You are on page 1of 3

Daily Report

Report No: OTC-SAR-DR-0030 Date: 8-Jul-2021


Project Name Remedial Measures Against Flooding In Al Jouf Province Annex 1

Owner Saudi Railway (SAR)

Consultant Khatib & Alami

Contractor Al-Omaier Trading & Contracting Company

Cumulative Planned Progress % (11.71 %) under review Cumulative Actual Progress % (10.30 %) under review
Day
Sat Sun Mon Tue Wed Thu Fri

Weather Status:
Windy Rainy Cloudy Sunny/Clear
Humidity: Low Medium High
Temperature: 38°-20°

Contractor Manpower in Site : ‫اﻷيدي العاملة لدى المقاول في الموقع‬

Administration officer

Construction Manager
Quantity Surveyor
Planning Engineer

Auto cad operator

Total Direct M.P


Total direct M.P
QA/QC inspector
QA/QC Engineer
QA/QC Manager

Design Engineer
Project Manager

Safety inspector
Chief Surveyor

Track Engineer

Security guard
-Skilled /Labor

&Accountant
HSE Engineer
HSE Manager

Site Engineer

Office Boy

-Operator
Surveyor

Lab tech
Forman

Driver

Total
Actual
1 1 1 1 3 1 1 1 1 1 3 1 1 5 22 2 17 1 3 7 4 34 56
Planned
0 0 0

Contractor Equipment in Site :‫المعدات لدى المقاول في الموقع‬


Roller Compactor

Concrete mixer
Concrete pump

Low/High Bed
DISEL Truck
Mobile Crane

Boom Truck

Dump Truck
Water Truck

Machinary
Excavator

Generator

Borehole
Back hoe

Loader
Bobcat
Grader

Roller
Dozer

Total
bus

Actual
1 1 1 1 2 4 1 1 1 1 14
Planned
0

Work in Progress Today : Work in Progress Tomorrow & RFIs:


Finish surface preparation of joint & application of sealant at culvert
1 1 nEEd RFI FOR demolishing culvert 1023 + 660.300
sta 1209+550
Finish surface preparation at culvert st 1202+750 and start
2 2 Survaying Work at sta. 1228+000 (R/S) Zone 4 .
application of sealant
Borehole activity stopped temporary today because of maintenance
3 3 Structure Excavation for Culvert Foundation sta. (1023+660) (RFIs)
for the machinary
4 Start BH#42 at sta 1243+850 4 Borehole - SPT Machine not working (Major Maintenance requerd)
5 5 Lining of the Joint at sta. (1209+950) (RFIs)
6 6 Preperation for Dismantling Railway at Sta. (1120+110)
7 7
8 8
9

Sta 1202+750

7/10/2021
Daily Report
Report No: OTC-SAR-DR-0030 Date: 8-Jul-2021

7/10/2021
Daily Report
Report No: OTC-SAR-DR-0030 Date: 8-Jul-2021

Submitted By Contractor: Reviewed By Consultant:

Name: Mustafa Amer (PM / Contractor Annex-1) Name: Engr. Abdulrahman Abdullah (PM - Consultant)]

Signature: Signature:

Date: 8/7/2021 Date:

7/10/2021

You might also like