Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


MAJOR INFRASTRUCTURE PROJECTS

Status as of NOVEMBER 30, 2018


Name of Project : WIDENING OF PERMANENT BRIDGES - NLTC BRIDGE (B00552LZ)ALONG A. CASTRO
AVENUE
Station Limits :
PROJECT DESCRIPTION: Widening of Permanent Bridges

PROJECT IMPACT: Intends in providing passage over the obstacle such as bodies of water or valley.

CONTRACTUAL DATA : FINANCIAL STATUS :


Project Component : P00202092LZ
Province : ILOCOS NORTE
Region : I Amount (P'000)
Location : LAOAG CITY Allocation Releases Obligation Disbursement
Source of Funds : GAA 2018 FY2017
Mode of Contract : FY2018 12,640.00 12,387.12 11,953.57
Implementing Office
DPWH ILOCOS
: NORTE 1ST DEO FY2019
Date of Bidding : 08-Jan-18 Total: -
Contractor : ZEDIK BUILDERS
Total Project Cost : 11,953,571.096

Revised Contract Amount :


Start Date : 16-Feb-18
Contract Duration : 189
Revised Contract Duration : -
Completion Date : 23-Aug-18
Revised Completion Date : -
PHYSICAL ACCOMPLISHMENT : REMARKS:
Previous To Date
Planned Accomplishment : 100.00% 100.00%
Actual Accomplishment : 100.00% 100.00%
Slippage : 0.00% 0.00%

PROJECT UPDATE: EQUIPMENT ON SITE:


Project Completed N/A

MANPOWER ON SITE:
N/A

ACTIVITIES UNDERTAKEN:
Clearing and Grubbing Concrete Railing Standard
Removal of Structures and Obstruction (Concrete) Structural Concrete (Class A, 27.58 Mpa)
Embankment from Borrow (Common Soil) Paint
Subgrade Preparation (Common Material) Carbon Fiber 1 Layer
Aggregate Subbase Course Carbon Fiber
PCCP Pavement, (0.28m thick) Stone Masonry
Precast Concrete Piles, driven Drain Pipe Galvanized
Precast Concrete Piles, furnished (400x400 mm) Single Arm Post, with Street Light LED
Splices Structural Concrete Injection and Crack Repair
Test Piles, furnished and driven

PROBLEMS/ISSUES: ACTIONS UNDERTAKEN:


N/A N/A

Prepared by: Submitted by: Approved by:

ROBERT G. RABAGO ROMEO M. BARTOLOME MARIA VENUS S. TORIO


Project Engineer Chief, Construction Section OIC, District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS

Status as of November 30, 2018


Name of Project : WIDENING OF PERMANENT BRIDGES - NLTC BRIDGE (B00552LZ)ALONG A. CASTRO AVENUE

Station Limits ###


:
BENEFITS:
SOCIAL ECONOMIC ENVIRONMENTAL OTHER BENEFITS
1. Reduces traffic and 1. 1. 1.
increases safety for Easy access and
travelers and deliveries of raw materials
commuters. and finished goods to
factories, warehouses,
. suppliers, distributors,
stores, and end-
consumers.
2

PROGRESS PHOTOGRAPHS:
AFTER:

LOCATION MAP:
Prepared by: Submitted by: Approved by:

GERRY G. JUCAR AQUILINO M. NICER MELANIO C. BRIOSOS, CESO IV


Asst. Chief, Construction Division SONA, Focal Person OIC-Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS

Status as of NOVEMBER 30, 2018


Name of Project : CONCRETING OF ROAD, BRGY. DIPILAT, VINTAR, ILOCOS NORTE

Station Limits :
PROJECT DESCRIPTIONConcreting of Local Roads

PROJECT IMPACT: Improved transport quality and minimize travel duration.

CONTRACTUAL DATA : FINANCIAL STATUS :


Project Component : P00255566LZ
Province : ILOCOS NORTE
Region : I Amount (P'000)
Location : LAOAG CITY Allocation Releases Obligation Disbursement
Source of Funds : GAA 2018 FY2017
Mode of Contract : FY2018 22,000.00 21,560.00 20,922.00
Implementing Office : DPWH ILOCOS NORTE 1ST DEO FY2019
Date of Bidding : 26-Feb-18 Total: -
Contractor : NORTHLANDER
CONSTRUCTION/VIKING
CONSTRUCTION & SUPPLIES (JV)
Total Project Cost : 20,922,667.40

Revised Contract Amount : 21,559,997.67


Start Date : 11-Apr-18
Contract Duration : 146
Revised Contract Duration : 176
Completion Date : 03-Sep-18
Revised Completion Date : 03-Oct-18
PHYSICAL ACCOMPLISHMENT : REMARKS:
Previous To Date
Planned Accomplishment : 100% 100.00%
Actual Accomplishment : 100% 100.00%
Slippage : 0% 0.00%

PROJECT UPDATE: EQUIPMENT ON SITE:


Project Completed

MANPOWER ON SITE:

ACTIVITIES UNDERTAKEN:
Removal of Actual Structures/Obstruction subgrade Preparation (Common Excavation) Pipe Culvert (RCPC, 910mm dia.)
Surplus Common Excavation Aggregate Subbase Course Grouted Riprap
Structure Excavation (Common Soil) PCC Pavement (0.23m thick) Stone Masonry
Embankment (from roadway excavation) Structural Concrete (Class A, 27.58 Mpa) Single Arm Post, with street light

PROBLEMS/ISSUES: ACTIONS UNDERTAKEN:


Project was suspended due to unworkable site condition Issued Work Suspension Order and instructed the
cause of Right of Way (ROW) contractor to provide catch-up plan.

Prepared by: Submitted by: Approved by:

ROBERT G. RABAGO ROMEO M. BARTOLOME MARIA VENUS S. TORIO


Project Engineer Chief, Construction Section OIC, District Engineer
of the Philippines
BLIC WORKS AND HIGHWAYS
STRUCTURE PROJECTS

NOVEMBER 30, 2018

Amount (P'000)
Disbursement

Pipe Culvert (RCPC, 910mm dia.)

Single Arm Post, with street light


Issued Work Suspension Order and instructed the
contractor to provide catch-up plan.

MARIA VENUS S. TORIO


OIC, District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS

Status as of November 30, 2018


Name of Project : CONCRETING OF ROAD, BRGY. DIPILAT, VINTAR, ILOCOS NORTE

Station Limits ###


:
BENEFITS:
SOCIAL ECONOMIC ENVIRONMENTAL OTHER BENEFITS
1. 1. Wider market or consumer 1. Easy access to rice 1.
Rise in land value base leads to better fields
economies of sale in
production
2.

Increase employment
opportunities.

PROGRESS PHOTOGRAPHS:
AFTER:

LOCATION MAP:
Prepared by: Submitted by: Approved by:

GERRY G. JUCAR AQUILINO M. NICER MELANIO C. BRIOSOS, CESO IV


Asst. Chief, Construction Division SONA, Focal Person OIC-Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS

Status as of NOVEMBER 30, 2018


Name of Project : REHABILITATION OF MPB, MARUAYA, PIDDIG, ILOCOS NORTE

Station Limits : N/A


PROJECT DESCRIPTION: Rehabilitation of Multi Purpose Building

PROJECT IMPACT:Intends in providing space for both permanent and temporary services and events.

CONTRACTUAL DATA : FINANCIAL STATUS :


Project Component : P00250548LZ
Province : ILOCOS NORTE
Region : I Amount (P'000)
Location : PIDDIG Allocation Releases Obligation Disbursement
Source of Funds : GAA 2018 FY2017
Mode of Contract : FY2018 800.00 799.99 789.05
Implementing Office : DPWH ILOCOS NORTE 1ST DEO FY2019
Date of Bidding : 07-May-18 Total: -
Contractor : ACCV BUILDERS
Total Project Cost : 789,047.54

Revised Contract Amount : -


Start Date : 06-Jun-18
Contract Duration : 60
Revised Contract Duration : 105
Completion Date : 04-Aug-18
Revised Completion Date : 18-Sep-18
PHYSICAL ACCOMPLISHMENT : REMARKS:
Previous To Date
Planned Accomplishment : 100.00% 100.00%
Actual Accomplishment : 100.00% 100.00%
Slippage : 0.00% 0.00%

PROJECT UPDATE: EQUIPMENT ON SITE:


Project Completed N/A

MANPOWER ON SITE:
N/A

ACTIVITIES UNDERTAKEN:
Removal of Structures and Obstruction Structural Concrete (Footings and SOF)
Structure Excavation (Common Soil) Structural Concrete (Columns)
Installation of Structural Steel Painting Works, Steel
Prepainted Metal Sheets (Long Span, 0.427 mm corrugated)

PROBLEMS/ISSUES: ACTIONS UNDERTAKEN:


Project was suspended due to unworkable site condition
cause by obstruction
Unworkable days due to intermittent rain.

Prepared by: Submitted by: Approved by:

ROQUE R. ABLAN ROMEO M. BARTOLOME MARIA VENUS S. TORIO


Project Engineer Chief, Construction Section OIC, District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS

Status as of November 30, 2018


Name of Project : REHABILITATION OF MPB, MARUAYA, PIDDIG, ILOCOS NORTE

Station Limits : N/A


BENEFITS:
SOCIAL
Serve as feeding ECONOMIC ENVIRONMENTAL
Serve as an OTHER BENEFITS
1. center for 1. Serve as training center 1. evacuation center 1.
malnourished for Brgy. Mates during
children. especially to those calamity/disaster
unemployed.
2.
Serve/can be rented as
a function hall for
occasions.

PROGRESS PHOTOGRAPHS:
AFTER:

LOCATION MAP:
Prepared by: Submitted by: Approved by:

GERRY G. JUCAR AQUILINO M. NICER MELANIO C. BRIOSOS, CESO IV


Asst. Chief, Construction Division SONA, Focal Person OIC-Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS

Status as of NOVEMBER 30, 2018


Name of Project : Completion of School Building, 2 Storey 10 Classrooms, Piddig, National High School

Station Limits : N/A


PROJECT DESCRIPTION: Construction of School Building

PROJECT IMPACT: Provide learning spaces and learning environments for the teaching of students under the
direction of teachers

CONTRACTUAL DATA : FINANCIAL STATUS :


Project Component : P00170056LZ
Province : ILOCOS NORTE
Region : I Amount (P'000)
Location : PIDDIG Allocation Releases Obligation Disbursement
Source of Funds : CY 2017 BEFF BATCH 1 FY2017
Mode of Contract : FY2018 666.10 666.10 664.10
Implementing Office : DPWH ILOCOS NORTE 1ST DEO FY2019
Date of Bidding : NORTH07-Nov-17
TECH BUILDERS Total: -
Contractor : & CONSTRUCTION
SUPPLY
Total Project Cost : 664,097.37

Revised Contract Amount : -


Start Date : 21-Nov-17
Contract Duration : 60
Revised Contract Duration : -
Completion Date : 19-Jan-18
Revised Completion Date : -
PHYSICAL ACCOMPLISHMENT : REMARKS:
Previous To Date
Planned Accomplishment : 100.00% 100.00%
Actual Accomplishment : 100.00% 100.00%
Slippage : 0.00% 0.00%

PROJECT UPDATE: EQUIPMENT ON SITE:


Project Completed

MANPOWER ON SITE:

ACTIVITIES UNDERTAKEN:
Grille Window
### Unglazed Tiles

PROBLEMS/ISSUES: ACTIONS UNDERTAKEN:


Prepared by: Submitted by: Approved by:

ROQUE R. ABLAN ROMEO M. BARTOLOME MARIA VENUS S. TORIO


Project Engineer Chief, Construction Section OIC, District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
MAJOR INFRASTRUCTURE PROJECTS

Status as of November 30, 2018


Name of Project : Completion of School Building, 2 Storey 10 Classrooms, Piddig, National High School

Station Limits : N/A

BENEFITS:
SOCIAL ECONOMIC ENVIRONMENTAL OTHER BENEFITS
1. 1. 1. 1.
Provide a better way
of taking care of enhancement of labor helps students
ourselves and market productivity and understand how their
consequently creating earnings. decisions and actions
a better society in affect the environment,
which to live builds knowledge and
skills necessary to
address complex
environmental issues, as
well as ways we can take
action to keep our
environment healthy and
sustainable for the future.

PROGRESS PHOTOGRAPHS:
AFTER:

LOCATION MAP:
Prepared by: Submitted by: Approved by:

GERRY G. JUCAR AQUILINO M. NICER MELANIO C. BRIOSOS, CESO IV


Asst. Chief, Construction Division SONA, Focal Person OIC-Regional Director