Professional Documents
Culture Documents
CONTRACT ID : 24KC0079
NAME : Construction of Multipurpose Building (Tribal Tulugan)
LOCATION : Lirongan, Talakag, Bukidnon
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
BID FORM
Date: March 11, 2024
Project Identification No.: 24KC0079
To: BAC CHAIRMAN
DPWH, Bukidnon 3RD DEO,
Dicklum, Manolo Fortich, Bukidnon
Having examined the Philippine Bidding Documents (PBDs) including the Suplplemental or Bid Bulletin Numbers (1), the receipt of
b. We offer to execute the Works for this Contract in accordance with the PBDs;
c. The total price of our Bid in words and figures, excluding any discounts offered below is;
#VALUE!
Php4,941,027.31
d. The discounts offered and the methodology for their application are:
None.
e. The total bid price includes the cost of all taxes, such as, but not limited to; Value Added Tax, which are itemized herein and
reflected in the detailed estimates,
f. Our Bid shall be valid within the period of 120 Calendar days, and it shall remain binding upon us at any time before the
expiration of that period;
g.
If our Bid is accepted, we commit to obtain a Performance Security in the amount of 30 percent of the Contract Price for the due
performance of the Contract, or a Performance Securing Declaration in lieu of the allowable forms of Performance Security, subject
to the terms and conditions of issued GPPB guidelines for this purpose;
h. We are not participating, as Bidders, in more than one Bid in this bidding process, other than alternative offers in accordance with
the Bidding Documents;
i.
We understand that this Bid, together with you written acceptance thereof included in your notification of award, shall constitute a
binding contract between us, until a formal Contract is prepared and executed; and
j. We understand that you are not bound to accept the Lowest Calculated Bid or any other Bid that you may receive.
k.
We likewise certify/confirm that the undersigned, is the duly authorized representative of the bidder, and granted full power and
authority to do, execute and perform any and all acts necessary to participate, submit the bid, and to sign and execute the ensuing
contract for the,
Construction of Multipurpose Building (Tribal Tulugan)
of the DPWH, BUKIDNON 3RD DISTRICT ENGINEERING OFFICE
l.
We acknowledge that failure to sign each and every page of this Bid Form, including the Bill of Quantites, shall be a ground for the
rejection of our Bid.
CONTRACT ID : 0
NAME : 0
LOCATION : 0
OWNER : DPWH, BUKIDNON 3RD DISTRICT ENGINEERING OFFICE
BID FORM
Signed :
Date :
Duly authorized to sign the Bid for & In Behalf of : FGW CONSTRUCTION CORPORATION
---------------------------------------------
CONTRACT ID : 24KC0079
NAME : Construction of Multipurpose Building (Tribal Tulugan)
LOCATION : Lirongan, Talakag, Bukidnon
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
BID FORM
Date: March 11, 2024
Project Identification No.: 24KC0079
To: BAC CHAIRMAN
DPWH, Bukidnon 3RD DEO,
Dicklum, Manolo Fortich, Bukidnon
Having examined the Philippine Bidding Documents (PBDs) including the Suplplemental or Bid Bulletin Numbers (1), the receipt of
b. We offer to execute the Works for this Contract in accordance with the PBDs;
c. The total price of our Bid in words and figures, excluding any discounts offered below is;
#VALUE!
Php4,941,027.31
d. The discounts offered and the methodology for their application are:
9.92% from the bid amount.
e. The total bid price includes the cost of all taxes, such as, but not limited to; Value Added Tax, which are itemized herein and
reflected in the detailed estimates,
f. Our Bid shall be valid within the period of 120 Calendar days, and it shall remain binding upon us at any time before the
expiration of that period;
g.
If our Bid is accepted, we commit to obtain a Performance Security in the amount of 30 percent of the Contract Price for the due
performance of the Contract, or a Performance Securing Declaration in lieu of the allowable forms of Performance Security, subject
to the terms and conditions of issued GPPB guidelines for this purpose;
h. We are not participating, as Bidders, in more than one Bid in this bidding process, other than alternative offers in accordance with
the Bidding Documents;
i.
We understand that this Bid, together with you written acceptance thereof included in your notification of award, shall constitute a
binding contract between us, until a formal Contract is prepared and executed; and
j. We understand that you are not bound to accept the Lowest Calculated Bid or any other Bid that you may receive.
k.
We likewise certify/confirm that the undersigned, is the duly authorized representative of the bidder, and granted full power and
authority to do, execute and perform any and all acts necessary to participate, submit the bid, and to sign and execute the ensuing
contract for the,
Construction of Multipurpose Building (Tribal Tulugan)
of the DPWH, BUKIDNON 3RD DISTRICT ENGINEERING OFFICE
l.
We acknowledge that failure to sign each and every page of this Bid Form, including the Bill of Quantites, shall be a ground for the
rejection of our Bid.
CONTRACT ID : 0
NAME : 0
LOCATION : 0
OWNER : DPWH, BUKIDNON 3RD DISTRICT ENGINEERING OFFICE
BID FORM
Signed :
Date :
Duly authorized to sign the Bid for & In Behalf of : FGW CONSTRUCTION CORPORATION
---------------------------------------------
BILL OF QUANTITIES
SUB-TOTAL
SUB-TOTAL
#VALUE!
TOTAL
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE!
#VALUE!
\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
DETAILED ESTIMATES
Item No : B.3(1)
Description : Permits and Clearances
Quantity : 1.00 LS
A. MATERIALS
P 37,600.00
Sub-total,A P 37,600.00
B. EQUIPMENT/FUEL/OIL
Permits and Clearances P
Sub-total,B P 0.00
C. LABOR
Labor P
Sub-total C P 0.00
Item No : B.5(1)
Description : Project Billboard/Signboard
Quantity : 2.00 each
A. MATERIALS
Project Billboard/Signboard P 9,000.00
COA & DPWH w/ Frame Sub-total,A P 9,000.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 1.00 days P 950.00
1 Foreman @P 789.00 /day for 1.00 days P 789.00
1 Skilled @P 569.00 /day for 1.00 days P 569.00
2 Laborer @P 437.00 /day for 1.00 days P 874.00
Sub-total C P 950.00
Item No : B.7(1)
Description : Occupational Safety and Health Program
Quantity : 1.00 L.s
A. MATERIALS
Occupational Safety and Health Program P 10,200.00
(Safety hat, safety shoes, first aid kit/medIcine, safety harnesh)
Sub-total,A P 10,200.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 First aider @P 400.00 /day for 120.00 days P 48,000.00
Sub-total C P 48,000.00
Item No : B.9(1)
Description : Mobilization/Demobilization
Quantity : 1.00 L.s
A. MATERIALS
Truck for minor equipments P 20,000.00
(1 bagger mixer, concrete vibrator, plate compactor, etc.)
Sub-total,A P 20,000.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
Labor P
Sub-total C P 0.00
Item No : 800(2)
Description : Clearring and Grubbing
Quantity : 1.00 L.s
COST ANALYSIS
A. MATERIALS
Sub-total,A P -
-
B. EQUIPMENT/FUEL/OIL
P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 3.00 days P 2,850.00
1 Foreman @P 789.00 /day for 3.00 days P 2,367.00
4 Laborer @P 437.00 /day for 3.00 days P 5,244.00
Sub-total C P 10,461.00
Item No : 801(1)
Description : Removal of Structures and Obstruction
Quantity : 1.00 L.s
COST ANALYSIS
A. MATERIALS
Sub-total,A P
-
B. EQUIPMENT/FUEL/OIL
minor tools & Breaker 3,811.20
P 3,811.20
C. LABOR
1 Engineer @P 950.00 /day for 2.00 days P 1,900.00
1 Foreman @P 789.00 /day for 2.00 days P 1,578.00
1 Skilled @P 569.00 /day for 2.00 days P 1,138.00
4 Laborer @P 437.00 /day for 2.00 days P 3,496.00
Sub-total C P 8,112.00
Item No : 803(1)a
Description : Structure Excavation, Common Soil
Quantity : 172.51 cu.m.
9 cu/hr
A. MATERIALS
Sub-total,A P -
-
B. EQUIPMENT/FUEL/OIL
1 Backhoe @P 18,200.00 /day for 2.40 days P 43,606.69
P 43,606.69
C. LABOR
1 Engineer @P 950.00 /day for 2.40 days P 2,276.17
1 Foreman @P 789.00 /day for 2.40 days P 1,890.42
1 Skilled @P 569.00 /day for 2.40 days P 1,363.31
4 Laborer @P 437.00 /day for 2.40 days P 4,188.16
Sub-total C P 9,718.06
Item No : 804(1)a
Description : Embankment from Structure Excavation, Common Soil
Quantity : 53.40 cu.m.
4.5 cu/hr
A. MATERIALS
Sub-total,A P -
B. EQUIPMENT/FUEL/OIL
1 Plate Compactor @P 984.00 /day for 1.48 days P 1,459.60
P 1,459.60
C. LABOR
1 Engineer @P 950.00 /day for 1.48 days P 1,409.17
1 Foreman @P 789.00 /day for 1.48 days P 1,170.35
2 Skilled @P 569.00 /day for 1.48 days P 1,688.03
4 Laborer @P 437.00 /day for 1.48 days P 2,592.87
Sub-total C P 6,860.42
Item No : 804(7)
Description : Gravel Fill
Quantity : 8.55 cu.m.
1 cu/hr
A. MATERIALS
Item No : 900(1)c
Description : Structural Concrete-3000psi (Class A, 28 days)
Quantity : 17.420 cu.m.
0.127 cu/hr
A. MATERIALS
Portland Cement, 40 kg. @P 280.00 /BAG 172.46 bag P 48,288.24
Washed sand @P 1,200.00 /cu.m. 13.03 cu.m. P 15,636.19
Gravel @P 1,200.00 /cu.m. 11.50 cu.m. P 13,796.64
Sub-total,A P 77,721.07
B. EQUIPMENT/FUEL/OIL
1 unit One bagger @P 1,424.00 /day for 17.15 days P 24,415.43
2 unit Concrete Vibrator @P 1,191.04 /day for 17.15 days P 40,842.36
Sub-total,B P 65,257.79
C. LABOR
1 Engineer @P 950.00 /day for 17.15 days P 16,288.39
1 Foreman @P 789.00 /day for 17.15 days P 13,527.93
2 Skilled @P 569.00 /day for 17.15 days P 19,511.77
6 Laborer @P 437.00 /day for 17.15 days P 44,955.94
Sub-total C P 94,284.04
Item No : 900(1)i
Description : Structural Concrete (Class A, 28 days)
Quantity : 29.800 L.s
0.3 cu/hr
A. MATERIALS
Portland Cement, 40 kg. @P 280.00 /BAG 295.02 bag P 82,605.60
Washed sand @P 1,200.00 /cu.m. 22.29 cu.m. P 26,748.48
Gravel @P 1,200.00 /cu.m. 19.67 cu.m. P 23,601.60
Sub-total,A P 132,955.68
B. EQUIPMENT/FUEL/OIL
1 unit One bagger @P 1,424.00 /day for 12.42 days P 17,681.33
2 unit Concrete Vibrator @P 1,191.04 /day for 12.42 days P 29,577.49
Sub-total,B P 47,258.83
C. LABOR
1 Engineer @P 950.00 /day for 12.42 days P 11,795.83
1 Foreman @P 789.00 /day for 12.42 days P 9,796.75
2 Skilled @P 569.00 /day for 12.42 days P 14,130.17
6 Laborer @P 437.00 /day for 12.42 days P 32,556.50
Sub-total C P 68,279.25
Item No : 902(1)a1
Description : Reinforcing Steel (Deformed) Grade 40
Quantity : 5,824.650 kg.
54 kg/hr
A. MATERIALS
DSB @P 55.00 /kg 5,824.65 kg P 320,355.75
Hacksaw Blade @P 60.00 /PC. 12.00 pc. P 720.00
#16 G.I. Tie Wire @P 70.00 /PC. 30.00 pc. P 2,100.00
Sub-total,A P 323,175.75
B. EQUIPMENT/FUEL/OIL
1 unit Bar Cutter @P 1,424.00 /day for 13.48 days P 19,199.77
1 unit Bar Bender @P 1,191.04 /day for 13.48 days P 16,058.78
Sub-total,B P 35,258.55
C. LABOR
1 Engineer @P 950.00 /day for 13.48 days P 12,808.84
1 Foreman @P 789.00 /day for 13.48 days P 10,638.08
4 Skilled @P 569.00 /day for 13.48 days P 30,687.28
6 Laborer @P 437.00 /day for 13.48 days P 35,352.39
Sub-total C P 89,486.58
DIRECT COST : Php 447,920.88
OCM : Php 53,750.51
PROFIT : Php 35,833.67
TAXES : Php 26,875.25
TOTAL COST Php 564,380.30
UNIT COST : P 96.90
Item No : 902(1)a2
Description : Reinforcing Steel (Deformed) Grade 60
Quantity : 3,076.130 kg.
53 kg/hr
A. MATERIALS
DSB @P 55.00 /kg 3,076.13 kg P 169,187.15
Hacksaw Blade @P 60.00 /PC. 12.00 pc. P 720.00
#16 G.I. Tie Wire @P 70.00 /PC. 30.00 pc. P 2,100.00
Sub-total,A P 172,007.15
B. EQUIPMENT/FUEL/OIL
1 unit Bar Cutter @P 1,424.00 /day for 7.26 days P 10,331.15
1 unit Bar Bender @P 1,191.04 /day for 7.26 days P 8,641.02
Sub-total,B P 18,972.18
C. LABOR
1 Engineer @P 950.00 /day for 7.26 days P 6,892.27
1 Foreman @P 789.00 /day for 7.26 days P 5,724.21
4 Skilled @P 569.00 /day for 7.26 days P 16,512.43
6 Laborer @P 437.00 /day for 7.26 days P 19,022.67
Sub-total C P 48,151.59
DIRECT COST : Php 239,130.92
OCM : Php 28,695.71
PROFIT : Php 19,130.47
TAXES : Php 14,347.86
TOTAL COST Php 301,304.96
UNIT COST : P 97.95
Item No : 903(1)
Description : Formworks and Falseworks
Quantity : 1.000 L.s
A. MATERIALS
Forms and Scaffolds:
2 x 3 x 8' Coco lumber @P 24.00 /bd.ft. 4,000.00 bd.ft. P 96,000.00
2 x 2 x 8 Coco lumber @P 24.00 /bd.ft. 4,000.00 bd.ft. P 96,000.00
1/2" x 4' x 8' Plywood @P 800.00 /PC. 30.00 pc. P 24,000.00
Assorted CWN @P 80.00 /kg 30.00 kg P 2,400.00
Sub-total,A P 218,400.00
B. EQUIPMENT/FUEL/OIL
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 12.00 days P 11,400.00
1 Foreman @P 789.00 /day for 12.00 days P 9,468.00
4 Skilled @P 569.00 /day for 12.00 days P 27,312.00
6 Laborer @P 437.00 /day for 12.00 days P 31,464.00
Sub-total C P 79,644.00
Item No : 1001(8)
Description : Sewer Line Works
Quantity : 1.00 L.s
A. MATERIALS
Sewer Line Works P 15,500.00
PVC pipes, clean ou w/ plug & sealing, Wye, Elbow, Coupling, Tee
Sub-total,A P 15,500.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 4.00 days P 3,800.00
1 Foreman @P 789.00 /day for 4.00 days P 3,156.00
1 Skilled @P 569.00 /day for 4.00 days P 2,276.00
1 Laborer @P 437.00 /day for 4.00 days P 1,748.00
Sub-total C P 10,980.00
A. MATERIALS
Storm Drainage and Downspout P 13,500.00
PVC pipes, clean ou w/ plug & sealing, Wye, Elbow, Coupling, Tee
Sub-total,A P 13,500.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 4.00 days P 3,800.00
1 Foreman @P 789.00 /day for 4.00 days P 3,156.00
1 Skilled @P 569.00 /day for 4.00 days P 2,276.00
1 Laborer @P 437.00 /day for 4.00 days P 1,748.00
Sub-total C P 10,980.00
A. MATERIALS
Septic Vault (Concrete/CHB) P 13,500.00
PVC pipes, clean ou w/ plug & sealing, Wye, Elbow, Coupling, Tee
Sub-total,A P 13,500.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 4.00 days P 3,800.00
1 Foreman @P 789.00 /day for 4.00 days P 3,156.00
2 Skilled @P 569.00 /day for 4.00 days P 4,552.00
2 Laborer @P 437.00 /day for 4.00 days P 3,496.00
Sub-total C P 15,004.00
Item No : 1002(24)
A. MATERIALS
Cold Water Line P 14,200.00
(Polypropylene, tee reducer,elbow, teflon tape)
Sub-total,A P 14,200.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 2.00 days P 1,900.00
1 Foreman @P 789.00 /day for 2.00 days P 1,578.00
1 Skilled @P 569.00 /day for 2.00 days P 1,138.00
1 Laborer @P 437.00 /day for 2.00 days P 874.00
Sub-total C P 5,490.00
Item No : 1003(1)a1
Description : Ceiling (4.5mm thk. Fiber Cement Board on Metal Frame)
Quantity : 114.00 sq.m
A. MATERIALS
FIBER CEMENT BOARD P 50,540.00
(4'x8'x4.5mm)
Sub-total,A P 50,540.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 7.00 days P 6,650.00
1 Foreman @P 789.00 /day for 7.00 days P 5,523.00
1 Skilled @P 569.00 /day for 7.00 days P 3,983.00
1 Laborer @P 437.00 /day for 7.00 days P 3,059.00
Sub-total C P 19,215.00
Item No : 1003(11)a1
Description : Fascia Board, Fiber Cement Board
Quantity : 40.43 m
A. MATERIALS
Fascia Board, Fiber Cement Board P 16,980.60
Sub-total,A P 16,980.60
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 3.00 days P 2,850.00
1 Foreman @P 789.00 /day for 3.00 days P 2,367.00
1 Skilled @P 569.00 /day for 3.00 days P 1,707.00
1 Laborer @P 437.00 /day for 3.00 days P 1,311.00
Sub-total C P 8,235.00
Item No : 1003(17)
Description : Carpenry and Joinery Works
Quantity : 1.00 L.s
A. MATERIALS
(s4s Lumber) P 9,000.00
Insect screen
Blackboard ( Lawanit, Ordinary plywood, Good lumber)
Sub-total,A P 9,000.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 3.00 days P 2,850.00
1 Foreman @P 789.00 /day for 3.00 days P 2,367.00
1 Skilled @P 569.00 /day for 3.00 days P 1,707.00
1 Laborer @P 437.00 /day for 3.00 days P 1,311.00
Sub-total C P 8,235.00
Item No : 1007(2)
Description : Aluminum Framed Glass Door
Quantity : 1.00 L.s
A. MATERIALS
Aluminum Framed Glass Door P 6,600.00
Sub-total,A P 6,600.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 4.00 days P 3,800.00
1 Foreman @P 789.00 /day for 4.00 days P 3,156.00
1 Skilled @P 569.00 /day for 4.00 days P 2,276.00
1 Laborer @P 437.00 /day for 4.00 days P 1,748.00
Sub-total C P 10,980.00
A. MATERIALS
Aluminum Glass Windows (Sliding Type) P 85,800.00
Sub-total,A P 85,800.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 6.00 days P 5,700.00
1 Foreman @P 789.00 /day for 6.00 days P 4,734.00
1 Skilled @P 569.00 /day for 6.00 days P 3,414.00
1 Laborer @P 437.00 /day for 6.00 days P 2,622.00
Sub-total C P 16,470.00
Item No : 1008(1)c
Description : Aluminum Glass Windows (Awning Type)
Quantity : 2.17 sq.m
A. MATERIALS
Aluminum Glass Windows (Awning Type) P 5,728.80
Sub-total,A P 5,728.80
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 2.00 days P 1,900.00
1 Foreman @P 789.00 /day for 2.00 days P 1,578.00
1 Skilled @P 569.00 /day for 2.00 days P 1,138.00
1 Laborer @P 437.00 /day for 2.00 days P 874.00
Sub-total C P 5,490.00
Item No : 1008(1)d
Description : Aluminum Glass Windows (Fixed Type)
Quantity : 14.18 sq.m
A. MATERIALS
Aluminum Glass Windows (Fixed Type) P 24,815.00
Sub-total,A P 24,815.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 6.00 days P 5,700.00
1 Foreman @P 789.00 /day for 6.00 days P 4,734.00
1 Skilled @P 569.00 /day for 6.00 days P 3,414.00
1 Laborer @P 437.00 /day for 6.00 days P 2,622.00
Sub-total C P 16,470.00
Item No : 1010(1)
Description : Frames (Jambs, Sills, Head Transoms and Mullions)
Quantity : 5.00 set
A. MATERIALS
FRAMES AND JAMBS P 47,500.00
(s4s Mahogany jamb)
Door frames, window frames
Sub-total,A P 47,500.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 8.00 days P 7,600.00
1 Foreman @P 789.00 /day for 8.00 days P 6,312.00
1 Skilled @P 569.00 /day for 8.00 days P 4,552.00
1 Laborer @P 437.00 /day for 8.00 days P 3,496.00
Sub-total C P 21,960.00
Item No : 1010(2)a
Description : Doors (Flush)
Quantity : 2.10 sq.m
A. MATERIALS
Doors (Flush) P 7,980.00
( 2.10mx 0.70m)
Sub-total,A P 7,980.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 1.00 days P 950.00
1 Foreman @P 789.00 /day for 1.00 days P 789.00
1 Skilled @P 569.00 /day for 1.00 days P 569.00
1 Laborer @P 437.00 /day for 1.00 days P 437.00
Sub-total C P 2,745.00
Item No : 1010(2)b
Description : Doors (Wood Panel)
Quantity : 6.72 sq.m
A. MATERIALS
PANEL DOOR P 30,240.00
Sub-total,A P 30,240.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 5.00 days P 4,750.00
1 Foreman @P 789.00 /day for 5.00 days P 3,945.00
1 Skilled @P 569.00 /day for 5.00 days P 2,845.00
1 Laborer @P 437.00 /day for 5.00 days P 2,185.00
Sub-total C P 13,725.00
Item No : 1013(2)a
Description : Fabricated Metal Roofing Accessories, Ridge/Hip Rolls
Quantity : 11.50 L.m
A. MATERIALS
Preformed Pre-painted, Ridge Roll P 6,095.00
Sub-total,A P 6,095.00
B. EQUIPMENT/FUEL/OIL
1 HANDRILL @P 150.00 /day for 1.00 days P 150.00
Sub-total,B P 150.00
C. LABOR
1 Engineer @P 950.00 /day for 1.00 days P 950.00
1 Foreman @P 789.00 /day for 1.00 days P 789.00
1 Skilled @P 569.00 /day for 1.00 days P 569.00
1 Laborer @P 437.00 /day for 1.00 days P 437.00
Sub-total C P 2,745.00
Item No : 1013(2)a2
Description : FABRICATED METAL ROOFING ACCESSORY, FLASHING, 0.6mm thk.
Quantity : 22.36 LM
A. MATERIALS
Preformed Pre-painted, Flashing P 14,086.80
Sub-total,A P 14,086.80
B. EQUIPMENT/FUEL/OIL
1 HANDRILL @P 150.00 /day for 3.00 days P 450.00
Sub-total,B P 450.00
C. LABOR
1 Engineer @P 950.00 /day for 3.00 days P 2,850.00
1 Foreman @P 789.00 /day for 3.00 days P 2,367.00
1 Skilled @P 569.00 /day for 3.00 days P 1,707.00
1 Laborer @P 437.00 /day for 3.00 days P 1,311.00
Sub-total C P 8,235.00
Item No : 1013(2)b
Description : Fabricated Metal Roofing Accessories, Flashing
Quantity : 80.86 L.m
A. MATERIALS
GUTTERS LONG SPAN P 44,473.00
Sub-total,A P 44,473.00
B. EQUIPMENT/FUEL/OIL
1 HANDRILL @P 150.00 /day for 7.00 days P 1,050.00
Sub-total,B P 1,050.00
C. LABOR
1 Engineer @P 950.00 /day for 4.00 days P 3,800.00
1 Foreman @P 789.00 /day for 4.00 days P 3,156.00
1 Skilled @P 569.00 /day for 4.00 days P 2,276.00
1 Laborer @P 437.00 /day for 4.00 days P 1,748.00
Sub-total C P 10,980.00
Item No : 1013(2)c
Description : Fabricated Metal Roofing Accessories, Gutter
Quantity : 23.00 L.m
A. MATERIALS
GUTTERS LONG SPAN P 17,250.00
Sub-total,A P 17,250.00
B. EQUIPMENT/FUEL/OIL
1 HANDRILL @P 150.00 /day for 4.00 days P 600.00
Sub-total,B P 600.00
C. LABOR
1 Engineer @P 950.00 /day for 4.00 days P 3,800.00
1 Foreman @P 789.00 /day for 4.00 days P 3,156.00
1 Skilled @P 569.00 /day for 4.00 days P 2,276.00
1 Laborer @P 437.00 /day for 4.00 days P 1,748.00
Sub-total C P 10,980.00
Item No : 1014(1)b2
Description : Prepainted Metal Sheets (Rib-Type, Longspan)
Quantity : 81.08 sq.m
A. MATERIALS
Pre-painted Roofing Sheet, Long span P 64,864.00
Touch-up paint
Sub-total,A P 64,864.00
B. EQUIPMENT/FUEL/OIL
1 HANDRILL @P 150.00 /day for 4.00 days P 600.00
Sub-total,B P 600.00
C. LABOR
1 Engineer @P 950.00 /day for 4.00 days P 3,800.00
1 Foreman @P 789.00 /day for 4.00 days P 3,156.00
1 Skilled @P 569.00 /day for 4.00 days P 2,276.00
1 Laborer @P 437.00 /day for 4.00 days P 1,748.00
Sub-total C P 10,980.00
Item No : 1018(5)
Description : Glazed Tiles
Quantity : 66.16 sq.m 0.16
1 sqm/hr
A. MATERIALS
Glazed tiles @P 120.00 /pc. 413.50 pc. P 49,620.00
Portland Cement @P 280.00 /bag 22.05 bag P 6,174.93
Tile Adhesive @P 450.00 /Pack 11.03 pack P 4,962.00
Tile Grout @P 85.00 /Pack 16.54 pack P 1,405.90
Tile Trim @P 120.00 /PC. 33.08 pc. P 3,969.60
Sub-total,A P 66,132.43
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 8.27 days P 7,856.50
1 Foreman @P 789.00 /day for 8.27 days P 6,525.03
4 Skilled @P 569.00 /day for 8.27 days P 18,822.52
4 Laborer @P 437.00 /day for 8.27 days P 14,455.96
Sub-total C P 47,660.01
Item No : 1018(2)
Description : Unglazed Tiles
Quantity : 46.10 sq.m 0.16
1.2 sqm/hr
A. MATERIALS
Glazed tiles @P 90.00 /pc. 288.12 pc. P 25,931.25
Portland Cement @P 280.00 /bag 15.37 bag P 4,302.67
Tile Adhesive @P 450.00 /Pack 7.68 pack P 3,457.50
Tile Grout @P 85.00 /Pack 11.53 pack P 979.63
Tile Trim @P 120.00 /PC. 23.05 pc. P 2,766.00
Sub-total,A P 37,437.04
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 4.80 days P 4,561.98
1 Foreman @P 789.00 /day for 4.80 days P 3,788.84
2 Skilled @P 569.00 /day for 4.80 days P 5,464.77
2 Laborer @P 437.00 /day for 4.80 days P 4,197.02
Sub-total C P 18,012.61
Item No : 1027(1)
Description : Cement Plaster Finish
Quantity : 581.19 sq.m
6 sqm/h
A. MATERIALS
Portland Cement, 40 kg. @P 280.00 /BAG 223.18 bag P 62,489.55
Washed sand @P 1,200.00 /cu.m. 25.46 cu.m. P 30,547.35
Sand Screen @P 320.00 /.m. 4.00 m P 1,280.00
Sub-total,A P 94,316.90
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 12.11 days P 11,502.72
1 Foreman @P 789.00 /day for 12.11 days P 9,553.31
6 Skilled @P 569.00 /day for 12.11 days P 41,337.14
6 Laborer @P 437.00 /day for 12.11 days P 31,747.50
Sub-total C P 94,140.67
Item No : 1032(1)a
Description : Painting Works (Masonry/Concrete)
Quantity : 695.19 sq.m
3 sqm/hr
A. MATERIALS
Concrete neutralizer @P 700.00 /gal. 17.00 gal P 11,900.00
Latex @P 850.00 /gal. 56.00 gal P 47,600.00
Concrete Putty @P 350.00 /gal. 6.00 gal P 2,100.00
Putty knife @P 600.00 /pc. 10.00 gal P 6,000.00
Tinting color @P 200.00 /pint 28.00 pint P 5,600.00
Paint Roller @P 350.00 /set 10.00 set P 3,500.00
Paint Brush @P 150.00 /set 10.00 set P 1,500.00
Sub-total,A P 78,200.00
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 28.97 days P 27,517.94
1 Foreman @P 789.00 /day for 28.97 days P 22,854.37
6 Skilled @P 569.00 /day for 28.97 days P 98,890.78
6 Laborer @P 437.00 /day for 28.97 days P 75,949.51
Sub-total C P 225,212.59
Item No : 1032(1)b
Description : Painting Works (Wood)
Quantity : 14.96 sq.m
1.3 sqm/hr
A. MATERIALS
Flat Enamel @P 950.00 /gal. 0.37 gal P 355.30
Paint thinner @P 420.00 /gal. 3.00 gal P 1,260.00
Concrete Putty @P 350.00 /gal. 0.12 gal P 43.63
Paint Roller @P 350.00 /set 2.00 set P 700.00
Paint Brush @P 150.00 /set 2.00 set P 300.00
Sub-total,A P 2,658.93
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 1.44 days P 1,366.54
1 Foreman @P 789.00 /day for 1.44 days P 1,134.95
3 Skilled @P 569.00 /day for 1.44 days P 2,455.45
3 Laborer @P 437.00 /day for 1.44 days P 1,885.82
Sub-total C P 6,842.76
Item No : 1032(1)c
Description : Painting Works (Steel)
Quantity : 151.71 sq.m
2.5 sqm/hr
A. MATERIALS
Roof paint @P 950.00 /gal. 6.07 gal P 5,764.98
Paint thinner @P 420.00 /gal. 2.02 gal P 849.58
Red Lid @P 650.00 /gal. 6.07 gal P 3,944.46
Sand Paper @P 150.00 /doz. 2.00 dozen P 300.00
Paint Brush @P 150.00 /set 2.00 set P 300.00
Sub-total,A P 11,159.02
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 7.59 days P 7,206.23
1 Foreman @P 789.00 /day for 7.59 days P 5,984.96
2 Skilled @P 569.00 /day for 7.59 days P 8,632.30
2 Laborer @P 437.00 /day for 7.59 days P 6,629.73
Sub-total C P 28,453.21
Item No : 1033(1)
Description : Metal Deck Panel
Quantity : 42.22 L.m
5 lm/hr
A. MATERIALS
@P 900.00 /lm 42.22 L.m P 37,998.00
Metal Deck Panel
Sub-total,A P 37,998.00
B. EQUIPMENT/FUEL/OIL
minor tools P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 1.06 days P 1,002.72
1 Foreman @P 789.00 /day for 1.06 days P 832.79
2 Skilled @P 569.00 /day for 1.06 days P 1,201.16
4 Laborer @P 437.00 /day for 1.06 days P 1,845.01
Sub-total C P 4,881.69
Item No : 1046(2)a1
Description : CHB Non Load Bearing (including Reinf. Steel) 100mm thk.
Quantity : 151.00 sq.m 37750
1.5 sq/hr
A. MATERIALS
Portland Cement, 40 kg. @P 280.00 /BAG 79.28 bag P 22,197.00
Washed sand @P 1,200.00 /cu.m. 6.61 cu.m. P 7,936.56
CHB @P 20.00 /pcs. 1,963.00 pcs P 39,260.00
10mm dia. DSB @P 190.00 /pcs. 131.00 pc. P 24,890.00
Tie Wire @P 79.00 /kg 2.62 kg P 206.98
Sub-total,A P 94,490.54
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 12.58 days P 11,954.17
1 Foreman @P 789.00 /day for 12.58 days P 9,928.25
4 Skilled @P 569.00 /day for 12.58 days P 28,639.67
4 Laborer @P 437.00 /day for 12.58 days P 21,995.67
Sub-total C P 72,517.75
Item No : 1047(3)
Description : Metal Structure Accessories
Quantity : 1.00 L.s
A. MATERIALS
@P 36,610.00 /LS 1.00 L.s P 36,610.00
Metal Structure Accessories
Sub-total,A P 36,610.00
B. EQUIPMENT/FUEL/OIL
minor tools 1,372.50
Sub-total,B P 1,372.50
C. LABOR
1 Engineer @P 950.00 /day for 5.00 days P 4,750.00
1 Foreman @P 789.00 /day for 5.00 days P 3,945.00
1 Skilled @P 569.00 /day for 5.00 days P 2,845.00
1 Laborer @P 437.00 /day for 5.00 days P 2,185.00
Sub-total C P 13,725.00
Item No : 1047(7)
Description : Structural Steel
Quantity : 1.00 L.s
A. MATERIALS
Structural Steel @P 72,000.00 /KG 1.00 L.s P 72,000.00
(Angle bar for trusses, steel plates, sagrod, purlins, turn buckle, etc.)
(welding rod, hacksaw blade, etc.)
Sub-total,A P 72,000.00
B. EQUIPMENT/FUEL/OIL
1 Welding Machine @P 2,840.00 /day for 12.00 days P 34,080.00
1 Oxygen-Acetylene @P 2,000.00 /day for 12.00 days P 24,000.00
1 Sander/Grinding machine @P 1,200.00 /day for 12.00 days P 14,400.00
Sub-total,B P 72,480.00
C. LABOR
1 Engineer @P 950.00 /day for 12.00 days P 11,400.00
1 Foreman @P 789.00 /day for 12.00 days P 9,468.00
2 Skilled @P 569.00 /day for 12.00 days P 13,656.00
4 Laborer @P 437.00 /day for 12.00 days P 20,976.00
Sub-total C P 55,500.00
DIRECT COST : Php 199,980.00
OCM : Php 23,997.60
PROFIT : Php 15,998.40
TAXES : Php 11,998.80
TOTAL COST : Php 251,974.80
UNIT COST : P 251,974.80
Item No : 1051(1)a
Description : Railing
Quantity : 1.00 L.s
A. MATERIALS
Railing P 45,000.00
Sub-total,A P 45,000.00
B. EQUIPMENT/FUEL/OIL
P
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 5.00 days P 4,750.00
1 Foreman @P 789.00 /day for 5.00 days P 3,945.00
2 Skilled @P 569.00 /day for 5.00 days P 5,690.00
2 Laborer @P 437.00 /day for 5.00 days P 4,370.00
Sub-total C P 18,755.00
Item No : 1100(10)
Description : Conduits, Boxes and Fittings
Quantity : 1.00 L.s
A. MATERIALS
Conduits, Boxes and Fittings @P 30,000.00 /ls 1.00 L.s P 30,000.00
(UPVC Pipe, coupling,conduit,adoptor,elbow, locknut & bushing)
(Junstion box, utility box, electrical tape, rubber tape solvent cement,
Tie wire, concrete nail, terminal lugs, etc.)
Sub-total,A P 30,000.00
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 5.00 days P 4,750.00
1 Foreman @P 789.00 /day for 5.00 days P 3,945.00
1 Skilled @P 569.00 /day for 5.00 days P 2,845.00
1 Laborer @P 437.00 /day for 5.00 days P 2,185.00
Sub-total C P 13,725.00
A. MATERIALS
Wires and Wiring Devices @P 46,860.00 /ls 1.00 L.s P 46,860.00
(THWN, swithes and convenience outlets)
Sub-total,A P 46,860.00
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 6.00 days P 5,700.00
1 Foreman @P 789.00 /day for 6.00 days P 4,734.00
2 Skilled @P 569.00 /day for 6.00 days P 6,828.00
2 Laborer @P 437.00 /day for 6.00 days P 5,244.00
Sub-total C P 22,506.00
Item No : 1102(1)
Description : Panelboard with Main and Branch Breakers
Quantity : 1.000 L.s
A. MATERIALS
@P 37,800.00 1.00 L.s P 37,800.00
Panelboard with Main and Branch Breakers Sub-total,A P 37,800.00
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 2.00 days P 1,900.00
1 Foreman @P 789.00 /day for 2.00 days P 1,578.00
1 Skilled @P 569.00 /day for 2.00 days P 1,138.00
1 Laborer @P 437.00 /day for 2.00 days P 874.00
Sub-total C P 5,490.00
Item No : 1103(1)
Description : Lighting Fixtures and Lamps
Quantity : 1.000 Ls.
A. MATERIALS
Lighting Fixtures and Lamps @P 69,000.00 1.00 Ls. P 69,000.00
(Compact Flourescent Lamp with box type canopy, and wall fan)
Sub-total,A P 69,000.00
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 3.00 days P 2,850.00
1 Foreman @P 789.00 /day for 3.00 days P 2,367.00
1 Skilled @P 569.00 /day for 3.00 days P 1,707.00
1 Laborer @P 437.00 /day for 3.00 days P 1,311.00
Sub-total C P 8,235.00
Item No : 1109(1)
Description : Grounding System
Quantity : 1.00 L.s
A. MATERIALS
0 @P 18,100.00 /LS 1.00 LS P 18,100.00
Sub-total,A P 18,100.00
B. EQUIPMENT/FUEL/OIL
NONE P 0.00
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 950.00 /day for 1.00 days P 950.00
1 Foreman @P 789.00 /day for 1.00 days P 789.00
1 Skilled @P 569.00 /day for 1.00 days P 569.00
1 Laborer @P 437.00 /day for 1.00 days P 437.00
Sub-total C P 2,745.00
Submitted By:
HELEN B. LAGUYAN
PROPRIETOR
E AND H CONSTRUCTION AND SUPPLY
VAT 5%
ocm 12%
cp 8%
4,950,000.00 98.2
120 CD
98.6 788.80
71.18 569.44
54.66 437.28
3134.25
-
(13,180.86)
-
(13,145.33)
#REF!
#REF!
#REF!
19,888.33
9,405.11
-
(19,888.30)
###
###
###
###
#REF!
0.000%
#REF!
#REF!
33,364.80
-
87,409.35
56,564.55
#REF!
#REF!
66,798.90
-
24,809.40
-
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
-
(13,513.50)
14,135.68
(41,260.22)
-
(11,327.40)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
-
(54,028.41)
#REF!
#REF!
#REF!
#REF!
#REF!
-
(80,331.30)
#REF!
69,323.39
14,230.76
87,409.35
99,503.04
12,093.69
41,310.37
(13,232.31)
97,317.93
57,221.27
(40,096.66)
Department of Public Works and Highways
Contract ID: 24KC0079
Contract Name: Construction of Multipurpose Building (Tribal Tulugan)
Location of the Contract: Lirongan, Talakag, Bukidnon
#VALUE!
CONTRACT ID : 24KC0079
CONTRACT NAME
: Construction of Multipurpose Building (Tribal Tulugan)
LOCATION OF THE CONTRACT : Lirongan, Talakag, Bukidnon
DURATION OF THE CONTRACT : 120 CD
SUBMITTED BY:
Name and signature of Bidder's Representative HELEN B. LAGUYAN Date: March 11, 2024
Position PROPRIETOR
Name of Bidder E AND H CONSTRUCTION AND SUPPLY