
In words: Pesos In words: Pesos
Two Thousand
Two Hundred
Three Hundred
Metal Structure Accessories Ninety and
twenty-Two and
1047 (3) c each 8.00 Thirty Cents
(T urnbuckle) Forty Cents
In figures: PhP In figures: PhP
290.30 2,322.40
In words: Pesos In words: Pesos
Twelve Thousand
Seventy-Two
Five Hundred Ninety-
Metal Structure Accessories (Cross and Fifty-Eight
1047 (4) kgs 173.53 Four and Eighty-One
Bracing) Cents Cents
In figures: PhP In figures: PhP
72.58 12,594.81
SUB TOTAL FOR THIS PAGE 18,547.20 182,407.68

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
In words: Pesos In words: Pesos
Eighteen Thousand
Ninety-One and Seven Hundred
Metal Structure Accessories (Steel Forty-Three Cents Nineteen and Thirty-
1047 (6) Plates) kgs 204.74 Eight Cents

In figures: PhP In figures: PhP


91.43 18,719.38
In words: Pesos In words: Pesos
Four Hundred Six Thousand Four
Five and Fifty Hundred Ten and
1047 (7) a Metal Structure Accessories (Bolts) kgs 15.81 Cents Ninety-Six Cents
In figures: PhP In figures: PhP
405.50 6,410.96
RAILINGS In words: Pesos In words: Pesos
Seventy-Two
Four Thousand Thousand Three
Thirty-Two hundred thirty-Four
1051 (1) Railing meter 17.94 and Eight Cents

In figures: PhP In figures: PhP


4,032.00 72,334.08
STEEL DOORS AND FRAMES In words: Pesos In words: Pesos

Five Thousand One One Hundred Eighteen


Thousand One Hundred
Hundred Sixty and Thirty Four and Thirty-
1006 (3) Grille Door sq.m 22.89 Ninety-Six Cents Seven Cents

In figures: PhP In figures: PhP


5,160.96 118,134.37
SUB TOTAL FOR THIS PAGE

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
FOLDING DOOR/PARTITION In words: Pesos In words: Pesos
Two Thousand One Hundred Thirty-
Nine Hundred Four Thousand Sevne
Three and Four Hundred One and Six
1044 (1) a Folding Door (Wooden) sq.m 46.40 Cents Cents

In figures: PhP In figures: PhP


2,903.04 134,701.06
ALUMINUM GLASS WINDOWS In words: Pesos In words: Pesos
One Hundred
Twenty-Eight
Eight Thousand Thousand Eight
Aluminum Glass Windows (Sliding Sixty-Four Hundred Sixty-
1008 (1) a sq.m 15.36 Three and Four
Type)
Cents
In figures: PhP In figures: PhP
8,064.00 123,863.04
Seven Thousand Seventy-Nine
Two Hundred Thousand Nine
Aluminum Glass Windows (Awning Fifty-Seven and Hundred Six and
1008 (1) c sq.m 11.01 Sixty-Cents Eighteen Cents
Type)
In figures: PhP In figures: PhP
7,257.60 79,906.18
PVC DOORS AND FRAMES In words: Pesos In words: Pesos
Five Thousand Sixteen Thousand
Six Hundred Nine Hundred
Forty-Four and Thirty-Four and
1043 (2) PVC Doors and Frames set 3.00 Eighty Cents Forty-Cents
In figures: PhP In figures: PhP
5,644.80 16,934.40
SUB TOTAL FOR THIS PAGE

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART D ELECTRICAL
WOODEN DOORS AND WINDOWS In words: Pesos In words: Pesos
Four Thousand Forty-One
Eight Hundred Thousand Six
thirty-Eight and Hundred Ten and
1010 (2) b Door (Wood Panel) sq.m 8.60 Forty Cents Twenty-Four Cents
In figures: PhP In figures: PhP
4,838.40 41,610.24
In words: Pesos In words: Pesos
Three Thousand
Twelve Thousand
Two Hundred
Nine Hundred Two
Frames (Jambs, Sills, Head, Transoms Twenty-Five and
1010 (1) set 4.00 and Forty Cents
and Mullions) Sixty Cents
In figures: PhP In figures: PhP
3,225.60 12,902.40
HARDWARE In words: Pesos In words: Pesos
Twenty-Seven
Twenty-Seven
Thousand Four
Thousand Four
Hundred
Hundred Seventeen
1004 (2) Finishing Hardware (Lockset & Hinges) l.s 1.00 Seventeen and
and Sixty Cents
Sixty Cents
In figures: PhP In figures: PhP
27,417.60 27,417.60
STORAGE DRAINAGE AND SEWERAGE SYSTEM In words: Pesos In words: Pesos

Forty Thousand Forty Thousand


Three Hundred Three Hundred
1001 (8) Sewer Line works l.s 1.00 Twenty Twenty

In figures: PhP In figures: PhP


40,320.00 40,320.00
SUB TOTAL FOR THIS PAGE

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
Four Thousand Twelve Thousand
One Hundred Three Hundred
Twelve and Thirty-Seven and
1001 (5) b Catch Basin, CHB each 3.00 Sixty-Four Cents Ninety-Two Cents
In figures: PhP In figures: PhP
4,112.64 12,337.92

Forty Thousand
Forty Thousand Three
Three Hundred
Hundred Twenty
1001 (9) Storm Drainage and DownSpout l.s 1.00 Twenty

In figures: PhP In figures: PhP


40,320.00 40,320.00
Fifty-Five
Fifty-Five Thousand
Thousand Six
Six Hundred Forty-
Hundred Forty-
1001 (11) Septic Vault (Concrete/CHB) l.s 1.00 One
One
In figures: PhP In figures: PhP
55,641.00 55,641.00
WATERPROOFING In words: Pesos In words: Pesos
Seven Thousand One Hundred
Seven Hundred Thirteen Thousand
Forty-One and Twenty and Two
1016 (1) b Waterproofing (Liquid) sq.m 14.60 Forty-Four Cents Cents
In figures: PhP In figures: PhP
7,741.44 113,025.02
SUB TOTAL FOR THIS PAGE

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PLUMBING WORKS In words: Pesos In words: Pesos
One Hundred Fifty-
Fifty-One
Four Thousand Eight
Thousand Six
Hundred Twenty-
Water Closet, elongated, Complete Hundred Nine and
1002 (5) b set 3.00 Eight and Eighty
Sixty Cents
(Flush Type) Cents
In figures: PhP In figures: PhP
51,609.60 154,828.80
In words: Pesos In words: Pesos
Twenty-Four
Seventy-Two
Thousand one
Thousand Five
Lavatory, Wall Hung, Complete Hundred Ninety-
1002 (14) a set 3.00 Hundred Seventy-Six
Two
(Manually Operated)
In figures: PhP In figures: PhP
24,192.00 72,576.00
Twenty-Four
Twenty-Four
Thousand Nine
Thousand Nine
Hundred Eighty-
Hundred Eighty-Eight
1002 (24) Cold Water Lines l.s 1.00 Eight amd Forty
amd Forty Cents
Cents
In figures: PhP In figures: PhP
24,988.40 24,988.40
WATER PUMPING SYSTEM In words: Pesos In words: Pesos
Sixty-Seven Sixty-Seven
Thousand Seven Thousand Seven
Hundred Thirty- Hundred Thirty-
1201 (8) Water Tank set 1.00 Seven and Sixty Seven and Sixty
Cents Cents
In figures: PhP In figures: PhP
67,737.60 67,737.60
SUB TOTAL FOR THIS PAGE

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
Department of Public Works and Highways
Davao City 1st District Engineering Office
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2,
Sasa, Davao City
Location of
: Davao City
the Contract
ABC: Php. 5,135,200.00
Contractor: Bill Hill Construction & Supply

BILL OF QUANTITIES

Pay Item Unit Price Amount


Description Unit Quantity
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
CONDUITS, BOXES & FITTINGS (CONDUIT WORKS/
WORKS/ CONDUIT ROUGH-IN) In words: Pesos In words: Pesos
One Hundred
One Hundred Forty-
Forty-Two
Two Thousand One
Thousand One
Conduits, Boxes & Fittings (Conduit Hundred Fifty-Two
1100 (10) l.s 1.00 Hundred Fifty-Two
Cents
Works/Conduit Rough-in) Cents
In figures: PhP In figures: PhP
142,152.00 142,152.00
WIRES AND WIRING DEVICES In words: Pesos In words: Pesos
One Hundred thirty- One Hundred thirty-
Seven Thousand Seven Thousand
Seven Hundred Seven Hundred
thirty-Three and thirty-Three and
1101 (33) wWires and Wiring Devices l.s 1.00 Twelve Cents Twelve Cents
In figures: PhP In figures: PhP
137,733.12 137,733.12
LIGHTING FIXTURES AND LAMPS In words: Pesos In words: Pesos
Four Hundred Four Hundred Sixty-
Sixty-Seven Seven Thousand
Thousand Seven Seven Hundred
1103 (1) Lighting Fixtures and Lamps l.s 1.00 Hundred Twelve Twelve

In figures: PhP In figures: PhP


467,712.00 467,712.00
POWER LOAD CENTER, SWITCHGEAR AND PANELBOARDS AND OTHER
OVERCURRENT PROTECTION DEVICES In words: Pesos In words: Pesos
Fourteen
Fourteen Thousand
Thousand Five
Five Hundred Fifteen
Panelboard with Main & Branch Hundred Fifteen
1102 (1) l.s 1.00 and Twenty Cents
and Twenty Cents
Breakers
In figures: PhP In figures: PhP
14,515.20 14,515.20
SUB TOTAL FOR THIS PAGE

Submitted by:

Melinda L. Tiu Date: March 21,2019


Name and Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Name of Bidder
19LB0193
Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2, Sasa, Davao City

SUMMARY

Materials
Fill Materials @ 750.00 / cu.m
Pre-Mix Concrete (3000psi) @ 3,500.00 / sq.m
Reinforcing Steel Bar @ 3,500.00 / / cu.m
#16 G.I Wire (2% of RSB) @ 64.00 / kgs
100 x 100 x 6mm Angle Bar @ 54.00 / kgs
Welding Rod (1kg/200kg of Steel) @ 100.00 / kgs
1/4" Ordinary Plywood @ 350.00 / pc
Reinforming Steel Deformed (Grade 40) @ 40.00 / kgs
Reinforming Steel Deformed (Grade 60) @ 40.00 / kgs
Fiber Cement Board @ 450.00 / pc
Wood Frame @ 45.00 / bd.ft
Nails @ 63.00 / kgs
Soil Poisoning @ 680.00 / liters
10mmØ x 6m @ 40.00 / kgs
Portland Cement @ 265.00 / bags
Coarse Aggregate @ 620.00 / cu.m
CHB - 4" x 8" x 16" (Load Bearing) @ 24.00 / pc
Sand @ 850.00 / cu.m
Unglazed Tiles @ 600.00 / sq.m
Ceiling (4.5mm Metal Frame/Fiber Cement Board) @ 700.00 / sq.m
Concrete Neutralizer @ 105.00 / ltr
Latex, Flat @ 578.00 / gal
Masonry Putty @ 420.00 / gal
Latex, Semi Gloss @ 578.00 / gal
Acri Color @ 90.00 / gal
Paint Thinner @ 362.00 / qrt
Paint Roller with Tray @ 90.00 / pc
Prepainted Metal Sheet (above 0.427mm) @ 480.00 / lin.m
(Rib Type/Long Span)
Fabricated Metal Roofing Accessory @ 180.00 / sq.m
(Gauge 26/Ridge/Hip Rolls) /
Rivets @ 0.70 / pc
Fabricated Metal Roofing Accessory @ 320.00 / lin.m
(Flashing/Gauge 26)
Structural Steel (Trusses) @ 65.00 / kgs
150x50x20x2.0mm @ 54.00 / kgs
Red Lead @ 200.00 / gal
Metal Structure Accessories (Sagrods) @ 150.00 / each
Metal Structure Accessories (Turnbuckle) @ 180.00 / each
Metal Structure Accessories (Cross Bracing) @ 64.00 / sq.m
Metal Structure Accessories (Steel Plates) @ 64.00 / / cu.m
Metal Structure Accessories (Bolts) @ 64.00 / sq.m
Metal Railing @ 2,500.00 / m
Grille Door @ 3,200.00 / sq.m

Equipment
One Bag Mixer @ 3,000.00 / day
Bar Bender (all electric models 3-phase) @ 2,800.00 / day
Bar Shear (all electric model-single phase) @ 1,800.00 / day
Scafolding (rental - 4 sets) @ 250.00 / day
Backhoe @ 4,500.00 / day
Plate Compactor @ 2,500.00 / day

Submitted y:

MELINDA L. TIU
Name & Signature of Bidder's Representative

March 21, 2019


GENERAL MANAGER Date
Position
BILL HILL CONSTRUCTION AND SUPPLY
Contractor
Contract ID: 19LB0193
Contract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2
Location of the Contract: Davao City
Department of Public Works and Highways
PRELIMINARY EXAMINATION OF FINANCIAL COMPONENT OF THE BID
Date of Submission/ Opening of Bids
Name of Contracto: : BILL HILL CONSTRUCTION & SUPPLY
Approved Budget fo
: : Php 5,135,200.00
TOTAL AMOUNTOF BID AS READ ₱ 5,078,047.67

BAC Chairperson
Implementing

BAC Member

BAC Member

BAC Member
Tab No.

Unit
1. Bid Form
2. Bid Prices in the Bill of Quantities
3. Detailed Estimates including a Summary sheet indicating the unit prices of construction
materials, labor rates and equipment rentals used in coming up with the bid
4. Quarterly/Monthly Cash Flow and Payment Schedule
Note: Any missing, incomplete or patently insufficient document in the above-mentioned checkl
is a gound for outright rejectionof the bid

Overall Rating: () Passed () Failed

DPWH-INFR-32-2016
Contract ID: 19LB0210
Contract Name: Construction/Completion of Multi-Purpose Building, Cabantian ES, Brgy. Cabantian, Davao City
Location of the Contract: Davao City
Department of Public Works and Highways
PRELIMINARY EXAMINATION OF FINANCIAL COMPONENT OF THE BID
Date of Submission/ Opening of Bids
Name of Contracto: : BILL HILL CONSTRUCTION & SUPPLY
Approved Budget fo
: : Php 2,970,000.00
TOTAL AMOUNTOF BID AS READ ₱ 2,855,918.39

BAC Chairperson
Implementing

BAC Member

BAC Member

BAC Member
Tab No.

Unit
1. Bid Form
2. Bid Prices in the Bill of Quantities
3. Detailed Estimates including a Summary sheet indicating the unit prices of construction
materials, labor rates and equipment rentals used in coming up with the bid
4. Quarterly/Monthly Cash Flow and Payment Schedule
Note: Any missing, incomplete or patently insufficient document in the above-mentioned checkl
is a gound for outright rejectionof the bid

Overall Rating: () Passed () Failed

DPWH-INFR-32-2016
Contract ID: 19LB0211
Contract Name: Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of the Contract: Davao City
Department of Public Works and Highways
PRELIMINARY EXAMINATION OF FINANCIAL COMPONENT OF THE BID
Date of Submission/ Opening of Bids
Name of Contracto: : BILL HILL CONSTRUCTION & SUPPLY
Approved Budget fo
: : Php 3,960,000.00
TOTAL AMOUNTOF BID AS READ ₱ 3,920,754.36

BAC Chairperson
Implementing

BAC Member

BAC Member

BAC Member
Tab No.

Unit
1. Bid Form
2. Bid Prices in the Bill of Quantities
3. Detailed Estimates including a Summary sheet indicating the unit prices of construction
materials, labor rates and equipment rentals used in coming up with the bid
4. Quarterly/Monthly Cash Flow and Payment Schedule
Note: Any missing, incomplete or patently insufficient document in the above-mentioned checkl
is a gound for outright rejectionof the bid

Overall Rating: () Passed () Failed

DPWH-INFR-32-2016
19LB0210
Construction/Completion of Multi-Purpose Building,2, Cabantian ES, Brgy. Cabantian, Davao City

SUMMARY

Materials
Fill Materials @ 750.00 / cu.m
Pre-Mix Concrete (3000psi) @ 3,500.00 / sq.m
Reinforcing Steel Bar @ 3,500.00 / / cu.m
#16 G.I Wire (2% of RSB) @ 64.00 / kgs
100 x 100 x 6mm Angle Bar @ 54.00 / kgs
Welding Rod (1kg/200kg of Steel) @ 100.00 / kgs
1/4" Ordinary Plywood @ 350.00 / pc
Reinforming Steel Deformed (Grade 40) @ 40.00 / kgs
Reinforming Steel Deformed (Grade 60) @ 40.00 / kgs
Fiber Cement Board @ 450.00 / pc
Wood Frame @ 45.00 / bd.ft
Nails @ 63.00 / kgs
Soil Poisoning @ 680.00 / liters
10mmØ x 6m @ 40.00 / kgs
Portland Cement @ 265.00 / bags
Coarse Aggregate @ 620.00 / cu.m
CHB - 4" x 8" x 16" (Load Bearing) @ 24.00 / pc
Sand @ 850.00 / cu.m
Unglazed Tiles @ 600.00 / sq.m
Ceiling (4.5mm Metal Frame/Fiber Cement Board) @ 700.00 / sq.m
Concrete Neutralizer @ 105.00 / ltr
Latex, Flat @ 578.00 / gal
Masonry Putty @ 420.00 / gal
Latex, Semi Gloss @ 578.00 / gal
Acri Color @ 90.00 / gal
Paint Thinner @ 362.00 / qrt
Paint Roller with Tray @ 90.00 / pc
Prepainted Metal Sheet (above 0.427mm) @ 480.00 / lin.m
(Rib Type/Long Span)
Fabricated Metal Roofing Accessory @ 180.00 / sq.m
(Gauge 26/Ridge/Hip Rolls) /
Rivets @ 0.70 / pc
Fabricated Metal Roofing Accessory @ 320.00 / lin.m
(Flashing/Gauge 26)
Structural Steel (Trusses) @ 65.00 / kgs
150x50x20x2.0mm @ 54.00 / kgs
Red Lead @ 200.00 / gal
Metal Structure Accessories (Sagrods) @ 150.00 / each
Metal Structure Accessories (Turnbuckle) @ 180.00 / each
Metal Structure Accessories (Cross Bracing) @ 64.00 / sq.m
Metal Structure Accessories (Steel Plates) @ 64.00 / / cu.m
Metal Structure Accessories (Bolts) @ 64.00 / sq.m
Metal Railing @ 2,500.00 / m
Grille Door @ 3,200.00 / sq.m

Equipment
One Bag Mixer @ 3,000.00 / day
Bar Bender (all electric models 3-phase) @ 2,800.00 / day
Bar Shear (all electric model-single phase) @ 1,800.00 / day
Scafolding (rental - 4 sets) @ 250.00 / day
Backhoe @ 4,500.00 / day
Plate Compactor @ 2,500.00 / day

Submitted y:

MELINDA L. TIU
Name & Signature of Bidder's Representative
March 21, 2019
Date
GENERAL MANAGER
Position
BILL HILL CONSTRUCTION AND SUPPLY
Contractor
19LB0211
Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City

SUMMARY

Materials
Fill Materials @ 750.00 / cu.m
Pre-Mix Concrete (3000psi) @ 3,500.00 / sq.m
Reinforcing Steel Bar @ 3,500.00 / / cu.m
#16 G.I Wire (2% of RSB) @ 64.00 / kgs
100 x 100 x 6mm Angle Bar @ 54.00 / kgs
Welding Rod (1kg/200kg of Steel) @ 100.00 / kgs
1/4" Ordinary Plywood @ 350.00 / pc
Reinforming Steel Deformed (Grade 40) @ 40.00 / kgs
Reinforming Steel Deformed (Grade 60) @ 40.00 / kgs
Fiber Cement Board @ 450.00 / pc
Wood Frame @ 45.00 / bd.ft
Nails @ 63.00 / kgs
Soil Poisoning @ 680.00 / liters
10mmØ x 6m @ 40.00 / kgs
Portland Cement @ 265.00 / bags
Coarse Aggregate @ 620.00 / cu.m
CHB - 4" x 8" x 16" (Load Bearing) @ 24.00 / pc
Sand @ 850.00 / cu.m
Unglazed Tiles @ 600.00 / sq.m
Ceiling (4.5mm Metal Frame/Fiber Cement Board) @ 700.00 / sq.m
Concrete Neutralizer @ 105.00 / ltr
Latex, Flat @ 578.00 / gal
Masonry Putty @ 420.00 / gal
Latex, Semi Gloss @ 578.00 / gal
Acri Color @ 90.00 / gal
Paint Thinner @ 362.00 / qrt
Paint Roller with Tray @ 90.00 / pc
Prepainted Metal Sheet (above 0.427mm) @ 480.00 / lin.m
(Rib Type/Long Span)
Fabricated Metal Roofing Accessory @ 180.00 / sq.m
(Gauge 26/Ridge/Hip Rolls) /
Rivets @ 0.70 / pc
Fabricated Metal Roofing Accessory @ 320.00 / lin.m
(Flashing/Gauge 26)
Structural Steel (Trusses) @ 65.00 / kgs
150x50x20x2.0mm @ 54.00 / kgs
Red Lead @ 200.00 / gal
Metal Structure Accessories (Sagrods) @ 150.00 / each
Metal Structure Accessories (Turnbuckle) @ 180.00 / each
Metal Structure Accessories (Cross Bracing) @ 64.00 / sq.m
Metal Structure Accessories (Steel Plates) @ 64.00 / / cu.m
Metal Structure Accessories (Bolts) @ 64.00 / sq.m
Metal Railing @ 2,500.00 / m
Grille Door @ 3,200.00 / sq.m

Equipment
One Bag Mixer @ 3,000.00 / day
Bar Bender (all electric models 3-phase) @ 2,800.00 / day
Bar Shear (all electric model-single phase) @ 1,800.00 / day
Scafolding (rental - 4 sets) @ 250.00 / day
Backhoe @ 4,500.00 / day
Plate Compactor @ 2,500.00 / day

Submitted y:

MELINDA L. TIU
Name & Signature of Bidder's Representative
March 21, 2019
Date
GENERAL MANAGER
Position

BILL HILL CONSTRUCTION AND SUPPLY


Contractor
Department of Public Works and Highways

Contract ID: 19LB0193


Conctract Name: Repair/Improvement of DOTr Building, Philippine Coast Guard Office Building 2
Location of Contract: Davao City
ABC: 5,135,200.00

CASH FLOW BY QUARTER

Percentage Accomplishment 4.08% 25.06% 56.91% 100%

Periodic Accomplishment (in Pesos) 207,378.19 1,065,186.15 1,617,205.94 2,188,277.39

Cumulative Accomplishment (in Pesos) 207,378.19 1,272,564.34 2,889,770.28 5,078,047.67

Time Elapsed First Quarter Second Quarter Third Quarter Fourth Quarter

Submiited by:

Melinda L. Tiu
Name & Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Contractor
Department of Public Works and Highways

Contract ID: 19LB0210


Conctract Name: Construction/Completion of Multi-Purpose Building, Cabantian ES, Brgy. Cabantian, Davao City
Location of Contract: Davao City
ABC: 2,970,000.00

CASH FLOW BY QUARTER

Percentage Accomplishment 2.01% 22.59% 61.21% 100%

Periodic Accomplishment (in Pesos) 57,378.19 587,807.69 1,102,807.96 1,107,924.55

Cumulative Accomplishment (in Pesos) 57,378.19 645,185.88 1,747,993.84 2,855,918.39

Time Elapsed First Quarter Second Quarter Third Quarter Fourth Quarter

Submiited by:

Melinda L. Tiu
Name & Signature of Bidder's Representative

GENERAL MANAGER
Position

Bill Hill Construction & Supply


Contractor
Department of Public Works and Highways

Contract ID: 19LB0211


Conctract Name: Construction of Multi-Purpose Building, Mudiang ES, Brgy. Mudiang, Davao City
Location of Contract: Davao City
ABC: 3,960,000.00

CASH FLOW BY QUARTER

Percentage Accomplishment 5.29% 28.12% 61.46% 100%

Periodic Accomplishment (in Pesos) 207,378.19 895,186.15 1,307,205.94 1,510,984.08

Cumulative Accomplishment (in Pesos) 207,378.19 1,102,564.34 2,409,770.28 3,920,754.36

Time Elapsed First Quarter Second Quarter Third Quarter Fourth Quarter

Submiited by:

Melinda L. Tiu
Name & Signature of Bidder's Representative
GENERAL MANAGER
Position

Bill Hill Construction & Supply


Contractor
1,107,924.55