Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Contents
Section A Register of Revisions
Section B Scope of Works to be undertaken
Section C Location of the Project
Section D Location of the Works to be Undertaken with the Project
Section E Site Access/Egress and Access to the Work Zone
Section F Emergency Contacts Details and Procedures
Section G McLaren Site Specific HSE Safety Induction
Section H Welfare facilities
Section I Personal Protective Equipment
Section J Plant/Equipment and tools to be Used
Section K Materials To be used
Section L Temporary Works
Section M Inspection and Test Regime
Section N Communication/Toolbox Talks/Training Requirements
Section O Works Permits
Section P Environmental and Waste Management
Section Q Programme for the Works
Section R Housekeeping and Storage
Section S Working at Height
Section T Occupational Health
Section U Sequence of Works/Activities
Appendices
Appendix A Site Logistic Plans and Other Design Information Relative to the Works
Appendix B Crisis/Emergency Plan
Appendix C COSHH Assessments and Material Data Sheets
Appendix D Risk Assessments
Appendix E Technical Information
Appendix F Inspection and Test Plans
Appendix G Third Party competency/certifications
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Rev. No Date Reason for Amendment Amended By Signature Has this amendment been
(Name) briefed to the operatives
involved and have the
operatives signed the register?
This method statement has been prepared in conjunction with the following documents.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
The work Describes Integration of FACP, PAVA & ELV System at Al Karama School, Phase 2, Abu Dhabi
The following Critical Hazards have been identified during the preparation of the scope of works, please refer to the Risk
Assessments within Appendix D.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Existing Services
As per current information, there is existing irrigation network passing outside the construction work
area.
Underground electrical cables for existing lighting poles within the plot have been removed prior to
commencing works at the area. A full survey has been undertaken to confirm this including an
underground service scan and trial trenches hand excavated in various locations around the project to
locate any services running into, or close to the plot.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
A permit to dig must be obtained from McLaren prior to any excavations commencing. =
Section D- Location of the Works to be Undertaken within the Project
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
In case of an Emergency/fire Alarm, all operatives, Staff and Visitors are required to report to the Assembly Point,
which is indicated on the site logistics drawing, as indicated by the symbol below. A roll call will be taken, and
registers checked to ensure that everyone is accounted for. No one will be allowed to leave the assembly point
until the Emergency Response Controller confirms that it is safe to do so.
Assembly Point
Please refer to the attached Crisis/Emergency Plan, (Appendix B) which is to be implemented where the need
arises.
The Qualified First Aiders for the Project are listed below, and the first Aid Boxes will be available within the
First Aid Room and in the Main Office Reception.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
On completion of the HSE induction, those involved in this activity will be briefed on the contents of the RAMS
by their respective Site Engineer or Supervisor. They will then be required a sign a RAMS Briefing Register (SAF019
UAE) confirming that they have been briefed and that they fully understand the RAMS and what is expected from
them during the execution of the works.
Any operative who will be operating any plant or equipment will be required to produce a copy of their Dubai/
Abu Dhabi Municipality/ENAS/EIAC approved competency certificate/card and proof of health to enable McLaren
to issue them with the Plant Operators Authorisation (SAF023 UAE).
Please ensure that any specific precautions for PPE as identified within MSDS/COSHH assessment or any
specific requirements by supplier/manufacturer are to be complied and adhered to.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
*Note: All relevant competency certificates to be submitted to HSE Manager/Eng./Advisor prior to start of any
activity.
*Note: All temporary Works require a design completed by a competent person and must be
approved by McLaren’s Temporary Works Coordinator (TWC)
**Note: All Temporary Works require a Temporary Works Permit to Load/ Strike
Section M- Inspection and Test Regime
All inspections and tests must be conducted in accordance with the work procedure approved with the
Hold and Inspection points signed off on the approved inspection and Test Plan and Check sheets.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
During the Preparation of this RAMS the following training for the staff and operatives has been identified;
Item Description of Training Has the Training been If not, when will be
completed? (Yes/No) completed (Date)
1 Work at Height Yes
2 Working near live service Yes
3 Manual Handling Yes
4 Scaffolding inspection and scaffolding erection Yes
5 Working with Power Tools Yes
*Note: All relevant certificates will be submitted prior to works commencing or during induction. Where the
training has not been carried out, it must do so prior to the works/activities commencing.
Item Description of the Work Permit Permit Issued By Tick only applicable
1 Permit to Enter Confined Space McLaren
2 Permit for Lifting Operations. McLaren
3 Permit to Dig McLaren
4 Permit to work Hot cutting or Welding McLaren
5 Permit to Work in Ceiling Void McLaren
6 Permit for Roof Access McLaren
7 Permit to Work with Ladders, steps/scaffold McLaren
8 Permit to Work at Height McLaren
9 Permit to Work – Electrical above 110V McLaren
10 Permit to Work with COSHH Items McLaren
11 Permit to Work at External Face of The Building McLaren
12 Permit for Removal of Existing Fall Protections McLaren
13 Permit for Pressure Testing McLaren
14 Permit for near Live service McLaren
Any other permits if required to be added
1 General Waste
2. Concrete Waste
3. Wooden Waste
4. Food Waste
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
5. Hazardous Waste
6. Paper / Cardboard Waste
Due to the nature of the works and the current site conditions, water shall be sprayed onto dirt/sand roads so
as to minimize dust pollution.
Where any plant is used, drip trays shall be placed underneath to catch any spilled oils or fuels. Oils and fuels will
be managed in accordance with the MSDS and the site Waste Management Plan.
All hazardous liquids must store in suitable, labelled containers with secondary containment to prevent ground
and water contamination.
Emergency spills kits must be available where any hazardous material is used.
Section Q- Programme for the Works.
6 Months
Combustible materials will be carefully managed and monitored in order to reduce the risk of fire.
Item Description Preventative Measures, (see also within the Risk Assessments)
1 Safety Critical Roles Anyone identified as safety critical (i.e. operators, riggers,
scaffolders, banksmen etc.) must have a medical check-up before
starting work
2 Bad Back/sprain due to A manual handing assessment will be carried out for all activities and
improper Manual handling all Operatives will receive Manual Handling training
3 Hand/Arm Vibration Exposure Action Values (EAVs) will be calculated for all vibration
activities. Where required, job rotation will be put in place and
recorded
4 Construction dust Roads shall be watered to minimise dust and housekeeping to be
carried out regularly.
RPE shall be provided for those at risk from hazardous dust
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
5 Noise Noise values will be monitored. Where required, job rotation will be
put in place and recorded. Where it is not possible to control noise,
PPE will be provided
6 Sun & Heat Sun creams will be provided for those that require it.
Drinking water and electrolyte additives will be provided.
Clothing shall cover legs and arms, gloves will be worn.
Summer Working Plans
7 Skin PPE shall provide as required by MSDS
Section U- Sequence of Works/Activities for Integration of FACP, PAVA & ELV System
RAMS to be briefed to all the operatives involved in the work
STARRT card to be prepared by assessing the area of work prior starting the work.
Supervisor to ensure all operatives have received a McLaren site basic induction
Supervisor to ensure all operatives have adequate PPE for the job including Full body harness.
Supervisor to ensure all operators having Competent certificate.
Supervisor to ensure that the site is clean and ready to start the work
Supervisor to ensure adequate tools are provided and should be visibly clean and tidy. Advise Site manager if
more tools are needed.
Supervisor to ensure that all hygienic PPE has been issued & being worn correctly.
Supervisor to ensure that proper barricade and warning signs are provided before starting any activity.
Supervisor to ensure proper working platforms such as ladders are being used and make sure that having
ladder permit on work
Transportation to site will be as per site requirement. Timing to be agreed with McLaren
Ensuring that unloading of materials is undertaken in designated area.
When offloading the materials precaution to be taken to avoid damages.
Ensure that no power is applied to the fire alarm panel and that all wiring is properly
connected.
Use the green grounding lug in the control panel for all measurements to ground. Each
circuit must test free of all grounds and extraneous voltages.
Use the volt/ohm meter to check each circuit type.
At the control panel, locate wires from each initiating device or indicating appliance
circuit.
Check each circuit for extraneous voltage by setting the volt / ohm meter to 300VAC.
The meter must read 0 volts.
Set the volt / Ohm meter to 60 VDC. The measurements must read 0 volts.
Set the volt / ohm meter to OHMS X 10 and check the circuits using resistance measurements
in following table. Locate and correct any abnormal conditions at this time.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Check all other system wiring to verify that each circuit is free of grounds and extraneous
voltages
Interfacing Procedure
Before switch off the panels Concern team will inform authorities and get approval for the
switch off procedure.
Switch off both the panels (New in Phase-2 and Existing in Phase-1).
Install the network cards in both the panels.
Terminate the network cables in both the panels.
Switch ON the panels.
Download the network program in both the panels.
Commissioning Procedure
Type of initiating devices used in this project and their test methods are as follows:
Smoke detector- Apply SOLO Aerosol in the smoke detector chamber until red LED glows
steady
Heat detector – Switch on and place the heat generator covering the detector until the red
LED glows steady.
Manual Call Point – Open the MCP using Simplex key.
Sprinkler Flow switch – Open the Test drain valve until FACP receives FIRE signal. (Sprinkler
Supplier coordination required).
Generate Smoke using the smoke Generator and hold the generator to the smoke chamber
of the smoke sensor.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Once the smoke is sensed by the detector ensure that the Red LED on the base to lit steady.
Verify the programmed sequence of the Initiating, notification and control devices.
Once panel reset ensure that the RED LED is off.
Verify the audible and visual devices respond on activation of corresponding initiating
devices.
Visually check for the LCD Display, LED Status, microphone, wiring and Batteries in the
control Panel.
On the LED Display check for date & Time, normal state display, alarm state display, trouble
state display, Panel Buzzer, Key functions and LED Display.
Battery to be sized for required back-up and check the operation by disconnecting and
connecting the batteries. Check the status indication and charger operation.
Inspect the fire phone display and check for the communication & multiple calls and
response with off hook.
Audio operations to be checked as audio in alarm condition, pre-recorded messages and
check for the fire phone paging and manual paging.
Schedule operations, device response time, network operation, auxiliary outputs and alarm
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Function test of devices shall be carried out loop by loop (randomly) as follows
Verify all interfaces are functioning in case of activation of corresponding initiating devices.
Test shall be carried out in the sequence of loop by loop. It will be tested by activating any
detector or break glass in the loop and verify the following effects are taken place.
It will be tested by activating one device in the building Also, one Manual Call Point will be
operated in each floor.
History Log
After successful testing of entire system, a historical log shall be generated and printed
for review and comments for inspectors.
WALK TEST
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
The system has a Walk test feature which allows a single person to test the devices. Walk
test enable will show as a trouble warning in the system and will be cleared after
successful exit of walk test. Walk test events also will be recorded in Main FACP. System
will reset itself after every device test.
After the successful commissioning the results will be recorded on the testing and
commissioning sheets attached with the document.
PAVA
Switch off both the panels PAVA panels including amplifier and router (New in Phase-2 and
Existing in Phase-1).
Connect the router to LAN network through dedicated portals.
Assign the portal for router interface.
Switch ON the panels.
Testing and Programming of NVR for CCTV System in CCTV Room, Phase-1:
Install new CCTV server with VMS in CCTV room, Phase-1.
Define the camera text based on the location.
Setup the existing NVR & name/verify the camera labels.
Connect the camera to NVR & verify the picture of each camera.
Assign the provided IP address to the camera via NVR.
Install the Ethernet switch in the New IDT (Intermediate Distribution Terminal) and configure it as
per provided IP Scheme.
The CCTV Cameras are connected to the Ethernet Switch via CAT6 cabling. The CCTV cameras are
terminated and linked with fibre connectivity to the existing Rack in Al Karamah School Phase-1.
The system is programmed for the different types of cameras used in the system
All the cameras are named according to the location
All the NVR time zone shall be programmed
All the NVR IPs shall be programmed
All the camera frame rates shall be programmed
All the sequencer out puts shall be programmed
Check all camera picture in monitors
Check all the live video function
Check all recording & play back function
Check all the NVR function through remote software
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Identify exact terminating locations in advance, keeping in mind that the cable must be pulled all
the way to where it will be terminated, not just into the room. This obvious though often
overlooked step can lead to costly mistakes if forgotten.
Carefully measure the cable's path before the conduit pull to avoid the need for splices. Not only
do splices cost time and money, but they also cause loss in both signal quality and strength. In
fact, most designers specify point-to-point or device-to-device runs to avoid needless signal loss
from splices.
Pull the pull tape into the conduit, or along the cable path, for an initial measurement, and add to
that extra length for splices, terminations, and future access coils, if specified. The amount of
additional cable needed for splicing depends on site conditions, splicing method used, and long-
range plans for cable usage.
Choose crews based on the length of the pull, total degrees of bend, tail loading (force required to
pull cable off feed reel). In most cases, two- or three-person crews are ideal. That way, one person
pays the cable off the reel and into the duct, while one or two others pull at the other end.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
A. Calibration Certificate
B. OTDR test in both direction @ 1310nm & 1550nm with OTDR.
A. Maximum loss Requirement: Optical Cable Loss < or = 0.4000 dB/km [1310nm]
B. Maximum loss Requirement: Optical Cable Loss < or = 0.400 dB/km [1550nm]
Install new BMS Workstation in BMS room, Phase-1 with new software.
This Section deals with integration of each Automation servers/ DDC Panel at the Head End/BMS
server/Management Level. Sample graphics shall be submitted separately for approval before commencement
of works in this section. Works shall commence once approval on sample graphics are attained.
Import architectural layout drawings of the building into the graphics software showing all
equipment’s connected to BMS.
Make static symbols of the various plants equipment’s like Air handling unit types, Fan types,
Chilled water pumps etc.
Insert dynamic symbols in the plant layout to display various plant data.
Project database shall be configured to be accessible through the workstation.
Establish communication with each automation server/ DDC panel.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
APPENDIX A
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
APPENDIX B
Al Karamah School, Phase 2
Abu Dhabi, UAE
CRISIS PLAN
Upon an incident, being discovered the first member of McLaren’s staff or the site operative
1.
discovering the incident shall inform the Project Manager and HSE department by Project
Emergency no- 056 898 7960
Both the Safety Officer and the first Aider are to attend the scene with their mobile. The project
2.
Manager or site receptionist waits in office ready to telephone relevant emergency services.
Both the Safety Officer and the first Aider are to assess the situation and put in place the relevant
3.
systems to end/deal with the emergency.
Both the Safety Officer and the first Aider are to ensure all trades are gathered at the assembly
4.
point and liaise with supervisor to account for all operatives - no person should leave site.
Either the Safety Officer or the first Aider phones the project Manager or site receptionist and
5.
informs him/her of which emergency services are required.
Both the Safety Officer and the first Aider keep trades informed of the situation and releases trades
9.
to return to work or leave site only when emergency services or The Project Manager instruct that
it is safe to do so, and all names of witnesses are recorded.
The Project Manager or Construction Manager are to arrange for photographs of the scene to be
10.
taken, and if necessary the area to be cordoned.
A full investigation of the Incident is to be carried out, with a written report being submitted the
11.
SHEQ Director, as soon as practicably possible after the incident, including all witness statements,
photos of the scene, induction and method statement records, recommendation to prevent a re-
occurrence and what action has been taken since the incident taking place.
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
APPENDIX C
N/A
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
APPENDIX- D
RISK ASSESSMENT
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
Heat stroke/ stress/ 7. Reduce oily related food and soft drinks.
cramp 8. Sharing heavy work.
9. Ensure that the operative is fit to work under
direct sunlight
10. Use of buddy system to monitor colleague’s
health
11. Scheduled rest breaks to be provided
(Frequent breaks, minimum 10 mins every 2
hours.
12. Drink water every 30 minutes and Electrolytes
as per manufacturer recommendation and
timescales.
13. Schedule work to minimize exposure.
14. Newly mobilized workers shall be
acclimatized and never assigned heavy task or
direct exposure to hot environment.
15. Re-schedule hard work activities in coolest
part of day where possible. Ensure no worker
work alone in heat stress area.
16. Site supervisors shall perform job rotation to
the workers. Must aware on TWL (thermal
work limit) and its necessary precautions.
17. Adequate PPE and proper clothing during
when working under high temperature e. g.
lightweight, cotton and light colored).
18. Train supervisors to detect and manage
symptoms of heat stress among the
workforce.
0
1
5
6
7
8
9
0
1 Approved By: Name Vishnu Mohan Position _PM________ Signature _ ________ ___________
1. Executing Steps:
1.1. Planning
a) Construction and HSE team must ensure that hazard identification is complete.
b) Construction and HSE team must prioritize the hazard issues, which are of significant in nature. (It means that
risks have well established legal requirements, potentially high risks).
c) Construction and HSE team to prepare the risk assessment plan for the priorities identified hazards for these
potential high risks.
APPENDIX-E
TECHNICAL INFORMATION
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
APPENDIX-F
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00
APPENDIX-G
Title: Integration of fire alarm system, PAVA & ELV System Ref. No: M1492-MCL-MCL-MSS-90
Project: Al Karamah School, Phase 2 Rev. No: 00
Prepared By: Anu Baby Approved By: Vishnu Mohan Rev. Date: 00