Consultant
Issued for:
For For
Approval Information
For Review For Action For Others
Remarks :
(A) No Objection x (B) No Objection with Comments (C) Revise and Resubmit
Signature:
Distribution:
PAL DANAT Abu Dhabi
District Cooling Plant Project
CONTENT
1. Introduction
2. Scope of Work
6. Training Requirements
8. Competency Certificate
9. Test Report
1. Introduction
Pal Danat District Cooling Plant under PAL Danat Cooling LLC is located in Abu Dhabi,
United Arab Emirates
2. Scope of Works
This method statement outlines the step involved in installation of Site Acceptance Test of
MV Cables
3.3 Supervisor
Coordinate and explain the work to carry out to the foreman.
Ensure the compliance of work as per standard project requirement
Update related work progress and report to Project Engineer.
3.4 Foreman
Shall be responsible for but not limited to the following activities
To guide and control the operatives
To ensure work is done as per approved drawings
To report the requirement and update the work progress to Supervisor.
The following staff from both Araner and Genfocus will be on site during the execution of
the works and will be responsible for managing the works:
5.1 MATERIALS
6. Training Requirements
1 PPE
2 Manual Handling
3 Safe use of hand tools
6 Electrical Safety
7 Working at Height
1.0 GENERAL
3. Supervisor to ensure all operatives have received a ARANER site basic induction
4. Supervisor to ensure all operatives have adequate PPE for the job including Full body harness.
5. Supervisor to ensure that competent workers are involved for scaffolding erection,
dismantling and inspection.
7. Ensure all operatives carry approved EMPLOYEE IDENTIFICATION CARD and display in Gate.
8. Supervisor to ensure adequate tools are provided and should be in good Condition
9. Supervisor to ensure that proper barricade and warning signs are provided before starting any
activity. Proper Barricading to be provided for any Lifting operation and material unloading
area
10. Supervisor to ensure proper working platforms such as ladders and scaffoldings are being
used and make sure, that all the working platforms are having permit to work.
11. Supervisor to ensure that competent workers are involved for scaffolding erection,
dismantling and inspection.
13. Make sure that the lifting equipment is adequately rated for the specified weight (shown on
the rated plate).
14. Make sure all operatives have taken COVID Vaccination and valid PCR Report with Negative
Result.
15. All employee will strictly comply Covid Related control measure and safety officer will monitor
16. Supervisor and safety officer will ensure that during summer break time nobody will move or
work direct sunlight between 12 to 3 pm.
18. Ensure that sufficient summer welfare facility in work place with First Aid Arrangement.
2. Store in charge / Supervisor to ensure that off material load not exceed 20kg / Person.
4. Check that the shop drawings and material submittals are approved and verify that the
materials are as per the approved by the Engineer.
6. Inspect the accessories stored on a reasonably flat surface free from large stones or sharp
projections.
9. Check work area is clean and safe to proceed for the installation works.
3. Testing Of MV KV cables
3.1.1 Procedure
1. Ensure the correct identification of Cable. The cable is disconnected at both ends. The cable
ends are maintained adequate clearances between conductor and metallic bodies. All ends
shall be provided with separation and temporary insulated.
2. Barricade the area with proper signage and a stand-by person shall be allotted other endwith
proper communication facility.
1. Check the cable phase identification and continuity by earthing each core individually in farend
and check with the multi meter in the test end side and ensure the phases are matching with
panels terminals.
2. Each core of the cable shall be checked for correct phase marking and recorded in the test
report sheet.
1. Apply 5 kV DC Voltage using a insulation resistance megger, for a duration of one minute in
one phase (other 2 phases will be shorted and earthed) and readings are to be taken and
recorded. Insulation Resistance acceptance criteria is 1 GΩ.
2. Discharge the Cable using Earth discharge stick wearing HV Rubber gloves
1. Equipment HV leads are to be connected to cable phases by crocodile clips. Earthing shall be
connected to the cable armour
2. Apply voltage and increase gradually to RMS value of 13.5 kV at a frequency range of 0.1
Hz for duration of 30 minutes on each phase with other phases earthed and leakage current
should be noted and the cable HV withstand is checked, the kit trips automatically if the
leakage current 5mA.
3. Discharge the phase after applying HV Test and repeat the test in other two phases. All values
shall be recorded.
1. Apply 5 kV DC Voltage for a duration of one minute in one phase (other 2 phases will be
earthed) and readings are to be taken and recorded. Insulation Resistance acceptance criteria
is 1 GΩ
2. Discharge the Cable using Earth discharge stick wearing HV Rubber gloves
4. On Satisfactory completion of test and approvals all cable shall be terminated to respective
terminal. All terminal bolts shall be tightened with adequate torque requirement
5. Proper housekeeping shall be done and all covers shall be closed. Barricading and signage
shall be removed and closeout all permits.
3.2.1 Procedure
1. Ensure the correct identification of Cable. The cable is disconnected at both ends. The cable
endsare maintained adequate clearances between conductor and metallic bodies. All ends
shall be provided with separation and temporary insulated.
2. Barricade the area with proper signage and a stand-by person shall be allotted other end with
proper communication facility.
1. Check the cable phase identification and continuity by earthing each core individually in far
endand check with the multi meter in the test end side and ensure the phases are matching
with panels terminals.
2. Each core of the cable shall be checked for correct phase marking and recorded in the test
report sheet.
1. Apply 5 kV DC Voltage using a insulation resistance megger, for a duration of one minute in
one phase (other 2 phases will be shorted and earthed) and readings are tobe taken and
recorded. Insulation Resistance acceptance criteria is 1 GΩ
2. Discharge the Cable using Earth discharge stick wearing HV Rubber gloves
1. Equipment HV leads are to be connected to cable phases by crocodile clips. Earthing shall be
connected to the cable armour
2. Apply voltage and increase gradually to RMS value of 4.01 kV at a frequency range of 0.1
Hz for duration of 30 minutes on each phase with other phases earthed and leakage current
should be noted and the cable HV withstand is checked, the kit trips automatically if the
leakage current is 5mA
3. Discharge the phase after applying HV Test and repeat the test in other two phases. All values
shall be recorded.
1. Apply 5 kV DC Voltage for a duration of one minute in one phase (other 2 phases will be
earthed) and readings are to be taken and recorded. Insulation Resistance acceptance criteria
is 1 GΩ
2. Discharge the Cable using Earth discharge stick wearing HV Rubber gloves
4. On Satisfactory completion of test and approvals all cable shall be terminated to respective
terminal. All terminal bolts shall be tightened with adequate torque requirement
5. Proper housekeeping shall be done and all covers shall be closed. Barricading and signage
shall be removed and closeout all permits.
8. Competency Certificate
9. Test Certificate
1 Cable Manufacturer
2 Cable type
3 Cable From
4 Cable To
5 Approximate cable length
6 Cable Tag
2.PHASING CHECK:
R phase Y phase B phase
4.HV TEST
5.EQUIPMENT DETAILS
SL.NO INSTRUMENT NAME MAKE/MODEL SERIAL NO CALIBRATION VALID
1 IR Tester Megger / MIT515
2 HV Test Kit HV Diagnostics / HVA60
3 Digital Multi Meter Fluke / 87V
1 Cable Manufacturer
2 Cable type
3 Cable From
4 Cable To
5 Approximate cable length
6 Cable Tag
2.PHASING CHECK:
R phase Y phase B phase
4.HV TEST