You are on page 1of 1

PORT ACCESS ELEVATED HIGHWAY PROJECT

SECTION 1 FROM STA.0+000 TO STA.5+270


Contract No: RDA/ADB/OCB/PAEH/CW/01
EMPLOYER :
Weather
ROAD DEVELOPMENT AUTHORITY

ENGINEER:
Sedalia Associates, Inc. Joint Venture With Roughton International Ltd And Mg Consultants
Date: 29-Aug-2022
(Pvt.) Limited
CONTRACTOR:
Day Not Holiday
CCECC-HPRB-HNRBI JV
DAILY WORK SCHEDULE PLAN
Work Time
No: Category Section Work Description Officer In Charge Contact No: Inspection Time Planned Work Ending time
07:30-18:30 18:30-07:30
1 P53R-U13 Concreting Mr. Hirantha (077) 760 5064 ● ● 18:30 till 19:00
2 P44L-U04 Concreting Mr. Hirantha (077) 760 5064 ● ● 21:30 till 19:00
3 P44R-U05 Concreting Mr. Hirantha (077) 760 5064 ● ● 0:00 till 5:00
4 P53R-U14 Concreting Mr. Hirantha (077) 760 5064 ● ● 2:30 till 5:00

P44R-U06, P109L-U15, P44L-U05, P46L-U11, P53R-U01, P53R-


5 Rebar work Mr. Hirantha (077) 760 5064 ● ● till 19:30
U15, P53L-U11, P108R-U03, P43L-U05, P43R-U04
Beam Yard
P53R-U13, P44L-U04, P44R-U05, P53R-U14, P45L-U06, P109R-
6 Form work preparation Mr. Hirantha (077) 760 5064 ● ● till 19:30
U16

P56L-U12,P53L-U5,P56L-U11,P46R-U13,P56L-U6,P48R-
7 Grouting Mr. Hirantha (077) 760 5064 ● ● till 19:30
U11,P56L-U13,P56L-U10,P47R-U5,P52L-U6,P47R-U4

8 Pier 49 sewer line construction work. Mr. Akesha (072) 389 4949 ● ● till 20:00
9 Pier 68, 75 trial pit Mr. Akesha (072) 389 4949 ● ● till 20:00
10 Pier 89 statue foundation formwork and concreting to the new location Mr. Akesha (072) 389 4949 ● ● till 20:00
Utility
11 Pier 96 manhole r/f preparation Mr. Akesha (072) 389 4949 ● ● till 20:00
12 Pier 103 data center finishing works & excavation for manhole constructions and R/F works Mr. Akesha (072) 389 4949 ● ● till 20:00
13 Pier 105 excavation for manhole constructions and R/F works Mr. Akesha (072) 389 4949 ● ● till 20:00
14 MS-0 site formwork work of the segment Mr. Shashi (071) 886 8722 ● ● till 20:00
15 SS-0 reinforcement work and formwork work of the segment Mr. Shashi (071) 886 8722 ● ● till 20:00
16 Pier 4 Excavation for pile cap Mr. Shashi (071) 886 8722 ● ● till 20:00
17 Pier 5 reinforcement work for pile cap Mr. Shashi (071) 886 8722 ● ● till 20:00
18 Pier 6 reinforcement work pier stem Mr. Shashi (071) 886 8722 ● ● till 20:00
19 Pier 7 Backfilling for the Pile cap Mr. Shashi (071) 886 8722 ● ● till 20:00
20 Pier 93 Reinforcement work of the capping beam Mr. Shashi (071) 886 8722 ● ● till 20:00
21 Pier 94 Installation of the form traveler Mr. Shashi (071) 886 8722 ● ● till 20:00
22 Pier 36 sheet pile drive Mr. Kumara (077) 518 0838 ● ● till 20:00
23 Pier 39A sheet pile drive Mr. Kumara (077) 518 0838 ● ● till 20:00
24 Pier 49 sheet pile removing Mr. Kumara (077) 518 0838 ● ● till 20:00
25 Pier 103 pile hacking Mr. Kumara (077) 518 0838 ● ● till 20:00
26 Pier 105 backfilling Mr. Kumara (077) 518 0838 ● ● till 20:00
27 Pier 101 RHS Shoring work Mr. Pasan (077) 948 4556 ● ● till 20:00
28 Pier 31 RHS pile cap backfilling Mr. Ruwan (076) 758 8179 ● ● till 20:00
29 Pier 34 RHS (R1&R2) Pier 2nd stage re-bar Mr. Ruwan (076) 758 8179 ● ● till 20:00
30 Elevated Bridge Pier 95 LHS Pier 2nd stage scaffolding works for Pier construction Mr. Ruwan (076) 758 8179 ● ● till 20:00
31 Construction Pier 95 RHS scaffolding works for Pier construction Mr. Ruwan (076) 758 8179 ● ● till 20:00
32 Pier 97 RHS scaffolding works for Pier construction Mr. Ruwan (076) 758 8179 ● ● till 20:00
33 Pier 100 MID Pier 3rd stage f w and concrete Mr. Ruwan (076) 758 8179 ● ● 10:00 till 20:00
34 Pier 44, 46 Capping Beam supporting structure work. Mr. Lakshan (076) 685 9238 ● ● till 20:00
35 Pier 45: Capping Beam capping beam arrange for bottom formwork. Mr. Lakshan (076) 685 9238 ● ● till 20:00
36 Pier 48: Capping Beam capping beam bearing plinth rebar and PT bar fixing work. Mr. Lakshan (076) 685 9238 ● ● till 20:00
37 Pier 52: Capping Beam capping beam bearing plinth location chipping work. Mr. Lakshan (076) 685 9238 ● ● till 20:00
38 Pier 53: Capping Beam capping beam arrange for grouting work. Mr. Lakshan (076) 685 9238 ● ● till 20:00
39 Pier 54: Capping Beam capping beam end sealing formwork and supporting structure removing Mr. Lakshan (076) 685 9238 ● ● till 20:00
40 Pier 56: Capping Beam removing supporting structure removing. Mr. Lakshan (076) 685 9238 ● ● till 20:00
41 Pier 56-57 segment transport & lifting Mr.Sadaruwan (071) 4391795 ● ● till 20:00
42 Pier 58-59 span tendon grouting preparation Mr.Sadaruwan (071) 4391795 ● ● till 20:00
43 Pier 37 : Capping Beam end seal work. Mr. Isuru (076) 4173227 ● ● till 20:00
44 Pier 46 : Capping Beam Portal beam supporting structure works Mr. Isuru (076) 4173227 ● ● till 20:00
45 Pier 47: Capping Beam Portal beam reinforcement. Mr. Isuru (076) 4173227 ● ● till 20:00
46 Pier 50: Capping Beam Portal beam formwork. Mr. Isuru (076) 4173227 ● ● till 20:00
47 Pier 107: Capping Beam Portal beam chipping work. Mr. Isuru (076) 4173227 ● ● till 20:00
Note: Please note that due to the shortage of fuel we are facing difficulties in finding machinery and also materials. As a result of that the efficiency of site construction has become low during these troubled times. At our site many activities has been stopped or getting delayed because of the lack of machinery and material. There for the progress of other activities are also low because of the
material and fuel issue.

Prepared By Checked and Approved By:

Planning Engineer - H.M.G.J.Bandaranayake Deputy Technical Manager: Tian Pengfei