Client MEP Civil Consultant Main Contractor Subcontractor

Consultant

PAL DANAT Abu Dhabi District


Cooling Plant Project

METHOD STATEMENT (MS)


Submittal No. : ARA-DC-MS-ELE-0031
Attention to : Mr. Varghese Viji Abraham
Revision : 00 Date: 01-02-2022
Resident Engineer
Number of Copies :
WE ARE SENDING HEREWITH: the following to be mentioned: (this is applicable for Method Statement Submittal)

Architectural Structural Mechanical  Electrical Control

Landscape Infrastructural Project Documents Prequalification Others

Issued for:
For For
 Approval Information
For Review For Action For Others

List of Enclosure/s (Tick the Related Box):

 Document Reference  General  Equipment  Testing & Reporting  Scope of Works

 Plant and Equipment Permits to work  Safety Quality Material

 Resources  Protection & Arrangements Emergency Arrangements Operatives Others

Description : Site Acceptance Test of MV Cables

Remarks :

FOR: (Subcontractor) FOR: (Main Contractor)

Faisal Nader Touma 01-02-2022


Project Manager Project Manager Date

Client / Consultant Comments:

1.Please refer attached excel sheet for comments.

Client / Consultant Status

(A) No Objection x (B) No Objection with Comments (C) Revise and Resubmit

(D) Rejected (E) Received for Information

Reviews By: Muhammad Atif 07-02-2022

Signature:

Distribution:
PAL DANAT Abu Dhabi
District Cooling Plant Project

Site Acceptance Test of


MV Cables
(ARA-DC-MS-ELE-0031 )

DISTRICT COOLING PLANT

Issued Reviewed Approved Date Stage Revision


GEM Y.Q. N.T. 01-02-2022 For Approval 00
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

CONTENT

1. Introduction

2. Scope of Work

3. Roles & Responsibilities

4. Emergency Contact Details

5. Materials, Tools & Equipment

6. Training Requirements

7. Sequence and Method

8. Competency Certificate

9. Test Report

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 2 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

1. Introduction
Pal Danat District Cooling Plant under PAL Danat Cooling LLC is located in Abu Dhabi,
United Arab Emirates

2. Scope of Works

This method statement outlines the step involved in installation of Site Acceptance Test of
MV Cables

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 3 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

3. Roles & Responsibilities

3.1 Project Manager


Project manager shall be responsible overall to complete all MEP works as per
specifications, budget, time, & quality.

3.2 Project Engineer


 Has full authority and overall responsibility to manage, supervise and control the
works.
 Coordinate with Supervisor for the execution of scope of works.
 Review the work progress is in line with the project requirement
 Make necessary arrangement and changes to evaluate the impact of schedule on the
project.

3.3 Supervisor
 Coordinate and explain the work to carry out to the foreman.
 Ensure the compliance of work as per standard project requirement
 Update related work progress and report to Project Engineer.

3.4 Foreman
 Shall be responsible for but not limited to the following activities
 To guide and control the operatives
 To ensure work is done as per approved drawings
 To report the requirement and update the work progress to Supervisor.

3.5 HSE Officer


 Daily Observation on site
 Safety Induction/TBT for the new employees at site
 Maintaining all the HSE documents needed at site.
 Risk assessment briefing to the operatives
 Maintaining HSE Audit for HSE development

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 4 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

4. Emergency Contact Details

The following staff from both Araner and Genfocus will be on site during the execution of
the works and will be responsible for managing the works:

Name Designation Company Contact Numbers

Yusuf Qawas Construction Manager ARANER 0521050249

Minhaj Ahmed HSE Officer ARANER 0524931365


Benny David Site Engineer GENFOCUS 0565465821
Subhash Site Supervisor GENFOCUS 0565465822

Shibin Babu HSE Officer GENFOCUS 0561450759

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 5 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

5. Materials, Tools and Equipment

5.1 MATERIALS

General Items  Insulation tester, Digital multimeter, HV Test Kit


Hazardous Substances  Nil
Note: Material safety data sheets for any hazardous substances must be attached to the
method statement in the appendices.

5.2 TOOLS & EQUIPMENT


Electrical
Hand Tools Working at Height Lifting Equipment
Equipment
Extension
Hammer ☐
Leads
☒ Ladder ☒ Corner Movers ☐
Screw Driver ☒ Power Drills ☐ Scaffolding ☒ Pallet Trolley ☐
Knives ☒ Lighting ☒ Podium Steps ☒ Manual Forklift ☐
Cutters ☐ Testing Equip.. ☒ Scissor Lift ☐ Server Lifter ☐
Other (specify) Other (specify) Other (specify) ☐ Other (specify)
☐ ☐ ☐

Note: All equipment must be inspected for serviceability and cleanliness prior to works.

5.3 PERSONAL PROTECTIVE EQUIPMENT

Clothing Overalls ☒ Work Trousers ☐ Safety Shoes ☒


Electrical
Hand Cotton Gloves ☒ Rubber Gloves ☒ ☒
Gloves
Eye / Face Safety Glasses ☒ Safety Goggles ☐ Face Shield ☒

Respiratory Dust Mask ☒ Respirator ☐ Full Face Mask ☐

Ear Ear Plugs ☐ Ear Defenders Other


☐ (Specify ☐
Fall Protection Harness ☒ Full Body Below)

Face Mask, Helmets, Safety Jackets

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 6 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

6. Training Requirements

No Type of Training (Specify)

1 PPE

2 Manual Handling
3 Safe use of hand tools

4 Safe use of Power tools


5 COVID-19 Precautions

6 Electrical Safety
7 Working at Height

8 ADDC Competency Certificate

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 7 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

7. Sequence and Method


The works will be carried out in the following sequences; from offloading the materials at site
to final fix including safety precautions taken during the sequence of works:

1.0 GENERAL

1. RAMS must be approved by main contractor.

2. Daily TBT must conduct prior to starting the work.

3. Supervisor to ensure all operatives have received a ARANER site basic induction

4. Supervisor to ensure all operatives have adequate PPE for the job including Full body harness.

5. Supervisor to ensure that competent workers are involved for scaffolding erection,
dismantling and inspection.

6. Supervisor to ensure all operators having competent certificate.

7. Ensure all operatives carry approved EMPLOYEE IDENTIFICATION CARD and display in Gate.

8. Supervisor to ensure adequate tools are provided and should be in good Condition

9. Supervisor to ensure that proper barricade and warning signs are provided before starting any
activity. Proper Barricading to be provided for any Lifting operation and material unloading
area

10. Supervisor to ensure proper working platforms such as ladders and scaffoldings are being
used and make sure, that all the working platforms are having permit to work.

11. Supervisor to ensure that competent workers are involved for scaffolding erection,
dismantling and inspection.

12. Ensuring that unloading of materials is undertaken in designated area.

13. Make sure that the lifting equipment is adequately rated for the specified weight (shown on
the rated plate).

14. Make sure all operatives have taken COVID Vaccination and valid PCR Report with Negative
Result.

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 8 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

15. All employee will strictly comply Covid Related control measure and safety officer will monitor

16. Supervisor and safety officer will ensure that during summer break time nobody will move or
work direct sunlight between 12 to 3 pm.

17. During summer time safety officer will monitor TWL.

18. Ensure that sufficient summer welfare facility in work place with First Aid Arrangement.

2. OFF-LOADING AND HANDLING OF MATERIALS

1. Materials will be offloaded from vehicle by manually.

2. Store in charge / Supervisor to ensure that off material load not exceed 20kg / Person.

3. Supervisor to be ensured the materials are as per approved submittals.

4. Check that the shop drawings and material submittals are approved and verify that the
materials are as per the approved by the Engineer.

5. Check that accessories are delivered pre-packed in standard quantities

6. Inspect the accessories stored on a reasonably flat surface free from large stones or sharp
projections.

7. Extra care should be exercised in handling wiring accessories to avoid damages.

8. Material inspection request to be submitted for Approval.

9. Check work area is clean and safe to proceed for the installation works.

3. Testing Of MV KV cables

3.1 Testing Of 11KV cables

3.1.1 Procedure

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 9 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

1. Ensure the correct identification of Cable. The cable is disconnected at both ends. The cable
ends are maintained adequate clearances between conductor and metallic bodies. All ends
shall be provided with separation and temporary insulated.

2. Barricade the area with proper signage and a stand-by person shall be allotted other endwith
proper communication facility.

3.1.2 Continuity and Phasing Check

1. Check the cable phase identification and continuity by earthing each core individually in farend
and check with the multi meter in the test end side and ensure the phases are matching with
panels terminals.

2. Each core of the cable shall be checked for correct phase marking and recorded in the test
report sheet.

3.1.3 Insulation Resistance Check (Before VLF Test)

1. Apply 5 kV DC Voltage using a insulation resistance megger, for a duration of one minute in
one phase (other 2 phases will be shorted and earthed) and readings are to be taken and
recorded. Insulation Resistance acceptance criteria is 1 GΩ.

2. Discharge the Cable using Earth discharge stick wearing HV Rubber gloves

3. Repeat the same test as above for other two phases.

3.1.4 HV (VLF) Test

1. Equipment HV leads are to be connected to cable phases by crocodile clips. Earthing shall be
connected to the cable armour
2. Apply voltage and increase gradually to RMS value of 13.5 kV at a frequency range of 0.1
Hz for duration of 30 minutes on each phase with other phases earthed and leakage current
should be noted and the cable HV withstand is checked, the kit trips automatically if the
leakage current 5mA.
3. Discharge the phase after applying HV Test and repeat the test in other two phases. All values
shall be recorded.

3.1.5 Insulation Resistance check (After VLF Test)

1. Apply 5 kV DC Voltage for a duration of one minute in one phase (other 2 phases will be
earthed) and readings are to be taken and recorded. Insulation Resistance acceptance criteria
is 1 GΩ

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 10 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

2. Discharge the Cable using Earth discharge stick wearing HV Rubber gloves

3. Repeat the same test as above for other two phases.

4. On Satisfactory completion of test and approvals all cable shall be terminated to respective
terminal. All terminal bolts shall be tightened with adequate torque requirement

5. Proper housekeeping shall be done and all covers shall be closed. Barricading and signage
shall be removed and closeout all permits.

6. Feeder will be energized and inform to ADDC.

3.2 Testing Of 3.3 KV

3.2.1 Procedure

1. Ensure the correct identification of Cable. The cable is disconnected at both ends. The cable
endsare maintained adequate clearances between conductor and metallic bodies. All ends
shall be provided with separation and temporary insulated.
2. Barricade the area with proper signage and a stand-by person shall be allotted other end with
proper communication facility.

3.2.2 Continuity and Phasing Check

1. Check the cable phase identification and continuity by earthing each core individually in far
endand check with the multi meter in the test end side and ensure the phases are matching
with panels terminals.
2. Each core of the cable shall be checked for correct phase marking and recorded in the test
report sheet.

3.2.3 Insulation Resistance check (Before VLF Test)

1. Apply 5 kV DC Voltage using a insulation resistance megger, for a duration of one minute in
one phase (other 2 phases will be shorted and earthed) and readings are tobe taken and
recorded. Insulation Resistance acceptance criteria is 1 GΩ

2. Discharge the Cable using Earth discharge stick wearing HV Rubber gloves

3. Repeat the same test as above for other two phases.

3.2.4 HV (VLF) Test

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 11 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

1. Equipment HV leads are to be connected to cable phases by crocodile clips. Earthing shall be
connected to the cable armour
2. Apply voltage and increase gradually to RMS value of 4.01 kV at a frequency range of 0.1
Hz for duration of 30 minutes on each phase with other phases earthed and leakage current
should be noted and the cable HV withstand is checked, the kit trips automatically if the
leakage current is 5mA
3. Discharge the phase after applying HV Test and repeat the test in other two phases. All values
shall be recorded.

3.2.5 Insulation Resistance check (After VLF Test)

1. Apply 5 kV DC Voltage for a duration of one minute in one phase (other 2 phases will be
earthed) and readings are to be taken and recorded. Insulation Resistance acceptance criteria
is 1 GΩ

2. Discharge the Cable using Earth discharge stick wearing HV Rubber gloves

3. Repeat the same test as above for other two phases.

4. On Satisfactory completion of test and approvals all cable shall be terminated to respective
terminal. All terminal bolts shall be tightened with adequate torque requirement

5. Proper housekeeping shall be done and all covers shall be closed. Barricading and signage
shall be removed and closeout all permits.

6. Feeder will be energized and inform to ADDC.

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 12 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

8. Competency Certificate

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 13 / 14 Date: 31/01/2022
Approved by: N.T.
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

Issued by : GEM Pag 12 / 14 Rev : 00


Reviewed by: PE
Date: 28/01/2022
Approved by: PM
Title P031 – Site Acceptance Test
of MV Cables

Project PAL DANAT Abu Dhabi


District Cooling Plant

9. Test Certificate

Issued by: GEM Rev. 0


Reviewed by: Y.Q. Pag 14 / 14 Date: 31/01/2022
Approved by: N.T.
PROJECT: PAL DANAT ABU DHABI DISTRICT COOLING PLANT

Client PAL DANAT COOLING Page 1 of 1


Main Contractor ARANER Date
Testing Company Equipment 11KV MV CABLE
Location Substation

VLF TEST REPORT FOR 11kV CABLE


1.CABLE DETAILS:

1 Cable Manufacturer
2 Cable type
3 Cable From
4 Cable To
5 Approximate cable length
6 Cable Tag

2.PHASING CHECK:
R phase Y phase B phase

3.INSULATION RESISTANCE TEST: (IR acceptance criteria= 1 GΩ)


Insulation Resistance Value
Ref. Applied Voltage Duration
Before HV test After HV test
R – (Y+B+E)
Y – (B+R+E) 5000 V DC 60 sec
B – (R+Y+E)

4.HV TEST

Applied Leakage Current (µA)


Ref. Voltage Duration frequency
(rms) 5min 10min 20min 30min
R-(Y+B+E)
Y-(B+R+E) 13.5kV 30min 0.1Hz
B-(R+Y+E)

5.EQUIPMENT DETAILS
SL.NO INSTRUMENT NAME MAKE/MODEL SERIAL NO CALIBRATION VALID
1 IR Tester Megger / MIT515
2 HV Test Kit HV Diagnostics / HVA60
3 Digital Multi Meter Fluke / 87V

Testing Contractor Main Contractor Approved by


NAME
SIGNATURE
DATE
COMPANY GENFOCUS
PROJECT: PAL DANAT ABU DHABI DISTRICT COOLING PLANT

Client PAL DANAT COOLING Page 1of 1


Main Contractor ARANER Date
Testing Company Equipment 3.3 KV MV CABLE
Location Substation

VLF TEST REPORT FOR 3.3kV CABLE


1.CABLE DETAILS:

1 Cable Manufacturer
2 Cable type
3 Cable From
4 Cable To
5 Approximate cable length
6 Cable Tag

2.PHASING CHECK:
R phase Y phase B phase

3.INSULATION RESISTANCE TEST: (IR acceptance criteria= 1 GΩ)


Insulation Resistance Value
Ref. Applied Voltage Duration
Before HV test After HV test
R – (Y+B+E)
Y – (B+R+E) 2500 V DC 60 sec
B – (R+Y+E)

4.HV TEST

Applied Leakage Current (µA)


Ref. Voltage Duration frequency
(rms) 5min 10min 20min 30min
R-(Y+B+E)
Y-(B+R+E) 4.01kV 30min 0.1Hz
B-(R+Y+E)
5.EQUIPMENT DETAILS
SL.NO INSTRUMENT NAME MAKE/MODEL SERIAL NO CALIBRATION VALID
1 IR Tester Megger / MIT515
2 HV Test Kit HV Diagnostics / HVA60
3 Digital Multi Meter Fluke / 87V

Testing Contractor Main Contractor Approved by


NAME
SIGNATURE
DATE
COMPANY GENFOCUS