SUMMARY OF BID PRICES


(All Part of Bill of Quantities)
Instruction for Completing the Summary of Bid Prices:
1. Part No. - Enter the "Part No." for each section of the Bill of Quantities (BOQ) whwre unit prices are entered.
2. Part Description - Enter the "Part Description corresponding to the "Part No."
3. Total Amount - Enter the "Total Amount" in Pesos for all pages having the same "Part Description"

Duration : 53 Calendar Days


ABC : 9,800,000.00
Item No. Description Total Amount
PART B OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking 7,945.94
B.5 Project Billboard / Signboard (2 - 4'x8' DPWH Billboard, 1 - 8'x8' COA 15,704.56
Billboard)
B.7(2) Occupational Safety and Health Program 231,050.77
B.8(2) Traffic Management 192,874.50
B.9 Mobilization/Demobilization 101,783.09
PART C EARTHWORK
101(6) Removal of Actual Structures/Obstruction (Concrete) 143,724.00
102(2) Surplus Common Excavation 193,160.10
103(1)a Structure Excavation (Common Soil) 169,123.50
103(3) Foundation Fill 52,192.88
103(6)a Pipe Culvert and Drain Excavation 92,925.00
105(1)a Subgrade Preparation, Common Material 290,917.20
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 384,969.92
PART E SURFACE COURSES
311(1)c2 Portland Cement Concrete Pavement (Unreinforced) 0.23 m. thk. 7 days 3,032,319.93
PART I-B DRAINAGE AND SLOPE PROTECTION STRUCRTURES
500(1)b3 Pipe Culverts, 910mm dia., Class IV, RCPC 1,766,595.94
500(3)a Lined Canal (Rectangular, CHB) 1,601,354.43

Name MARK JOSEPH C. RUBINOS in the capacity of Authorized Managing Officer

Signed DATE: March 18, 2022

Duly authorized to signed the Bid for and on behalf of NEN Builders and Development Services Corp.
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy.
Gov. Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

SUMMARY OF BID PRICES


(All Part of Bill of Quantities)
Instruction for Completing the Summary of Bid Prices:
1. Part No. - Enter the "Part No." for each section of the Bill of Quantities (BOQ) whwre unit prices are entered.
2. Part Description - Enter the "Part Description corresponding to the "Part No."
3. Total Amount - Enter the "Total Amount" in Pesos for all pages having the same "Part Description"

Duration : 53 Calendar Days


ABC : 9,800,000.00
Item No. Description Total Amount
500(3)a Lined Canal (Rectangular, CHB) 648,125.47
502(1)a3 Manholes (910 mm dia. Concrete) ( Ductile Iron Gully Grating) 188,158.85
506(1) Stone Masonry (Headwall) 214,104.16
PART H MISCELLANEOUS STRUCTURES
600(4) Curb and Gutter (Cast in Place) 181,203.75
601 (1) Sidewalk (100 mm thk) 115,970.40

PART A EARHWORK
1707 (1) Aggregate Subbase Course 77,795.63

Sub Total for This Page: 9,702,000.00


Total of All Amount in Words

Nine Million Seven Hundred Two Thousand Pesos.

Name MARK JOSEPH C. RUBINOS in the capacity of Authorized Managing Officer

Signed DATE: May 4, 2022

Duly authorized to signed the Bid for and on behalf of NEN Builders and Development Services Corp.
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov. Vicente
Duterte, Agdao, Davao City
Location of the Contract : Davao City

BILL OF QUANTITIES
Part No. ______________ Part Description : _________________________
Part Item Description Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART B OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and km 0.626 In Words In Words
Staking Twelve Thousand Six Hundred Ninety Three Seven Thousand Nine Hundred Forty Five
Pesos and 19/100. Pesos and 94/100.
In Figures 12,693.19 In Figures 7,945.94
B.5 Project Billboard / Signboard Each 3.00 In Words In Words
(2 - 4'x8' DPWH Billboard, 1 - Five Thousand Two Hundred Thirty Four Fifteen Thousand Seven Hundred Four
8'x8' COA Billboard) Pesos and 85/100. Pesos and 56/100.
In Figures 5,234.85 In Figures 15,704.56
B.7(2) Occupational Safety and L.S. 1.00 In Words In Words
Health Program Two Hundred Thirty One Thousand Fifty Two Hundred Thirty One Thousand Fifty
Pesos and 77/100. Pesos and 77/100.
In Figures 231,050.77 In Figures 231,050.77
B.8(2) Traffic Management L.S. 1.00 In Words In Words
One Hundred Ninety Two Thousand Eight One Hundred Ninety Two Thousand Eight
Hundred Seventy Four Pesos and 50/100. Hundred Seventy Four Pesos and 50/100.
In Figures 192,874.50 In Figures 192,874.50
B.9 Mobilization/Demobilization L.s. 1.00 In Words In Words
One Hundred One Thousand Seven Hundred One Hundred One Thousand Seven Hundred
Eighty Three Pesos and 9/100. Eighty Three Pesos and 9/100.
In Figures 101,783.09 In Figures 101,783.09

In Words
SUB TOTAL FOR THIS PAGE Five Hundred Forty Nine Thousand Three
Hundred Fifty Eight Pesos and 86/100.
In Figures 549,358.86

Submitted by:

MARK JOSEPH C. RUBINOS DATE: March 18, 2022


(Name & Signature of Bidder's Representative)
Authorized Managing Officer
Position

NEN Builders and Development Services Corp.


Name of Bidder
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov. Vicente
Duterte, Agdao, Davao City
Location of the Contract : Davao City

BILL OF QUANTITIES
Part No. ______________ Part Description : _________________________
Part Item Description Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART C EARTHWORK
101(6) Removal of Actual cu.m. 57.20 In Words In Words
Structures/Obstruction
Two Thousand Five Hundred Twelve Pesos One Hundred Forty Three Thousand Seven
(Concrete)
and 66/100. Hundred Twenty Four Pesos.
In Figures 2,512.66 In Figures 143,724.00
102(2) Surplus Common Excavation cu.m. 979.90 In Words In Words
One Hundred Ninety Seven Pesos and 12/10 One Hundred Ninety Three Thousand One
Hundred Sixty Pesos and 10/100.
In Figures 197.12 In Figures 193,160.10
103(1)a Structure Excavation Cu.m. 504.30 In Words In Words
(Common Soil) Three Hundred Thirty Five Pesos and 36/100. One Hundred Sixty Nine Thousand One
Hundred Twenty Three Pesos and 50/100.
In Figures 335.36 In Figures 169,123.50
103(3) Foundation Fill cu.m. 50.40 In Words In Words
One Thousand Thirty Five Pesos and 57/100. Fifty Two Thousand One Hundred Ninety
Two Pesos and 88/100.
In Figures 1,035.57 In Figures 52,192.88
103(6)a Pipe Culvert and Drain cu.m. 185.10 In Words In Words
Excavation Five Hundred Two Pesos and 3/100. Ninety Two Thousand Nine Hundred Twenty
Five Pesos.
In Figures 502.03 In Figures 92,925.00
105(1)a Subgrade Preparation, sq.m. 2,437.50 In Words In Words
Common Material One Hundred Nineteen Pesos and 35/100. Two Hundred Ninety Thousand Nine
Hundred Seventeen Pesos and 20/100.
In Figures 119.35 In Figures 290,917.20

In Words
SUB TOTAL FOR THIS PAGE Nine Hundred Forty Two Thousand Forty
Two Pesos and 68/100.
In Figures 942,042.68

Submitted by:

MARK JOSEPH C. RUBINOS DATE: March 18, 2022


(Name & Signature of Bidder's Representative)
Authorized Managing Officer
Position

NEN Builders and Development Services Corp.


Name of Bidder
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov. Vicente
Duterte, Agdao, Davao City
Location of the Contract : Davao City

BILL OF QUANTITIES
Part No. ______________ Part Description : _________________________
Part Item Description Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART D SUB-BASE AND BASE COURSE
200(1) Aggregate Subbase Course cu.m. 487.50 In Words In Words
Seven Hundred Eighty Nine Pesos and 68/100. Three Hundred Eighty Four Thousand Nine
Hundred Sixty Nine Pesos and 92/100.
In Figures 789.68 In Figures 384,969.92
PART E SURFACE COURSES
311(1)c2 Portland Cement Concrete sq.m. 2,446.00 In Words In Words
Pavement (Unreinforced) 0.23 One Thousand Two Hundred Thirty Nine Three Million Thirty Two Thousand Three
m. thk. 7 days Pesos and 71/100. Hundred Nineteen Pesos and 93/100.
In Figures 1,239.71 In Figures 3,032,319.93
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
500(1)b3 Pipe Culverts, 910mm dia., ln.m. 139.00 In Words In Words
Class IV, RCPC Twelve Thousand Seven Hundred Nine One Million Seven Hundred Sixty Six
Pesos and 32/100. Thousand Five Hundred Ninety Five Pesos
and 94/100.
In Figures 12,709.32 In Figures 1,766,595.94
500(3)a Lined Canal (Rectangular, ln.m. 333.00 In Words In Words
CHB) Four Thousand Eight Hundred Eight One Million Six Hundred One Thousand
Pesos and 87/100. Three Hundred Fifty Four Pesos and 43/100.
In Figures 4,808.87 In Figures 1,601,354.43
500(3)a Lined Canal (Rectangular, ln.m. 132.00 In Words In Words
CHB) Four Thousand Nine Hundred Ten Pesos Six Hundred Forty Eight Thousand One
and 4/100. Hundred Twenty Five Pesos and 47/100.
In Figures 4,910.04 In Figures 648,125.47

In Words
SUB TOTAL FOR THIS PAGE Seven Million Four Hundred Thirty Three
Thousand Three Hundred Sixty Five Pesos
and 68/100.
In Figures 7,433,365.68

Submitted by:

MARK JOSEPH C. RUBINOS DATE: March 18, 2022


(Name & Signature of Bidder's Representative)
Authorized Managing Officer
Position

NEN Builders and Development Services Corp.


Name of Bidder
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov. Vicente
Duterte, Agdao, Davao City
Location of the Contract : Davao City

BILL OF QUANTITIES
Part No. ______________ Part Description : _________________________
Part Item Description Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
502(1)a3 Manholes (910 mm dia. each 7.00 In Words In Words
Concrete) ( Ductile Iron Gully
Twenty Six Thousand Eight Hundred One Hundred Eighty Eight Thousand One
Grating)
Seventy Nine Pesos and 84/100. Hundred Fifty Eight Pesos and 85/100.
In Figures 26,879.84 In Figures 188,158.85
506(1) Stone Masonry (Headwall) cu.m. 49.60 In Words In Words
Four Thousand Three Hundred Sixteen Two Hundred Fourteen Thousand One
Pesos and 62/100. Hundred Four Pesos and 16/100.
In Figures 4,316.62 In Figures 214,104.16
600(4) Curb and Gutter (Cast in ln.m 117.00 In Words In Words
Place) One Thousand Five Hundred Forty Eight One Hundred Eighty One Thousand Two
Pesos and 75/100. Hundred Three Pesos and 75/100.
In Figures 1,548.75 In Figures 181,203.75
601 (1) Sidewalk (100 mm thk) sq.m 117.00 In Words In Words
Nine Hundred Ninety One Pesos and 20/100. One Hundred Fifteen Thousand Nine
Hundred Seventy Pesos and 40/100.
In Figures 991.20 In Figures 115,970.40
1707 (1) Aggregate Subbase Course cu.m. 94.70 In Words In Words
Eight Hundred Twenty One Pesos and 50/100. Seventy Seven Thousand Seven Hundred
Ninety Five Pesos and 63/100.
In Figures 821.50 In Figures 77,795.63

In Words
Total for this Part: Seven Hundred Seventy Seven Thousand
Two Hundred Thirty Two Pesos and 79/100.
In Figures 777,232.79
In Words
GRAND TOTAL Nine Million Seven Hundred Two Thousand
Pesos.
In Figures 9,702,000.00

Submitted by:

MARK JOSEPH C. RUBINOS DATE: March 18, 2022


(Name & Signature of Bidder's Representative)
Authorized Managing Officer
Position

NEN Builders and Development Services Corp.


Name of Bidder
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part B Description: OTHER GENERAL REQUIREMENT


Pay Item No.: B.4(1)
Description: Construction Survey and Staking
Unit of Measurement : km Quantity : 0.626

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


24.00 bd.ft. 9 pcs. - 2x2x8 coco lumber 18.00 432.00
3 gal Paint 645.00 1,935.00
2 pcs Field Books 45.00 90.00

TOTAL Equipment Rental/Material Cost P 2,457.00

II. DIRECT LABOR

No. of Qty. Description Rate per Day No. of Days COST (ADD)
2 Instrumentman 650.00 1 1,300.00
4 Surveyman 550.00 1 2,200.00
3 Laborer 350.00 1 1,050.00

SUB-TOTAL 4,550.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 4,550.00

Total Direct Cost P 7,007.00


O.C.M. P -
Profit P 560.56
TAX P 378.38
Total Indirect Cost P 938.94
Total Cost P 7,945.94
Unit Cost P 12,693.19
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy.
Gov. Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part B Description: OTHER GENERAL REQUIREMENT


Pay Item No.: B.5
Description: Project Billboard / Signboard (2 - 4'x8' DPWH Billboard, 1 - 8'x8' COA Billboard)
Unit of Measurement : each Quantity : 3.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


90.00 bd.ft. Post 18 - 2" x 3" x 10' 18.00 1,620.00
48.00 bd.ft. Extended Nailer 18 - 2" x 2" x 8' 18.00 864.00
60.00 bd.ft. Diagonal Bracing 12 - 2" x 3" x 10' 18.00 1,080.00
39.99 bd.ft. Cross Bracing 12 - 2" x 2" x 10' 18.00 719.82
15.00 bd.ft. Staking 18.00 270.00
3.00 sht. 1/2" thk x 4 x 8 Marine Plywood 714.00 2,142.00
3.00 kgs Assorted C.W. Nails 76.00 228.00
3.00 lot Painting & Lettering 1,700.00 5,100.00

TOTAL Equipment Rental/Material Cost P 12,023.82

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 1.0 650.00
1 Skilled Labor 475.00 1.0 475.00
2 Unskilled Labor 350.00 1.0 700.00

SUB-TOTAL 1,825.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 1,825.00

Total Direct Cost P 13,848.82


O.C.M. P -
Profit P 1,107.91
TAX P 747.84
Total Indirect Cost P 1,855.74
Total Cost P 15,704.56
Unit Cost P 5,234.85
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part B Description: OTHER GENERAL REQUIREMENT


Pay Item No.: B.7(2)
Description: Occupational Safety and Health Program
Unit of Measurement : L.S. Quantity : 1.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


50 pcs Safety Helmet 44.79 2,239.58
50 pcs Safety Shoes 424.63 21,231.25
50 pcs Gloves 77.04 3,852.08
50 pcs Reflectorized Safety Vest 286.67 14,333.33
3 pcs Medical Kit 6,629.17 19,887.50
1 pc Signages for Safety 39,579.49 39,579.49

TOTAL Equipment Rental/Material Cost P 101,123.24

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Safety Officer 17,378.00 0.72 12,454.23
1 First Aider 12,582.00 7.17 90,171.00

SUB-TOTAL 102,625.23
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 102,625.23

Total Direct Cost P 203,748.48


O.C.M. P -
Profit P 16,299.88
TAX P 11,002.42
Total Indirect Cost P 27,302.30
Total Cost P 231,050.77
Unit Cost P 231,050.77
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part B Description: OTHER GENERAL REQUIREMENT


Pay Item No.: B.8(2)
Description: Traffic Management
Unit of Measurement : L.S. Quantity : 1.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1.00 L.S. Traffic Management 20,000.00 7.16666667 143,333.33

TOTAL Equipment Rental/Material Cost P 143,333.33

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 5 3,250.00
4 Skilled Labor 475.00 5 9,500.00
8 Unskilled Labor 350.00 5 14,000.00

SUB-TOTAL 26,750.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 26,750.00

Total Direct Cost P 170,083.33


O.C.M. P -
Profit P 13,606.67
TAX P 9,184.50
Total Indirect Cost P 22,791.17
Total Cost P 192,874.50
Unit Cost P 192,874.50
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part B Description: OTHER GENERAL REQUIREMENT


Pay Item No.: B.9
Description: Mobilization/Demobilization
Unit of Measurement : L.s. Quantity : 1.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1 units Stake Cargo 1,162.50 56.10 65,217.52
1 unit Motorized Road Grader, G710A 5 -
1 unit Vibratory Roller (10 m.t.), SP56 5 -
1 unit Bulldozer (155 Hp), D65A-8 5 -
1 unit Backhoe w/ Breaker (0.80 cu.m.) 5 -
1 unit Payload (1.50 cu.m.) 5 -
4 unit Transit Mixer (5 cu.m.) 906.25 5 18,125.00
3 unit Dumptruck (10 cu.m.) 906.25 5 13,593.75

TOTAL Equipment Rental/Material Cost P 96,936.27

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)

SUB-TOTAL -
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P -

Total Direct Cost P 96,936.27


O.C.M. P -
Profit P -
TAX P 4,846.81
Total Indirect Cost P 4,846.81
Total Cost P 101,783.09
Unit Cost P 101,783.09
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part C Description: EARTHWORKS


Pay Item No.: 101(6)
Description: Removal of Actual Structures/Obstruction (Concrete)
Unit of Measurement : cu.m. Quantity : 57.20

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1 unit Backhoe w/ Pavement Breaker 8,800.00 5 44,000.00
1 unit Backhoe 8,800.00 5 44,000.00
1 unit Dump Truck 7,250.00 9 65,250.00

TOTAL Equipment Rental/Material Cost P 109,250.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Construction Foreman 650.00 5 3,250.00
2 Unskilled Labor 350.00 5 3,500.00

SUB-TOTAL 6,750.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 6,750.00

Total Direct Cost P 116,000.00


O.C.M. P 11,600.00
Profit P 9,280.00
TAX P 6,844.00
Total Indirect Cost P 27,724.00
Total Cost P 143,724.00
Unit Cost P 2,512.66
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part C Description: EARTHWORKS


Pay Item No.: 102(2)
Description: Surplus Common Excavation
Unit of Measurement : cu.m. Quantity : 979.90

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1 unit Bulldozer 8,800.00 4.0 35,200.00
1 unit Pay Loader 7,800.00 4.0 31,200.00
1 unit Pay Loader @ Disposal Site 7,800.00 1.0 7,800.00
3 unit Dump Truck 6,425.00 4.0 77,100.00
1 unit Backhoe 8,250.00 4.0 33,000.00

TOTAL Equipment Rental/Material Cost P 149,100.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 4.0 2,600.00
3 Laborer 350.00 4.0 4,200.00

SUB-TOTAL 6,800.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 6,800.00

Total Direct Cost P 155,900.00


O.C.M. P 15,590.00
Profit P 12,472.00
TAX P 9,198.10
Total Indirect Cost P 37,260.10
Total Cost P 193,160.10
Unit Cost P 197.12
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part C Description: EARTHWORKS


Pay Item No.: 103(1)a
Description: Structure Excavation (Common Soil)
Unit of Measurement : Cu.m. Quantity : 504.30

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


2 unit Dump Truck 7,250.00 13 188,500.00
1 unit Backhoe 8,800.00 13 114,400.00

TOTAL Equipment Rental/Material Cost P 114,400.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 13 8,450.00
3 Laborer 350.00 13 13,650.00

SUB-TOTAL 22,100.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 22,100.00

Total Direct Cost P 136,500.00


O.C.M. P 13,650.00
Profit P 10,920.00
TAX P 8,053.50
Total Indirect Cost P 32,623.50
Total Cost P 169,123.50
Unit Cost P 335.36
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part C Description: EARTHWORKS


Pay Item No.: 103(3)
Description: Foundation Fill
Unit of Measurement : cu.m. Quantity : 50.40

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1 unit Plate Compactor 1,000.00 5 5,000.00
1 unit Water Truck 5,725.00 5 28,625.00

TOTAL Equipment Rental/Material Cost P 33,625.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 5 3,250.00
3 Unskilled Labor 350.00 5 5,250.00

SUB-TOTAL 8,500.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 8,500.00

Total Direct Cost P 42,125.00


O.C.M. P 4,212.50
Profit P 3,370.00
TAX P 2,485.38
Total Indirect Cost P 10,067.88
Total Cost P 52,192.88
Unit Cost P 1,035.57
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part C Description: EARTHWORKS


Pay Item No.: 103(6)a
Description: Pipe Culvert and Drain Excavation
Unit of Measurement : cu.m. Quantity : 185.10

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


2 unit Dump Truck 7,250.00 3 43,500.00
1 unit Backhoe 8,800.00 3 26,400.00

TOTAL Equipment Rental/Material Cost P 69,900.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 3 1,950.00
3 Unskilled Labor 350.00 3 3,150.00

SUB-TOTAL 5,100.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 5,100.00

Total Direct Cost P 75,000.00


O.C.M. P 7,500.00
Profit P 6,000.00
TAX P 4,425.00
Total Indirect Cost P 17,925.00
Total Cost P 92,925.00
Unit Cost P 502.03
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part C Description: EARTHWORKS


Pay Item No.: 105(1)a
Description: Subgrade Preparation, Common Material
Unit of Measurement : sq.m. Quantity : 2,437.50

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1 unit Road Grader 8,250.00 13 107,250.00
1 unit Road Roller 6,700.00 13 87,100.00
1 unit Water Truck 5,725.00 4 22,900.00

TOTAL Equipment Rental/Material Cost P 217,250.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 13 8,450.00
2 Laborer 350.00 13 9,100.00

SUB-TOTAL 17,550.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 17,550.00

Total Direct Cost P 234,800.00


O.C.M. P 23,480.00
Profit P 18,784.00
TAX P 13,853.20
Total Indirect Cost P 56,117.20
Total Cost P 290,917.20
Unit Cost P 119.35
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part D Description: SUB-BASE & BASE COURSE


Pay Item No.: 200(1)
Description: Aggregate Subbase Course
Unit of Measurement : cu.m. Quantity : 487.50

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1 unit Road Grader 8,250.00 2 13,868.53
1 unit Road Roller 6,700.00 2 11,262.93
1 unit Water Truck 5,725.00 0.42 2,404.50

560.63 cu.m. 500.00 280,312.50

TOTAL Equipment Rental/Material Cost P 307,848.47


II. DIRECT LABOR
No. of Qty. Rate per Hour/Day COST (ADD)
1 Construction Foreman 650.00 2 1,092.67
3 Unskilled Labor 350.00 2 1,765.09

SUB-TOTAL 2,857.76
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 2,857.76

Total Direct Cost P 310,706.22


O.C.M. P 31,073.07
Profit P 24,858.72
TAX P 18,331.90
Total Indirect Cost P 74,263.69
Total Cost P 384,969.92
Unit Cost P 789.68
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part E Description: SURFACE COURSE


Pay Item No.: 311(1)c2
Description: Portland Cement Concrete Pavement (Unreinforced) 0.23 m. thk. 7 days
Unit of Measurement : sq.m. Quantity : 2,446.00

I. EQUIPMENT RENTAL/MATERIALS:
No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)
71.00 kg. Reinforcing Steel Bar 44.00 3,124.00
48.00 lit. Curing Compound 95.00 4,560.00
20.00 lit. Asphalt Sealant 44.00 880.00
76.00 m. Steel Forms (Rental) 61.00 4,636.00
21.00 cu.m. Sand 556.00 11,676.00
38.00 cu.m. Gravel 676.00 25,688.00
358.00 bag Cement 260.00 93,080.00
1.00 pc Concrete Saw 8,000.00 8,000.00
2.00 m. Pipe Sleeve, 2"Ø 97.00 194.00
2.00 lit. Grease/Tar 300.00 600.00
TOTAL Materials Cost P 152,438.00

4.00 unit Transit Mixer 7,250.00 31.00 899,000.00


2.00 unit Concrete Vibrator 1,030.00 31.00 63,860.00
1.00 unit Concrete Batch Plant 14,100.00 31.00 437,100.00
1.00 unit Payloader 11,550.00 31.00 358,050.00
1.00 unit Concrete Screeder 4,360.00 31.00 135,160.00
1.00 unit Water Truck 5,725.00 31.00 177,475.00
1.00 unit Concrete Saw 260.00 31.00 8,060.00
1.00 unit Bar Cutter 1,750.00 4.00 7,000.00

TOTAL Equipment Rental P 2,085,705.00

TOTAL Equipment Rental/Material Cost P 2,238,143.00


II. DIRECT LABOR
No. of Qty. Description Rate per Hour/Day COST (ADD)
1 Construction Foreman 650.00 31.00 20,150.00
4 Skilled Labor 475.00 31.00 58,900.00
12 Unskilled Labor 350.00 31.00 130,200.00

SUB-TOTAL 209,250.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 209,250.00

Total Direct Cost P 2,447,393.00


O.C.M. P 244,739.30
Profit P 195,791.44
TAX P 144,396.19
Total Indirect Cost P 584,926.93
Total Cost P 3,032,319.93
Unit Cost P 1,239.71
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part G Description: DRAINAGE & SLOPE PROTECTION STRUCTURE


Pay Item No.: 500(1)b3
Description: Pipe Culverts, 910mm dia., Class IV, RCPC
Unit of Measurement : ln.m. Quantity : 139.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


139 pcs. 910mmØ RCPC 2,500.00 347,500.00
151 bags Portland Cement 258.00 38,958.00
9 cu.m. Washed Sand 700.00 6,300.00
18.0 cu.m. Gravel Bedding 850.00 15,300.00

2.00 unit Backhoe 8,800.00 40 709,456.00


1.00 unit Plate Compactor 1,000.00 40 40,310.00

TOTAL Equipment Rental/Material Cost P 1,157,824.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 80 52,000.00
2 Mason 475.00 80 76,000.00
5 Laborer 350.00 80 140,000.00

SUB-TOTAL 268,000.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 268,000.00

Total Direct Cost P 1,425,824.00


O.C.M. P 142,582.40
Profit P 114,065.92
TAX P 84,123.62
Total Indirect Cost P 340,771.94
Total Cost P 1,766,595.94
Unit Cost P 12,709.32
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part G Description: DRAINAGE & SLOPE PROTECTION STRUCTURE


Pay Item No.: 500(3)a
Description: Lined Canal (Rectangular, CHB)
Unit of Measurement : ln.m. Quantity : 333.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1,866 bags Portland Cement 258.00 481,428.00
127.0 cu.m. Washed Sand 700.00 88,900.00
206.0 cu.m. Washed Gravel 850.00 175,100.00
2,772.6 kg. Reinforcing Bars 44.00 121,993.05
55.5 kg. Tie Wire 80.00 4,436.11

2.00 unit Dumptruck 7,250.00 14.0 203,000.00


1.00 unit One Bagger Concrete Mixer 1,670.00 34.0 56,780.00
1.00 unit Concrete Vibrator 1,030.00 34.0 35,020.00

TOTAL Equipment Rental/Material Cost P 1,166,657.16

II. DIRECT LABOR


No. of Qty. Rate per Hour/Day COST (ADD)
1 Construction Foreman 650.00 34 22,100.00
2 Skilled Labor 475.00 34 32,300.00
6 Unskilled Labor 350.00 34 71,400.00

SUB-TOTAL 125,800.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 125,800.00

Total Direct Cost P 1,292,457.16


O.C.M. P 129,245.72
Profit P 103,396.57
TAX P 76,254.97
Total Indirect Cost P 308,897.26
Total Cost P 1,601,354.43
Unit Cost P 4,808.87
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part G Description: DRAINAGE & SLOPE PROTECTION STRUCTURE


Pay Item No.: 500(3)a
Description: Lined Canal (Rectangular, CHB)
Unit of Measurement : ln.m. Quantity : 132.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


740 bags Portland Cement 258.00 190,920.00
51.0 cu.m. Washed Sand 700.00 35,700.00
82.0 cu.m. Washed Gravel 850.00 69,700.00
1,100.5 kg. Reinforcing Bars 44.00 48,422.86
22.0 kg. Tie Wire 80.00 1,760.83

2.00 unit Dumptruck 7,250.00 6.0 87,000.00


1.00 unit One Bagger Concrete Mixer 1,670.00 14.0 23,380.00
1.00 unit Concrete Vibrator 1,030.00 14.0 14,420.00

TOTAL Equipment Rental/Material Cost P 471,303.69

II. DIRECT LABOR


No. of Qty. Rate per Hour/Day COST (ADD)
1 Construction Foreman 650.00 14 9,100.00
2 Skilled Labor 475.00 14 13,300.00
6 Unskilled Labor 350.00 14 29,400.00

SUB-TOTAL 51,800.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 51,800.00

Total Direct Cost P 523,103.69


O.C.M. P 52,310.37
Profit P 41,848.30
TAX P 30,863.12
Total Indirect Cost P 125,021.78
Total Cost P 648,125.47
Unit Cost P 4,910.04
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part G Description: DRAINAGE & SLOPE PROTECTION STRUCTURE


Pay Item No.: 502(1)a3
Description: Manholes (910 mm dia. Concrete) ( Ductile Iron Gully Grating)
Unit of Measurement : each Quantity : 7.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


34 bags Portland Cement 258.00 8,772.00
2.0 cu.m. Washed Sand 700.00 1,400.00
4.0 cu.m. Washed Gravel 850.00 3,400.00
2 shts. 10mm thk. Ordinary Plywood 714.00 1,428.00
2,000 bd.ft. Assorted Coco lumber 18.00 36,000.00
590.08 kgs Reinforcing Steel Bars 44.00 25,963.48

TOTAL Equipment Rental/Material Cost P 76,963.48


II. DIRECT LABOR
No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 14.0 9,100.00
2 Carpenter 475.00 14.0 13,300.00
2 Mason 475.00 14.0 13,300.00
8 Laborer 350.00 14.0 39,200.00

SUB-TOTAL 74,900.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 74,900.00

Total Direct Cost P 151,863.48


O.C.M. P 15,186.35
Profit P 12,149.08
TAX P 8,959.95
Total Indirect Cost P 36,295.37
Total Cost P 188,158.85
Unit Cost P 26,879.84
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part G Description: DRAINAGE & SLOPE PROTECTION STRUCTURE


Pay Item No.: 506(1)
Description: Stone Masonry (Headwall)
Unit of Measurement : cu.m. Quantity : 49.60

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1.00 unit One Bagger Mixer 1,670.00 6 1,670.00
1.00 unit Water Truck 5,725.00 1 5,725.00
1.00 unit Backhoe 8,800.00 1 8,800.00

273.00 bag Portland Cement 258.00 70,434.00


15.00 cu.m. Sand 700.00 10,500.00
1.00 cu.m. Gravel Fill 850.00 850.00
15.00 m Weep Holes (PVC) 390.00 5,850.00
1.00 sq.m. Filter Cloth 175.00 175.00
53.00 cu.m. Boulders 800.00 42,400.00

TOTAL Equipment Rental/Material Cost P 146,404.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)
1 Project Foreman 650.00 6 3,900.00
2 Mason 475.00 6 5,700.00
8 Laborer 350.00 6 16,800.00

SUB-TOTAL 26,400.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 26,400.00

Total Direct Cost P 172,804.00


O.C.M. P 17,280.40
Profit P 13,824.32
TAX P 10,195.44
Total Indirect Cost P 41,300.16
Total Cost P 214,104.16
Unit Cost P 4,316.62
Department of Public Works and Highways (DPWH)
Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part H Description: MISCELLANEOUS STRUCTURES


Pay Item No.: 600(4)
Description: Curb and Gutter (Cast in Place)
Unit of Measurement : ln.m Quantity : 117.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


117 pcs. Curb and Gutter (Cast in Place) 1,250.00 146,250.00

TOTAL Equipment Rental/Material Cost P 146,250.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)

SUB-TOTAL -
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P -

Total Direct Cost P 146,250.00


O.C.M. P 14,625.00
Profit P 11,700.00
TAX P 8,628.75
Total Indirect Cost P 34,953.75
Total Cost P 181,203.75
Unit Cost P 1,548.75
Department of Public Works and Highways (DPWH)
Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part H Description: MISCELLANEOUS STRUCTURE


Pay Item No.: 601 (1)
Description: Sidewalk (100 mm thk)
Unit of Measurement : sq.m Quantity : 117.00

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


117.00 sq.m Sidewalk (100 mm thk) 800.00 93,600.00

TOTAL Equipment Rental/Material Cost P 93,600.00

II. DIRECT LABOR


No. of
No. of Qty. Description Rate per Hour/Day Hours/Days COST (ADD)

SUB-TOTAL -
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P -

Total Direct Cost P 93,600.00


O.C.M. P 9,360.00
Profit P 7,488.00
TAX P 5,522.40
Total Indirect Cost P 22,370.40
Total Cost P 115,970.40
Unit Cost P 991.20
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract : Davao City

DETAILED ESTIMATES

Part I-A Description: EARTHWORK (FLOOD CONTROL CONTROL)


Pay Item No.: 1707 (1)
Description: Aggregate Subbase Course
Unit of Measurement : cu.m. Quantity : 94.70

I. EQUIPMENT RENTAL/MATERIALS:

No. of Qty. Description Rental/Unit Cost No. of days COST (ADD)


1 unit Road Grader 8,250.00 0.47 3,877.50
1 unit Road Roller 6,700.00 0.47 3,149.00
1 unit Water Truck 5,725.00 0.12 675.55

108.91 cu.m. Aggragate Subbase Materials 500.00 54,452.50

TOTAL Equipment Rental/Material Cost P 62,154.55


II. DIRECT LABOR
No. of Qty. Rate per Hour/Day COST (ADD)
1 Construction Foreman 650.00 0.47 305.50
2 Unskilled Labor 350.00 0.47 329.00

SUB-TOTAL 634.50
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 634.50

Total Direct Cost P 62,789.05


O.C.M. P 6,278.91
Profit P 5,023.12
TAX P 3,704.55
Total Indirect Cost P 15,006.58
Total Cost P 77,795.63
Unit Cost P 821.50
TIME MOTION ANALYSIS
2a/8

ITEM 102 : DISPOSAL OF WASTE MATERIALS


QUANTITY : #REF! cu.m.
Quarry Distance : 7.0 kms
Quarry Site : Brgy. Langtud
Dumptruck travel time without load = Quarry Distance
Velocity of DT w/out load
= 7.00 kms. X 60 mins./hr.
40 km/hr.
= 420.0 min. = 10.50 min.
40.0

Dumptruck travel time with load = Quarry Distance


Velocity of DT w/ load
= 7.00 kms. X 60 mins./hr.
35 km/hr.
= 420.0 min. = 12.00 min.
35.0

time loading = 10 min ; turning time = 4 min = 14.00 min.


time unloading = 4 min ; turning time = 4 min = 8.00 min.
Total DT travel time = 44.50 min.

No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 10.11 trips/day
Total DT travel time 44.50
say 10.00 trips/day

Using No. of Units Dumptrucks: 3 units 10W Dumptrucks

Volume hauled per day: 10 trips x 3 DT x 8 cu.m = 240.00 cu.m./day

=
No. of days to complete hauling = #REF! cu.m. #REF! days

240.00 cu.m./day say #REF! days

Loader Requirement:

Capacity of Loader par day = 30 cu.m. x 8.0 hrs./day


= 240.0 cu.m.

Use the maximum Loader requirement = 240.0 cu.m.


240.0 cu.m.
= 1.00 day/s

say 1.0 Loader/s


TIME MOTION ANALYSIS
2a/8

ITEM 102 : DISPOSAL OF WASTE MATERIALS


QUANTITY : #REF! cu.m.
Quarry Distance : 5.0 kms
Quarry Site : Brgy. Langtud
Dumptruck travel time without load = Quarry Distance
Velocity of DT w/out load
= 5.00 kms. X 60 mins./hr.
40 km/hr.
= 300.0 min. = 7.50 min.
40.0

Dumptruck travel time with load = Quarry Distance


Velocity of DT w/ load
= 5.00 kms. X 60 mins./hr.
35 km/hr.
= 300.0 min. = 8.57 min.
35.0

time loading = 10 min ; turning time = 4 min = 14.00 min.


time unloading = 4 min ; turning time = 4 min = 8.00 min.
Total DT travel time = 38.07 min.

No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day

Using No. of Units Dumptrucks: 3 units 10W Dumptrucks

Volume hauled per day: 11 trips x 3 DT x 8 cu.m = 264.00 cu.m./day

=
No. of days to complete hauling = #REF! cu.m. #REF! days

264.00 cu.m./day say #REF! days

Loader Requirement:

Capacity of Loader par day = 30 cu.m. x 8.0 hrs./day


= 240.0 cu.m.

Use the maximum Loader requirement = 264.0 cu.m.


240.0 cu.m.
= 1.10 day/s

say 1.0 Loader/s

TIME MOTION ANALYSIS


2a/8

ITEM 102 : DISPOSAL OF WASTE MATERIALS


QUANTITY : #REF! cu.m.
Quarry Distance : 5.0 kms
Quarry Site : Brgy. Langtud
Dumptruck travel time without load = Quarry Distance
Velocity of DT w/out load
= 5.00 kms. X 60 mins./hr.
40 km/hr.
= 300.0 min. = 7.50 min.
40.0

Dumptruck travel time with load = Quarry Distance


Velocity of DT w/ load
= 5.00 kms. X 60 mins./hr.
35 km/hr.
= 300.0 min. = 8.57 min.
35.0

time loading = 10 min ; turning time = 4 min = 14.00 min.


time unloading = 4 min ; turning time = 4 min = 8.00 min.
Total DT travel time = 38.07 min.

No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day

Using No. of Units Dumptrucks: 3 units 10W Dumptrucks

Volume hauled per day: 11 trips x 3 DT x 8 cu.m = 264.00 cu.m./day

=
No. of days to complete hauling = #REF! cu.m. #REF! days

264.00 cu.m./day say #REF! days

Loader Requirement:

Capacity of Loader par day = 30 cu.m. x 8.0 hrs./day


= 240.0 cu.m.

Use the maximum Loader requirement = 264.0 cu.m.


240.0 cu.m.
= 1.10 day/s

say 1.0 Loader/s

TIME MOTION ANALYSIS


2a/8

ITEM 102 : DISPOSAL OF WASTE MATERIALS


QUANTITY : #REF! cu.m.
Quarry Distance : 5.0 kms
Quarry Site : Brgy. Langtud
Dumptruck travel time without load = Quarry Distance
Velocity of DT w/out load
= 5.00 kms. X 60 mins./hr.
40 km/hr.
= 300.0 min. = 7.50 min.
40.0

Dumptruck travel time with load = Quarry Distance


Velocity of DT w/ load
= 5.00 kms. X 60 mins./hr.
35 km/hr.
= 300.0 min. = 8.57 min.
35.0

time loading = 10 min ; turning time = 4 min = 14.00 min.


time unloading = 4 min ; turning time = 4 min = 8.00 min.
Total DT travel time = 38.07 min.

No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day

Using No. of Units Dumptrucks: 3 units 10W Dumptrucks

Volume hauled per day: 11 trips x 3 DT x 8 cu.m = 264.00 cu.m./day


=
No. of days to complete hauling = #REF! cu.m. #REF! days

264.00 cu.m./day say #REF! days

Loader Requirement:

Capacity of Loader par day = 30 cu.m. x 8.0 hrs./day


= 240.0 cu.m.

Use the maximum Loader requirement = 264.0 cu.m.


240.0 cu.m.
= 1.10 day/s

say 2.0 Loader/s

ITEM 200 : AGGREGATE SUB-BASE COURSE


QUANTITY : #REF! cu.m.
Quarry Distance : 20.0 kms
Quarry Site : Maragusan River, Maragusan
Dumptruck travel time without load = Quarry Distance
Velocity of DT w/out load
= 20.00 kms. X 60 mins./hr.
40 km/hr.
= 1,200.0 min. = 30.00 min.
40.0

Dumptruck travel time with load = Quarry Distance


Velocity of DT w/ load
= 20.00 kms. X 60 mins./hr.
35 km/hr.
= 1,200.0 min. = 34.29 min.
35.0

time loading = 10 min ; turning time = 4 min = 14.00 min.


time unloading = 4 min ; turning time = 4 min = 8.00 min.
Total DT travel time = 86.29 min.

No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 5.21 trips/day
Total DT travel time 86.29
say 5.00 trips/day

Using No. of Units Dumptrucks: 3 units 10W Dumptrucks

Volume hauled per day: 5 trips x 3 DT x 8 cu.m. = 120.00 cu.m./day

=
No. of days to complete hauling = #REF! cu.m. #REF! days

120.00 cu.m./day say #REF! days

Loader Requirement:

Capacity of Loader par day = 30 cu.m. x 8.0 hrs./day


= 240.0 cu.m.

Use the maximum Loader requirement = 120.0 cu.m.


240.0 cu.m.
= 0.50 day/s

say 1.0 Loader/s


ITEM 200 : AGGREGATE SUB-BASE COURSE
QUANTITY : #REF! cu.m.
Quarry Distance : 15.0 kms
Quarry Site : Maragusan River, Maragusan
Dumptruck travel time without load = Quarry Distance
Velocity of DT w/out load
= 15.00 kms. X 60 mins./hr.
40 km/hr.
= 900.0 min. = 22.50 min.
40.0

Dumptruck travel time with load = Quarry Distance


Velocity of DT w/ load
= 15.00 kms. X 60 mins./hr.
35 km/hr.
= 900.0 min. = 25.71 min.
35.0

time loading = 10 min ; turning time = 4 min = 14.00 min.


time unloading = 4 min ; turning time = 4 min = 8.00 min.
Total DT travel time = 70.21 min.

No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 6.41 trips/day
Total DT travel time 70.21
say 6.00 trips/day

Using No. of Units Dumptrucks: 3 units 10W Dumptrucks

Volume hauled per day: 6 trips x 3 DT x 8 cu.m. = 144.00 cu.m./day

=
No. of days to complete hauling = #REF! cu.m. #REF! days

144.00 cu.m./day say #REF! days

Loader Requirement:

Capacity of Loader par day = 30 cu.m. x 8.0 hrs./day


= 240.0 cu.m.

Use the maximum Loader requirement = 144.0 cu.m.


240.0 cu.m.
= 0.60 day/s

say 1.0 Loader/s

ITEM 300 : #REF!


QUANTITY : #REF! cu.m.
Quarry Distance : 15.0 kms
Quarry Site : Maragusan River, Maragusan
Dumptruck travel time without load = Quarry Distance
Velocity of DT w/out load
= 15.00 kms. X 60 mins./hr.
40 km/hr.
= 900.0 min. = 22.50 min.
40.0

Dumptruck travel time with load = Quarry Distance


Velocity of DT w/ load
= 15.00 kms. X 60 mins./hr.
35 km/hr.
= 900.0 min. = 25.71 min.
35.0

time loading = 10 min ; turning time = 4 min = 14.00 min.


time unloading = 4 min ; turning time = 4 min = 8.00 min.
Total DT travel time = 70.21 min.

No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 6.41 trips/day
Total DT travel time 70.21
say 6.00 trips/day

Using No. of Units Dumptrucks: 3 units 10W Dumptrucks

Volume hauled per day: 6 trips x 3 DT x 8 cu.m. = 144.00 cu.m./day

=
No. of days to complete hauling = #REF! cu.m. #REF! days

144.00 cu.m./day say #REF! days

Loader Requirement:

Capacity of Loader par day = 30 cu.m. x 8.0 hrs./day


= 240.0 cu.m.

Use the maximum Loader requirement = 144.0 cu.m.


240.0 cu.m.
= 0.60 day/s

say 1.0 Loader/s


No. of days to complete hauli = - cu.m. #DIV/0! days
=
- cu.m./day say #DIV/0! days
BACK-UP COMPUTATION
3a/8

ITEM 104: EMBANKMENT


NOTE: Please refer to the quantity sheet for the total volume

Volume = #REF! cu.m


Shrinkage Factor:@ 25% #REF! cu.m x 1.25 = #REF! cu.m

Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days

COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days

WATERTRUCK: Every 1 unit 3 days interval of compactor


No. of days required: #REF! / 3 = #REF! days say #REF! days

TECHNICAL: = No. of days of Hauling + No. of days of compaction/2


= #REF! + #REF! = #REF! days say #REF! days

Volume = #REF! cu.m


Shrinkage Factor:@ 25% #REF! cu.m x 1.25 = #REF! cu.m

Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days

COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days

WATERTRUCK: Every 1 unit 3 days interval of compactor


No. of days required: #REF! / 3 = #REF! days say #REF! days

TECHNICAL: = No. of days of Hauling + No. of days of compaction/2


= #REF! + #REF! = #REF! days say #REF! days

BACK-UP COMPUTATION
5b/8

ITEM 200: AGGREGATE SUB-BASE COURSE

Volume = #REF! cu.m. 1 = #REF! cu.m


Shrinkage Factor: @ 15 % #REF! x 1.15 = #REF! cu.m

Equipments Required :
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 cu.m/day
No. of days required: #REF! / 420 = #REF! days say #REF! days

COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days

WATERTRUCK: Every 1 unit 3 days interval of compactor


No. of days required: #REF! / 3 = #REF! days say #REF! days

TECHNICAL: = No. of days of Hauling + No. of days of compaction/2


= #REF! + #REF! = #REF! days say #REF! days

ITEM 200: AGGREGATE SUB-BASE COURSE

Volume = #REF! cu.m. 1 = #REF! cu.m


Shrinkage Factor: @ 15 % #REF! x 1.15 = #REF! cu.m

Equipments Required :
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 cu.m/day
No. of days required: #REF! / 420 = #REF! days say #REF! days

COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days

WATERTRUCK: Every 1 unit 3 days interval of compactor


No. of days required: #REF! / 3 = #REF! days say #REF! days

TECHNICAL: = No. of days of Hauling + No. of days of compaction/2


= #REF! + #REF! = #REF! days say #REF! days
BACK - UP COMPUTATION

ITEM SCOPE OF WORK

505(2) GROUTED RIPRAP

Volume = = #REF! say #REF! cu.m.

Quantity:
Volume Multiplier
Cement = #REF! x 4.5 = #REF! bags say #REF! bags
Sand = #REF! x 0.625 = #REF! say #REF! cu.m.
Boulders = #REF! x 0.95 = #REF! say #REF! cu.m.

506 STONE MASONRY

Volume = = #REF! say #REF! cu.m.

Quantity:
Volume Multiplier
Cement = #REF! x 4.5 = #REF! bags say #REF! bags
Sand = #REF! x 0.625 = #REF! say #REF! cu.m.
Boulders = #REF! x 0.95 = #REF! say #REF! cu.m.

507(1) Rubble Concrete

Volume = = #REF! say #REF! cu.m.

Quantity:
Volume Multiplier
Cement = #REF! x 5.5 = #REF! bags say #REF! bags
Sand = #REF! x 0.625 = #REF! say #REF! cu.m.
Boulders = #REF! x 0.95 = #REF! say #REF! cu.m.
Department of Public Works and Highways (DPWH)

Contract ID :22LB0413
Contract Name Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract Davao City

SUMMARY DATA SHEET

MANPOWER
Project Engineer 1,000.00 / day
C & M Foreman / Eng'ng Assistant 650.00 / day
Laborer / T&C Helper 350.00 / day
Mason/ Steelman/ Carpenter/ Painter 475.00 / day
Welder/Eletrician 420.00 / day
H.E.O. (Bulldozer/Excavator/Loader/Grader/Crane/Prime Mover) 550.00 / day
Driver (Dumptruck/Water Truck) 475.00 / day
L.E.O. (Compactor, Vibrator, Mixer) 425.00 / day

EQUIPMENT FUEL CONSUMPTION OPERATED Rental 100%


Crane 80.00 lit. / day 21,250.00 / day
Bulldozer 80.00 lit. / day 14,900.00 / day
Back hoe 60.00 lit. / day 8,800.00 / day
Dump Truck 50.00 lit. / day 7,250.00 / day
Water Truck 35.00 lit. / day 5,725.00 / day
Road Grader 50.00 lit. / day 8,250.00 / day
Road Roller 40.00 lit. / day 6,700.00 / day
Pay Loader 50.00 lit. / day 11,550.00 / day
Transit Mixer 40.00 lit. / day 7,250.00 / day
PRIME MOVER/ LOW BED TRAILER 60.00 lit. / day 9,300.00 / day
Single Bagger Concrete Mixer 6.00 lit. / day 1,670.00 / day
Concrete Vibrator 6.00 lit. / day 1,030.00 / day
PLATE COMPACTOR 5.00 lit. / day 1,000.00 / day
Chainsaw Operated 2,400.00 / day
Concrete Cutter Operated 1,250.00 / day
BAR CUTTER /BAR SHEAR Operated 1,750.00 / day
BAR BENDER Operated 1,100.00 / day
Concrete Batch Plant 14,100.00 / day
Concrete Screeder 4,360.00 / day
Concrete Saw 260.00 / day
DIESEL 50.00 / liter
GASOLINE 60.00 / liter

Submitted by:

MARK JOSEPH C. RUBINOS DATE: May 4, 2022


(Name & Signature of Bidder's Representative)
Authorized Managing Officer
Position
NEN Builders and Development Services Corp.
Name of Bidder
Department of Public Works and Highways (DPWH)

Contract ID :22LB0413
Contract Name Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract Davao City

SUMMARY DATA SHEET

MATERIALS
Portland Cement 258.00 / bags
Reinforcing Deformed bars 44.00 / kg.
Asphalt cement 60/70 Hot poured 44.00 / liter
Plastic Canvass (12 ft. wide) 141.60 / mtrs
Hacksaw blade (Heavy duty) 82.00 / pcs
Deformed bars/RSB (Grade 40) 42.00 / kgs.
Assorted CW Nails 76.00 / kgs.
Tarpauline - as per design 25.00 / sq.ft.
Ordinary plywood, 10mm thk. x 4' x 8' 714.00 / pc/s
Ordinary plywood, 5mm thk. x 4' x 8' 612.00 / pc/s
Coco Lumber 18.00 / bdft.
Coco Net 120.00 sq.m.
Coco Log 390.00 ln.m.
Vegitation 81.00 sq.m.
Tie Wire, G.I # 16 80.00 / kgs.
4" CWN 70.00 / kgs.
Boulders Extraction 50.00 / cu.m.
CHB 4" 20.00 / pcs
REINFORCING STEEL 44.10 / kgs.
TIE WIRE # 16 76.00 / kgs.
HACKSAW BLADE 70.00 / pcs
WASHED GRAVEL 850.00 / cu.m.
WASHED GRAVEL Y-Y 700.00 / cu.m.
WASHED SAND 700.00 / cu.m.
AGGREGATE BASE COARSE 500.00 / cu.m.
AGGREGATE SUB-BASE COARSE 500.00 / cu.m.
BOULDERS 800.00 / cu.m.
GOODMIX 500.00 / cu.m.

Submitted by:

MARK JOSEPH C. RUBINOS DATE: May 4, 2022


(Name & Signature of Bidder's Representative)
Authorized Managing Officer
Position

NEN Builders and Development Services Corp.


Name of Bidder
Department of Public Works and Highways (DPWH)

Contract ID :22LB0413
Contract Name Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov.
Vicente Duterte, Agdao, Davao City
Location of the Contract Davao City

SUMMARY DATA SHEET

Embankment Borrow 400.00 / cu.m.


CWN 4" 1,305.00 / keg
CWN 4" 65.00 / kgs.
CWN 3" 1,350.00 / keg
CWN 3" 65.00 / kgs.
CWN 2 1/2" 1,863.00 / keg
CWN 2 1/2" 72.00 / kgs.
CWN 1 1/2" 1,800.00 / keg
CWN 1 1/2" 75.00 / kgs.
ANGLE BAR 100mm x 100mm x 9mm thk. x 6m 13,550.00 / length
PIPE, B.I. Sch. 40, 4" Ø x 6M 3,645.00 / length
PLAIN G.I. SHEET, 0.04mm thk x 4' x 8' type II, Grade C 535.00 / sht
ORDINARY PLYWOOD, GRADE B(INTERIOR), 17mm thk. x 4' x 8' 890.00 / sht
ORDINARY PLYWOOD, PS MARKED, 11mm thk. x 4' x 8' 612.00 / sht
ORDINARY PLYWOOD, 5mm thk. x 4' x 8' type II Grade C 330.00 / sht
610 mm PIPE CULVERT 1,560.00 / pcs
910 mm PIPE CULVERT 2,500.00 / pcs
1220 mm PIPE CULVERT 7,500.00 / pcs
1830 mm PIPE CULVERT 11,500.00 / pcs
GEMELINA LUMBER 32.00 / bd.ft.
COCO LUMBER 17.00 / bd.ft.
COCO TRUNKS 1,500.00 / pcs
Steel Sheet Pile 4,800.00 / ln.m.
PAINT, PERMACOAT LATEX PAINT 515.00 / gals
REFLECTORIZED TRAFFIC PAINT (YELLOW). PREM. GRADE 2,900.00 / gals
ROLLER BRUSH SET #7 90.00 / pcs
4" PAINT BRUSH 45.00 / pcs
3" PAINT BRUSH 45.00 / pcs
2" PAINT BRUSH 45.00 / pcs

Submitted by:

MARK JOSEPH C. RUBINOS DATE: May 4, 2022


(Name & Signature of Bidder's Representative)
Authorized Managing Officer
Position

NEN Builders and Development Services Corp.


Name of Bidder
Department of Public Works and Highways (DPWH)

Contract ID : 22LB0413
Contract Name : Rehabilitation of Road including drainage canal, Purok Vilguz & Kasadya, Brgy. Gov. Vicente Duterte, Agdao, Davao City

Location of the Contract : Davao City


ABC : 9,800,000.00

CASH FLOW BY QUARTER

YEAR
PARTICULAR TOTAL
FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER
Percentage Accomplishment 100.00% 25.17% 26.21% 29.21% 19.41%
AMOUNT 2,441,532.94 2,543,316.03 2,834,233.23 1,882,917.80
Cumulative Percentage Accomplishment 100.00% 25.17% 51.38% 80.59% 100.00%
AMOUNT 2,441,532.94 4,984,848.97 7,819,082.20 9,702,000.00

Submitted by:

MARK JOSEPH C. RUBINOS DATE: May 4, 2022


(Name & Signature of Bidder's Representative)
Authorized Managing Officer
Position

NEN Builders and Development Services Corp.


Name of Bidder

You might also like