Professional Documents
Culture Documents
PROGRAM OF WORK
(For all types of Project)
Date : Dec. 19, 2016
PROJECT DESCRIPTION :
a. Installation of Reinforcing Steel (Deformed), Suspended Slab, and Beams
b. Tiling Works on all second floor and 1 C.R.
c. Ceilings, Doors, Aluminum Doors and Windows
d. Metal Railings at Stairs
e. Electrical and Plumbing Works
I. ESTIMATED COST
A. DIRECT COST
C. VAT (5% of D.C. and I.C. Per D.O. # 22) 4.59 134,805.79
Prepared : Submitted:
BELEN A. SAPALLEDA WILHELMINA B. KASIM CAYAMOMBAO D. DIA JORGE U. SEBASTIAN, JR., CESO III
Head, BAC Technical Working Group OIC - Chief, Maintenance Division OIC - Asst. Regional Director Regional Director
DETAILED UNIT PRICE ANALYSIS
Sub-total for B P -
C. Total (A+B) 40,981.12
D. Output/day -
Sub-total for B P -
C. Total (A+B) 1,739.60
D. Output/day - each/day
Sub-total for B P -
C. Total (A+B) 89,899.20
D. Output/day