Professional Documents
Culture Documents
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 66.53 61,969,824.65
A.2 Labor 3.97 3,700,100.98
A.3 Equipment Expenses 7.50 6,982,769.81
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.59 4,279,869.29
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.578 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.783 l.s 1.00 198,530.15 198,530.15
B.5 Project Billboard 0.021 each 2.00 5,261.56 2,630.78
Occupational Safety and Health
B.7 0.690 mon 8.10 174,872.60 21,589.21
Program
B.9 Mobilization and Demobilization 0.866 l.s 1.00 219,592.80 219,592.80
PART C: EARTHWORKS
101(3)a Removal of PCCP 0.101 sq 314.90 25,721.48 81.68
102(2) Surplus Excavation 0.094 cu.m 333.00 23,718.76 71.23
PART D: SUBBASE AND BASE COURSE
200 (1) Aggregate Subbase Course 1.348 cu.m 253.00 341,720.09 1,350.67
PART F: BRIDGE CONSTRUCTION
103(2)a Bridge Excavation (Common Soil) 1.233 cu.m 1,354.00 312,516.40 230.81
Structural Steel Sheet Piles, Furnished
400(6) 8.152 ln.m 702.00 2,066,734.95 2,944.07
(Cofferdam)
Structural Steel Sheet Piles, Driven
400(12) 0.994 ln.m 390.00 252,081.18 646.36
(Cofferdam)
1300(2b)1 Steel Tubular Pile, 450 mm dia., supply 16.941 m 430.00 4,295,179.23 9,988.79
1300(2b)2 Steel Tubular Pile, 450 mm dia., drive 4.432 m 410.00 1,123,683.04 2,740.69
404 (1)a Reinforcing Steel Bar, Grade 40 2.025 kg. 7,682.00 513,464.11 66.84
404 (1)b Reinforcing Steel Bar, Grade 60 28.114 kg. 105,569.70 7,127,823.92 67.52
405 (1)b3 Structural Concrete, Class A 23.534 cu.m 610.87 5,966,497.42 9,767.28
407(8) Lean Concrete, Fc=17 MPA 0.333 cu.m 16.40 84,328.95 5,142.01
412 (1) Elastomeric Bearing Pad 0.197 each 8.00 50,014.16 6,251.77
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 57.85 19,115,126.50
A.2 Labor 6.28 2,076,538.41
A.3 Equipment Expenses 12.60 4,161,403.09
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.59 1,517,938.92
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.573 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.437 l.s 1.00 111,164.02 111,164.02
B.5 Project Billboard 0.019 each 2.00 4,930.90 2,465.45
Occupational Safety and Health
B.7 0.665 mon 7.80 169,038.80 21,671.64
Program
B.9 Mobilization and Demobilization 0.596 l.s 1.00 151,506.80 151,506.80
PART C: EARTHWORKS
101(3)a Removal of PCCP 0.217 sq 675.30 55,159.46 81.68
PART D: SUBBASE AND BASE COURSE
200 (1) Aggregate Subbase Course 2.103 cu.m 396.00 534,866.23 1,350.67
PART F: BRIDGE CONSTRUCTION
103(2)a Bridge Excavation (Common Soil) 0.164 cu.m 181.00 41,776.56 230.81
1300(2b)1 Steel Tubular Pile, 450 mm dia., supply 21.770 m 544.00 5,536,118.76 10,176.69
1300(2b)2 Steel Tubular Pile, 450 mm dia., drive 5.700 m 510.00 1,449,591.12 2,842.34
405 (1)b3 Structural Concrete, Class A 10.136 cu.m 269.78 2,577,552.85 9,554.28
407(8) Lean Concrete, Fc=17 MPA 0.121 cu.m 6.00 30,852.06 5,142.01
412 (1) Elastomeric Bearing Pad 0.197 each 8.00 50,014.16 6,251.77
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 60.40 20,024,069.80
A.2 Labor 5.02 1,663,902.24
A.3 Equipment Expenses 11.29 3,742,120.14
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.60 1,523,276.23
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 0.551 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.048 l.s 1.00 35,022.16 35,022.16
B.5 Project Billboard 0.007 each 2.00 4,878.56 2,439.28
Occupational Safety and Health
B.7 0.334 mon 11.60 242,933.60 20,942.55
Program
B.9 Mobilization and Demobilization 0.605 l.s 1.00 439,185.60 439,185.60
PART C: EARTHWORKS
102(2) Surplus Excavation 0.006 cu.m 59.62 4,246.58 71.23
PART D: SUBBASE AND BASE COURSE
200 (1) Aggregate Subbase Course 0.056 cu.m 30.84 41,016.35 1,329.97
PART F: BRIDGE CONSTRUCTION
103(2)a Bridge Excavation (Common Soil) 0.717 cu.m 2,256.96 520,928.37 230.81
Shoring, Cribbing and Related Works
103(5)a 0.540 l.s 1.00 392,449.95 392,449.95
(Shoring)
Structural Steel Sheet Piles, Furnished
400(6) 8.675 ln.m 2,140.08 6,300,538.64 2,944.07
(Cofferdam)
Structural Steel Sheet Piles, Driven
400(12) 1.802 ln.m 2,024.40 1,308,495.23 646.36
(Cofferdam)
1300(2b)1 Steel Tubular Pile, 450 mm dia., supply 32.592 m 2,352.00 23,672,148.29 10,064.69
1300(2b)2 Steel Tubular Pile, 450 mm dia., drive 8.184 m 2,234.40 5,944,270.74 2,660.34
401(2)a Railing, Concrete Side Barrier 0.840 ln.m 150.00 609,899.79 4,066.00
404 (1)a Reinforcing Steel Bar, Grade 40 1.447 kg. 15,620.89 1,051,128.13 67.29
404 (1)b Reinforcing Steel Bar, Grade 60 18.907 kg. 201,793.46 13,732,389.12 68.05
Structural Concrete, Class A,
405 (1)b2 16.900 cu.m 1,315.88 12,274,669.42 9,328.11
27.58MPA @ 14 days
407(8) Lean Concrete, Fc=17 MPA 0.207 cu.m 30.00 150,210.28 5,007.01
412 (1) Elastomeric Bearing Pad 0.069 each 8.00 50,014.16 6,251.77
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 58.24 54,252,499.16
A.2 Labor 5.39 5,019,318.91
A.3 Equipment Expenses 14.34 13,360,437.33
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.59 4,280,135.73
17,250,594.93
17,250,594.93
-
89,882,850.33
89,882,850.33
-
Department of Public Works and Highways
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 0.983 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.239 l.s 1.00 97,362.64 97,362.64
B.5 Project Billboard 0.012 each 2.00 4,930.90 2,465.45
Occupational Safety and Health
B.7 0.516 mon 9.90 209,875.40 21,199.54
Program
B.9 Mobilization and Demobilization 0.745 l.s 1.00 303,013.60 303,013.60
PART C: EARTHWORKS
101(3)a Removal of PCCP 0.009 sq 42.90 3,504.13 81.68
PART D: SUBBASE AND BASE COURSE
200 (1) Aggregate Subbase Course 1.213 cu.m 365.33 493,441.11 1,350.67
PART F: BRIDGE CONSTRUCTION
103(2)a Bridge Excavation (Common Soil) 0.245 cu.m 432.00 99,709.81 230.81
Shoring, Cribbing and Related Works
103(5)a 1.052 l.s 1.00 428,046.75 428,046.75
(Shoring)
Structural Steel Sheet Piles, Furnished
400(6) 3.241 ln.m 448.00 1,318,941.96 2,944.07
(Cofferdam)
Structural Steel Sheet Piles, Driven
400(12) 0.356 ln.m 224.00 144,785.09 646.36
(Cofferdam)
1300(2b)1 Steel Tubular Pile, 450 mm dia., supply 25.323 m 1,046.00 10,304,240.45 9,851.09
1300(2b)2 Steel Tubular Pile, 450 mm dia., drive 6.580 m 977.00 2,677,654.47 2,740.69
401(2)a Railing, Concrete Side Barrier 0.618 ln.m 60.00 251,481.15 4,191.35
405 (1)b2 Structural Concrete, Class A 10.608 cu.m 451.77 4,316,335.71 9,554.28
412 (1) Elastomeric Bearing Pad 0.123 each 8.00 50,014.16 6,251.77
505(a) Grouted Riprap, Class A (Line Canal) 0.357 cu.m 38.00 145,319.46 3,824.20
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 59.99 31,820,469.55
A.2 Labor 4.78 2,535,235.14
A.3 Equipment Expenses 11.94 6,335,336.14
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.59 2,437,173.06
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 0.604 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.127 l.s 1.00 84,053.79 84,053.79
B.5 Project Billboard 0.007 each 2.00 4,712.90 2,356.45
Occupational Safety and Health
B.7 0.282 mon 8.70 186,540.20 21,441.40
Program
B.9 Mobilization and Demobilization 0.916 l.s 1.00 606,027.20 606,027.20
B.15(1) Detour/Access Road 3.460 l.s 1.00 2,290,007.74 2,290,007.74
PART D: SUBBASE AND BASE COURSE
200 (1) Aggregate Subbase Course 0.641 cu.m 235.50 424,217.29 1,801.35
PART F: BRIDGE CONSTRUCTION
103(2)a Bridge Excavation (Common Soil) 0.378 cu.m 1,083.00 249,966.96 230.81
Shoring, Cribbing and Related Works
103(5)a 0.646 l.s 1.00 427,292.40 427,292.40
(Shoring)
Structural Steel Sheet Piles, Furnished
400(6) 3.977 ln.m 894.00 2,631,995.79 2,944.07
(Cofferdam)
Structural Steel Sheet Piles, Driven
400(12) 0.436 ln.m 446.00 288,277.45 646.36
(Cofferdam)
1300(2b)1 Steel Tubular Pile, 450 mm dia., supply 8.516 m 560.00 5,636,225.78 10,064.69
1300(2b)2 Steel Tubular Pile, 450 mm dia., drive 2.285 m 532.00 1,512,122.50 2,842.34
401(2)a Railing, Concrete Side Barrier 0.712 ln.m 118.20 471,334.86 3,987.60
Structural Steel, Furnished, Fabricated,
403(5) 35.306 kg. 120,914.55 23,368,074.08 193.26
and Erected (Craneway)
404 (1)a Reinforcing Steel Bar, Grade 40 0.351 kg. 3,478.38 232,494.57 66.84
404 (1)b Reinforcing Steel Bar, Grade 60 10.174 kg. 99,603.25 6,733,847.59 67.61
Structural Concrete, Class A,
405 (1)b2 9.856 cu.m 656.66 6,523,442.33 9,934.28
27.58MPA @ 14 days
727 (1) Non Shrink Grout, Fc'=41 MPA 0.050 cu.m 0.96 33,121.19 34,501.24
Prestressed Structural Concrete Member,
406 (1)d2 AASHTO Girder Type IV, L=19.25m.
9.352 each 8.00 6,189,687.42 773,710.93
407(8) Lean Concrete, Fc=17 MPA 0.128 cu.m 17.92 84,716.25 4,727.47
Laminated Bearing Pad (300 X 400 X
412 (1) 0.221 each 24.00 146,135.76 6,088.99
55mm)
Expansion Joint, 50mm gap with
413 (2) 0.024 ln.m 18.68 15,989.20 855.95
complete accessories
Premolded Expansion Joint Filler with
413 (1)a 0.003 sq.m 7.50 1,919.20 255.89
Sealant (12mm thk)
413 (2) Polysterene Joint Filler (20mm thk) 0.001 sq.m 14.68 816.70 55.63
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 64.66 56,881,906.46
A.2 Labor 2.81 2,475,455.20
A.3 Equipment Expenses 7.76 6,829,208.66
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.43 3,898,620.70
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.142 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.240 l.s 1.00 84,051.13 84,051.13
B.5 Project Billboard 0.015 each 2.00 5,264.90 2,632.45
Occupational Safety and Health
B.7 0.516 mon 8.40 180,706.40 21,512.67
Program
B.9 Mobilization and Demobilization 0.746 l.s 1.00 261,224.80 261,224.80
PART C: EARTHWORKS
100(1) Clearing and Grubbing 0.016 has 0.07 5,679.84 81,140.50
Removal of Existing Structures
101(1)c 1.617 l.s 1.00 566,414.23 566,414.23
(affected by RROW)
101(9) Removal of Existing Guardrails Post 0.000 each 6.00 163.99 27.33
400(12) Structural Steel Sheet Piles, Driven (Cofferdam) 1.506 ln.m 816.00 527,431.39 646.36
401(2)a Railing, Concrete Side Barrier 0.882 ln.m 72.00 308,724.99 4,287.85
402(b.1)2 Timber Structures for Craneway 3.781 span 6.00 1,323,893.94 220,648.99
Structural Steel (Furnished,
403(5) 0.666 kg 1,207.00 233,151.93 193.17
Fabricated and Erected)
404 (1)a Reinforcing Steel Bar, Grade 40 1.657 kg. 8,412.16 580,213.87 68.97
404 (1)b Reinforcing Steel Bar, Grade 60 24.364 kg. 119,460.98 8,531,708.73 71.42
Structural Concrete, Class A,
405 (1)b2 21.287 cu.m 751.58 7,454,447.02 9,918.37
27.58MPA @ 14 days
407(8) Lean Concrete, Fc=17 MPA 0.323 cu.m 21.60 113,271.12 5,244.03
412 (1) Elastomeric Bearing Pad 0.152 each 8.00 53,054.16 6,631.77
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 56.95 25,998,233.11
A.2 Labor 5.06 2,308,982.89
A.3 Equipment Expenses 14.70 6,710,898.89
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.59 2,097,390.41
CALUMANGI II BRIDGE
12.00 8.00 20.00 - - - #DIV/0!
PART A, FACILITIES FOR THE ENGINEERS
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.00 l.s 450,000.00 12.00 8.00 20.00 90,000.00 27,000.00 117,000.00 567,000.00 567,000.00
Sub-Total of Part A 450,000.00 90,000.00 27,000.00 117,000.00 567,000.00
543,270,496.37
-
APPROVED BUDGET FOR THE CONTRACT
Bridge Construction Replacement Program (BCRP) II : Potungan Bridge, Dapitan City, Zamboanga del Norte
Project Name and Location
Station Limits : Approaches Sta. 1805+080.00 - Sta. 1805+340.00 Bridges Sta. 1805+183.81 - Sta. 1805+244.00
Length : 60.20 ln.m. Contract Duration : 261.00 Calendar Days
Station Limits : Approaches Sta. 1849+041.40 - Sta. 1849+683.40 Bridges Sta. 1849+315.00 - Sta. 1849+351.84
Length : 36.84 ln.m. Contract Duration : 252.00 Calendar Days
Estimated Direct MARK-UP IN PERCENT TOTAL MARK-UPS
Item No. Description Quantity Unit VAT TOTAL INDIRECT COST TOTAL COST TOTAL COST
Cost OCM PROFIT % VALUE
(1) (2) (3) (4) (5) (6) (7) (8) (9) = (5)X(8) (10) = [(5)+(9)]*5% (11) = (9) + (10) (12) = (5) + (11) (13) = (12) / (3)
12.00 8.00 20.00 - - - #DIV/0!
PART A, FACILITIES FOR THE ENGINEERS
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.00 l.s 400,000.00 12.00 8.00 20.00 80,000.00 24,000.00 104,000.00 504,000.00 504,000.00
Sub-Total of Part A 400,000.00 80,000.00 24,000.00 104,000.00 504,000.00
Bridge Construction Replacement Program (BCRP) II : Widening of Militar Bridge, Zamboanga del Sur
Project Name and Location
Station Limits : Approaches Sta. 1675+529.95 - Sta. 1676+225.95 Bridges Sta. 1675+829.95 - Sta. 1675+925.95
Length : 96.00 ln.m. Contract Duration : 339.00 Calendar Days
Bridge Construction Replacement Program (BCRP) II : Calumangi Bridge I, Dumingag, Zamboanga del Sur
Project Name and Location
Station Limits : Approaches Sta. 1674+652.00 - Sta. 1675+000.00 Bridges Sta. 1674+952.50 - Sta. 1674+987.50
Length : 35.00 ln.m. Contract Duration : 255.00 Calendar Days
Estimated Direct MARK-UP IN PERCENT TOTAL MARK-UPS
Item No. Description Quantity Unit VAT TOTAL INDIRECT COST TOTAL COST TOTAL COST
Cost OCM PROFIT % VALUE
(1) (2) (3) (4) (5) (6) (7) (8) (9) = (5)X(8) (10) = [(5)+(9)]*5% (11) = (9) + (10) (12) = (5) + (11) (13) = (12) / (3)
12.00 8.00 20.00 - - - #DIV/0!
PART A, FACILITIES FOR THE ENGINEERS
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.00 l.s 400,000.00 12.00 8.00 20.00 80,000.00 24,000.00 104,000.00 504,000.00 504,000.00
Sub-Total of Part A 400,000.00 80,000.00 24,000.00 104,000.00 504,000.00
Bridge Construction Replacement Program (BCRP) II : Calumangi Bridge II, Dumingag, Zamboanga del Sur
Project Name and Location
Station Limits : Approaches Sta. 1675+000.00 - Sta. 1675+342.00 Bridges Sta. 1675+012.00 - Sta. 1675+042.00
Length : 30.00 ln.m. Contract Duration : 252.00 Calendar Days
Estimated Direct MARK-UP IN PERCENT TOTAL MARK-UPS
Item No. Description Quantity Unit VAT TOTAL INDIRECT COST TOTAL COST TOTAL COST
Cost OCM PROFIT % VALUE
(1) (2) (3) (4) (5) (6) (7) (8) (9) = (5)X(8) (10) = [(5)+(9)]*5% (11) = (9) + (10) (12) = (5) + (11) (13) = (12) / (3)
12.00 8.00 20.00 - - - #DIV/0!
PART A, FACILITIES FOR THE ENGINEERS
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.00 l.s 450,000.00 12.00 8.00 20.00 90,000.00 27,000.00 117,000.00 567,000.00 567,000.00
Sub-Total of Part A 450,000.00 90,000.00 27,000.00 117,000.00 567,000.00
Bridge Construction Replacement Program (BCRP) II : Widening of Coloy Bridge, Zamboanga Sibugay
Project Name and Location
Bridge Construction Replacement Program (BCRP) II : Lower Landing Bridge, Zamboanga del Norte
Project Name and Location
Station Limits : Approaches Sta. 1673+980.00 - Sta. 1674+340.00 Bridges Sta. 1674+133.47 - Sta. 1674+159.31
Length : 25.84 ln.m. Contract Duration : 234.00 Calendar Days
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.824 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.490 l.s 1.00 107,479.39 107,479.39
B.5 Project Billboard 0.025 each 2.00 5,380.90 2,690.45
Occupational Safety and Health
B.7 0.833 mon 8.50 182,651.00 21,488.35
Program
B.9 Mobilization and Demobilization 0.751 l.s 1.00 164,694.60 164,694.60
B.15(1) Detour/Access Road 13.829 l.s 1.00 3,033,221.34 3,033,221.34
PART C: EARTHWORKS
100(1) Clearing and Grubbing 0.022 has 0.06 4,868.43 81,140.50
PART F: BRIDGE CONSTRUCTION
103(2)a Bridge Excavation (Common Soil) 0.957 cu.m 909.00 209,806.06 230.81
Shoring, Cribbing and Related Works
103(5)a 1.948 l.s 1.00 427,292.40 427,292.40
(Shoring)
401(2)a Railing, Concrete Side Barrier 1.300 ln.m 68.20 285,212.44 4,182.00
402(b.1)2 Timber Structures for Craneway 5.396 ln.m 35.00 1,183,467.60 33,813.36
404 (1)a Reinforcing Steel Bar, Grade 40 0.257 kg. 836.79 56,345.17 67.33
404 (1)b Reinforcing Steel Bar, Grade 60 19.101 kg. 61,525.05 4,189,622.45 68.10
Structural Concrete, Class A,
405 (1)b2 24.920 cu.m 563.21 5,465,737.90 9,704.62
27.58MPA @ 14 days
727 (1) Non Shrink Grout, Fc=17 MPA 0.149 cu.m 0.32 32,670.40 102,094.99
Prestressed Structural Concrete Member,
406 (1)g10 AASHTO Girder Type IV, L=34.10m.
24.753 each 4.00 5,429,234.72 1,357,308.68
407(8) Lean Concrete, Fc=17 MPA 0.300 cu.m 14.30 65,887.15 4,607.49
Elastomeric Bearing Pad (400 X 600 X
412 (1) 0.222 each 8.00 48,711.92 6,088.99
56mm)
412 (2) Compressible Pad, 30mm thk 0.072 sq.m 1.82 15,881.20 8,725.93
Expansion Joint, 50mm gap with
413 (2) 0.073 ln.m 18.68 15,989.20 855.95
complete accessories
Premolded Expansion Joint Filler with
413 (1)a 0.009 ln.m 8.00 1,919.20 239.90
Sealant (12mm thk)
Premolded Expansion Joint Filler with
413 (1)a 0.004 ln.m 3.36 816.70 243.06
Sealant (30mm thk)
414 Forms and Falseworks 2.715 l.s 1.00 595,572.60 595,572.60
Anchor Bar (45mm dia. X 200mm),
712 (1) 0.040 each 24.00 8,846.85 368.62
Expansion Type
PART G: DRAINAGE AND SLOPE PROTECTION
Metal Drain (150mm dia. X 750mm GI
517 (1)a 0.010 each 11.88 2,265.55 190.70
Pipe) w/ complete accessories
TOTAL 100.000 21,933,575.15
Name of Project : Bridge Construction Replacement Program (BCRP) II : Calumangi Bridge I,
Dumingag, Zamboanga del Sur
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 60.38 18,114,711.47
A.2 Labor 5.38 1,613,083.13
A.3 Equipment Expenses 7.35 2,205,780.56
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.38 1,313,271.66
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 1.955 l.s 1.00 450,000.00 450,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.460 l.s 1.00 105,882.01 105,882.01
B.5 Project Billboard 0.023 each 2.00 5,378.56 2,689.28
Occupational Safety and Health
B.7 0.785 mon 8.40 180,706.40 21,512.67
Program
B.9 Mobilization and Demobilization 0.715 l.s 1.00 164,694.60 164,694.60
B.15(1) Detour/Access Road 11.961 l.s 1.00 2,753,221.34 2,753,221.34
PART C: EARTHWORKS
100(1) Clearing and Grubbing 0.021 has 0.06 4,868.43 81,140.50
104(2)a Embankment from Common Borrow 0.509 cu.m. 603.00 117,089.64 244.66
105 (1)a Subgrade Preparation 0.208 sq.m. 3,120.00 47,835.32 15.33
PART D: SUBBASE AND BASE COURSE
200 (1) Aggregate Subbase Course 7.616 cu.m 1,021.00 1,753,208.31 1,717.15
PART E: SURFACE COURSES
300 (1) Aggregate Surface Course 0.802 cu.m 129.00 184,621.40 1,431.17
Portland Cement Concrete
311(1)e1 3.391 sq.m. 498.60 780,616.24 1,565.62
Pavement, 0.28m thick
PART F: BRIDGE CONSTRUCTION
103(2)a Bridge Excavation (Common Soil) 0.791 cu.m 788.77 182,055.81 230.81
401(2)a Railing, Concrete Side Barrier 1.057 ln.m 58.20 243,392.43 4,182.00
404 (1)a Reinforcing Steel Bar, Grade 40 0.257 kg. 876.91 59,046.65 67.33
404 (1)b Reinforcing Steel Bar, Grade 60 21.180 kg. 71,596.98 4,875,482.66 68.10
Structural Concrete, Class A,
405 (1)b2 23.745 cu.m 563.21 5,465,737.90 9,704.62
27.58MPA @ 14 days
727 (1) Non Shrink Grout, Fc'=41 MPA 0.142 cu.m 0.32 32,670.40 102,094.99
Prestressed Structural Concrete Member,
406 (1)g10 AASHTO Girder Type IV, L=29.10m.
20.142 each 4.00 4,636,434.54 1,159,108.64
407(8) Lean Concrete, Fc=17 MPA 0.286 cu.m 14.30 65,887.15 4,607.49
Elastomeric Bearing Pad (400 X 600 X
412 (1) 0.212 each 8.00 48,711.92 6,088.99
56mm)
412 (2) Compressible Pad, 30mm thk 0.069 sq.m 1.82 15,881.20 8,725.93
Expansion Joint, 50mm gap with
413 (2) 0.069 ln.m 18.68 15,989.20 855.95
complete accessories
Premolded Expansion Joint Filler with
413 (1)a 0.008 ln.m 8.00 1,919.20 239.90
Sealant (12mm thk)
Premolded Expansion Joint Filler with
413 (1)a 0.004 ln.m 3.36 816.70 243.06
Sealant (30mm thk)
Anchor Bar (45mm dia. X 200mm),
712 (1) 0.038 each 24.00 8,846.85 368.62
Expansion Type
PART G: DRAINAGE AND SLOPE PROTECTION
505(2)a Grouted Riprap, Class A 1.459 cu.m 102.22 335,935.50 3,286.40
508 Handlaid Rock Embankment 0.141 cu.m. 18.62 32,552.78 1,748.27
Metal Drain (150mm dia. X 750mm GI
517 (1)a 0.010 each 10.56 2,265.55 214.54
Pipe) w/ complete accessories
TOTAL 100.000 23,018,860.42
Name of Project : Bridge Construction Replacement Program (BCRP) II : Calumangi Bridge II,
Dumingag, Zamboanga del Sur
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 65.47 19,640,440.53
A.2 Labor 4.52 1,357,246.16
A.3 Equipment Expenses 6.74 2,021,173.74
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.59 1,378,400.44
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 0.749 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.042 l.s 1.00 22,509.33 22,509.33
B.5 Project Billboard 0.010 each 2.00 5,261.56 2,630.78
Occupational Safety and Health
B.7 0.393 mon 9.90 209,875.40 21,199.54
Program
B.9 Mobilization and Demobilization 0.823 l.s 1.00 439,185.60 439,185.60
PART C: EARTHWORKS
101(3)a Removal of PCCP 0.012 sq 80.00 6,534.51 81.68
102(2) Surplus Excavation 0.006 cu.m 47.00 3,347.69 71.23
PART D: SUBBASE AND BASE COURSE
200 (1) Aggregate Subbase Course 0.069 cu.m 24.00 37,052.94 1,543.87
PART F: BRIDGE CONSTRUCTION
1300(2b)1 Steel Tubular Pile, 450 mm dia., supply 27.758 m 1,472.00 14,815,222.06 10,064.69
1300(2b)2 Steel Tubular Pile, 450 mm dia., drive 7.349 m 1,380.00 3,922,423.03 2,842.34
401(2)a Railing, Concrete Side Barrier 0.435 ln.m 56.00 231,925.82 4,141.53
412 (1) Compressible Pad, 30mm thk 0.092 each 8.00 49,054.16 6,131.77
I. ESTIMATED COST
A. DIRECT COST
A.1 Materials 59.63 41,190,768.98
A.2 Labor 4.63 3,201,091.13
A.3 Equipment Expenses 13.00 8,980,161.10
C. VAT (5% of D.C. and I.C. per D.O. # 197) 4.55 3,143,947.20
Bureau : DPWH
Region : IX
District/ City : Zamboanga City
PROGRAM OF WORK
(For all types of Project)
A.1.1 (3) Bunkhouse (7.00m X 9.00m) 0.551 l.s 1.00 400,000.00 400,000.00
PART B: OTHER GENERAL REQUIREMENTS
B.4(5) Bridge Survey and Staking 0.275 l.s 1.00 200,127.53 200,127.53
B.5 Project Billboard 0.007 each 2.00 5,378.56 2,689.28
Occupational Safety and Health
B.7 0.326 mon 11.30 237,099.80 20,982.28
Program
B.9 Mobilization and Demobilization 0.834 l.s 1.00 606,027.20 606,027.20
PART F: BRIDGE CONSTRUCTION
Bridge Excavation above ordinary
103(2)a 0.244 cu.m 537.00 177,064.05 329.73
water level
Bridge Excavation below ordinary
103(2)b 0.244 cu.m 1,400.00 177,073.00 126.48
water level
400 (4)a1 Precast Concrete Piles, Furnished 14.054 ln.m 2,286.00 10,210,926.42 4,466.72
400(6) Structural Steel Piles, Furnished 5.577 ln.m 1,647.00 4,051,580.54 2,459.98
400(12) Structural Steel Piles, Driven 2.140 ln.m 1,098.00 1,554,777.63 1,416.01
400(14) Precast Concrete Piles, Driven 5.808 m 2,159.00 4,219,717.82 1,954.48
Test Piles, Furnished and Driven
400(16) 0.663 ln.m 90.00 481,421.03 5,349.12
(400mm X 400mm)
401(2)a Railing, Concrete Side Barrier 1.075 ln.m 192.00 780,671.73 4,066.00
Structural Steel, Furnished, Fabricated,
403(5) 20.859 kg. 81,945.64 15,154,464.52 184.93
and Erected
404 (1)a Reinforcing Steel Bar, Grade 40 0.412 kg. 4,448.38 299,331.05 67.29
404 (1)b Reinforcing Steel Bar, Grade 60 13.589 kg. 145,075.50 9,872,635.20 68.05
Structural Concrete, Class A,
405 (1)b2 11.702 cu.m 911.45 8,502,103.11 9,328.11
27.58MPA @ 14 days
Prestressed Structural Concrete Member,
406 (1)d5 AASHTO Girder Type IV, L=23.25m.
10.367 each 8.00 7,531,624.90 941,453.11
407(8) Lean Concrete, Fc=17 MPA 0.143 cu.m 22.60 104,129.35 4,607.49
412 (1) Elastomeric Bearing Pad 0.268 each 32.00 194,847.68 6,088.99