Professional Documents
Culture Documents
Implementing Agency
Noted By:
3.0 Annexes
Annex “A” Project Bar Chart & S-Curve page 7-8
Extension of Time
: 0 Calendar Days
Revised Contract
Completion Date
PROJECT UPDATE
The following contract requirements are all submitted at BCDA Field Office located at
Capas, Tarlac:
- Construction Schedule and S-Curve;
- Manpower Schedule;
- Construction Schedule;
- Equipment Utilization Schedule;
- Construction Safety and Health, Sanitation and Security Program;
- PERT/CPM;
- Contractor’s All-Risk Insurance;
- Personal Accident Insurance; and
- Shop drawings
Pre-Construction Activity:
- Joint as stake survey.
- Establishment of centerline.
- Establishment of RROW limit.
- Establishment of drainage structures.
- Application of tree cutting permit.
- Joint Tree Inventory with CENRO.
General:
- Construction of Field Office
- Facilities for the engineer were provided.
Earthworks
N/A
N/A
Construction
of Bridge
N/A
Drainage and
Slope Protection
N/A
N/A
Street
Landscape
The activity for this this period is as follows:
N/A
Most of the documentary requirements for the project like as-stake plans
schedules and other pertinent documents are already transmitted at BCDA
Site Office located at Capas, Tarlac.
As of February 03, 2021, the project is at 0.1003% versus the scheduled percent
accomplishment of 0.0543% which makes it advance by 0.046%. Most of the
activities were for the facilities of engineers and other pre-construction activity
such as above-mentioned activity.
FEBRUARY 2021
09-Feb-21 14-Feb-21 19-Feb-21 24-Feb-21 01-Mar-21
ITEM NO. DESCRIPTION QTY UNIT % WT
05-Feb-21 10-Feb-21 15-Feb-21 20-Feb-21 25-Feb-21
30 35 40 45 50
A FACILITIES FOR THE ENGINEER 1.02%
Construction of Field Office for the Engineer (Minimum of 180 sq. m) 1.00 l.s. 0.27% 0.02% 0.02% 0.02% 0.02%
Provision of Living Quarters for the Engineer (2 units – Rental Basis) 30.00 mo. 0.06% 0.001% 0.001% 0.001% 0.001% 0.001%
Operations and Maintenance of Field Office for the Engineer 15.00 mo. 0.15% 0.002% 0.002% 0.002% 0.002% 0.002%
Operations and Maintenance of Living Quarters for the Engineer 15.00 mo. 0.08% 0.001% 0.001% 0.001% 0.001% 0.001%
Provision of 2 units - 4x4 Pick-up Type Service Vehicle for the Engineer 30.00 mo. 0.21% 0.002% 0.002% 0.002% 0.002% 0.002%
Operations and Maintenance of 2 units – 4x4 Pick-up Type Service 30.00 mo. 0.11% 0.001% 0.001% 0.001% 0.001% 0.001%
Provision of Progress Photographs 15.00 mo. 0.02% 0.000% 0.000% 0.000% 0.000% 0.000%
Provision of Communication Facility for the Engineer 6.00 ea. 0.03% 0.000% 0.000% 0.000% 0.000% 0.000%
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 15 | 49
J a n u a r y 2 0 2 1
Annex “E1”
Mobilized Equipment and
Tools Schedule
- O (OPERATIONAL)
- I (IDLE)
- B (BREAKDOWN)
02 Project Engineer 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 2 2 2
03 QS Head 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1
04 Architect - - - - - - - - - - - - - - - - - - - - - 1 1 1
05 Geodetic Engineer 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1
06 Instrument Man 2 2 2 2 2 2 - 2 2 2 2 2 2 - 2 2 2 2 2 2 - 3 3 3
07 Survey Aide 4 4 4 4 4 4 - 4 4 4 4 4 4 - 4 4 4 4 4 4 - 6 6 6
08 Safety Practitioner - - - - - - - - - - - - - - - - - - - - - 1 1 1
09 Foreman 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1 1 1 1 - 1 1 1
10 Carpenter 6 6 6 6 6 6 - 6 6 6 6 6 6 - 6 6 6 6 6 6 - 6 6 6
11 Mason 8 8 8 8 8 8 - 8 8 8 8 8 8 - 8 8 8 8 8 8 - 8 8 8
12 Steelman 2 2 2 2 2 2 - 2 2 2 2 2 2 - 2 2 2 2 2 2 - 2 2 2
13 Welder 5 5 5 5 5 5 - 5 5 5 5 5 5 - 5 5 5 5 5 5 - 5 5 5
14 Electrician 3 3 3 3 3 3 - 3 3 3 3 3 3 - 3 3 3 3 3 3 - 3 3 3
15 Helper 13 12 13 11 13 13 - 11 10 12 13 12 13 - 13 13 12 11 12 13 - 12 11 13
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 19 | 49
J a n u a r y 2 0 2 1
Annex “E3”
List of Delivered Materials
CONSTRUCTION OF WAREHOUSE
CONSTRUCTION OF WAREHOUSE