Department of Public Works and Highways


Contract ID: 20LA0151
Contract Name: Concreting of Camp Manuel T. Yan Sr. Road, Brgy. Tuburan, Mawab
Location of the Contract: Compostela Valley Province
Department of Public Works and Highways
COMPOSTELA VALLEY DISTRICT ENGINEERING OFFICE
Nabunturan, Comval Province

SUPPLEMENTAL BULLETIN NO. 055


Subject: REVISION OF BILL OF QUANTITIES, PROJECT DESCRIPTION
and APPROVED BUDGET FOR THE CONTRACT
This Supplemental Bulletin No. 055 is issued to amend provisions in the Bidding Documents (BDs) for the above stated
Contract, as follows:
Current Provision of BDs (including Previous Amended Provision of BDs under this Supplemental
Amendments) Bulletin
As posted in the Phil-GEPS and DPWH: Revision of bill of quantities, and project description, and Approved
Budget for the Contract (ABC)

Item No. Description Qty. Unit Item No. Description Qty. Unit
Part B – Other General Requirements Part B – Other General Requirements
B.4(1) Construction Survey and 2.47 Km B.4(1) Construction Survey and 2.61 Km
Staking Staking
B.12 Removal and 1.00 Ls
Relocation of Utilities
Part C – Earthworks Part C – Earthworks
100(1) Clearing and Grubbing 3.03 Ha 100(1) Clearing and Grubbing 2.54 Ha
100(3)a2 Individual Removal of 88.00 Each 100(3)a2 Individual Removal of 98.00 Each
Trees, 301-500 mm. dia. Trees, 301-500 mm. dia.
(small) (small)
102(2) Surplus Common 94,551.00 Cu.m 102(2) Surplus Common 73,518.00 Cu.m
Excavation Excavation
103(2)a Structure Excavation 112.00 Cu.m 103(2)a Structure Excavation 124.00 Cu.m
(Common Soil) (Common Soil)
103(3) Foundation Fill 11.00 Cu.m 103(3) Foundation Fill 9.00 Cu.m
103(6)a Pipe Culvert and Drain 82.00 Cu.m 103(6)a Pipe Culvert and Drain 87.00 Cu.m
Excavation (Common Soil) Excavation (Common Soil)
104(1)a Embankment from 13,066.00 Cu.m 104(1)a Embankment from 11,098.00 Cu.m
Roadway Excavation Roadway Excavation
(Common) (Common)
105(1)a Subgrade Preparation 21,037.00 Sq.m 105(1)a Subgrade Preparation 22,818.00 Sq.m
(Common Material) (Common Material)
Part D – Sub-Base and Base Course Part D – Sub-Base and Base Course
200(1) Aggregate Subbase Course 7,472.00 Cu.m 200(1) Aggregate Subbase Course 7,862.00 Cu.m
Part E – Surface Course Part E – Surface Course
311(1)e1 Portland Cement Concrete 16,512.98 Sq.m 311(1)e1 Portland Cement Concrete 17,477.14 Sq.m
Pavement (Unreinforced), Pavement (Unreinforced),
0.28m thick (14 days) 0.28m thick (14 days)
Part G – Drainage & Slope Protection Structure Part G – Drainage & Slope Protection Structure
500(1)a Pipe Culverts, 910mm dia. 47.00 Lin.m 500(1)a Pipe Culverts, 910mm dia. 28.00 Lin.m
(36ӯ), Class IV, RCPC (36ӯ), Class IV, RCPC
500(1)b6 Pipe Culverts, 1520mm 11.00 Lin.m 500(1)b6 Pipe Culverts, 1520mm 16.00 Lin.m
dia. (60ӯ), Class IV, dia. (60ӯ), Class IV,
RCPC RCPC
506(1) Stone Masonry 47.00 Cu.m 506(1) Stone Masonry 39.00 Cu.m
Part H – Miscellaneous Structures
612(1) Reflectorized 842.53 Sq.m
Thermoplastic
Pavement Marking
White

Page 1 of 2
.

SUPPLEMENTAL BULLETIN NO. 055

Project Description: Project Description:


Concreting (width = 6.70m., thk. = 280 mm) Concreting (width = 6.70m., thk. = 280 mm)
Roadway Excavation Roadway Excavation
- Common Surplus Excavation - Common Surplus Excavation
Construction of Minor Drainage Structures Removal and Relocation of Utilities
Construction of Minor Drainage Structures
Application of Reflectorized Thermoplastic Pavement markings
ABC: Php55,487,464.59 ABC: Php55,487,376.77

All other scope of works not included in this revision remains the same. This Supplemental Bulletin shall form an integral
part of the said Bidding Documents.

For the guidance and information of all concerned.

RONALD B. CARIAGA
BAC Chairperson