SINOHYDRO SAUDI ARAMCO OIL COMPANY

Planner & Control Engineer Sunny --- Lead Project Engineer


Highest Temperature: 43℃ Lowest Temperature: 30℃
Arcangel P. Gurain, Jr. Abdulmohsin Abdou

MIP UPGRADE TANAJIB ROADS PACKAGE 15 OVERALL %


Clearing &
Contract No.: 6600046061 BI No.: 10-02454
Grubbing
Cut Fill
As of Tuesday, June 2, 2020 56.07% 23.94% 0.00%
Daily Report - Major Work Status
% Cmplt
% Cmplt Total Length Total Length
Work Item Unit Budgeted Total Previous Today Cumulative Remaining /To Go Station Limit Work Item Unit Budgeted Total Previous Today Cumulative current est. Remaining /To Go Station Limit
current est.Qty Done (m) Done (m)
Qty
INDUSTRIAL ROAD SOUTH MARINE ROAD

Clearing & Grubbing m² 112,881.65 97,200.00 97,200.00 86.11% 15,681.65 13.89% 2+650-11+400 8,100.00 Clearing & Grubbing m² 170,383.98 - 0.00% 170,383.98 100.00%

2+650-4+500/5+200-
5+300/6+200-
Cut m³ 22,700.90 14,928.90 14,928.90 65.76% 7,772.00 34.24% 6+500/7+350-
2,400.00 Cut m³ 38,878.90 - 0.00% 38,878.90 100.00%
7+800/8+200-8+600

Fill m³ 61,704.30 Fill m³ - - #DIV/0! - #DIV/0!


NORTH MARINE ROAD PARKING AREA
Clearing & Grubbing m² 173,100.00 159,800.00 159,800.00 92.32% 13,300.00 7.68% 1+500-15+400 13,200.00 Clearing & Grubbing m² 18,418.75 18,418.75 18,418.75 100.00% - -
2+500-2+650/5+050-
5+200/6+750-
7+850/7+350-
Cut m³ 77,620.86 14,956.50 14,956.50 19.27% 62,664.36 80.73% 7+450/7+800- 2,250.00 Cut m³ 2,496.61 - 0.00% 2,496.61 100.00%
8+000/8+000-
8+400/8+400-
8+500/8+500-
Fill m³ 76,819.20 Fill m³ 8,000.49 - 0.00% 8,000.49 100.00%

EQUIPMENTS / TOOLS MOBILIZATION


Activity Manpower Equipment/Vehicle Description Today Remarks
HEAVT EQUIPMENT / VEHICLE
LAYDOWN YARD
CONTRACTOR
CAMP / TEMP.

Hydro / Mobile Crane / Heavy Lift Crane


Ambulance 1-Standby
50ton Truck Crane
Excavator
Grader 3-Standby, No Work (Parking Area)
Loader 2-Standby (No Work)
Road Roller Compactor 4-Standby, (No Work)
Curing for Concrete Walkways 4 1 Dump Truck 9-Standby, (No Work)
SAPMT OFFICE &
LAYDOWN YARD
CONTRACTOR &

Bulldozer 3-Standby, No Work (Parking Area)


Asphalt Paver
Pnuematic Roller
Asphalt Tanker
Concrete Mixer Turck
Concrete Boomplacer
Water Tank Truck 4-Standby (No Work)
Trailer
DYNA
INDUSTRIAL
TANAJIB

Forklift
ROAD

JCB
Boom Truck
Fuel Tank Truck
Bobcat
Bus
Fuel Tank Truck
NORTH TANAJIB
MARINE ROAD

Pick-up / Car / Mini Bus 2


SUB-TOTAL 2
TOOLS / MACHINE
Air Compressor
Generator
Welding Machine
Drill / Grinder
Surveying Machine w/ Complete Accessories (GPS/Total Station)
SOUTH TANAJIB
MARINE ROAD

Asphalt Cutter
Wood Cutter / Saw
Plate Compactor
Steel Cutting Machine
Water Pump
Vibrator Protable
SUB-TOTAL 0
TOTAL 2
MANPOWER MOBILIZATION (Unit: Man-Day)
SAFANIYAH
VILLAGE

Today Remarks
INDIRECT MANPOWER
Company Representative
Project Manager 1 Approved by SA
Construction Manager 1 Approved by SA
Construction Superintendent 1 Approved by SA
QA/QC Manager 1 Approved by SA
PARKING AREA

Procurement Manager 1 Approved by SA


Lead Civil Engineer 1 Approved by SA
Lead Electrical Engineer 1
Road Engineer
Chief Surveyor 1 Approved by SA
Interface Manager 1 Approved by SA
Safety Supervisor 1 Approved by SA
CADD Operator 1
TRAFFIC LIGHTS Contract Officer 1
QA/QC Inspector
QA/QC Document Controller 1
Document Controller 1 Approved by SA
QA/QC Supervisor 1
Planning & Control Engineer 1 Approved by SA
Nurse 1 Approved by SA
Saudi Employee
SUB-TOTAL 17
SOLAR STREET

Today Remarks
LIGHTING

DIRECT MANPOWER
Foreman
Safety Officer
Work Permit Receiver
Capenter
Mason
Rebarman/SteelMan
Plumber
Electrician
Flagman/Fire Watchman
OTHER WORKS

Surveyor
Driver 1
Rigger
Watchman 1
Painter
Welder
Laborer / Helper 2
Heavy Equipment Operator
SUB-TOTAL 4
TOTAL 4 1 TOTAL 21

EHS STATISTICS Previous Week To Date S.No. CONSTRUCTION / SITE ISSUES ACTION PLAN / REMARKS REASON TIME TEMP.
WEEKLY MANPOWER 1 Due to the curfew imposed by the Govt., activities on site will be affected. Once timing of curfew will start, work will resume at Temp. Laydown Yard for Fabrication.
Total Man-Hours Worked 3360 28633 2 Due to the lockdown, vendors, suppliers are closed which affects us in purchasing
Wematerials.
are trying to communicate/negotiate with the vendors & suppliers if they can supply us materials.
Fatal Injury 0 0 3 Telephone Line (STC, Mobily, Govt., Military & Police) & Fiber Optic Cable Safety Precaution and Coordination with the Owner.
Lost Time Injury 0 0 4
First Aid Injury 0 0 5
STOP WORK HSE
First Aid Treatment 0 0 SAFETY ISSUES ACTION PLAN / REMARKS Compliance
7:00AM 32ºC
Environmental Incident 0 0 1
Average Manpower 48 54 2
HOURS WITHOUT LTI 3360 28633 3
LOAST DAYS 0 0 4
EMVINRONMENTAL INCIDENT 0 0 5

Planned & Scheduled By: Prepared By: Verified & Checked By: Approved By:

Engr. ARCANGEL P. GUARIN, JR. Engr. NOE "JOJO" T. DEJUCOS, JR. Engr. LI RONGPING Engr. ERWIN JESSIE P. PELAEZ
Planning & Scheduling Engineer Construction Superintendent Construction Manager Project Manager