Republic of the Philippines

City of Makati

PROGRAM OF WORKS
Date: 12 November 2017
Name and Location of Project: Appropriation: Php 242,000,000.00
ASPHALT OVERLAY OF AYALA AVENUE & SEN. GIL PUYAT AVENUE Source of Funds: City Government
(Former Buendia Avenue) Project Duration: 180 Calendar Days
Desirable Starting
City of Makati Upon Approval
Date:
Mode of
By Contract
Implementation:
Project Category:
ROAD MAINTENANCE/REHABILITATION
Project Description:
Ayala Avenue: Major Junction - From Edsa (Brgy. San Lorenzo), Makati Ave., Paseo de Roxas, VA Rufino St., to Metropolitan
Ave. (Brgy San Antonio) (Length: 1.90km)
Sen. Gil Puyat Avenue: West End - Taft Ave., Osmeña Highway (SLEX), Chino Roces Ave., Ayala Ave., Makati Ave., Paseo
de Roxas, East End - Edsa (Makati) (Length: 5.40km)
TOTAL LENGTH: 7,300 Ln.M.
MINIMUM EQUIPMENT REQUIREMENTS MINIMUM TECHNICAL PERSONNEL REQUIRED
NO. DESCRIPTION NO. DESCRIPTION
6 Dumptruck (10 Wheeler) 1 Project Manager
1 Payloader 1 Project Engineer
1 Asphalt Mixing Plant 1 Materials Engineer
3 Backhoe/Excavator 1 Geodetic Engineer
3 Asphalt Paver Finisher 1 Surveyor
1 Motorized Grader 1 General Foreman
1 Water Truck 1 Materials Laboratory Technician
1 Water Pump 4 Masons
2 Vibratory Roller 4 Carpenters
2 Steel Wheel Rollers 4 Skilled Laborers
2 Pnuematic Tire Rollers 15 Unskilled Laborers
1 Mobile Crane (45 T)
1 Traffic Safety Devices (lot)
2 Generator Set
2 Sweeping Machine/Power Broom
1 Material Transfer Vehicle
2 Asphalt Distributor Truck
ITEM NO. DESCRIPTION QUANTITY UNIT % TOTAL COST
PART A FACILITIES FOR THE ENGINEER
A.1.1 (8) Provision of Field Office for the Engineers 6.00 months 0.10 252,000.00
A.1.2 (4) Provisionof Service Vehicle for the Engineer 6.00 months 0.08 189,000.00

PART B OTHER GENERAL REQUIREMENTS


A.1.4(1) Provision of Progress Photograhs 6.00 moths 0.03 62,118.00
B.5 Project Billboard/Signboard 2.00 each 0.00 11,083.80
B.7 Occupational Safety and Health Program 6.00 months 0.11 270,900.00
B.8 Traffic Management 6.00 months 0.13 315,000.00
B.9 Mobilization and Demobilization 1.00 LS 0.32 777,000.00

PART E SURFACE COURSES


302 (2) Bituminous Tack Coat (Emulsified Asphalt) 77.35 M.T. 2.78 6,736,179.45
Bituminous Concrete Surface Course (50mm
310 (b.3) 154,700.00 sq.m. 94.36 228,363,244.03
thk.) Hot Laid

Asphalt Overlay of Ayala Avenue and Sen. Gil Puyat Avenue (Former Buendia Avenue) Page 1 of 2
PART H MISCELLANEOUS STRUCTURES
Reflectorized Thermoplastic Pavement Markings
612 (1) 4,843.98 sq.m. 2.06 4,985,472.66
(White)
Reflectorized Thermoplastic Pavement Markings
612 (2) 30.00 sq.m. 0.02 38,001.60
(Yellow)
TOTAL 100.00 241,999,999.54

Prepared by: Checked and reviewed by:

Engr. Elmer V. Acuesta Engr. Leopoldo V. Panumog


Infrstructure Development Sector Environmental Service Sector

Submitted by: Recommending Approval:

Engr. Merlina G. Panganiban, EnP-Phd Mr. Rhoderick R. Torres


Development Department (UOD) Budget Department Head

Approved by:

Hon. Mar-Len Abigail S. Binay


City Mayor

Asphalt Overlay of Ayala Avenue and Sen. Gil Puyat Avenue (Former Buendia Avenue) Page 2 of 2