You are on page 1of 3

Daily Report

Report No: OTC-SAR-DR-0027 Date: 1-Jul-2021


Project Name Remedial Measures Against Flooding In Al Jouf Province Annex 1

Owner Saudi Railway (SAR)

Consultant Khatib & Alami

Contractor Al-Omaier Trading & Contracting Company

Cumulative Planned Progress % (11.40 %) under review Cumulative Actual Progress % (10.25 %) under review
Day
Sat Sun Mon Tue Wed Thu Fri

Weather Status:
Windy Rainy Cloudy Sunny/Clear
Humidity: Low Medium High
Temperature: 39°-23°

Contractor Manpower in Site : ‫اﻷيدي العاملة لدى المقاول في الموقع‬

Administration officer

Construction Manager
Planning Engineer

Quantity Surveyor

Auto cad operator

Total Direct M.P


Total direct M.P
QA/QC inspector
QA/QC Engineer
QA/QC Manager

Design Engineer
Project Manager

Track Engineer

Track Engineer
Safety inspector

-Skilled /Labor
Chief Surveyor

Security guard
&Accountant
HSE Engineer
HSE Manager

Site Engineer

Office Boy

-Operator
Surveyor

Lab tech
Forman

Driver

Total
Actual
1 1 1 1 1 3 1 1 1 1 1 3 1 1 18 2 17 1 3 7 4 34 52
Planned
0 0 0

Contractor Equipment in Site :‫المعدات لدى المقاول في الموقع‬


Roller Compactor

Concrete mixer
Concrete pump

Low/High Bed
DISEL Truck
Mobile Crane

Dump Truck
Boom Truck

Water Truck

Machinary
Excavator

Generator

Borehole
Back hoe

Loader
Bobcat
Grader

Roller
Dozer

Total
bus

Actual
1 1 1 2 4 1 1 1 1 13
Planned
0

Work in Progress Today : Work in Progress Tomorrow & RFIs:


1 Service Road Preperation At Sta. (1100+000) Lift Side . 1 Service Road Preperation At Sta. (1100+000) Lift Side .

2 Survaying Work for Zone 4 2 Survaying Work for Zone 4 (RFIs)


3 Working in Access Road Between Asphalt Road and (Zone 1) 3 Working in Access Road Between Asphalt Road and (Zone 1)
4 Borehole Activity Type - SPT Sta. Station 1142+921 Left side 4 Borehole Activity Type - SPT Sta.1175+781 Right side (RFIs)

5 Structure Excavation for Bridge Foundation sta. 1243+850 Zone 5 5 Structure Excavation for Bridge Foundation sta. 1243+850 (RFIs)

6 Preperation for Dismantling Railway at Sta. (1119+261) 6 Preperation for Dismantling Railway at Sta. (1120+110)

7/1/2021
Daily Report
Report No: OTC-SAR-DR-0027 Date: 1-Jul-2021
Borehole Activity Type - SPT

Service Road Preperation

Site Safety Work

Structure Excavation for Bridge Foundation

Displaying of signboard in progress

7/1/2021
Daily Report
Report No: OTC-SAR-DR-0027 Date: 1-Jul-2021

Areas where Work Not Available as Planned (Issue if any needed to be cleared)

Submitted By Contractor: Reviewed By Consultant:

Name: Mustafa Amer (PM / Contractor Annex-1) Name: Engr. Abdulrahman Abdullah (PM - Consultant)]

Signature: Signature:

Date: 01/07/2021. Date:

7/1/2021

You might also like