You are on page 1of 2

MINUTES

OF MEETING
        

Project Name: Remedial Measures Against Flooding in Al‐Jouf‐ANNEX‐2 ‐ SAPAC


Minutes Of Meeting No. 005 Date: 02/06/2021
Avenue: Microsoft Teams Time: 1:00 PM
Chaired by : Abdul Rahman Abdullah Recorded by : Adel Sabry
Attendees :
Staff Name Role Email / Phone
SAR Turki Bin Hamdan Project Manager
SAR Mohannad Ali Aldibasi Annex1 Manager
SAR Tamim Ahmed Abnami Project Site Manager (Annex 1&2)
K&A Abdul Rahman Abdullah Project Manager
K&A Abdel Kader Chaaban Contract Engineer
K&A Adel Eid Civil Engineer
K&A Hamouda Ali Track Engineer
K&A Tamer Al Deeb Bridge Engineer
K&A Amjath Mancheri Planning Engineer
K&A Omar Survey Engineer
K&A Jaafar QS Engineer
K&A Ashri Manalo QC Engineer
K&A Ayaz Ahmed HSE
K&A Adel Sabry DC
SAPAC Saeed Mohamed Project Manager
SAPAC Osama Mabrouk TM
Distribution : All attendees
Item Description Action By Date

1 Agenda
1.1 Discuss practical plan to accelerate project implementation 
2 Minutes
2.1 Time Schedule
2.1.1 Contractor submited the cost & resource loaded schedule /programe on 06 May 2021.
Consultant reviewed with and rejected (Code C) on 11 May 2021,  due to some incompliance with the 
project/Contract requirements and was instructed to re‐submit the project time schedule incorparating 
corrections, within 5 Days counting from the reopening day after EID holiday.
  SAPAC 06‐Jun‐21
Monthly Report:
contractor need to prepare and submit the monthly report for April and May (Table of Content is given) 
review and approval.
The weekly report format is given to fill and submit for reveiw and approval.Not yet submitted.
2.2 Performance Bond /Guarantee Bond / Insurances.
2.2.1 Care and Supply of Documents:
To Provide one full edition of the publications (such as, but not limited to, Technical Standards and Codes  SAPAC
of Practice) named in the Specification, etc..
Contractor to submit today 2/6/21 
The Contract Price:  SAPAC 2/6/2021
The breakdown of each unit price of the Bill of Quantities.
/K&A
Re‐Submitted and under reveiw in cordination between the engineer and the contractor
Insurances:
SAPAC
To expedite the submission and completeness of all the insurances.
Remaining the projects insureances and will be submitted Sunday 6/6/21
2.3 Site Mobilization and Accommodation to Consultant:
2.3.1 Site Offices: To prepare snag list
SAPAC 6/6/2021
Contract to submit mobilization plan by today 2/6/21
2.4 Design submittals:
2.4.1
2.5 Surveying work: 

Page 1 of 2   
MINUTES OF MEETING
        

Item Description Action By Date

2.5.1 The contractor should expedite the submittals of site related work activties (B.M & 
topographic survey report) (3 points out of 56 ) were submitted 
the client requested to the contractor to expedite the works to be 100%"
Contractor submitted NGL for points 42,43,44 and 45 , its under revision by the  SAPAC 6/6/2021
engineer
Contractor to submit mitigation plan due to delay in work progress SAR
Contractor to increase one more survey team
2.6 Work Progress on Site:
2.6.1 • Contractor should be submitting method of statement for demolishing for 
approval.
Discussion solutions  for zones (7&8) 27‐04‐2021
The contractor should be submitting shopdrawing  of soluations with deatails for  SAPAC
approval from the engineer
Contractor will submit shop drawing for each station (Approved station in detail)

2.7 Quality Assurance & Quality Control
2.7.1 The contractor shall proposed the Quality Manager  SAPAC
2.8.1 Labor ID and Access to Site:
2.8.1 Labour Card / Site Access cards for all employees/Labours need to be provided by Contractor at 
Site.
Client will provide updates next week SAR 6/6/2021
2.9 Question and answers session‐ other items

Meeting Ended at 3:25 PM

Page 2 of 2   

You might also like