You are on page 1of 23

Department of Public Works and Highways (DPWH)

Contract ID : 19IG0007
Contract Name : Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and
Landslide - Primary Roads - Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-
Location of the Contract : K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

BID FORM

Date: November 6, 2018


IAEB No. 19IG0007

To:

BAC CHAIRMAN
DPWH - Leyte 5th District Engineering Office
Brgy. Hipusngo, Baybay City, Leyte

We, the undersigned, declare that:

(a) We have examined and have no reservation on the Bidding Documents, including Addenda, for the Contract:

Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary
Roads - Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580,
K0994+680-K0994+780

(b) We offer to execute the Works for this Contract in accordance with the Bid and Bid Data Sheet, General and Special
Conditions of Contract accompanying this Bid;
The Total price of our Bid, excluding any discounts offeres in item (d) below is:

Thirty Million Eight Hundred Ninety Nine Thousand Eighty Eight Pesos & 70/100
(P 30,899,088.70 )
The discounts offered and the methodology for their apllication is: (___)

(c) Our Bid shall be valid for a period of 120days from the date fixed for the Bid submission deadline in accordance with the
Bidding Documents, and it shall remain binding upon us and may be accepted at any time before the expiration of that period;

(d) If our Bid accepted, we commit to obtain a Performance Security in the amount of (___) percent of the Contract Price for the
due perforamce of the Contract;

(e) Our firm, including any subcontractors or suppliers for any part of the Contract, have nationalities from the following eligible
countries;

(f) We are not participating, as Bidders, in more than one Bid in this Bidding process, other than alternative offers in accordance
with the Bidding Documents;

(g) Our firm, its affiliates or subsidiaries, including any subcontractors or suppliers for any part of the Contract, has not been
declared ineligible by the Funding Source;

(h) We understand that this Bid, together with your written acceptance therof included in your notification of award, shall
constitute of binding contract between us, until a formal Contract is prepared and executed; and

(i) We understand that you are not bound to accept the Lowest Evaluated Bid or any other Bid that you may receive.

Name: ROGELIO P. ALLOSA

In the Capacity of: Proprietor/General Manager

Signed:

Duly authorized to sign the Bid for and on Behalf of : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

Date : November 6, 2018


CID No. 19IG0007 - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads -

Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

SUMMARY OF BID PRICES


(All Parts of Bill of Quantities)

Instructions for completing the Summary of Bid Prices:


1. Part No. Enter the "Part No." for each section of the Bill of Quantities (BOQ) where unit prices are entered.

2. Part Description - Enter the "Part Description" corrresponding to the "Part No."

3. Total Amount - Enter the "Total Amount" in Pesos for all pages having the same "Part Description"

Contract ID: 19IG0007


Part No. Part Description Total Amount

OTHER GENERAL REQUIREMENTS


B 3,222,786.85
(Vol. II, Revised 2012 Edition DPWH Specifications for Highways, Bridges & Airports)
EARTHWORKS
C 3,490,179.68
(Vol. II, Revised 2012 Edition DPWH Specifications for Highways, Bridges & Airports)
SURFACE COURSE
E 726,640.74
(Vol. II, Revised 2012 Edition DPWH Specifications for Highways, Bridges & Airports)
DRAINAGE AND SLOPE PROTECTION STRUCTURES
G 23,459,481.43
(Vol. II, Revised 2012 Edition DPWH Specifications for Highways, Bridges & Airports)

TOTAL BID PRICE CARRIED FORWARD TO FORM OF BID 30,899,088.70


Total of All Amounts in words
Pesos Thirty Million Eight Hundred Ninety Nine Thousand Eighty Eight Pesos & 70/100

Project to be completed within 229 calendar days

READ AND ACCEPTED AND GOOD FOR AGREEMENT :

ROGELIO P. ALLOSA November 6, 2018


(Name and Signature of the Bidder or Duly Authorized Bidder's Representative) (Date)

Proprietor/General Manager
(Position of the Bidder or Duly Authorized Bidder's Representative)

R. ALLOSA CONSTRUCTION & TRUCKING SERVICES


(Name of the Bidder)
CID No. 19IG0007 - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads -
Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

BILL OF QUANTITIES

Part No. : B Part Description : OTHER GENERAL REQUIREMENTS


(Vol. II, Revised 2012 Edition, DPWH Specifications for Highways, Bridges and Airports)
Activity Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
(1) (2) (3) (4) (5) (6)
In words : Pesos In words : Pesos

Four Thousand One Hundred Thirty Eight Thousand Two Hundred Seventy Four
B.5 Project Billboard/Signboard each 2.00 Seven Pesos & 39/100 Pesos & 78/100

In figures: Pesos 4,137.39 In figures: Pesos 8,274.78

In words : Pesos In words : Pesos

Two Hundred Eighty Nine Thousand Two Hundred Eighty Nine Thousand Four
B.7(2) Occupational Safety & Health Program l.s. 1.00 Four Hundred Fifty Six Pesos & 40/100 Hundred Fifty Six Pesos & 40/100

In figures: Pesos 289,456.40 In figures: Pesos 289,456.40

In words : Pesos In words : Pesos

Five Hundred Forty Three Thousand Five Hundred Forty Three Thousand Three
Three Hundred Two Pesos & 12/100 Hundred Two Pesos & 12/100
B.8(2) Traffic Management l.s. 1.00

In figures: Pesos 543,302.12 In figures: Pesos 543,302.12

In words : Pesos In words : Pesos

One Hundred Ninety Nine Thousand Five One Hundred Ninety Nine Thousand Five
B.9 Mobilization/Demobilization l.s. 1.00 Hundred Eighty Four Pesos & 00/100 Hundred Eighty Four Pesos & 00/100

In figures: Pesos 199,584.00 In figures: Pesos 199,584.00

In words : Pesos In words : Pesos

Two Million One Hundred Eighty Two Two Million One Hundred Eighty Two
B.15(1) Detour/Access Road l.s. 1.00 Thousand One Hundred Sixty Nine Pesos Thousand One Hundred Sixty Nine Pesos &
& 55/100 55/100

In figures: Pesos 2,182,169.55 In figures: Pesos 2,182,169.55

TOTAL COST (PART B) Php 3,222,786.85


(Carried to Summary)
(Pesos : Three Million Two Hundred Twenty Two Thousand Seven Hundred Eighty Six Pesos
& 85/100

and Centavos

Part No. : C Part Description : EARTHWORKS


(Vol. II, Revised 2012 Edition, DPWH Specifications for Highways, Bridges and Airports)
Activity Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
(1) (2) (3) (4) (5) (6)
In words : Pesos In words : Pesos

100(1) ha. 0.42 Six Hundred Ninety Thousand Six Two Hundred Ninety Thousand Seventy Six
Clearing and Grubbing
Hundred Fifty Seven Pesos & 69/100 Pesos & 23/100

In figures: Pesos 690,657.69 In figures: Pesos 290,076.23


In words : Pesos In words : Pesos

101(1) Removal of Structures and Obstruction l.s. 1.00 One Million Sixty Two Thousand Five One Million Sixty Two Thousand Five
Hundred Eleven Pesos & 88/100 Hundred Eleven Pesos & 88/100

In figures: Pesos 1,062,511.88 In figures: Pesos 1,062,511.88


In words : Pesos In words : Pesos

104(1)a Embankment from Roadway Excavation, Common cu.m. 3,151.00 One Million Two Hundred Sixty Eight
Soil Four Hundred Two Pesos & 67/100 Thousand Eight Hundred Thirteen Pesos &
17/100

In figures: Pesos 402.67 In figures: Pesos 1,268,813.17

In words : Pesos In words : Pesos

104(2)a Embankment from Borrow, Common Soil cu.m. 560.00 One Thousand Five Hundred Fifty One Eight Hundred Sixty Eight Thousand Seven
Pesos & 39/100 Hundred Seventy Eight Pesos & 40/100

In figures: Pesos 1,551.39 In figures: Pesos 868,778.40


TOTAL COST (PART C) Php 3,490,179.68
(Carried to Summary)
(Pesos :
Three Million Four Hundred Ninety Thousand One Hundred Seventy Nine Pesos
& 68/100

and Centavos
CID No. 19IG0007 - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads -
Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

BILL OF QUANTITIES

Part No. : E Part Description : SURFACE COURSE


(Vol. II, Revised 2012 Edition, DPWH Specifications for Highways, Bridges and Airports)
Activity Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
(1) (2) (3) (4) (5) (6)
In words : Pesos In words : Pesos

300(1) Gravel Surface Course cu.m. 126.00 Five Thousand Seven Hundred Sixty Six Seven Hundred Twenty Six Thousand Six
Pesos & 99/100 Hundred Forty Pesos & 74/100

In figures: Pesos 5,766.99 In figures: Pesos 726,640.74

TOTAL COST (PART E) Php 726,640.74


(Carried to Summary)
(Pesos : Seven Hundred Twenty Six Thousand Six Hundred Forty Pesos & 74/100

and Centavos

CID No. 19IG0007 - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads -
Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

BILL OF QUANTITIES DRAINAGE AND SLOPE PROTECTION


Part No. : G Part Description : STRUCTURES
(Vol. II, Revised 2012 Edition, DPWH Specifications for Highways, Bridges and Airports)
Activity Description Unit Quantity Unit Price (Pesos) Amount (Pesos)
No.
(1) (2) (3) (4) (5) (6)
In words : Pesos In words : Pesos

Three Thousand Seven Hundred Eighty Three Million Fifty One Thousand Nine
506(1) Stone Masonry cu.m. 806.00 Six Pesos & 55/100 Hundred Fifty Nine Pesos & 30/100

In figures: Pesos 3,786.55 In figures: Pesos 3,051,959.30

In words : Pesos In words : Pesos

507(1) Rubble Concrete cu.m. 1,024.00 Two Million Nine Hundred Sixty Seven
Two Thousand Eight Hundred Ninety
Thousand Five Hundred Seventy Two Pesos
Eight Pesos & 02/100
& 48/100

In figures: Pesos 2,898.02 In figures: Pesos 2,967,572.48

In words : Pesos In words : Pesos


Twelve Million Six Hundred Sixteen
509(1)b1 Steel Sheet Piles, Slope Protection ln.m. 2,925.00 Four Thousand Three Hundred Thirteen
Thousand Six Hundred Seven Pesos &
Pesos & 37/100
25/100

In figures: Pesos 4,313.37 In figures: Pesos 12,616,607.25


In words : Pesos In words : Pesos

510(2) Concrete, Slope Protection cu.m 1,065.00 Four Million Eight Hundred Twenty Three
Four Thousand Five Hundred Twenty
Thousand Three Hundred Forty Two Pesos
Eight Pesos & 96/100
& 40/100

In figures: Pesos 4,528.96 In figures: Pesos 4,823,342.40

TOTAL COST (PART G) Php 23,459,481.43


(Carried to Summary)
(Pesos : Twenty Three Million Four Hundred Fifty Nine Thousand Four Hundred Eighty One Pesos
& 43/100

and Centavo
TOTAL AMOUNT (ALL PARTS) Php 30,899,088.70
(Carried to Summary)
(Pesos : Thirty Million Eight Hundred Ninety Nine Thousand Eighty Eight Pesos & 70/100

and Centavos

READ AND ACCEPTED AND GOOD FOR AGREEMENT :

ROGELIO P. ALLOSA November 6, 2018


(Name and Signature of the Bidder or Duly Authorized Bidder's Representative) (Date)

Proprietor/General Manager
(Position of the Bidder or Duly Authorized Bidder's Representative)

R. ALLOSA CONSTRUCTION & TRUCKING SERVICES


(Name of the Bidder)
DETAILED COST ESTIMATES

19IG0007
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part B Other General Requirements :

B.5 Project Billboard/Signboard 2.00 each 4,137.39

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A
T Marine Plywood, 4'x8'x1/2" 1.00 pc 645.00 645.00
E 4' x 8' Tarpaulin 32.00 sq.ft 44.00 1,408.00
R CWN Nails 0.50 kg 68.00 34.00
I Coco Lumber 42.00 bd. Ft. 14.00 588.00
A
L
S

TOTAL FOR MATERIALS 2,675.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U
I
P Service/Stake Truck cap 6-8MT/195hp 1 4.00 782.00 3,128.00
M Misc. handtools 79.60
E
N
T

TOTAL FOR EQUIPMENT 3,207.60


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 4.00 70.00 280.00
B Skilled Laborer 1 4.00 51.00 204.00
O Laborer 2 4.00 39.00 312.00
R

TOTAL FOR LABOR 796.00

TOTAL DIRECT COST 6,678.60


TOTAL INDIRECT COST 1,596.19
O.C.M. - 10% 667.86
PROFIT - 8% 534.29
VAT - 5% 394.04
TOTAL ITEM COST 8,274.79
UNIT COST 4,137.39

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part B Other General Requirements :

B.7(2) Occupational Safety & Health Program 1.00 l.s. 289,456.40

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A Safety Shoes 1,832.00 m-day 2.67 4,891.44
T Safety Helmet 1,832.00 m-day 0.24 439.68
E Safety Gloves 1,832.00 m-day 7.67 14,051.44
R
I
A
L
S

TOTAL FOR MATERIALS 19,382.56


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U
I
P
M
E
N
T

TOTAL FOR EQUIPMENT 0.00


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A
B Part-time Safety Practitioner 1 1,832.00 74.38 136,255.00
O First Aider 1 1,832.00 54.38 99,615.00
R

TOTAL FOR LABOR 235,870.00

TOTAL DIRECT COST 255,252.56


TOTAL INDIRECT COST 34,203.84
O.C.M. - 10%
PROFIT - 8% 20,420.20
VAT - 5% 13,783.64
TOTAL ITEM COST 289,456.40
UNIT COST 289,456.40

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part B Other General Requirements :

B.9 Mobilization/Demobilization 1.00 l.s. 199,584.00

NAME & SPECIFICATION QUANTITY NO. OF HRS. UNIT COST COST

E Dump Truck (10 - 11 cu.m.) 2 15.00 1,415.00 42,450.00


Q Crawler Crane 4 15.00 1,310.00 78,600.00
U Water Truck (Cap. 1000 gal.) 1 15.00 2,420.00 36,300.00
I Service/Stake Truck cap 6-8MT/195hp 1 15.00 782.00 11,730.00
P Low Bed Trailer with Tractor 1 15.00 1,400.00 21,000.00
M
E
N
T

TOTAL COST 190,080.00


TOTAL DIRECT COST 190,080.00
TOTAL ESTIMATED DIRECT COST (Civil Works) 21,783,170.36
TOTAL ESTIMATED DIRECT COST ( 1% of EDC) 217,831.70
TOTAL INDIRECT COST 9,504.00
O.C.M. - 10% -
PROFIT - 8% -
VAT - 5% 9,504.00
TOTAL ITEM COST 199,584.00
UNIT COST 199,584.00

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part B Other General Requirements :

B.8(2) Traffic Management 1.00 l.s. 543,302.12

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M Warning Sign (Tarpaulin & Framing) 6.00 sq.m. 2,500.00 15,000.00


A Barricades (Bamboo Poles w/ Reflector & Concrete Base) 36.00 pcs. 1,500.00 54,000.00
T Night Lightings (Lighting Fixture) 36.00 ln.m. 1,220.00 43,920.00
E
R
I
A
L
S

TOTAL FOR MATERIALS 112,920.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U
I
P Service/Stake Truck cap 6-8MT/195hp 1 384.00 782.00 300,288.00
M Misc. handtools 5,990.40
E
N
T

TOTAL FOR EQUIPMENT 306,278.40


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A
B
O Unskilled Laborer 4 384.00 39.00 59,904.00
R

TOTAL FOR LABOR 59,904.00

TOTAL DIRECT COST 479,102.40


TOTAL INDIRECT COST 64,199.72
O.C.M. - 10%
PROFIT - 8% 38,328.19
VAT - 5% 25,871.53
TOTAL ITEM COST 543,302.12
UNIT COST 543,302.12

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007

Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay
- South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part C Earthworks :

101(1) Removal of Structures and Obstruction 1.00 l.s. 1,062,511.88

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A
T
E
R
I
A
L
S

TOTAL FOR MATERIALS 0.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U
I
P Backhoe w/ Pavement Breaker (Cap. 0.80 cu.m.) 1 112.00 2,500.00 280,000.00
M Payloader (Cap. 1.5 cu.m.) 1 112.00 1,800.00 201,600.00
E Dump Truck (Cap. 10-11 cu.m.) 2 112.00 1,600.00 358,400.00
N Miscellaneous 1,596.00
T

TOTAL FOR EQUIPMENT 841,596.00


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 112.00 72.50 8,120.00
B
O Unskilled Laborer 2 112.00 35.00 7,840.00
R

TOTAL FOR LABOR 15,960.00

TOTAL DIRECT COST 857,556.00


TOTAL INDIRECT COST 204,955.88
O.C.M. - 10% 85,755.60
PROFIT - 8% 68,604.48
VAT - 5% 50,595.80
TOTAL ITEM COST 1,062,511.88
UNIT COST 1,062,511.88

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007

Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay
- South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part C Earthworks :

100(1) Clearing and Grubbing 0.42 ha. 690,657.69

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A
T
E
R
I
A
L
S

TOTAL FOR MATERIALS 0.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U
I Payloader 1 55.00 1,300.00 71,500.00
P Bulldozer 1 55.00 1,200.00 66,000.00
M Dump Truck (Cap. 10-11 cu.m.) 1 55.00 1,600.00 88,000.00
E Miscellaneous 783.75
N
T

TOTAL FOR EQUIPMENT 226,283.75


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 55.00 72.50 3,987.50
B
O Unskilled Laborer 2 55.00 35.00 3,850.00
R

TOTAL FOR LABOR 7,837.50

TOTAL DIRECT COST 234,121.25


TOTAL INDIRECT COST 55,954.98
O.C.M. - 10% 23,412.13
PROFIT - 8% 18,729.70
VAT - 5% 13,813.15
TOTAL ITEM COST 290,076.23
UNIT COST 690,657.69

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007

Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay
- South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part C Earthworks :

104(1)a Embankment from Roadway Excavation, Common Soil 3,151.00 cu.m. 402.67

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A
T
E
R
I
A
L
S

TOTAL FOR MATERIALS 0.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q Bulldozer 1 85.00 3,300.00 280,500.00
U Backhoe 1 85.00 2,500.00 212,500.00
I
P Vibratory Roller 1 85.00 1,495.00 127,075.00
M Motorized Road Grader 140Hp/G710A 1 85.00 2,170.00 184,450.00
E Water Truck (Cap. 1000 gal.) 1 85.00 2,420.00 205,700.00
N Miscellaneous 1,258.00
T

TOTAL FOR EQUIPMENT 1,011,483.00


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 85.00 70.00 5,950.00
B Laborer 2 85.00 39.00 6,630.00
O
R

TOTAL FOR LABOR 12,580.00

TOTAL DIRECT COST 1,024,063.00


TOTAL INDIRECT COST 244,751.06
O.C.M. - 10% 102,406.30
PROFIT - 8% 81,925.04
VAT - 5% 60,419.72
TOTAL ITEM COST 1,268,814.06
UNIT COST 402.67

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007

Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay
- South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part C Earthworks :

104(2)a Embankment from Borrow, Common Soil 560.00 cu.m. 1,551.39

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A
T Common borrow materials 700.00 cu.m. 600.00 420,000.00
E
R
I
A
L
S

TOTAL FOR MATERIALS 420,000.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U Motorized Road Grader 140Hp/G710A 1 45.00 2,170.00 97,650.00
I Vibratory Roller 1 45.00 1,495.00 67,275.00
P Water Truck (Cap. 1000 gal.) 1 45.00 2,420.00 108,900.00
M Miscellaneous 669.75
E
N
T

TOTAL FOR EQUIPMENT 274,494.75


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 47.00 72.50 3,407.50
B Laborer 2 47.00 35.00 3,290.00
O
R

TOTAL FOR LABOR 6,697.50

TOTAL DIRECT COST 701,192.25


TOTAL INDIRECT COST 167,584.95
O.C.M. - 10% 70,119.23
PROFIT - 8% 56,095.38
VAT - 5% 41,370.34
TOTAL ITEM COST 868,777.20
UNIT COST 1,551.39

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007

Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part E Surface Course

300(1) Gravel Surface Course 126.00 cu.m. 5,766.99

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A
T Gravel surface course materials 144.90 cu.m. 1,200.00 173,880.00
E
I
A
L
S

TOTAL FOR MATERIALS 173,880.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U Vibratory Roller 1.00 65.00 1,495.00 97,175.00
I Motorized Road Grader 140Hp/G710A 1.00 65.00 2,170.00 141,050.00
P Water Truck (Cap. 1000 gal.) 1.00 65.00 2,420.00 157,300.00
M
E
N
T Misc. handtools 169.00

TOTAL FOR EQUIPMENT 395,694.00


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 65.00 72.50 4,712.50
B Skilled Laborer 1 65.00 47.50 3,087.50
O Laborer 4 65.00 35.00 9,100.00
R

TOTAL FOR LABOR 16,900.00

TOTAL DIRECT COST 586,474.00


TOTAL INDIRECT COST 140,167.29
O.C.M. - 10% 58,647.40
PROFIT - 8% 46,917.92
VAT - 5% 34,601.97
TOTAL ITEM COST 726,641.29
UNIT COST 5,766.99

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part G Drainage and Slope Protection Structures:

507(1) Rubble Concrete 1,024.00 cu.m. 2,898.02

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A Rubble Concrete 1,024.00 cu.m. 1,600.00 1,638,400.00
T
E
R
I
A
L
S

TOTAL FOR MATERIALS 1,638,400.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E Backhoe 1.00 160.00 2,500.00 400,000.00


Q Dump Truck (10 - 11 cu.m.) 1.00 160.00 1,415.00 226,400.00
U Concrete Mixer (1 bagger) 1.00 160.00 170.00 27,200.00
I Miscellaneous 9,376.00
P
M
E
N
T

TOTAL FOR EQUIPMENT 662,976.00


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 160.00 70.00 11,200.00
B Skilled Laborer 4 160.00 51.00 32,640.00
O Laborer 8 160.00 39.00 49,920.00
R

TOTAL FOR LABOR 93,760.00

TOTAL DIRECT COST 2,395,136.00


TOTAL INDIRECT COST 572,437.50
O.C.M. - 10% 239,513.60
PROFIT - 8% 191,610.88
VAT - 5% 141,313.02
TOTAL ITEM COST 2,967,573.50
UNIT COST 2,898.02

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part G Drainage and Slope Protection Structures:

509(1)b1 Steel Sheet Piles, Slope Protection 2,925.00 ln.m. 4,313.37

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A Steel Sheet Piles, Slope Protection 2,925.00 ln.m. 2,600.00 7,605,000.00
T materials
E
R
I
A
L
S

TOTAL FOR MATERIALS 7,605,000.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q Crawler Crane 1.00 240.00 3,125.00 750,000.00
U Vibro Hammer 1.00 240.00 2,900.00 696,000.00
I Backhoe 1.00 240.00 2,500.00 600,000.00
P Low Bed Trailer with Tractor 1.00 240.00 1,400.00 336,000.00
M Misc. 17,808.00
E
N
T

TOTAL FOR EQUIPMENT 2,399,808.00


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 240.00 70.00 16,800.00
B Skilled Laborer 4 240.00 51.00 48,960.00
O Laborer 12 240.00 39.00 112,320.00
R

TOTAL FOR LABOR 178,080.00

TOTAL DIRECT COST 10,182,888.00


TOTAL INDIRECT COST 2,433,710.23
O.C.M. - 10% 1,018,288.80
PROFIT - 8% 814,631.04
VAT - 5% 600,790.39
TOTAL ITEM COST 12,616,598.23
UNIT COST 4,313.37

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007
Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part G Drainage and Slope Protection Structures:

510(2) Concrete, Slope Protection 1,065.00 cu.m 4,528.96

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A
T Concrete, Slope Protection 1,065.00 cu.m 3,200.00 3,408,000.00
E materials
R
I
A
L
S

TOTAL FOR MATERIALS 3,408,000.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U Concrete Mixer (1 bagger) 1.00 160.00 170.00 27,200.00
I Backhoe 1.00 160.00 2,500.00 400,000.00
P
M Misc. 5,248.00
E
N
T

TOTAL FOR EQUIPMENT 432,448.00


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 160.00 70.00 11,200.00
B Skilled Laborer 2 160.00 51.00 16,320.00
O Laborer 4 160.00 39.00 24,960.00
R

TOTAL FOR LABOR 52,480.00

TOTAL DIRECT COST 3,892,928.00


TOTAL INDIRECT COST 930,409.79
O.C.M. - 10% 389,292.80
PROFIT - 8% 311,434.24
VAT - 5% 229,682.75
TOTAL ITEM COST 4,823,337.79
UNIT COST 4,528.96

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007

Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part G Drainage & Slope Protection Structures :

506(1) Stone Masonry 806.00 cu.m. 3,786.55

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A Boulders 846.30 cu.m. 700.00 592,410.00
T Cement 5,239.00 bag 262.00 1,372,618.00
E Washed Sand 241.80 cu.m. 880.00 212,784.00
R
I PVC Weepholes 241.80 ln.m. 96.75 23,394.15
A Gravel Fill 16.12 cu.m. 972.00 15,668.64
L Filter cloth 241.80 l.m. 160.00 38,688.00
S Miscellaneous 12,332.00

TOTAL FOR MATERIALS 2,267,894.79


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U
I
P Backhoe 1.00 61.00 2,500.00 152,500.00
M Concrete Mixer (1 bagger) 1.00 61.00 170.00 10,370.00
E
N Misc. handtools 2,952.40
T

TOTAL FOR EQUIPMENT 165,822.40


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 61.00 70.00 4,270.00
B Skilled Laborer 2 61.00 51.00 6,222.00
O Laborer 8 61.00 39.00 19,032.00
R

TOTAL FOR LABOR 29,524.00

TOTAL DIRECT COST 2,463,241.19


TOTAL INDIRECT COST 588,714.64
O.C.M. - 10% 246,324.12
PROFIT - 8% 197,059.30
VAT - 5% 145,331.23
TOTAL ITEM COST 3,051,955.83
UNIT COST 3,786.55

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
DETAILED COST ESTIMATES

19IG0007

Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Tacloban - Baybay -
South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

ITEM NO. NAME OF ITEM QUANTITY & UNIT UNIT COST


Part B Other General Requirements:

B.15(1) Detour/Access Road 1.00 l.s. 2,182,169.55

NAME & SPECIFICATION QUANTITY UNIT UNIT COST COST

M
A Detour/Access Road 1.00 l.s. 1,299,995.00 1,299,995.00
T
E
R
I
A
L
S

TOTAL FOR MATERIALS 1,299,995.00


NAME & CAPACITY NO. OF UNITS NO. OF HOURS HOURLY RATE COST

E
Q
U Crawler Crane 1.00 50.00 3,125.00 156,250.00
I Vibro Hammer 1.00 50.00 2,900.00 145,000.00
P Backhoe 1.00 50.00 2,500.00 125,000.00
M
E
N
T

TOTAL FOR EQUIPMENT 426,250.00


DESIGNATION NO. OF PERSONS NO. OF HOURS HOURLY RATE COST

L
A Foreman 1 91.00 72.50 6,597.50
B Skilled Laborer 2 91.00 51.00 9,282.00
O Laborer 6 91.00 35.00 19,110.00
R

TOTAL FOR LABOR 34,989.50

TOTAL DIRECT COST 1,761,234.50


TOTAL INDIRECT COST 420,935.05
O.C.M. - 10% 176,123.45
PROFIT - 8% 140,898.76
VAT - 5% 103,912.84
TOTAL ITEM COST 2,182,169.55
UNIT COST 2,182,169.55

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES

__________________________
(Authorized Signature)
CID No. 19IG0007 - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads -
Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

SUMMARY OF MATERIALS COST

NO. MATERIALS W/ DESCRIPTION UNIT UNIT COST


1 Marine Plywood, 4'x8'x1/2" pc 645.00
2 Ord. Plywood 4x8x1/2 pc 595.00
3 4' x 8' Tarpaulin sq.ft 44.00
4 CWN Nails kg 68.00
5 Coco Lumber bd. Ft. 14.00
6 Safety Shoes m-day 2.67
7 Safety Helmet m-day 0.24
8 Safety Gloves m-day 7.67
9 Common borrow materials cu.m. 600.00
10 Gravel surface course materials cu.m. 1,200.00
11 Rubble Concrete cu.m. 1,600.00
12 Steel Sheet Piles, Slope Protection ln.m. 2,600.00
13 Boulders cu.m. 700.00
14 Concrete, Slope Protection cu.m 3,200.00
15 Cement bag 262.00
16 Washed Sand cu.m. 880.00
17 PVC Weepholes ln.m. 96.75
18 Gravel Fill cu.m. 972.00
19 Filter cloth l.m. 160.00
20 Detour/Access Road l.s. 1,299,995.00
21 Gravel Fill cu.m. 798.00
22 PVC Weepholes ln.m. 96.75
23 Warning Sign (Tarpaulin & Framing) sq.m. 2,500.00
24 Barricades (Bamboo Poles w/ Reflector & Concrete Base) pcs. 1,500.00

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES Date : November 6, 2018

( Authorized Signing Official )


CID No. 19IG0007 - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads -

Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

SUMMARY OF EQUIPMENT RATE

NO. EQUIPMENT W/ DESCRIPTION RATE/HOUR

1 Dump Truck (10 - 11 cu.m.) 1,415.00


2 Backhoe w/ Pavement Breaker (Cap. 0.80 cu.m.) 2,500.00
3 Batching Plant 30cu.m. 2,600.00
4 Vibratory Roller 1,495.00
5 Motorized Road Grader 140Hp/G710A 2,170.00
6 Water Truck (Cap. 1000 gal.) 2,420.00
7 Crawler Crane 3,125.00
8 Vibro Hammer 2,900.00
9 Concrete Mixer (1 bagger) 170.00
10 Payloader 1,300.00
11 Cutting Outfit 545.00
12 Vibro Hammer 2,900.00
13 Low Bed Trailer with Tractor 1,400.00
14 Bar Cutter Single Phase 218.00
15 Concrete Mixer (1 bagger) 170.00

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES November 6, 2018

( Authorized Signing Official )


CID No. 19IG0007 - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads -
Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

SUMMARY OF MANPOWER RATE

NO. MANPOWER W/ DESCRIPTION RATES/HOUR


1 Part-time Safety Practitioner 74.38
2 First Aider 54.38
3 Foreman 70.00
4 Skilled Laborer 51.00
5 Laborer 39.00

SUBMITTED BY : R. ALLOSA CONSTRUCTION & TRUCKING SERVICES November 6, 2018

( Authorized Signing Official )


CID No. 19IG0007 - Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads -
Tacloban - Baybay - South Rd - K0988+420-K0988+520, K0988+530-K0988+585, K0990+460-K0990+580, K0994+680-K0994+780

CASH FLOW BY QUARTER AND PAYMENT SCHEDULE

PARTICULAR % Wt. 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter

No. of Calendar Days 229 57.25 57.25 57.25 57.25

ACCOMPLISHMENT 25.00% 25.00% 25.00% 25.00%

CASH FLOW 7,724,772.17 7,724,772.17 7,724,772.17 7,724,772.17

COMMULATIVE ACCOMPLISHMENT 25.00% 50.00% 75.00% 100.00%

COMMULATIVE CASH FLOW (P) 100% 7,724,772.17 15,449,544.35 23,174,316.52 30,899,088.70

ROGELIO P. ALLOSA November 6, 2018


(Name and Signature of the Bidder or Duly Authorized Bidder's Representative)

Proprietor/General Manager
Name and Signature of Bidder's Authorized Representative

R. ALLOSA CONSTRUCTION & TRUCKING SERVICES


Name of the Bidder