Professional Documents
Culture Documents
Zone S9 (Phase 4)
9 March 2015
Submitted by:
Prepared for:
Aon Fire Protection Engineering (Aon FPE) has been retained by Jabal Omar Development Company to prepare Buildings within the JOD are composed of two major elements, which are podiums and towers. There are 17
this Fire Strategy Report for Zone S9 of the Jabal Omar Development (JOD). The involvement of Aon FPE is to podiums, and a total of 39 towers located above the podium levels. Various podiums cover the entire plot and
provide a fire and life safety review of the project to qualify the design to Civil Defense requirements and “embrace” the site topography to generate public spaces and private courtyards. The podiums accommodate
applicable codes. This report is intended to be reviewed for formal approval by Civil Defense. public facilities such as retail, mall, service, hotel lobbies and restaurants, as well as private prayer areas and
parking. Towers are mainly used as hotels, as well as for permanent and temporary residence. The podiums are
The goal of this report is strategic in nature. It presents a Fire Safety Strategy as design advice based on the designated as N1, N2, N3, N4, N5, N6A, N6B, N6C, S1, S2, S3/S4, S6, S7, S8, S9, S10&S11, for a total of 17
minimum prescriptive code requirements to stakeholders, the design development team, and Civil Defense. In podiums. The JOD also contains an Infrastructure Zone that consists of internal vehicle roads, pedestrian routes,
addition, this report is intended to act as a supporting document to assist Civil Defense in granting an approval for tunnels, utility and service buildings and technical galleries that serve the podiums/towers.
Phase 4, S9 of the Jabal Omar Development Project. Current design documents will need to be further developed
in order to comply with the applicable codes and Fire Safety Strategy. 1.3 General Description of Zone S9
The primary objective of the fire and life safety design is to provide an environment for occupants that is Zone S9 is an irregular shaped parcel of land. The north and east edge is a large curve, formed by Road B. On
reasonably safe from fire; both through protection and improvement of survivability of all occupants, whether they the opposite side of Road B is Zone S1, and beyond it is Al-Haram. The southern edge is a straight line formed
are or are not intimate with the initial development of a fire. An additional objective is to provide life safety during by Pedestrian Spine 4.The west edge is generally a straight line with an indentation in it formed at Roundabout #1.
emergencies, which can be mitigated using methods comparable to those used in case of fire. A third objective is That location is also one of the main entrances to the building. West of the Roundabout #1 is Road C, and north
to provide for reasonably safe crowd movement, and where required, reasonably safe non-emergency crowd of Roundabout #1 is Mussallah Piazza, so named because of the large and important Mussallah located on the
management. north side of the Piazza (on Zone N4), directly opposite of Zone S9. The easy access to the Mussallah provides
Zone S9 with a significant convenience. That proximity also impacts the general configuration of S9, as it is
Detailed design drawings, contractor submittals required to be approved by Civil Defense, and implementation will divided internally by an open air corridor that serves as a passage from Zone S10 to through Zone S9 and then to
be provided under separate contract. Once approved, this Fire Safety Report will be included in the reference Musallah Piazza. This occurs at the Commercial 2 Floor level of Zone S9, where an open-air volume of this
documents applicable to the development. Fire and life safety systems for the entire development will be passage divides the upper three floors of the podium of S9 (namely Commercial 2, 3, and 4).
coordinated, with the systems between all buildings (podiums and towers) being specified for compatibility,
particularly the fire command centers. In addition, the emergency plan (including evacuation and response) will
be required to be coordinated by the project stakeholders with Civil Defense. This will be developed under a
separate project contract.
The scope of the report is for Zone S9 contains 3 residential (hotel) high-rise towers (known as SR7A, SR7B, and
SR3) which are located above the five-level Zone S9 podium. In addition to the five levels above, grade, the
podium has three levels of basements. The hotel operator for S9 will be Sofitel.
It is important to note that the scope of this report is only for those times of the year when the activities at Jabal
Omar and Makkah do not include large numbers of people who are on pilgrimage. During such special times,
special provisions for crowd management will be necessary to prevent Zones S9 from becoming overcrowded to a
point that they have not been designed to accommodate. This includes consideration both of limiting the
maximum occupant loads within the building (particularly the retail areas); and of the gathering of people around
the perimeter of the building. In this later condition, consideration needs to be given to constantly maintaining the
immediate and unobstructed access of Civil Defense, fire services, and other emergency responders to the Zone
S9 building, including access to life safety systems (such as fire hydrants, Siamese connections, stairwells, fire
service access elevators, the fire command center, and fire pumps). Evaluation of such special conditions
requires participation of the various stakeholders in the project, and their cooperation with Civil Defense to
develop and implement the appropriate plans and procedures.
The building on Zone S9 consists of three hotel towers which are on top of an 8-level podium. Five of the podium As previously noted, five of the eight levels of the podium of Zone S9 are above grade, so the total height of the
levels are above grade and the other three levels are below grade. The uses within the towers are primarily hotel towers in Zone S9, including the podium levels is 27 floors for all three towers (not including the elevator machine
guestrooms, while the podium contains multiple uses on the various levels, including commercial (retail), both room penthouses). It should be noted that the uppermost basement is actually above the level of the ground, but
public and back-of-the-house areas of the hotel; parking, and storage. measurement of above grade in this example is taken from the top of the raised roadway system which complete
encircles the project. However the lowest level of Civil Defense access is from the Basement 1 Level, which is
The general uses of the podium, starting at the lowest level, are as follows: Basement Level 3 is the lowest level, approximately 5 meters below the raised roadway construction.
and contains a series of water storage tanks and their associated pump rooms; hotel storage areas, and
automobile parking facilities. Basement Level 2 includes the upper areas of the water tanks; hotel storage, and The lower grade around the base of the podium varies from a high of about +317.9, down to +316.7 along road C.
additional automobile parking. There is also a limited amount of Commercial shops, which line an underground Road B wraps around the building in a broad curve that could essentially be considered two sides of the building,
corridor that connects under Road B, to Zone S2. Basement Level 1 has back-of-the-house facilities including and descends in height from about +317 where it intersects with Road A, down to about +315.3 where it meets the
various technical rooms, the primary kitchen area of the hotel, loading dock and associated facilities; hotel right-of-way for Pedestrian Spine 4.
laundry, linen and uniforms areas; staff locker and changing rooms; and hotel storage areas.
The main roof of the podium is at +339.55, resulting in the podium height ranging from about 20 to 22 meters, with
The Ground Floor Level contains the hotel lobby, which has major entries from both the east and the south sides. an average height of approximately 21 meters, which is the “grade plane” as defined in NFPA 5000, and is used in
In addition to the hotel back-of-the-house office areas; there is a cafeteria, some multi-purpose meeting rooms, some (but not all) calculation requirements in NFPA. The top of the highest main roof of all three towers is at
some commercial facilities, and the fire command center also located on this level. A five-story atrium connects approximately elevation +423.8. Therefore, the height of towers above the podium is (423.8 – 339.55 =) 84.25
the Ground Floor Level up to the Commercial 4 Level, which is highest level of the podium. meters. The total height of the towers above the grade plane is approximately (84.25 + 21 =) 105.25 meters.
The Commercial 1 Floor is occupied primarily by dining facilities, mechanical equipment rooms, and a limited The height of towers from the lowest level of Civil Defense access is approximately (105 + 5 =) 110 meters. The
assortment of other uses, including some smaller commercial facilities, a fitness room, offices of the hotel elevation of the highest occupied floor of all the towers is the guestroom located on the 1st Upper Mechanical
manager, and offices of the guard manager. In addition to the central atrium, this level also has a two-story Floor, which is at +413.65. Therefore the height of the highest occupied floor above the top of the podium is (413
opening with a communicating stairs which opens to the lobby level below. - 316 =) 97 meters. Because of the height of the building, it is classified as a high-rise building per GCC and NFPA
requirements.
Commercial 2 Floor is the lowest level of a 3-story outdoor corridor (crest line) that essentially divides the top
three floors of the podium into two halves; and features escalators that provide vertical connection between those 1.3.3 Zone S9 Floor Plate Sizes
levels. This level is predominately commercial use consisting of numerous retail shops, with a limited amount of
mechanical rooms. The Commercial 3 Floor is also predominately similar commercial uses and a limited amount The typical floor plates for Towers SR3, SR7A and SR7B are essentially the same shape, size (approximately 865
of mechanical rooms; but also contains about 500 square meters of Administrative Offices. square meters), and orientation. Each tower is served by a common corridor with access to two exit stairs. There
are six passenger elevators, divided with three each in the two hoistways. In addition, each tower has a
Commercial 4 Floor is the uppermost level of the podium, and also consists primarily of Commercial spaces. It designated fire service access elevator which shares a designated fire service access elevator lobby with a
also includes a more than 200 square meters of space of high hazardous use that contains emergency generators service elevator. Refer to the fire strategy drawings for floor plan details.
and the fuel storage tanks required to operate them.
The tower floors are numbered in the drawings starting with the lowest tower floor numbered as the Lower
The Lower Technical Floor includes the roof of the two halves of the podium, and the first floors of the towers Technical Floor, and the next 19 floors (which are guestroom floors) are number Floors 1 to 19 inclusive. The top
above the podium. There are no public functions on the roof areas, and all three of the towers contain mechanical st nd
two floors are the 1 Upper Technical and the 2 Upper Technical Floors. That numbering system of the tower
equipment rooms at this level. The numbering system for all three towers identifies the guestroom floors by floors is maintained within this report.
st
number, with the 1st Floor being the first floor immediately above the Lower Technical Floor. The 1 Floor is
st
therefore the second level of the tower. From the main hotel entry level at the Ground Floor, the 1 Floor of each The gross building area of the podium levels of Zone S9 is approximately 7,000 square meters in area; but the
of the three towers is six levels above the Ground Floor (Ground Floor; plus 4 levels of Commercial; plus one net areas vary significantly. The net areas varying from about 4,960 to about 5,750 square meters for the five
Technical Floor = 6 levels). lower podium levels; and from about 3,515 to about 3,870 for the three upper podium levels (that are divided by
the external corridor (crest line). The gross building area of the podium levels for Zone S9 varies significantly by
Each of the three towers have a total of 22 levels above the podium roof, plus 2 levels of elevator machine room level. Sections through the podiums and the towers are indicated at the end of Section 1.4 of this report, for
penthouses on the very top of each tower. In addition to the Lower Technical Room Floor, and the 19 Floors of reference purposes.
Guestrooms, there is a First Upper Technical Room Floor (that contains approximately 210 square meters of
second level guestroom space that has the primary entrance on the 19th Floor), and a Second Upper Technical 1.3.4 Zone S9 Civil Defense Access
Room Floor. These technical floors contain both mechanical equipment and two-story water storage tanks. As
previously noted, there is a two-story elevator machine room penthouse on the very top of each of the three Civil Defense access to Zone S9 is provided on 70% of the building podium perimeter. This includes the entire
towers. Each of these is approximately 150 square meters in area. length adjacent to Road A and Road B. There is limited Civil Defense access along the side adjacent to
Pedestrian Spine 4.
As previously noted, the Lower Mechanical Floor is the first level above the podium that follows the “footprint” of
the towers, and not the footprint of the Podium.
The levels of this tower, from the top down, are as follows:
The Podium for Zone S9 is divided into two areas. There are five above grade levels which contain many public
functions, including those of the hotel as well as a significant amount of restaurants and shops. There are the
three below-grade levels which primarily contain hotel back-of-the-house areas; parking, and water storage tanks
for the entire building. The functions on each of the podium levels, from the top down, are as follows:
(Elevation +339.95) Lower Technical Floor: This is the main roof of podium (as well as being the Lower
Technical Floor at all three towers
Commercial-4 (+333.65) Commercial Floor 4: Divided by open air corridor (crest line), with mercantile (retail
shops) and mechanical on both sides. Emergency generators on the east side. Open
atrium from Ground Floor
Commercial-3 (+329.45) Commercial Floor 3: Divided by open air corridor (crest line), with mercantile (retail
shops) and mechanical on both sides. Open atrium from Ground Floor at east side of
the building.
Commercial-2 (+325.25) Commercial Floor 2: Divided by open air corridor (crest line), with mercantile (retail
shops) and mechanical on both sides. Open atrium from Ground Floor at east side of
the building.
Commercial-1 (+320.65) Commercial Floor 1: Assembly (restaurants). Open atrium from Ground Floor, and
two-story opening with communicating stair from Ground Floor below.
Ground Floor (+316.00) Main Entrance to hotel portion of the building, including the hotel lobby [Entry from
Road B, on the east side.] DIAGRAM 1.4: (Section B-B) Vertical Distribution Of Uses In Jabal Omar for Zone S9
Basement-1 (+311.00) Basement-1 Floor: Hotel back-of-the-house, including hotel kitchens, laundry, staff
lockers and changing areas, loading docks, storage, mechanical and transformers.
Basement-2 (+307.80) Basement-2 Floor: Parking, limited commercial area (adjacent to Pedestrian Spine 4),
mechanical, upper portion of two story water storage tanks, and pump rooms for water
systems.
Basement-1 (+304.60) Basement-1 Floor: Parking, storage areas, and the lower portion of two story water
storage tanks.
GCC Fire Code; including the Part-1 Edition 2003, Part-2 Edition 2006, and GCC Fire Code addendum to Part-1 NFPA 110, Standard for Emergency and Standby Power Systems, 2010 Edition
issued in 2009 are the initial codes required for compliance with for fire protection and life safety design of JOD. NFPA 111, Standard on Stored Electrical Energy Emergency and Standby Power Systems, 2007 Edition
In addition the GCC Fire Code references other GCC standards and requirements, include, but are not
necessarily limited to, the following: NFPA 204, Standard for Smoke and Heat Venting, 2009 Edition
NFPA 220, Standard on Types of Building Construction, 2009 Edition
Basis and Requirements for Testing and Examining Steam Boilers and Hot Water Boilers [in GCC Fire Code,
Chapter 4, Section 4] NFPA 418, Standard for Heliports, 2006 Edition
Electrical Lifts for People and Goods” GCC Standards Specification [GCC Fire Code, Chapter 4, Sections 6 NFPA 2001, Standard on Clean Agent Extinguishing Systems, 2009 Edition
and 9] NFPA 88A: Standard for Parking Structures, 2011 Edition
Artificial Electrical Lighting, Electrical Conduit: Specifications of the Ministry of Electricity [GCC Fire Code, NFPA 105, Standard for the Installation of Smoke Door Assemblies and Other Opening Protectives, 2007
Chapter 3, Section 6; and Chapter 4, Section 2] Edition.
NFPA 252, Standard Methods of Fire Tests of Door Assemblies, 2008 Edition
2.3 NFPA Codes and Standards
NFPA codes and standards are essentially a supplement to the GCC Fire Codes adopted by the Makkah Civil 2.4 Other Codes and Standards
Defense and the Kingdom of Saudi Arabia. The NPFA codes and standards are applied where they are found to
provide more detailed requirements than are available within the GCC Fire Code. The following is a list of NFPA The list of referenced codes and standards is not intended to exclude the use of British Standards (BS), European
codes that are or may be used for the implementation of the Fire Safety Strategy Plan. NFPA 5000 and NFPA Standards (EN) and other international standards for design of active fire protection and life safety systems if the
101 are two of the most significant documents for this project. Because of the date of original commencement of reference design standard is widely used in Saudi Arabia, has gained acceptance by the Statutory Authorities, and
this project, the 2009 editions of NFPA 5000 and NFPA 101 are utilized as the basis for the evaluation. complements the active and passive fire and life design methodology established by the applicable building codes
Consequently the various other NFPA standards referenced by those two documents are editions from that year and standards. Such codes and standards might include the following, as noted:
and the years immediately prior to 2009. However, with proper review and coordination, it can be acceptable to
use the more recent editions, if properly applied with the context of other applicable aspects of other applicable British Building Regulations, Approved Document B, 2006 Edition (Reference Document Only)
codes and standards: British Building Regulations, Approved Document F, 2010 Edition (Reference Document Only)
NFPA 5000, Building Construction and Safety Code, 2009 Edition BS 7346-7:2006 Edition, Components For Smoke And Heat Control Systems. Code of Practice On Functional
Recommendations And Calculation Methods For Smoke And Heat Control Systems For Covered Car Parks.
NFPA 101, Life Safety Code, 2009 Edition (Reference Document Only)
NFPA 1, Uniform Fire Code, 2009 Edition BS EN 12101-3:2002, Smoke and Heat Control Systems. Specification for Powered Smoke And Heat Exhaust
NFPA 10, Standard for Portable Fire Extinguishers, 2010 Edition Ventilators. (Reference Document Only)
Residential Buildings are divided into two major types, of which only one applies to this project; which is In a Separated Occupancy building, occupancy separation is required to be vertical and horizontal to provide
“Communal Residential Buildings” [GCC Fire Code Part-1, Chapter 8]. It includes both apartments and hotels. complete separation between occupancy divisions in the building. Where the occupancy separation is horizontal,
Within this type there are three additional categories. Only Category C applies to this project. It includes hotels, structural members supporting the separation are required to be protected by an equivalent fire resistive
apartments or similar residential uses. Category C Residential Buildings are classified as having a Fire Risk of construction.
“Slight Risk” per the GCC Code.
In addition, NFPA 5000 classifies the hazards of the contents into three classifications, which are Low Hazard,
Commercial Buildings and Public Markets are divided into two categories, both of which apply to this project. Ordinary Hazard, and High Hazard. High Hazard is further classified into five Levels. NFPA 5000 does not assign
Category A includes commercial shops used to serve the public (which would include the various retail shops a classification of hazard to new occupancies; but does require the design professional to identify and classify the
within this project); and Category B includes “…buildings or parts of buildings occupied by not more than 50 users hazard of the building contents, based on the requirements of the code [NFPA 5000, Section 6.3].
at the time and used for office purposes…” (which would include any such office facilities within the project). The
Fire Risk Classification for both Category A and Category B is “Medium Risk” [GCC Fire Code Part-1, Chapter 9]. Where exit access from one occupancy traverses another occupancy, the multiple occupancy is treated as a
mixed occupancy. Incidental uses within mercantile, business or storage use can be permitted to be considered a
Warehouse and Parking uses are divided into three categories. Of the three categories, only Category B for part of the predominant occupancy. NFPA does not specify a percentage of floor area to define an incidental use
“…buildings with closed sides for car parking…” applies to this project. Car parking facilities are classified as area.
“Medium Risk”. [GCC Fire Code Part-1, Section 11-9/2].
3.2.2 Uses, Categories and Risks
Assembly buildings are divided into three categories. Category A is building with an occupant content of more
than 1,000 people; Category B, 300 to 1,000 people; and Category C, 50 to 300 people. Residential Occupancies are further divided into apartments and hotel. Residential buildings are classified as
having a Low Hazard classification per NFPA.
The GCC Code requires independent escape ways for all uses contained within the Zone S9 project. It requires
that for commercial buildings which contain both Category A and Category B, are designated “mixed use” and Mercantile Occupancies are further divided within the NFPA codes into three classes. Class A are mercantile
classified as “Medium Risk”, and each use must be separated so that each forms an independent fire occupancies having an aggregate gross area of more than 2,800 square meters, or occupying more than three
compartment with independent escape ways [GCC Fire Code Part-1, Section 9-4]. The separation of the uses floors for sales purposes. Class B are mercantile occupancies between 280 to 2,800 square meters of aggregate
and the requirement to provide independent escape ways (which would include both corridors and exit stairs) are gross area and not occupying more than three stories for sales purposes; or not more than 280 square meters
both important requirements, and are further noted within this report in the sections related to egress. gross area and occupying two or three stories for sales purposes. Class C are all mercantile occupancies of not
more than 280 square meters gross area used for sales purposes occupy one story. Mercantile buildings are
classified as having an Ordinary Hazard classification.
Storage Occupancies include requirements for parking garages, which are classified as being enclosed, open or
open not less than 50% on all sides. The Zone S9 garage is classified as an enclosed garage and is classified as
having an Ordinary Hazard classification.
Accessibility Requirements: Each of the occupancies in NFPA 5000 requires compliance with accessibility
requirements of Chapter 11 of NFPA 5000.
Separation of Occupancies: Under NFPA, all of these areas are required to have a minimum of a 2-hour rated
separation, with a few exceptions. No separation is required between any of the three sizes of Assembly
occupancies; only 1-hour is required between Assembly areas with less than 300 occupants, and Business
Occupancy; and 3-hours are required between an Assembly Occupancy with more than 1,000 occupants and a
Storage Occupancy (such as the garage). NFPA permits a reduction of 1-hour in the ratings for buildings
equipped with an approved automatic sprinkler system [NFPA 6.1.14.4.3].
High Risk
Emergency generator fuel storage and EPS Rooms
(High Hazard)
The Podium of S9 will have escalators connecting three and two stories that open from the commercial level 2 up
to Commercial 4 Floor Refer to Diagram 3.3.1.a for location of escalators.
GCC Requirements for Openings for Escalators: The GCC requirements state that each escalator has to be 3.3.2 Liquid Fuel Storage
individually studied by Civil Defense. It further notes that when installing escalators, consideration must be given
to prevent the spread of smoke through the openings of the escalators. [GCC Code: Chapter 4, section 5]. 3.3.2.1 Daily Fuel Tanks
NFPA Requirements for Openings for Escalators: Escalators are not required to be enclosed if they are within Brief Description: For the Zone S9 project, the daily fuel storage tanks for the emergency generators have been
large open areas such as an atrium and enclosed shopping malls. In buildings protected throughout with an located on the southwest side of the highest level of the podium. This is the commercial level 4. They are located
approved automatic sprinkler system, escalator openings shall be protected in accordance with a method detailed within the Emergency Generator Room on that level, which also contains the emergency generators for the
in NFPA 13, or in accordance with a method approved by the authority having jurisdiction. [NFPA 5000, Section project. The Emergency Generator Room is to be enclosed with a 4-hour fire rated construction. It should be
8.12.5.2]. noted that this level of the podium is essentially 5 levels above grade plane.
NFPA 13 does not require closely spaced sprinklers and draft stops around large openings (such as atrium It is essential that in addition to the walls enclosing the room have that fire rating, that the fire rating of the ceiling
buildings) where all adjoining levels and spaces are protected by automatic sprinklers in accordance with NFPA also be confirmed to provide a 4-hour fire rating. This includes confirmation of any pipe or other penetrations
13, and where the openings have all horizontal dimensions between opposite edges of 6 meters or greater and an through the walls and ceilings of those rooms; including air intake and exhaust shafts connecting these rooms with
area of 93 square meters or greater [NFPA 13, 8.15.4.4]. the exterior or elsewhere within the building. Since there are no known doors that have been tested in
accordance with the applicable regulations to have a 4-hour fire rating, it will be essential to provide a properly
If those criteria are not met at escalators, stairs or similar floor openings are unenclosed and where sprinkler designed vestibule at the entry to each of these rooms which has 4-hour walls and has doors which are rated a
protection is serving as the alternative to enclosure of the vertical opening, the floor openings involved must be minimum of 90-minute.
protected by closely spaced sprinklers in combination with draft stops.
GCC Code Requirements
The draft stops are required to be located immediately adjacent to the opening; be at least 457mm deep; and be
of non-combustible or limited-combustible material that will stay in place before and during sprinkler operation. Section 4-8 of the GCC Fire Code Part-1 contains requirements for liquid fuel storage as follows:
The sprinklers are required to be spaced not more than 1800mm apart and be 152mm to 305mm from the draft Liquid fuel should be kept in special rooms which have a fire rating of not less than 4 hours, including 4-hour
stop on the side away from the opening [NFPA 13, 8.15.4]. Refer to Diagram 3.3.2 for draft stop and sprinkler rated doors.
example. Ventilation both at the upper and the lower levels of the room.
A curb is to be built at the door, Adequate in height for the walls to act like a tank to contain 10% of the stored
liquid.
NFPA Requirements 4. Latch or lock hardware shall be permitted in doors only if their occupant load is more than 5.
NFPA limits the amount of hazardous material permitted within a given occupancy based on Maximum Allowable D. Ventilation Requirements – In accordance with NFPA 5000, Section 34.3.2.5:
Quantities (MAQ) or based on a specific protection schemes (Protection Level 1 through 5). The protection levels
1. Mechanical ventilation shall be at a rate of not less than 5.1 liters per sec per square meter. Make up air
are based on the type hazard and contain specific requirements depending on the hazard levels.
shall be provided, and provision shall be made for locating the makeup air openings avoiding the short
circuiting the ventilation. Exhaust ducts shall not extend into plenums.
The MAQ concept relies on a concept of control areas, while the protection level relies on a comprehensive
protection and does not limit the amount of hazardous material that can be stored within a given occupancy. 2. Natural Ventilation shall be provided as an alternate to mechanical exhaust ventilation where natural
ventilation shall be shown as acceptable to the materials being stored.
Specific requirements for liquid fuels for emergency generators are provided in NFPA 37, Standard for the
Installation and Use of Stationary Combustion Engines and Gas Turbines. NFPA 37, Section 6.3.2.3 limits the E. Standby Power Requirements – Standby power shall be provided in accordance with NFPA 70.
aggregate capacity of all fuel tanks to 5,000 L (1320 gal) unless that portion exceeding 5000 L (1320 gal) is
enclosed in a 3-hr rated room (Section 6.3.6). However, Section 6.3.2.3 allows storage of unlimited fuel if the F. Spill Control and Secondary Containment – Spill control and secondary containment needs to be provided
engine rooms or mechanical room is designed using recognized engineering practices with suitable fire detection, for rooms containing fuel storage (NFPA 5000, Section 34.3.2.8).
fire suppression, and containment means to prevent the spread of fire beyond the room of origin.
G. Exterior Wall Requirements – For the room containing the fuel storage, the location shall be such that not
Storage of bulk fuel tanks (buried or in vaults) are regulated by NFPA 30, Flammable and Combustible Liquids less than 25% of the perimeter wall is an exterior wall (NFPA 5000, Section 34.3.4.2).
Code. MAQ or Protection levels of NFPA 5000 Chapter 34 are not applicable.
H. Minimum Distance to Property Lines or Horizontal Separation – Not less than 9.1 m ((NFPA 5000,
Section 34.3.4.3).
Zone S9 Fuel Storage Protection
NFPA 37 Requirements (Emergency Generator Fuel Protection):
The total amount of fuel exceeds the MAQ subscribed in Table 34.1.3.1 thus, use of control areas will not be
used. Protection will be provided following the Protection Levels reference in NFPA 5000 Section 34.3.
Fuel tanks dedicated for the generator shall be constructed in accordance with the applicable requirements of
NFPA 30, Flammable and Combustible Liquids Code or in accordance with API 620, Design and Construction of
Additional passive protection, including an increased up to 4-hr rated walls and a 4-rated vestibule (with two, 90-
Large Welded Low-pressure Storage Tanks.
minute rated fire doors) will be provided to separate the emergency generator rooms housing the daily fuel tanks.
Active fire detection and fire suppression, as well as spill containment will be also provided in accordance with Specific requirements for liquid fuels for emergency generators are provided in NFPA 37, Standard for the
NFPA 37, Section 6.3.2.3. Thus, daily tanks sizes will not be limited to the maximum allowable quantities listed in Installation and Use of Stationary Combustion Engines and Gas Turbines. NFPA 37, Section 6.3.2.3 limits the
NFPA 5000, Chapter 34.
aggregate capacity of all fuel tanks to 5,000 L (1320 gal) unless that portion exceeding 5,000 L (1,320 gal) is
enclosed in a 3-hr rated room (Section 6.3.6).
In summary, the protection of the emergency rooms containing the daily fuel tanks will be protected in accordance
with NFPA 5000, Section 34.3.4 (Protection Level 2) and NPFA 37 Chapter 6, NFPA 30, Chapter 21. Review of However, Section 6.3.2.3 allows storage of unlimited fuel if the engine rooms or mechanical room is designed
all the requirements noted above must be performed by the design team for the emergency generator room using recognized engineering practices with suitable fire detection, fire suppression, and containment means to
located in S9. The following summary of major requirements is provided as guidance only: prevent the spread of fire beyond the room of origin. Additional requirements included:
A. Suppression System Requirements – Automatic sprinkler systems need to be provided, water flow alarms
A. Rooms containing only fuel tanks shall be constructed of walls, floor, and ceiling having a fire resistance rating
shall be monitored and electronic supervision of supervisory signals shall be provided in the enclosures
of not less than 3 hours with the walls bonded to the floor (NFPA 37, Section 6.3.6.1).
containing the fuel storage (NFPA 5000, Section 34.3.2),
B. At least 380 mm clearance shall be left around each tank for the purpose of inspection and repair (NFPA 37,
B. Separation Requirements – The fuel storage room needs to be separated from the adjacent areas by 2
Section 6.3.6.1.2).
hours for storage occupancies (NFPA 5000, Table 34.3.2.3).
C. Each tank room shall be provided with spill containment consisting of either a wall, a curb, or a dike having a
C. Means of Egress Requirements – In accordance with NFPA 5000, Section 34.3.2.4:
capacity, at least equal to that of the largest tank (NFPA 37, Section 6.3.6.3). Exception: A spill containment
system of lesser capacity equipped with an overflow or drainage system that is adequate in size and location
1. The travel distance limit is 30 meters. to convey any spillage of fuel to a tank (inside or outside) or to a safe area outside the structure.
2. Egress capacity is 18 mm per person for stairs or 10 mm per person for level components and ramps. D. Floor openings shall be protected by a ramp or curb of sufficient height to contain the entire contents of the
tank within the walls to the height corresponding to the level of fuel that will be retained (NFPA 37, Section
3. Not less than two (2) means of egress shall be provided from each storage room/ enclosure (unless the 6.3.6.4).
area is less than 18.6 square meters, travel distance within the room to entry door is less than 7.6 meters,
and have an occupant load of less than 3 persons).The storage room shall be arranged such that there
F. Ventilation for tank rooms shall be sufficient to maintain the concentration of vapors within the room at or C. Atmospheric storage tanks shall be vented to prevent the development of vacuum or pressure above the 1.0
below 25 percent of the LFL of the fuel used (NFPA 37, Section 6.3.6.5.1). psi (6.9 KPa) maximum operating pressure (NFPA 30, Section21.4.3.4).
G. Liquid fuel supply systems, including drains from carburetors, shall be designed and installed to minimize, as 3.3.2.2. Buried Bulk Fuel Storage for Zone S09
far as practicable, the accidental discharge of fuel into the engine room or structure (NFPA 37, Section 6.5.1)
S09 is served with 3 bulk buried fuel tanks located southeast of zone S09. The capacity of each bulk fuel tank is
H. Alarms, float-controlled valves, or mechanical or remote-reading level gauges or protected sight glass gauges 15,000 Liters. Refer to Diagram below for location of the buried tanks. Refer to Appendix E for a larger drawing.
shall be installed to aid personnel in properly operating the fuel system (NFPA 37, Section 6.5.2)
I. Stationary-powered fuel pumps supplying fuel tanks shall have “stop” controls sensitive to a tank’s high liquid
level (NFPA 37, Section 6.5.3).
J. Fuel tanks supplied by pumps shall be provided with all of the following (NFPA 37, Section 6.5.4):
An overflow line
A high-level alarm
A high-level automatic shutoff
K. The overflow line shall be continuous piping, without valves or traps, back to the source tank or to a collection
system (NFPA 37, Section 6.5.4.1).
L. The capacity of the overflow line shall exceed the delivery capacity of the supply lines to the fuel tank (NFPA
37, Section 6.5.4.2).
M. Overflows, vents, fuel piping, and fuel tanks shall not be located at or near engine air intake, exhaust piping,
mufflers, or filters where the potential exists to over pressurize the fuel system piping (NFPA 37, Section
6.5.5).
N. Relief piping shall be routed, without valves or traps, back to the source tank or to a collection system (NFPA
37, Section 6.5.6.1).
O. Piping for fuel tanks other than engine-mounted tanks shall be in accordance with Chapter 27 of NFPA 30,
Flammable and Combustible Liquids Code (NFPA 37, Section 6.6.3).
P. The fill pipe shall terminate outside the building at a point at least 600 mm from any building opening at the
same or lower level (NFPA 37, Section 6.6.3.1). DIAGRAM 3.3.2.2 Buried Fuel Tanks
Q. Vent piping shall be installed in accordance with Chapter 27 of NFPA 30, Flammable and Combustible Liquids Bulk buried shall be installed and design in accordance with NFPA 30, Chapter 23.
Code and it shall terminate outside the building at a point at least 600 mm from any building opening at the
same or lower level (NFPA 37, Section 6.7.1.1). Buried Bulk Fuel Storage shall comply with the following:
R. Piping to aboveground supply tanks filled from tank cars or tank vehicles by centrifugal pumps shall be A. All underground tanks shall be listed for underground installation and shall be installed in accordance with the
provided with check valves to prevent backflow (NFPA 37, Section 6.8.4). manufacturer’s instructions (NFPA 30, Section 23.3.2).
Additional requirements from NFPA 30 shall be as follows: B. Underground tanks and their piping shall be protected by either of the following (NFPA 30, Section 23.3.5):
A. Storage tanks shall be vented to prevent the development of vacuum or pressure that can distort the tank or A properly engineered, installed, and maintained cathodic protection system in accordance with
exceed the rated design pressure of the tank when the tank is filled or emptied or because of atmospheric recognized engineering standards of design
temperature changes. Normal vents shall be located above the maximum normal liquid level (NFPA 30, Approved or listed corrosion-resistant materials or systems
Section 21.4.3.1).
C. Underground tanks or tanks under buildings shall be located with respect to existing building foundations and
supports so that the loads carried by the foundation are not transmitted to the tank (NFPA 30, Section 23.4.1).
At least 36 in. (900 mm) of backfill NFPA Requirements: Waste and recyclable storage rooms and waste/ linen chutes requirements are contained in
At least 18 in. (450 mm) of compacted backfill of a type recommended by the tank manufacturer and at NFPA 82 Standard on Incinerators and Waste and Linen Handling Systems and Equipment” (2009 is the most
least 6 in. (150 mm) of reinforced concrete recent edition), which indicate in Chapter 8 that waste storage rooms with more than 0.765 cubic meters or more
At least 18 in. (450 mm) of compacted backfill of a type recommended by the tank manufacturer and at of un-compacted waste are required to have a minimum of 1 hour fire separation, with doors rated not less than
least 8 in. (200 mm) of asphaltic concrete 3/4 hours; and that room is to be provided with automatic sprinklers. The requirements for rooms in which waste
material is being handled or compacted are 2 hour separation with doors rated not less than 1 ½ hours; and the
J. When asphaltic or reinforced concrete paving is used as part of the protection, it shall extend at least 12 in. room be provided with automatic sprinklers.
(300 mm) horizontally beyond the outline of the in all directions
Waste/linen chute, chute service room, and chute collection room (chute discharge room) are required to comply
K. Tank venting systems shall be provided with sufficient capacity to prevent blowback of vapor or liquid at the fill
with the following:
opening while the tank is being filled (NFPA 30, Section 23.6.1).
Waste/linen chutes are required to be enclosed by walls or partitions, providing 2-hours fire resistance.
L. Vent piping shall be sized in accordance with Table 23.6.2, but shall not be less than 32 mm nominal inside Waste/linen chute service openings are protected by an approved (listed) self-closing door that provides 90-
diameter (NFPA 30, Section 23.6.2). minute fire resistance.
Waste/linen chutes are protected by automatic sprinklers within the chute at or above the top service opening
M. Connections for all tank openings shall be liquid tight and vapor tight (NFPA 30, Section 23.13.1). of the chute and at alternate floor levels, with a mandatory sprinkler located at the lowest service level.
The doors of chutes open only to a service room that is designed and used exclusively for accessing the
N. Openings for manual gauging, if independent of the fill pipe, shall be provided with a liquid tight and vapor
tight cap or cover. Covers shall be kept closed when not gauging (NFPA 30, Section 23.13.2). chute opening.
The chute service room is separated from other spaces by 1-hour fire rated wall enclosures and protected by
O. If inside a building, each such opening shall be protected against liquid overflow and possible vapor release automatic sprinklers. Openings into such a room shall be protected by 45-minute fire rated doors, provided
by means of a spring-loaded check valve or other approved device (NFPA 30, Section 23.13.2.1). with approved self-closing devices.
The size of the chute service room is required not to be less than that required to maintain a minimum
P. Fill and discharge lines shall enter tanks only through the top (NFPA 30, Section 23.13.3). 152.4mm clearance between the intake opening of the chute and the closed service room door.
The bottom of a waste/linen chute is required to be protected by an approved (listed) automatic closing or self-
Q. Fill lines shall be sloped toward the tank (NFPA 30, Section 23.13.4).
closing door of construction that provide 90-minute fire resistance.
R. Filling, emptying, and vapor recovery connections for Class II liquids that are connected and disconnected Chute discharge doors are permitted to be held open by a fusible link.
shall be located outside of buildings at a location free from any source of ignition and not less than 1.5 meters Waste/linen chutes must discharge directly into a room having a minimum fire resistance rating not less than
from any building opening or air intake (NFPA 30, Section 23.13.6). that specified for the chute (2-hours fire resistance). Openings into such a room shall be protected by
approved self-closing fire doors having a minimum fire protection rating not less than specified for the chute
S. Such connections shall be closed and liquid tight and vapor tight when not in use (NFPA 30, Section
(90-minute fire rated doors).
23.13.6.1).
GCC Code Requirements: GCC Fire Code Part-1 identifies in Section 1-2/1/1/8 that high rise buildings are NFPA Code: The NFPA Code requires that for assembly occupancies, and for hotel occupancies, any room
buildings with a special nature. It does not have a separate chapter for high rise requirements, but it does containing high pressure boilers, refrigerating machinery, transformers, or other service equipment subject to
distribute requirements for high rise buildings throughout the GCC Fire Code. These include the requirements for possible explosion must not be located directly under, or directly adjacent to exits. In addition, all such rooms are
lightning protection for high rise buildings, in accordance with the conditions and specifications of Civil Defense to be effectively cut off from other parts of the building in accordance with the Special Hazard Protection
and the Ministry of Electricity [GCC Fire Code Part-1, Section 4-2/13]. The GCC Code also requires that for requirements Section 8.15 of NFPA 5000. These include, but are not limited to a minimum of a 1 hour fire rated
buildings which are 28 or more meters in height, one or more elevators be reserved to help fire fighters [GCC Fire separation; protection of the area with an automatic extinguishing system.
Code Part-1, Section 4-6/4]. For Residential Buildings and for Assembly Buildings, the GCC requirements are
more restrictive, and require fire fighter elevators for buildings which are 6 floors or 20 meters in height (whichever 3.3.7 Fire Pump Rooms
is less) [GCC Fire Code Part-1, Tables 5-4 and 8-4 C].
Minimum requirements for fire pump rooms are contained in NFPA Standard 20. The 2010 edition requires all
The GCC Fire Code requires certain high rise buildings to be provided with manual alarms and automatic alarms. indoor fire pump rooms for high rise buildings to be protected by 2 hour fire rated construction. The 2010 edition
This provision applies to Residential Buildings of both Category A and C when they exceed 30 meters in height; includes the requirement that fire pump rooms, which are not directly accessible from the outside, shall be
and to Commercial Buildings of both Category A and B, when they exceed 28 meters in height. In addition, a “wet accessible through an enclosed passageway from an enclosed stair or exterior exit; and that the enclosed
standpipe system”, and occupant-use hose network are required for each of those building types when they passageway shall have a minimum 2 hour fire resistance rating.
exceed the aforementioned heights. Finally, they are also required to be equipped with a standby power system.
[GCC Fire Code Part-1, Tables 9-3A and 8-3 C]. 3.3.8 Laundry Rooms and Chutes
Commercial Buildings are required to provide a horizontal exit for temporary refuge in high rise commercial Laundry rooms and chutes are regulated by NFPA 82 “Standard on Incinerators and Waste and Linen Handling
buildings on floors and locations which exceed 3,000 square meters. [GCC Fire Code Part-1, Section 9-6/7/4]. Systems and Equipment”, which requires that service opening rooms be separated from all other parts of a
building by a fire resistance rating equal to that of the chute, but not less than 1-hour, with ¾ hour rated doors
NFPA Requirements: NFPA 5000 defines a high rise as a building that has an occupied floor more than 23 when protected by an automatic sprinkler system for gravity systems; and not less than 1-hour with ¾ hour rated
meters above the lowest level of Civil Defense vehicle access. Chapter 33 of NFPA 5000 contains detailed doors for pneumatic systems (with or without sprinkler system protection). Loading doors are required to be rated
requirements for high rise buildings. Most significant is the requirement for an Emergency Command Center. The a minimum of 1-hour. The collector discharge area is required to be separated from all other parts of the building
location, design, content and Civil Defense access of this center is required to be approved by the Civil Defense. by a minimum fire resistance rating of 2-hours, with a minimum of 1½ hour rating on doors and dampers, and the
It is to be separated from the remainder of the building by a minimum of 1 hour fire resistive rating; have an area discharge area is required to be protected by an automatic sprinkler system. More information and details of code
of not less than 19 square meters (NFPA 5000, 2012), with a minimum dimension of 3.05 meters (NFPA 5000, requirements of linen chute and discharge room are provided in section 3.3.4 of this report.
2012). Detailed requirements of the minimum contents of the command center are identified in Section 33.3 of
NFPA 5000, and is noted in the section “Fire Command Center, FCC” which appears below in this report.
3.3.9 Electrical Equipment and Transformer Rooms
Acceptance testing of the equipment within the command center is required by the code.
The National Electrical Code (NFPA 70) is referenced by NFPA 5000, including requirements for electrical
NFPA 5000 also has specific minimum requirements for means of egress doors; detection, alarm and
equipment and electrical transformer rooms. Typical small electrical closets containing circuit breakers and small
communication systems; extinguishment requirements; exit stair enclosures; emergency lighting and standby
dry transformers (and no other uses or contents) do not require any special fire resistive enclosures if they are
power; and smoke control. In addition, for buildings over 36.57 meters in height, at least one firefighting lift (first
protected with an automatic sprinkler system. If there is no sprinkler system in them, a 2-hour rated enclosure is
responders use elevator) is required. NFPA 5000 requires that for mixed occupancy buildings, the most
required. Dry-Type transformers rated larger than 112-1/2 kVA are required to be installed in a room with a
restrictive, applicable, high rise building provisions and fire protection system requirements shall apply to all
minimum of a 1-hour fire resistive construction (including a ¾ hour door, with self-closing and latching hardware).
portions of the building [NFPA 5000, Section 6.2.3.4].
Dry transformers over 35,000 volts must be enclosed in a vault with a 3-hour rating; which can be reduced when
the transformer is protected with a fixed extinguishing system, such as sprinklers, or an approved gaseous agent
3.3.5 Elevator (Lift) Requirements extinguishing system. For all electrical spaces, it is important that all penetrations be properly sealed, as noted in
the section of this report about “Penetration Sealing”.
As noted above, both the GCC Code and NFPA 5000 requires at least one elevator for use by fire fighters. The
GCC Code requirements are similar to the NFPA Code requirements, which also references ANSI Standard
3.3.10 Emergency Equipment and Storage Rooms
A17.1. Both the GCC Fire Code Part-1 and NFPA require a 2-hour enclosure around the elevator hoist way and
the machine room. The GCC Fire Code Part-1 permits the inclusion of an elevator within a stairwell (NFPA does
the GCC Fire Code, NFPA 101 and NFPA 70 require a higher level of fire-resistive separation for emergency
not) if it meets the fire protection and prevention requirements. It requires that all elevators must have a lobby
equipment rooms and other more hazardous accessory building areas, which are summarized as follows:
separated from the building by fire resistant walls and doors. The GCC code also requires a sign in the elevator
stating that children below 14 years old are not permitted to use the elevator without the supervision of an adult.
Note: Special requirement from Civil Defense for Phase 4, S09 requires two (2) dedicated firefighter
elevators. Thus, each hotel tower will have two elevators dedicated for Civil Defense Access.
Room or Area Fire-resistive Separation (hours) Small typical electrical closet rooms and telephone rooms in the hotel towers will be protected using passive fire
barriers. In accordance with NFPA 13, 2010 Ed, Section 8.15.10.3 ssprinklers are allowed to be omitted in
2-hours; or 1 hour with sprinklers or other approved electrical equipment rooms where all of the following conditions are met:
Transformer rooms
suppression system [NFPA 70]
(1) The room is dedicated to electrical equipment only.
Emergency generator rooms 4-hours [GCC Part 1, Section 8-2]
(2) Only dry-type electrical equipment is used.
Diesel storage tank rooms 4-hours [GCC Part 1, Section 8-4]
(3) Equipment is installed in a 2-hour fire-rated enclosure including protection for penetrations.
Fire pump rooms 2-hours [NFPA 20]
(4) No combustible storage is permitted to be stored in the room.
Electrical closets 1-hour [NFPA 70 – see commentary ] Note: Special requirement from Civil Defense for Phase 4, S09. All penetrations (i.e. ductwork) into the
Electrical Vaults (over 600 Volts, nominal) 3-hours [NFPA 70] electrical rooms will be protected as smoke barrier and will require motorized smoke dampers.
Garbage, Trash, and Recycling Service 4-hour garbage chute [ GCC Part 1, Section 4- 3] 1-hour The GCC Fire Code Part-1 has few specific restrictions on height which impact the Zone S9 project. The GCC
Rooms [NFPA 82] Code uses stringent requirements on Area Limitations and Construction Type to provide appropriate levels of life
safety.
4-hours [GCC Part -1, Section 4-3]
Garbage Processing Rooms 4.1.2 Area Limitations in the GCC Fire Code
2-hour [NFPA 82]
The GCC Fire Code Part-1 divides the maximum amount of area of uses into fire compartments. Unlike some
3.3.11 Steam Boilers and Hot Water Boilers building codes, the use of automatic sprinkler systems in a building does not result in any modification (or
increase) in the maximum allowable area.
GCC Code Requirements: GCC Fire Code requirements for the installation of steam boilers and hot water boilers
require compliance with the requirements of GCC Standard Specification “Basis and Requirements for Testing Additional general requirements for fire compartments are 1) each floor is to be considered a separate fire
and Examining Steam Boilers and Hot Water Boilers”, and related conditions from Civil Defense. [GCC Fire Code compartment; 2) each unit area with a use different from that nature (or primary use) of the building is to be
Part-1, Section 4-4]. Boiler rooms are required to be constructed in rooms with a 4 hour fire rating, equipped with considered a separate fire compartment; and 3) vertical shafts such as stairwells and light wells are to be
doors with the same rating and with automatic closing devices. Identification signage is also required to be fixed considered a separate fire compartment.
onto the door. The GCC Fire Code expresses preference (but does not require) for boiler rooms to be located
opposite of the external wall of a building, and when that is not applicable, that consideration should be given to The requirements for fire limits appear both in Chapter 1, and in the individual chapters for specific building types.
locate it in a manner which would minimize the impact in the event of an explosion. It is also preferred (but not The general information is as follows: [GCC Fire Code Part-1: Table 1-3, “Division of Buildings into Fire
required) that the entrance to the boiler room be directly from the outside. The location of that entrance is Compartments”].
required to not create a fire hazard to the main exit way in the building. In addition, natural ventilation is required
Residential Buildings: 3,000 square meters maximum
for boiler rooms, both for the purpose of ventilation and for removal of smoke.
Each housing unit is considered a separate secondary fire compartment
NFPA Requirements: Requirements for boiler rooms are contained in Chapter 8 and each chapter of the various Commercial Shops: 2,000 square meters maximum
occupancy types in NFPA 5000. The minimum requirement is 1 hour separation and protection by automatic Each leased unit is a separate secondary fire compartment
sprinklers. Offices: 3,000 square meters maximum
Each leased unit is a separate secondary fire compartment
Storage (A) Slight Risk: 5,000 square meters, and 1,500 cubic meters maximum
Stores keeping non-combustible products
4.2 Height and Area Limits of the NFPA Codes Construction Requirements of NFPA 5000: Chapter 33 for High Rise Buildings
Under certain conditions, Section 33.1.3.2 permits a reduction in building construction type. That section states
4.2.1 Height Limitations in the NFPA Codes “For buildings, other than mercantile occupancies or industrial and storage occupancies with ordinary and high
hazard contents exceeding the maximum allowable quantities per control area as set forth in 34.1.3, Type I (442)
Height limits within NFPA 5000 appear in Section 7.4, and are impacted by the occupancy, the construction type, construction shall be permitted to be reduced to Type I (332), and Type I (332) construction shall be permitted to
and if the building is provided with an approved, electrically supervised automatic sprinkler system in accordance be reduced to Type II (222).”
with NFPA 13.
The Zone S9 project contains both mercantile and storage occupancies. Based on the information received, it
Since the Zone S9 project is a high rise as defined by NFPA 5000 (more than 23 meters in height from the lowest appears that the fuel storage required for the emergency generators on the commercial 4 floor qualify as high
level of Civil Defense vehicle access to the height of the highest occupied floor); and since high rise buildings are hazard contents that exceed the maximum allowable quantities. Therefore, this project will not be qualified for the
required to have an approved sprinkler system; and since it is more than 55 meters in height (the maximum limit reduction in construction type for a high rise building with a fully automated sprinkler system.
for Type II buildings with approved sprinkler systems) it is required to be Type I construction.
As previously noted, the minimum construction type permitted by NFPA (Non-separated Occupancies) is Type I
For Type I buildings which have an approved sprinkler system; and which have the various occupancy types (332), however, due to the presence of the high hazard, all the structure supporting the high hazard area will need
contained in the Zone S9 project; all of the areas are unlimited and the number of floors is unlimited. When such to provide a four-hour rating. If this high hazard is relocated to an acceptable location, additional analysis of the
buildings are not more than 128 meters in height, they are classified as Type I (332). When they are above 128 plans, and potential modifications to the building might result in a reduction to Type II (222). Refer to Diagram
meters in height, they are classified as Type I (442), Since the Zone S9 project is less than 128 meters in height, 5.1 for a summary of the Project height data.
it can be classified as Type I (332).
5.2 Structural Fire Resistance
4.2.2 Area Limitations in the NFPA Code
Table 1-7, in Chapter 1 of the GCC Fire Code, identifies the minimum construction requirements for structural
Like height limits, area limits for NFPA 5000 appear in Section 7.4, and are impacted by the occupancy, the elements. It notes that all structural elements, including columns, beams, floor slabs, roofs, and structural walls,
construction type, and if the building is provided with an approved, electrically supervised automatic sprinkler are to be constructed from non-combustible, fire resistive materials, suitable to the nature of usage, and that the
system in accordance with NFPA 13. As previously noted for height limits in the NFPA Codes, the Zone S9 degree of fire resistive ratings (in hours) is to comply with the contents of Table 1-7 as a minimum. It also notes
building would have unlimited areas for the types of occupancies it contains; and provided that it is a minimum of that when the building is being used for more than one purpose, the degree of fire resistance may be increased for
Type I (332) construction; and complies with other requirements as noted below. columns and beams per the recommendations of Civil Defense. Those requirements are tabulated as follows,
both for structural and for non-structural construction in the Tables identified as Table 5-2-1 “Comparison: GCC
Code and NFPA Type I (442) and Type I (332) Construction: Bearing Construction” and Table 5-2-2
5. Construction Classification & Fire Resistance Ratings “Comparison: GCC Code and NFPA Type I (442) and Type I (332) Construction: Non-Bearing Construction”.
As previously noted in Section 1.3 of this Report, “General Description of Zone S9”, the height of the three towers
is approximately 115 meters from the ground floor to the highest roof on the elevator machine room. The height is
based on following the NFPA criteria noted below for the determination of the minimum construction type.
DIAGRAM 5.1: Building Height Data [Dubai office to provide section for S9;
Parking Garage
Most Stringent
(Industrial and
Residential and
Bearing Construction GCC Code
Multiple Floors
Requirement
Type I (442)
Type I (332)
Warehouse)
442 to GCC
332 to GCC
NFPA 5000: Chapter 1
Commercial
442 to 332
NFPA 5000 Difference GCC Code Table 7.3.2.1 Table 1-7
and Table 1-4
Parking Garage
Most Stringent
(Industrial and
Residential and
Multiple Floors
Requirement
GCC Code
Warehouse)
Type I (442)
442 to GCC
332 to GCC
NFPA 5000:
Commercial
Type (332)
442 to 332
Chapter 1 [Table 7-1] External
Table 7.2.1.1 Walls and Walls
Table 1-7
Exterior Non-Bearing Separating from
Walls 0 0 0 -4 -4 4 4 4 Neighboring Buildings
or the Risky parts of
Exterior Bearing Walls the Building
Supporting more than
one floor, columns, or 4 3 +1 0 -1 4 External Walls and
other bearing walls Walls Separating from [Table 7.3.2.1] Assembly, GCC: 15
4 4 Neighboring Buildings residential, Business (low meters
Supporting one floor
4 3 +1 0 -1 4 hazard); more than 3 0 before
[Table 1-4]
only or the Risky parts of 1st Construction
the Building meters rating is 0
Supporting a roof only 4 3 +1 0 -1 4 Classification:
0 Separation to
Interior Bearing Walls [Table 7.3.2.1] Mercantile GCC: 15 neighboring building is
& Storage (Parking garage) meters more than 15 meters
Supporting more than Walls separating Exit with moderate hazard; 0 before
one floor, columns, or 4 3 +1 +2 +1 4 Ways, Lift Well, more than 3 meters rating is 0
other bearing walls Skylight, Stairway,
Supporting one floor 2 4 Service Tracks
only 3 3 0 +1 +1 4 GCC:
(Horizontal and [Table 7.3.2.1] Assembly,
Rating 1
Supporting a roof only 3 2 +1 -1 0 4 Vertical) residential, Business (low 1 from 5 to 15 [Table 1-4]
hazard); 1.5 to 3 meters 1st Construction
meters
Classification:
Columns 1 Separation to
Supporting more than [Table 7.3.2.1] Mercantile GCC: neighboring building is
one floor, columns, or 4 3 +1 +2 +1 4 & Storage (Parking garage)
1
Rating is 1 5 to 15 meters
other bearing walls with moderate hazard; 1.5 from 5 to 15
Columns, Beams,
Supporting one floor 2 4 Roof Slabs
to 3 meters meters
only 3 2 +1 +1 0 4
Supporting a roof only 3 2 +1 +1 0 4 GCC:
[Table 7.3.2.1] Assembly,
Rating is 2
residential, Business (low 1 hours up to [Table 1-4]
Beams, Girders, hazard); 0 to 1.5 meters 1st Construction
Trusses, and Arches 5 meters
Classification:
2 Separation to
Supporting more than [Table 7.3.2.1] Mercantile GCC:
one floor, columns, or 4 3 +1 +2 +1 4 neighboring building is
& Storage (Parking garage) Rating is 2
other bearing walls with moderate hazard; 0 to 2 less than 5 meters
Columns, Beams, hours up to
Supporting one floor 2 4 Roof Slabs 1.5 meters 5 meters
only 2 2 0 0 0 4
Supporting a roof only 2 2 0 0 0 4 [Table 7-1]
Interior Non-Bearing
Floor-Ceiling Walls 0 0 0 -4 -4 4 2 4 Internal Walls and
Assemblies 2 2 0 NA NA 2 None identified [Table 7-1] Not listed Partitions
[Table 1-4] Fixed
[Table 1-4] Ceiling 1
2 and Floor Tiles
Internal Partitions
The GCC provides requirements to separate occupancy based on their Risk Classification (Slight, Medium and
High) The following table provides the required fire-resistance between occupancies found in this project.
2
At this location, NFPA 5000 requires the installation of material which has been tested in accordance with NFPA
≤ 645 cm =D-H-90 251, and ASTM 2307 “Standard Test Method for Determining Fire Resistance of Perimeter Fire Barrier Systems
Fire barriers 2 1.5 645* 2
>645 cm = D-H-W-90 Using Intermediate Scale, Multi-Story Test Apparatus”, and having a rating at least equal to the floor assembly.
Fire Joint Protective Systems: The third location requiring penetration sealing is at the various building joints and
2
Shafts, exit ≤ 645 cm =D-H-90 other joints which occur between fire walls, fire barrier walls, floors, floor/ceiling assemblies, roof/ceiling
enclosures and exit 2 1.5 645* 2 assemblies, at the intersections of exterior walls and the perimeter of the floor assembly. At these locations the
>645 cm = D-H-T or D-H-T-W-
passageway walls sealing materials and systems are required to be tested in accordance with ASTM E1966, “Standard Test Method
90
for Fire-Resistive Joint Systems”, or ANSI/UL 2079 “Standard for Tests for Fire Resistance of Building Joint
Systems”.
Other fire barriers 1 0.75 Max. size tested D-H-NT-45
Persons Residential Apartments Not stated Not stated 18.6 [.0537] Apartments
Hotel Rooms Hotels
250 Persons < Q. L. ≤ 300 3.00 1.50 [interpreted to mean guest 15.00 0.07 18.6 [.0537] [Uses within a hotel are as
Persons rooms or suites] noted below]
Restaurants 4.00 0.25 (see below) Restaurants
300 Persons < Q. L. ≤ 1000 Clear Width + 0.05 m per every 8 Clear Width + 0.05 m per every 10
Persons Persons increase Persons increase 9.3 [.1075] Kitchens
(see below) Dining Areas
Q. L. > 1000 Persons Extra Exit Stair with clear width not Extra Exit Door with clear width not
0.28 [3.57] Waiting Areas
less than 1.52m per every 500 less than 1.52m per every 500
persons increase persons increase 0.65 net [1.538] Movable Seating;
concentrated use
Moveable Seating: Less
6.2.2 NFPA Requirements 1.4 net [714]
concentrated
Fixed Seating Actual number of seats Actual number of seats Fixed Seating
NFPA identifies minimum width of egress components, and uses capacity factors of 7.6 mm per occupant for
stairways, and 5 mm for level components (such as corridors and doors) and ramps. The exception to this for the Meeting Rooms 1.00 0.15 [*] (see below) Meeting Rooms
Zones S09 project would be areas with High Hazard contents exceeding the maximum MAQ per control area; 0.65 net [1.538] Movable Seating;
[*] Note: The value of 0.15 occupants per square concentrated use
which the capacity factors used are 18 mm for stairways, and 10 mm for level components and ramps. [NFPA
meter is listed in the text of the code, but might be a
5000, Table 11.3.3.1].The minimum width of 915 mm is used for exits serving less than 50 occupants [NFPA typo; with "1.00" being the correct value (which is 1.4 net [714] Moveable Seating: Less
Hotels
Hotels
5000, 11.3.4.1 (2)]. NFPA requirements for exit stairs are a minimum width of 1120 mm for a cumulative occupant mathematically correct for the square meters per concentrated
load assigned to the stair of less than 2,000 occupants, and 1420 mm for a cumulative occupant load assigned to occupant, and similar to the NFPA values.) Actual number of seats Fixed Seating
the stair of 2,000 or more occupants. The increase width is only required to occur at the lower portion of the stair, Markets (shopping Mercantile Use
centers) 0.75 1.33 (see below)
starting at the floor where the cumulative occupant load first exceeds the 2,000 occupant quantity. [NFPA 101,
7.2.2.2.1.2]. Central Markets 2.00 0.5 2.8 [0.357] Sales on Street Floor
Small Markets Specifically Specifically Sales on two or more
3.7 [0.270]
NFPA requirements permit projections into the path of egress of not more than 114 mm on each side, and at a not stated not stated street floors
height of not more than 965 mm above the floor, or above the nosing at a stair. This provision accommodates Showrooms (listed twice Sales area on floor below
1.50 0.67 2.8 [0.357]
stair handrails and door handles. In the locations where the stair and landing handrails form a part of a guard, with 2 values) street floor
Conference Halls Sales area on floor above
such projections are permitted at a height of 1065 mm and below. 1.00 1.00 5.6 [0.179] street floor
Showrooms (listed twice Areas used only for
Markets
6.2.3 Egress Convergence
Storage
46.5 [0.0215] Storage Occupancies or
Mercantile Occupancies
NOTES:
1. Codes used are GCC Code, Part-1 (2003 edition) and NFPA 101 Life Safety Code (2009 edition).
2. All values are specifically stated in the respective codes unless they are indicated in brackets. Values indicated in brackets are calculated
values, based on the values specifically stated in the text of the respective code.
6.4 Egress Components The GCC Code [Chapter 8, Section 4] requires stairs of different occupancies (including residential stairs) to be
completely independent from stairs of other occupancies, and lead directly to the outside. There are some
6.4.1 Corridors locations where that condition does not occur within the Zone S9 project, and those must be addressed and
modified on an individual basis within the context of the fire and life safety strategy for this Zone.
The GCC Fire Code Part-1 requires the following minimum widths for corridors for the uses within the Zones S09
project. The GCC Fire Code Part-1 also requires that in Residential uses, emergency exits must be provided for
apartments in the second floor, which lead to the main passageway or a staircase. The GCC Fire Code Part-1
Commercial [GCC Fire Code Part-1, Section 9-6] requires that a vestibule is to be provided at the exit stairs in various types of occupancies, including both
Residential and Commercial uses [Sections 3-13/1, 8-1/6, and 9-6/6]. The vestibules are required to have a
Category A (Retail) 2 meters main passageways minimum dimension of 1.5 meters between the doors in the closed position, and a minimum clearance of 1 meter
Category A (Retail) 1.5 meters (secondary passages separating the display areas) between the doors when in the open position. Therefore an increased dimension in door width would result in an
Category B (Offices) 1.5 meters main passageways increased dimension for the vestibule to be greater than the 1.5 meters minimum. [GCC Fire Code Part-1,
Section 3-9]
Residential [GCC Fire Code Part-1, Section 8-6]
There are some locations where that condition does not occur within the Zone S9 project, and those must be
Category A (Apartments) 1.5 meters for main passageways
addressed and modified on an individual basis within the context of the fire and life safety strategy for this Zone.
1.2 meters for branch corridors
Category C (Hotels) 2.0 meters for main passageways In accordance with the GCC Fire Code [Section 3-3/4], the minimum clear width of the exit doors/corridors and
1.2 meters for branch corridors stairs will be determined based on the maximum occupant load (persons) in the building or any part of the building
at any time as given in Table 3-4 of the GCC Fire Code Part-1. Those requirements have previously been noted
Assembly [GCC Fire Code Part-1, Section 5-6] in this report in the section on “Size of Means of Egress”. For both the GCC Fire Code Part-1 and NFPA, the stair
2 meters for main passageways width is based on the maximum occupant load of a floor being served by that stair. [GCC Fire Code – Part-1,
1.5 meters for branch corridors Chapter 3].
Storage [GCC Fire Code Part-1, Section 11-6] Exit stairs are required to comply with the following requirements GCC Fire Code Part-1 [Chapter 3] as well as
2 meters for main passageways NFPA 101:
1.5 meters for branch corridors
Maximum Opening in Guard: [GCC Fire Code – Part-1, Section 3-8] 100 mm
Maximum Riser Height: GCC Fire Code – Part-1 [Chapter 3, Section 13] 180 mm
Minimum Tread Depth: GCC Fire Code – Part-1 [Section 3-12] 280 mm Open spiral stairs are not permitted to be used as a means of egress in residential, assembly and commercial
areas. They can be provided for convenience purposes only in lobby areas.
Minimum Tread Depth: [NFPA 101 Table 7.2.2.2.1.1. (a)] 280 mm 6.4.4 Balconies
Minimum Headroom: [NFPA 101 Table 7.2.2.2.1.1 (a)] 2,030 mm Any balconies used as components of the means of egress on podium floors are required to comply with GCC
Fire Code, Part-1 requirements for balconies and exterior stairs referenced in Sections 3-17 and 3-16. The height
Maximum Height between Landings of openings exposed to the balconies shall not be less than 2 meters and the width of the balconies shall not be
14 Risers = 2,520mm less than 1.5 meters. The walls facing the exterior stairs are required to be separated by fire resistant
GCC Fire Code – Part-1[ Section 3-12] (14 x 180 = 2,520 mm)
construction, fire doors equipped with self-closing devices, and fire windows within the limits of 3 meters in
Maximum Height between Landings: [NFPA 101 Table 7.2.2.2.1.1 (a)] 3 ,660 mm accordance with GCC Fire Code Part-1, Section 3-16/2.
Minimum Height between Landings: Per NFPA 101 Section 7.5.3 Exterior Ways of Exit Access shall be permitted to be by means of any exterior
3 Risers balcony, porch, gallery, or roof. The long side of the balcony, porch, gallery, or similar space shall be at least 50
GCC Fire Code – Part-1 [Section 3-12]
percent open and shall be arranged to restrict the accumulation of smoke. Exterior exit access balconies shall be
Minimum Handrail Height: separated from the interior of the building by walls and opening protectives as required for corridors, unless the
900 mm
GCC Fire Code – Part-1 [3-12] For interior parts of building exterior exit access balcony is served by at least two remote stairs that can be accessed without any occupant
traveling past an unprotected opening to reach one of the stairs, or unless dead ends on the exterior exit access
Minimum Handrail Height [NFPA 101: 7.2.2.4.4.1] 865 mm do not exceed 6100 mm.
Minimum Handrail Height: Exterior exit access shall be arranged so that there are no dead ends in excess of those permitted for dead-end
1200 mm
GCC Fire Code – Part-1 [3-12] For exterior parts of building) corridors. Per NFPA 101 Section 7.2.2.6.3.1, exterior stairs shall be separated from the interior of the building by
Maximum Handrail Height: [NFPA 101: 7.2.2.4.4.4] construction with the fire resistance rating required for enclosed stairs with fixed or self-closing opening
965 mm protectives, except as follows:
[Not stated for GCC]
Minimum Clearance between Handrail and Wall: Exterior stairs serving an exterior exit access balcony that has two remote outside stairways or ramps shall be
40 mm
[GCC Fire Code – Part-1, Section 3-8] permitted to be unprotected.
Exterior stairs serving two or fewer adjacent stories, including the story where the exit discharges, shall be
permitted to be unprotected where there is a remotely located second exit.
6.6 Exit Access Travel Distance, Common Path of Travel Maximum Travel Distance
40 meters [GCC, Table 11-3]
The following requirements apply for the Exit Access Travel Distance, Common Path of Travel, and Dead-end 122 meters [NFPA, Table A7.6]
Conditions, with Automatic Sprinklers in accordance with GCC Fire Code Part-1 and NFPA 101 requirements for Common Path of Travel (measured as a direct distance)
the occupancies based on hazard classification, which are: 15 meters [GCC, Table 11-3]
30 meters [NFPA, Table A7.6]
Residential Occupancy: Dead End Corridor
7.5 meters [GCC, Table 11-3]
Maximum Travel Distance (from unit door to exit) 30 meters [NFPA, Table A7.6]
30 meters [GCC, Table 8-2]
99 meters [NFPA Table A7.6] Assembly Occupancy:
Common Path of Travel (inside unit)
10 meters [GCC, Table 8-2]
38 meters [NFPA Table A7.6] Requirements for Assembly occupancies under the GCC Code have several variables. Travel distance ranges
Dead End Corridor from 15 meters to 30 meters [GCC Code, Chapter 5]. The Common Path of Travel, measured as a direct
7.5 meters [GCC, Table 8-2] distance, ranges from 15 meters to 30 meters [GCC Code, 5-6/5]. In big multi-purpose halls, without partitions,
15 meters [NFPA Table A7.6] the common path of travel, measured as a direct distance from the most remote point in the hall to the exit, could
be increased to exceed 30 meters if the exit doors/stairs are well distributed around the building with distances in
Retail/Merchandise Occupancy: between not to exceed 60 meters [GCC Code, Chapter 5, 6/5/2]. Under NFPA, Travel Distance is 76 meters; the
Common Path of Travel and the Dead End Corridor length are both 6.1 meters. However, a Dead End Corridor is
Maximum Travel Distance not permitted under the GCC Code.
45 meters [GCC, Table 9-2]
76 meters [NFPA, Table A7.6]
In accordance with GCC Fire Code Part-1, travel distances might be increased by 50% in buildings protected by
Common Path of Travel (measured as a direct distance)
an approved, supervised automatic sprinkler system. The common path of travel for the retail/mercantile
15 meters [GCC, Table 9-2]
30 meters [NFPA, Table A7.6] occupancy, commercial/office occupancy, and car parking, is given above as direct distance between the most
Dead End Corridor remote point in the unit or space to the exit door. Therefore, as per GCC, section 3-3/1/9, the common path of
7.5 meters [GCC, Table 9-2] travel = 1.5 direct travel. The more complex factors for the GCC Code are summarized in the Tables 6-6-1 and 6-
15 meters [NFPA, Table A7.6] 6-2.
Commercial/Office Occupancy:
LOCATION NUMBER OF FLOOR CONDITION separates the two halves of the podium. However, information on the drawings is inadequate to confirm
NO YES OCCUPANTS
compliance of exiting toward Zone S10 (on the other side of the pedestrian spine), and to confirm compliance with
Common Path of Travel exiting in the opposite direction toward Zone N4.
10 ---- ----- Basement ------
(CPT)
Common Path of Travel Upper TABLE 6-6-2 GCC CODE: Common Path of Travel, Travel Distance and Dead End Condition; Storage
15 ---- ----- Buildings Category (A) (Parking Garage)
inside apartments Floors
Residential
indicated as involving discharging from the stair and out into the area behind the reception desk of the hotel. That
10 ---- 15 Mezzanine Connected to the ground floor
should be modified by so as to provide the option of exiting through the main passenger elevator lobby and
15 ---- 30 All floors In case of offices. discharging through the doors that are utilized by Stair 3. Although having both Stair 3 and Stair 6 from the same
tower utilize the same exit is by itself, not compliant with the codes; providing the option of exiting through the
Common Path of Travel
lobby should provide an acceptable level of safety, if adequate egress and safety conditions through the lobby are
from the furthest point In case of internal open staircase in
12 ---- ----- All floors properly provided and maintained. Refer to Appendix “C” for an exit diagram.
in the floor to the door the commercial buildings (offices)
of the staircase
At all stairs where there is egress both from below and from levels above, it is mandatory that provisions be made
If exits are provided in more than one
20 30 ----- Basement to prevent occupants from inadvertently passing the door that is at the level of exit discharge. In addition, it is
Travel Distance from direction
essential to confirm that the capacity of exit corridors leading from the those stairs is compliant with code
office door / shops door If exits are provided in more than one
30 45 ----- All floors requirements, including but not necessarily limited to fire ratings, separations, adequate width for the occupant
to protected exits/ stairs direction
load, and doors opening in the direction of exit discharge.
7.5 11.25 ----- All floors At dead ends.
6.8 Exit Signage
6.7 Exit Discharge
Exits are required to be marked by an approved sign that is readily visible from any direction of exit access. Exit
The exit stairs are required to extend to and provide access to a public way at the grade/ground levels. Ventilation signs are required at every door, corridor, passage or stair that is considered part of the means of egress. Access
system discharge outlet should be located as remotely as possible away from any exit discharge locations. to exits is required to be marked by approved, readily visible signs. New sign placement shall be such that no
point in an exit access corridor (escape way) is in excess of the rated viewing distance or 30 m, whichever is less,
For Zone S9 project the discharge points are as follows: From the three basement levels, all exiting is in an from the nearest sign. The lighting level is required to be not less than 55 Watt on the surface of the exit sign.
upward direction, with the exception of a very small portion commercial at the Basement 2 level, immediately Tactile signage is required be provided to meet all of the following criteria: (1) Tactile signage shall be located at
adjacent to (but separated from) the pedestrian spine. One of the two means of egress from that area is via a each exit door requiring an exit sign; and (2) Tactile signage shall read as follows: “EXIT”. [NFPA 101, Section
stair within Zone S9 (Stair 8). There is also egress via corridor in the opposite direction toward Zone S1. The 7.10.1; and GCC Fire Code Part-1, Section 3-7].
information regarding that connection is inadequate, including with regards to occupancy use beyond Zone S9,
NFPA 5000 and NFPA 101require emergency lighting facilities to provide initial illumination that is not less than an Refer to the approved Site Infrastructure and Utilities Master Plan - Fire Strategy Report, dated 26 March 2013 for
average of 10 lux at the floor and, at any point, not less than 1 lux, measured along the path of egress at floor comprehensive details of the overall site water distribution system.
level. Illumination levels are permitted to decrease to not less than an average of 6.5 lux and, at any point, not less
than 0.65 lux at the end of 1 1/2 hours. A maximum-to-minimum illumination uniformity ratio of 40 to 1 is not to be 7.2 Water Tanks for Zone S9 (Including Towers SR3, SR7A and SR7B)
exceeded. New emergency power systems for emergency lighting are required to be at least Type 10, Class 1.5,
Level 1, in accordance with NFPA 110, Standard for Emergency and Standby Power Systems. Two fire protection tanks, which are located on the top of each SR7A, SR7B and SR3 tower (Upper Tech Floors 1
3
and 2), provide a total capacity of 450 m3 (225 m each). The total duration available for each Tower is 120
The emergency lighting system is required to be arranged to provide the required illumination automatically in the 3
minutes. Two fire protection tanks, which are located on the Basement 3, provide a total capacity of 450 m (225
event of any interruption of normal lighting due to any of the following: 3
m each). The total duration available for each Tower is 120 minutes. Refer to the color coded firefighting strategy
drawings and riser diagrams (Appendix D on this report) for additional details.
Failure of a public utility or other outside electrical power supply
Opening of a circuit breaker or fuse Water tanks will be provided with water-level detectors designed to initiate supervisory signals whenever the
Manual act(s), including accidental opening of a switch controlling normal lighting facilities water-level is less than the required reserve. Water tanks will be provided with dedicated vent. Water tanks within
the buildings will be designed and installed in accordance with provisions of Section 1/1 of GCC Fire Code Part-2
6.10 Emergency Plans and NFPA 22.
Emergency plans are required for high-rise building where required by the specific occupancy chapters 12 through 7.3 Fire Pump Systems
43, which further requires that the plans shall be prepared in accordance with the requirements in NFPA 101,
Section 4.2. The emergency plans shall include the following information:
The fire pump systems for the entire Zone S9 project (Podium S09 and Towers SR7A, SR7B, SR3) consist of
eight (8) pumps. There will be a set of primary and standby electric pumps for each tower and podium. The set of
Emergency procedures
pumps serving the podium are located in Basement 3 level. The set of pumps for each tower are located in the
Methods
Preferred evacuation routes for each event, including appropriate use of elevators Upper Technical 1 of each tower. Table 7-3 shows a summary of the fire pumps. Please note that the final fire
pumps size located in Zone S09 will be determined during shop drawings preparation.
Special consideration should also be given to life safety systems including, but not limited to:
Movement of occupants to safety TABLE 7-3. Fire Pump Schedule
Control of fire and smoke
Psychological features Fire Pump Schedule
Communications systems
Elevators Location Tower Flow (gpm) Head (m) Fire pump set no.
Emergency planning, and
Overall system reliability
Upper Technical 1 SR7A 1000 92 1 (2 pumps)
The objective of the emergency plan is to protect the occupants, maintain structural integrity and ensure systems Upper Technical 1 SR7B 1000 92 1 (2 pumps)
effectiveness. In the event of various types of emergencies including but not limited to fire, weather, medical,
power loss, chemical, bomb threats or other hazards. The plan may further define Individual roles and Upper Technical 1 SR3 1000 92 1 (2 pumps)
responsibilities, notification, warning, and communications procedures, information about the location and use of
common emergency equipment and emergency shutdown procedures. Location at Podium Flow (gpm) Head (m) Fire pump set no.
The fire pump assemblies will be sized to provide the required fire water demand for the water-based fire Space Hazard Design Density Operational Area Total Combined
suppression systems including automatic sprinkler systems and standpipe systems. The pump will be sized based Classification
on the hydraulic calculations and water demand requirements referenced in GCC Fire Code Part-2, NFPA 13, Inside and
NFPA 14, and NFPA 20. Outside Hose
gpm/ft2 mm/min m2 ft2 Demand (gpm)
The fire pump system assembly and components will be UL listed and FM approved as required by Section
B2/2/5/3 in GCC Fire Code Part-2. Fire pump controllers and electrical installations and connections to the fire Restaurants Light Hazard 0.10 4.1 1500 139 100
alarm panel will be in accordance with Appendix A for Section 2/2 in GCC Fire Code Part-2, NFPA 20, NFPA 70, seating areas
and NFPA 72. Specifications and performance of the fire pump assemblies including pipes, valves and fittings
depending on the type of the fire pump assemblies will be in accordance with specifications required in Appendix Office Light Hazard 0.10 4.1 1500 139 100
B of section 2/2 in GCC Fire Code Part-2. Additional special fire pump specification requirements referenced in
Chapters 5, 6, and 7 in NFPA 20 will be also applicable. An additional jockey pump will be stored on site for quick Guest room Light Hazard 0.10 4.1 1500 139 100
replacement.
Mechanical Ordinary Hazard- 1 0.15 6.1 1500 139 250
7.4 Civil Defense Hydrants and Connection Points rooms
External fire hydrants will be utilized for firefighter operations. The hydrants will be pillar-type and will be provided Parking Ordinary hazard – 1 0.15 6.1 1500 139 250
at Road A and Road B. Refer to the approved Site Infrastructure and Utilities Master Plan - Fire Strategy Report,
dated 26 March 2013 for location of hydrant location, spacing, and fire department access roads. Laundry Ordinary Hazard -1 0.15 6.1 1500 139 250
Civil Defense connection points (breeching inlets) in the buildings will be provided for automatic sprinkler systems, Storage but do Ordinary Hazard- 2 0.2 8.1 1500 139 250
standpipe systems. Every connection point will have between 2 to 4 connections sized at 100-150 mm as required not exceed 12ft
in Section 2/1/8/1 in GCC Fire Code Part-2. The connection points will be labeled to indicate the systems and the (3.66 m) of height
zones which they serve in accordance with NFPA 24, Section 5.9.5. Each connection point will be equipped with
individual check valves that will allow each hose to be disconnected independently. The breeching inlets for S09 Kitchen Ordinary Hazard -1 0.15 6.1 1500 139 250
will be located along Road A and Road B. Refer to the Civil Access Drawings for exact location. Refer to Section
10 for further discussion. The podium floor plate will be served by three fire sprinkler zones per floor. Each sprinkler control zone will have a
floor control assembly that regulates the wet fire sprinkler system pressure and provides pressure gages, water
Note: Due to the height of the building and the limited capacity of the Civil Defense fire truck to lift water flow switches, shutoff valves, and test & drain valves.
beyond 60 meters, the use of breeching inlets supplying the podium zones only was recommended by
Civil Defense. Clear notes/signs of each breeching inlet shall be provided depending on the final design Refer to the color coded firefighting strategy drawings for location of these systems. . Final design layout and
layout. calculations will be developed by the contractor and submitted to Aon for review and approval.
7.5 Automatic Sprinkler Systems (Podium and Towers) 7.6 Standpipe System
An electrically supervised wet-automatic sprinkler system will be provided throughout S09 as required for high-rise The standpipe system for the entire project will be interconnected at the lower podium level and at the top of each
buildings in accordance with GCC Fire Code Part-1. Automatic we fire sprinkler system will not be provided in tower. The towers will have two stairs and each stair will have a standpipe riser with a Class I, 65 mm hose valve
electrical closet rooms and telephone rooms. However, these rooms will be provided with a clean agent fire connection.
suppression system.
Listed pressure regulating stations will control the system pressure to 7 bar (100 psi). Bypass check valves will be
The wet-rise automatic sprinkler systems will be designed, installed, maintained and supervised in accordance provided around the pressure regulating stations to allow the fire pumper truck(s) to pressurize the high pressure
with the most stringent requirements in NFPA 13 and Section 4/1 of GCC Fire Code Part-2. The water demand for zone during firefighting and to refill the tower water tanks. Pressure monitoring switches will indicate to the fire
automatic sprinkler system is hydraulically calculated in accordance with NFPA 13, Section 22.3 and Section 22.4. alarm control panel when a high pressure condition exists. The standpipe and hose system shall be installed to
provide full coverage in accordance with section 3/3/6/2 and section 3/3/6/3/1 in GCC Fire Code Part-2 and NFPA
The density/area curves will be used in accordance with Figure 4/1-1 in GCC Fire Code Part-2 and Figure 14, Section 7.3.2. Standpipes will be provided in the following areas:
11.2.3.1.1 in NFPA 13. The hazard classification will be based on hazard group classification for protected areas
The flame extinguishing concentration for class B fuels will be determined by the cup burner method referenced in 7.11 Fire Extinguishers
Appendix B in NFPA 2001 as referenced in Section 4/8/6/4 in GCC Fire Code Part-2 and Section 5.4.2 in NFPA
2001. The flame extinguishing concentration for class A fuels will be determined in accordance with by test as part Jabal Omar S09 podium and towers are required to be provided with manual fire extinguishers in accordance with
of the listing program and will conform to UL 2127 or UL 2166. The system will be designed to avoid unwanted Tables for special occupancy requirements in GCC Fire Code. The type of fire extinguishers will be selected in
discharge through a supervised disconnection switch. accordance with section Table 2-1 in GCC Code Part-1 and chapter 5 in NFPA 10. Spacing between fire
2
extinguishers will not exceed 20m and there will be at least one extinguisher for every 200 m .
The pipes will be in accordance with Section 4.2.1 in NFPA 2001 and will be from noncombustible materials other
than cast iron as referenced in Section 4/8/5/4 in GCC Fire Code Part-2 having physical and chemical
characteristics such that integrity under predictable stress. The storage containers will be located to be accessible
for inspection, testing, recharging, and other maintenance activities and will be located as close to the hazard as
8. Fire Alarm/Emergency Communication Systems
possible. The thickness of the piping will be calculated in accordance with ASME B31.1, including B31.1a 1999
addenda and B31.1b addenda. The internal pressure will not be less than normal discharging pressure in agent The following describes the design approach and equipment required for the installation of a new fire alarm
container at 21°C or 85% of maximum pressure in the container at maximum storage temperature not less than detection and control system for the SR7A, SR7B and SR3 high rise Towers and the S9 Podium of the Jabal
55°C. Omar Development Project. This information is to be used to prepare the design documents for the automatic fire
alarm, detection, and notification systems.
7.8 Foam-Water Spray System
A Foam-Water Spray System will be provided for fuel tank. The foam-water spray system will be a listed system
including the foam tank, proportioning system, piping, valves, pipe fittings, and hangers, detection, actuation,
8.1.1 Provision of Automatic Fire Alarm and Detection Systems All fire alarm control equipment, including devices, appliances, and associated devices that are supervised will
be required to be monitored for the integrity of the interconnecting conductors, or equivalent paths, so that the
The automatic fire alarm notification and detection systems with the required initiation, notification, and occurrence of a single open or a single ground-fault condition in the installation conductors or other signaling
communication, and associated fire and life safety systems will be installed where required in compliance with channels is automatically indicated within 200 second.
NFPA 101 2009 Edition, NFPA 5000 2009 Edition, NFPA 72 2010 Edition for high-rise areas. Operator Fire Life
Safety Standards exceeding NFPA requirements will also apply. 8.1.4 Sequence of Operation
NFPA requires guestroom corridor smoke detection for hotels, but does not require area detection throughout. A general sequence of operation for the fire alarm and the associated life safety systems is illustrated in the cause
Area detection which exceeds NFPA requirements may be provided where ambient conditions permit. and effect matrices shown in Appendix A.
8.1.2 Network Control Equipment Positive alarm sequence operation will be used for all automatic detection devices as described in NFPA 72
23.8.1.3.1.1. This sequence permits a signal from the first detector in alarm to sound an audible/visual signal at
The notification system design will also provide the ability for selective paging and evacuation capabilities to the CCMS. Operators will then 15 seconds to acknowledge the alarm. If the alarm is not acknowledged within 15
predefined zones or areas within each building or throughout the entire complex. Audible paging messages will seconds an audible and visual alarm signal will be actuated on the floor of alarm, one floor above and one floor
need to be provided in the same languages used on signage throughout Makkah. below the alarm floor. Once the acknowledged train personal will have 180 seconds to investigate and evaluate
the alarm condition and reset the panel. If no reset occurs within the 180 seconds an evacuation sequence will be
actuated. If a second detector is activated during the alarm investigation period, the evacuation sequence will be
Emergency communications systems are designed and used to provide automatic and manual communications Remote fire alarm annunciators will be required at defined locations to aid in responding to alarm events. The
information about emergencies. Two-way telephone jacks shall be provided at each elevator lobby, within each annunciators will indicate the present system status, time and date on a visible liquid crystal display (LCD) display
elevator car, in the elevator machine rooms, and each floor level inside the exit stair, fire pump rooms, elevator at all times, and allow the ability to acknowledge or reset alarm events through programmable password-protected
machine rooms, generator rooms and emergency power and standby power rooms as required by NFPA access levels.
72.24.5.1.11.
8.1.10 Fire Alarm Power Supplies
Two-way communications circuits shall be selectable from the command center either individual or by floor or
stairwell. Command for the emergency communications is located in the CCMS rooms and will be designed in Fire alarm power supplies will be required to provide synchronized 24-volt output circuits for visual notification
accordance with the requirements of NFPA 5000, Chapter 33. appliances. Normal operating power for each FACU will be from dedicated 220 VAC, single-phase, 60 Hz circuits
supplied from a building distribution power panel. Battery backup, capable of providing a minimum of 24 hours of
8.1.7 Voice Messaging System standby power to operate all alarm notification appliances as prescribed by NFPA 72 will be required. All power
supplies will provide a minimum of 20% spare capacity and be monitored for fault conditions by the FACU.
A Voice Messaging System (VMS) is required to be an integral part of each FACU and will be required to include
a paging microphone that has the ability to provide one-way voice communication. It also utilizes digital pre- Power supplies shall be mechanically protected and dedicated VAC 220 single-phase circuits shall be identified at
recorded messages transmitted to all defined alarm zones within the areas served by speakers. The VMS for both the power supply and the power distribution panel as required by NFPA 72 Chapter 10.5.
each system will also be required to have capabilities for selective paging by defined alarm zone and have an “all
call” feature to allow all defined alarm zones to be paged simultaneously. 8.2 Initiating Devices
Audio amplifiers for the VMS will be required to be provided in centrally located areas. The power output of the Intelligent alarm initiating devices for the fire alarm notification and detection systems will include point
amplifiers must be sized to provide required speakers, plus spare watts per zone for future expansion. All addressable input devices such as smoke detectors, heat detectors, combination and multi-criteria detectors.
amplifiers will require electrical supervision and listed for fire alarm signaling use. Detector type was selected based on the detector’s anticipated response to the following conditions:
The secondary power supply for the emergency voice alarm communications is supplied from the emergency Ceiling shape and surface
generator. Service will be required to be capable of operating the system under no-load or standby conditions for Ceiling height
a minimum of 24 hours and then be capable of operating the system under an emergency condition for a period of Configuration of contents in the protected area
15 minutes at the maximum connected load in compliance with NFPA 72, Chapter 24.
Combustion characteristics and probable equivalence ratio of the anticipated fires involving the fuel loads
within the protected area
8.1.8 Fire Alarm Control Equipment Compartment ventilation
Ambient temperature, pressure, altitude, humidity, and atmosphere
Each fire alarm control unit (FACU) will be required to have its own microprocessor and memory, and capable of
supervising each individual device or loop circuit such that any trouble, normal, alarm, or supervisory outputs are
Addressable manual call points will be installed. Addressable input modules will be required for monitoring non-
individually annunciated through the network system. Each loop circuit will be required to provide a minimum of
addressable input devices such as output points from supplementary systems such as sprinkler system control
10 percent expansion capability for each addressable loop to provide future expansion capabilities and
valves or other suppression systems.
construction changes. The main memory system will be required to provide display, printout, and control of 150
percent of the actual alarm and command points for each system. All basic alarm and control software will be The devices in both the logic circuitry and the communication circuitry will be protected by software against
included. Each FACU will be required to be capable of on-site programming and all data entered will reside in the undesirable effects from proximate electrical and electronic devices such as hand held radios and cellular
system. FACU shall comply with the installation guidelines referenced in the NFPA 70 and NFPA 72. telephones. Care should be taken not to install wiring directly on top of fluorescent light fixtures, variable
All guestrooms are equipped with single-station or multiple-station smoke alarms containing an integral sounder Mechanical Rooms
base horn. This sounder base horn will actuate only when the guestroom smoke alarm is in alarm. Where Electrical Rooms
guestrooms are equipped with more than one smoke alarm, upon activation of any guestroom smoke alarm all Telecommunication Rooms
smoke alarm sounder base horns within the same guestroom must actuate. The sounder bases must reset Restaurants
automatically once the smoke has cleared. Commercial Spaces
Storage Rooms
All single-station or multiple-station smoke alarms shall be in accordance with NFPA 101, Chapter 9.6.2.10., and Access Corridors
Back of House Corridors
NFPA 72 Chapters 3.3.176 and 29. The detectors are required to be listed for use in accordance with ANSI/IEEE
C2, National Electrical Safety Code, 2007. ANSI/UL 217, Standard for Single and Multiple Station Smoke Alarms,
Smoke detectors will be point addressable, programmable by the control panel, controlled by the detector
2006, revised 2008.
electronics, and provide remote indicating LEDs. Detectors will be assigned a sensitivity level for alarm threshold
by the central controller, if not programmed to respond to a specific fire occupancy profile, based on environment,
NFPA 101, Chapter 9.6.2.10.3 states where two or more smoke alarms are required within a guestroom unit,
time of day, or other programmable functions. The detectors will also respond at the level assigned whether in the
suite of rooms, or similar area, they shall be arranged so that operation of any smoke alarm shall cause the alarm
online or default mode. Activation of each smoke detector shall annunciate the point address, alarm zone, and
in all smoke alarms within the guestroom, suite of rooms, or similar area to sound. Remote annunciation is
device location at the FACU and in the CCMS.
provided at the fire alarm annunciator to identify any room where smoke detectors are in alarm. Detectors will be
remotely monitored at CCMS and will indicate a supervisory audible and visual signal at the fire alarm panel.
8.2.4 Combination and Multi-Criteria Detectors
8.2.3 Smoke Detectors Combination detectors which gather analog data information from 2 different fire sensing elements (photoelectric
and heat temperature) convert analog data into digital signals and analyzes the data signal to reduce the
Where required, smoke detectors will be installed and used to prevent smoke spread by initiating control of fans,
likelihood of false alarms. Multi-criteria detectors gather information from more than 2 different sensing elements.
dampers, doors, and other equipment in accordance with the requirements of NFPA 72, Chapter 17. The
These devices were specified in areas where nuisance alarms were more likely to occur such as electrical closets
detectors are required to be listed for use as open area protective coverage and will be insensitive to air velocity
and trolley rooms.
changes.
Multi-criteria detectors are intelligent, point addressable devices. Programmable by the control panel, these
Smoke detectors are used for the control of air moving equipment in accordance with the requirements of NFPA
detectors provide onboard indicating LEDs. Detectors will be assigned a sensitivity level for alarm threshold by
90A, Chapter 6.4. In-duct smoke sampling equipment shall be mounted in a compatible housing, or in compliance
the central controller, if not programmed to respond to a specific fire occupancy profile, based on environment,
with the manufacturer’s specifications. These detectors shall be specifically programmable as in-duct smoke
time of day, or other programmable functions. The detectors will also respond at the level assigned whether in the
detection in the software database. Smoke detectors listed for use in air distribution systems shall be installed to
online or default mode. Activation of each smoke detector shall annunciate the point address, alarm zone, and
restrict the circulation of smoke and located as follows:
device location at the FACU and in the CCMS.
Downstream of the air filters and ahead of any branch connections in air supply systems having a
capacity greater than 944 L/sec (2000 ft3/min).
Heat detectors will be used to shut down elevator power prior to sprinkler operation are addressed in NFPA 72 Active Elements Passive Elements
Chapter 21.5 and 21.6. Heat detectors shall be placed within 610 mm of each sprinkler head and be installed in
accordance with the requirements of Chapter 21.4. The detector shall have both a lower temperature rating and a Opening Protection (smoke dampers, rated doors,
Stair Pressurization Fans
higher sensitivity as compared to the sprinkler. Coordination will be required during the design phase to verify adjustable door sweeps, etc.)
compliance with approved codes and standards.
Zoned Smoke Control System (Hotel Corridors) Walls (corridors, occupancy separations, etc.)
8.4.4 Access Control and Security Systems
Elevator Pressurization Fans for the use of Makkah Residential Units separation (Rated separation between
Access control or security systems door locks compliant with NFPA 101 7.2.1.6.3.will require interlocks with the Civil Defense (MCD) fire fighters Residential Units)
building fire alarm system for unlocking exit doors. Doors requiring connection to the fire alarm system must
unlock prior to or concurrent with occupant notification and shall remain unlocked until the FACU is reset as Shafts Enclosures (stair enclosure, elevator hoistway,
Car Park Smoke Removal Systems
required by NFPA 72 Chapter 21.8. mechanical shafts, etc.)
The tower is divided into a series of compartments, or smoke zones (i.e.: separate floor levels), and sub-
9. Smoke Control Systems compartments, or sub-zones (i.e. individual guestroom units). Typically, each smoke zone is enclosed on all sides
by walls, floors, and ceilings that are referred to as smoke barriers in the code because they are assigned
minimum requirements for tightness of construction as identified in NFPA 5000, Section 8.11.
The following Smoke Control Strategy has been developed with the support of advance computer modeling,
including Computational Fluid Dynamic (CFD). A technical smoke control rational analysis report and supporting
Openings in these smoke barriers are also equipped with active and passive elements to limit the migration of
computer model results are included in the Exhibit 1 and Exhibit 2.
smoke. It is important to note that maintenance of a tenable environment within the smoke-control zone of fire
origin is not a requirement. Only walls, floors, and ceilings that are designated as separate smoke zones (not
9.1 Smoke Control Strategy and Design Concept sub-zones) within a building need to be constructed as smoke barriers. In the hotel towers, each guestroom will
be considered an individual smoke zone, separated from adjacent units and from adjacent floors by horizontal
The intent of smoke-control is to limit the migration of hazardous amounts of smoke to the zone of origin, thereby assemblies and from stairwell and elevator shaft enclosures by fire barriers.
providing a tenable environment for the evacuation or relocation of occupants. The system is intended to remain
functional during firefighting operations. The high rise hotel will be designed to meet the smoke proof exit enclosure requirements of NFPA 5000, Section
33.3.3.1 and Section 11.2.3. Similarly, the GCC Section 3-4/2 requires emergency exit stairs be separated from
It is a well-established, code-supported principle of fire protection engineering that properly designed and installed the rest of the building by barriers to prevent the spread of the fire and smoke. A minimum positive pressure
automatic sprinklers will limit smoke production in the event of a fire. While automatic sprinklers respond directly differential (12.5 Pa, per Section 5.2, NFPA 92A) will be provided between the alarm zone (smoke zone where the
to the source of the fire, the smoke control system must manage the smoke produced by the fire, which often fire alarm originated) and the exit stair. The resulting positive pressure differentials measured from the exit stair
migrates away from the source of the fire. Smoke management is therefore meant to be a combination of enclosures to the alarm zone are intended to prevent smoke migration to multiple building levels via these
1
containment and removal if necessary . potential pathways. The occupants in the hotel towers are different that the occupants in the podium areas. The
difference is related to occupants’ alertness during the course of the day. Occupants in the hotel will be asleep
In the case of the Jabal Omar Zone S9, the building is compartmentalized into a series of primarily residential while occupants in the podium (restaurant, mall, etc) will be awake and alert.
occupancies in the hotel towers. The podium portion has multiple, separated, mixed occupancies consisting of
retail, storage (i.e. parking garage), and residential (Hotel guestrooms). All these occupancies are connected An enhanced smoke control system has been developed for the Jabal Omar Projects to address this condition. A
vertically by exit stair enclosures and elevator shafts. higher degree of safety is proposed for the hotel tower due to the type of occupants. The overall smoke control
strategy takes into consideration the architectural design of the elevators. Elevators are provided without lobbies
The proposed smoke control design seeks to take advantage of this compartmentalization by implementing a in the hotel portion of the towers, while at the same time, the same elevators are provided with lobbies in the
smoke containment strategy. The overall smoke management strategy will utilize a combination of active and podium area. Essentially, this architectural design condition creates two (2) virtual zones: smoke zone (1) in the
passive components to contain hazardous amounts of smoke to the zone of fire origin. Table 9.1 provides a hotel tower where there elevators open directly into the corridors, and smoke zone (2) in the podium where the
summary of these active and passive elements. Refer to Exhibit 1, Smoke Control Rational Analysis Report for a elevators are separated with fire/smoke rated lobbies and lobby doors. Refer to Diagram 9.1 for a schematic
comprehensive Smoke Control Strategy discussion. representation of this condition.
Computer models were prepared to verify the possibility to provide elevator pressurization throughout the entire
tower (Tower + Podium). However, pressurization of the entire elevator shafts when there are two conditions
(elevators without lobby and elevator with lobbies) created an unbalanced pressure differentials. The proposed
engineered smoke control system will rely in passive separation between the elevator lobbies and the rest of the
podium floors in the virtual zone SEC-2. The virtual zone SEC-1 will rely on the corridor exhaust system to create
1 nd
Drysdale, D. An Introduction to Fire Dynamics, 2 Edition. John Wiley & Sons Ltd., Chichester: 1998. Page 397.
The hotel towers SR7A, SR7B, SR03 will have passenger elevators without lobbies (open directly into the hotel
corridor). Essentially, the hotel corridor acts as a larger elevator lobby. The elevators connect the hotel tower
floors to the podium levels floors. Refer to Diagram 9.1.1 for a typical guest room floors. Protection of elevator
hoist-ways (smoke-proof) will be provided using fire rated elevator doors (Diagram 9.1.2) and a zone smoke
control system (corridor exhaust system). The corridor exhaust system will keep the corridor under negative
pressure in relation to the elevator shaft (12.5 Pa) thus, preventing smoke from entering the elevator shafts.
Pressurization of the core passenger elevators will not be provided.
DIAGRAM 9.1: Hotel On Top of Podium – 2 Virtual smoke zones DIAGRAM 9.1.2: Fire Rated Elevator Doors (SR7A, SR7B, SR03)
DIAGRAM 9.1.5: Firefighter Elevator Pressurization (SR7A, SR7B, SR03) - Highlight in Red color
NFPA 92A, Section 1.2.1 establishes the requirements for smoke-control systems that use pressure differences
across barriers to accomplish one or more of the following:
Limit smoke from entering stairwells, means of egress, smoke refuge areas, elevator shafts, or similar areas
Maintain a tenable environment in smoke refuge areas and means of egress during the time required for
DIAGRAM 9.1.4: Corridor Exhaust and Elevator Shaft Design Concept evacuation
Inhibit the migration of smoke from the smoke zone
Provide conditions outside the smoke zone that enable emergency response personnel to conduct search and
rescue operations and to locate and control the fire
9.1.2 Hotel on Top of Podium Design Concept (Firefighter Elevator Lobby) Contribute to the protection of life and to the reduction of property loss
The hotel towers SR7A, SR7B, SR03 and podiums will be provided with dedicated firefighting elevators. The All structural components described in this section are defined as smoke barriers and will be sealed to the
firefighting elevators will be provided with lobbies. The fire/smoke rated lobbies and lobby doors provide protection maximum allowable leakage area specifications of NFPA 5000 Section 8.11.
to prevent smoke from entering into the firefighting elevator shafts. To further enhance the smoke control system,
a positive pressure differential between the elevator hoist-way and the elevator lobby will be provided by 9.2.1 Passive Barriers
pressurizing the elevator shaft. A minimum positive pressure differential (12.5 Pa, per Section 5.2, NFPA 92A) will
be provided between the elevator door and the lobby. Passive smoke barriers, which may or may not have a fire-resistive rating, could be used in addition to the active
smoke control systems to limit smoke migration from the zone of fire origin to the surrounding areas of the
9.1.3 Podium building. In the passive smoke control approach, the exit enclosures are directly pressurized to prevent an
infiltration of smoke into the path of egress. This method relies on the natural compartmentalizing effect of smoke
The 2 podium and common areas above the parking floors will be separated at each floor by horizontal barriers to assist in smoke containment.
assemblies and from stairwell and elevator shaft enclosures by fire barriers. Each level will be considered an
individual smoke zone. Barriers, and any openings in them, will minimize air leakage and restrict the passage of smoke. NFPA 92A
Section 4.6.1 and Table A.4.6.1 provides openings and leakage area ratios to be incorporated in the design or
The parking garage will also be separated by horizontal assemblies and will be separated from stairwell and passive systems.
elevator shaft enclosures by fire barriers. As required by the Gulf Co-operation Council (GCC) Fire Code Part-1,
Section 11-9/6, the parking garage will be provided with a smoke removal system. Refer to Exhibit 2, Car park The prescribed leakage ratios references on NFPA 92A, Table A.4.6.1 allow the design team to select leakage
Smoke Exhaust CFD Report for further details. rations based on tight, average, and loose construction type. The design team must be aware that selecting very
loose for fairly porous smoke barrier construction might not accurately correspond to the construction of the
project. Modern high-rise construction does not typically have such significant leakage.
Passive barriers include the following building elements: 9.4 Smokeproof Enclosure Requirements
Floor-ceiling assemblies
Corridors NFPA 5000, Section 33.3.3.1 requires all vertical exit stair enclosures to be smoke proof enclosures. Similarly, the
Shafts GCC Section 3-4/2 requires emergency exit stairs be separated from the rest of the building by barriers to prevent
Elevator lobbies the spread of the fire and smoke. Additionally, NFPA 5000, Section 33.1.3.1 allows a reduction on fire resistance
Stair enclosures rated construction when the exit stairs comply with the smokeproof enclosures requirements.
These building elements create the boundaries of defined smoke-control zones and sub-zones, and must be A smokeproof enclosure must limit the movement of products of combustion produced by a fire (NFPA 5000,
visually verified during the special inspections. Any passive barriers found not compliant will be resealed using Section 3.3.182.2). A smokeproof enclosure will be enclosed from the highest point to the lowest point by barriers
smoke barrier construction. Smoke barrier construction will be provided with opening protection. having 2-hour fire resistance ratings. Where a vestibule is used, it will be within the 2-hour-rated enclosure and will
be considered part of the smokeproof enclosure (NFPA 5000, Section 11.2.3.3)
9.2.2 Openings in Smoke Barriers
The smokeproof enclosure will be permitted to be created by using natural ventilation, by using mechanical
In accordance with NFPA 5000, Section 8.11.4.2, openings in smoke barriers will be protected by self-closing ventilation incorporating a vestibule, or by pressurizing the enclosure (NFPA 5000, 11.2.3.2). The project will use
devices or automatic-closing devices (such as smoke dampers) actuated by the required controls for the smoke- a mechanical pressurization approach to comply with the smokeproof enclosure requirements.
control system. All door openings in smoke barriers will be protected by tight fitting smoke and draft-control
assemblies having a fire-protection rating of not less than 20 minutes when tested in accordance with NFPA 252. Every smokeproof enclosure will discharge into a public way, into a yard or court having direct access to a public
way, or into an exit passageway. Such exit passageways will be without openings other than the entrance from
Doors in exit enclosures and other rated assemblies must comply with NFPA 5000 Section 8.7.5.2 requirements. the smokeproof enclosure and the door to the outside yard, court, or public way. The exit passageway will be
Such doors will not have louvers, mail slots, or similar openings. The door and frame will bear an approved label separated from the remainder of the building by a 2-hour fire resistance rating (NFPA 5000, Section 11.2.3.5).
or other identification showing the name of the manufacturer, the name of the third-party inspection agency, the
fire protection rating and, for fire doors in exit enclosures and exit passageways, the maximum transmitted 9.4.1 Smokeproof Enclosure Access
temperature end point.
For smokeproof enclosures, other than those consisting of a pressurized enclosure complying with 11.2.3.9,
In accordance with NFPA 105, Section 4.5.6.1 Smoke door assemblies installed where pressurization is provided access to the smokeproof enclosure will be by way of a vestibule or by way of an exterior balcony (NFPA 5000,
to restrict smoke movement will be required to have a bottom seal. Section 11.2.3.6). As noted above, a pressurization method is proposed for this project, which is an alternate
method to providing smoke proof enclosures.
Doors will be self-closing or will be automatic closing by actuation of a smoke detector in accordance with NFPA
5000, Section 11.2.1.8. Smoke and draft-control door assemblies will be provided with a gasket installed to Therefore, stair vestibules are not required to comply with the provision of smokeproof enclosures. However, this
provide a seal where the door meets the stop on both sides and across the top. project has stairs with vestibules. When a vestibule is provided, the doorway into the vestibule will be protected
with an approved fire door assembly having a 1-1⁄2-hour fire protection rating, and the fire door assembly from the
9.3 Active Smoke Control Systems Strategy vestibule to the smokeproof enclosure will have not less than a 20-minute fire protection rating. Doors will be
designed and installed in accordance with NFPA 105 to minimize air leakage in accordance with NFPA 5000,
In accordance with NFPA 92A, Section 4.3 the design approach for active smoke control systems will be one or a Section 11.2.1.1.4 and will be self-closing or will be automatic-closing by actuation of a smoke detector within 3.05
combination of the following: meters (10 feet) of the vestibule door (NFPA 5000, Section 11.2.3.4)
Stairwell pressurization
Zoned smoke control (Corridor Exhaust) 9.4.2 Smokeproof Pressurization Method
Firefighter’s Elevator Pressurization
Car Park Ventilation and smoke removal Smokeproof enclosures using pressurization will use an approved engineered system with a design pressure
difference across the barrier of not less than 12.5 Pa (0.05 inch) water column in sprinklered buildings (NFPA
Consider a fire inside of a single standalone room or area. As the fire develops, so too does the production of 5000, Section 11.2.3.9.1). The above mentioned pressure difference must be capable of maintained under likely
smoke inside the room. The rate of fire development, determined by the burning rate, is determined primarily by conditions of stack effect, wind, and interaction with other active smoke control systems.
the relative amounts of fuel and oxidizer in the room as well as the presence of automatic sprinklers. It is a well-
established, code-supported principle of fire protection engineering that properly designed and installed automatic
sprinklers will severely limit smoke production in the event of a fire. While automatic sprinklers respond directly to
2 3 nd
Klote, John & Milke, James. Principles of Smoke Management. W. Stephen Comstock, ASHRAE: 2002. Drysdale, D. An Introduction to Fire Dynamics, 2 Edition. John Wiley & Sons Ltd., Chichester: 1998. Page 397
In accordance with NFPA 5000, Section 11.2.3.9.2, equipment and ductwork for pressurization will be located as The factors involved with design and analysis of stairwell pressurization systems are:
follows: Building and Stairwell height
Exterior to the building and directly connected to the enclosure by ductwork enclosed in noncombustible or Flow areas of building components
limited-combustible construction Minimum and maximum deign pressure differences,
Within the enclosure with intake and exhaust air vented directly to the outside or through ductwork enclosed Atmospheric pressure, building temperature, stairwell temperature, and outdoor temperature (Summer/Winter
by a 2-hour fire resistance–rated separation Conditions)Type of stairwell pressuring system
Within the building, under the following conditions: Wind effects and smoke feedback
– Where the equipment and ductwork are separated from the remainder of the building, including other
mechanical equipment, by a 2-hour fire resistance–rated separation. For buildings with pressurized stairwells and other pressurization smoke control systems, analysis of these
– Where the building, including the enclosure, is protected throughout by an approved, electrically systems must be done considering all of the pressurization system operation together as they would during a fire.
supervised automatic sprinkler system installed in accordance with Section 55.3, and the equipment and This comprehensive analysis is required because the pressurization smoke control systems in a building interact
ductwork are separated from the remainder of the building, including other mechanical equipment, by not with each other and the overall air flow paths a very complex. Therefore, for buildings with multiple pressurization
less than a 1-hour fire resistance–rated separation. smoke control systems, analysis using CONTAM is required.
In all cases specified above, the openings into the required fire resistance–rated separations will be limited to 9.5 Elevator Pressurization
those needed for maintenance and operation and will be protected by self-closing fire protection–rated devices
(NFPA 5000, Section 11.2.3.9.3). 9.5.1 Elevator Hoistway Smokeproof Requirements
9.4.4 Smoke-proof Pressurization Power Requirements The GCC Part-1, Chapter 4, Section 6/5/2 requires smoke and fire be prevented from entering the elevator
hoistways and spreading vertically to upper floors. GCC 4-6/5/6 also requires ventilation for elevator hoistways to
In accordance with NFPA 5000, Section 11.2.3.12, emergency power supply system (EPSS) is required for dispose smoke in case of fire. The Phase I or Phase II elevator recall levels for both, passenger and fire fighter’s
smokeproof pressurization systems. A Type 60, Class 2, Level 2, EPSS for will be provided in accordance with elevators must be carefully analyzed when pressurization of elevator hoistways are provided.
NFPA 110.
The requirement from GCC and NFPA 5000 are somewhat similar when it comes to providing fire fighter’s
The generator will be located in a room having a minimum 1-hour fire resistance–rated separation from the elevator protection. However, the requirements for passenger elevators between the NFPA 5000 and GCC do not
remainder of the building. The generator will have a fuel supply not less than that which is adequate to operate the agree. The core passenger elevators and the fire fighters elevators will be designed as described in the following
equipment for 2 hours. The transfer switch equipment and the standby panel board will be located in a room sections
having a minimum 1-hour fire resistance–rated separation from the remainder of the building and normal electrical
equipment. 9.5.2 Core Passenger Elevator Design Concept
Elevator hoistways typically require a minimum positive pressure of 12.5 Pa (0.05 inches of water) and a
9.4.5 Smokeproof Door Requirements
maximum positive pressure will be determined based the door closing forces.(NFPA 92A, Section 5.2). However,
as discussed in Section 9.1, the overall smoke control strategy for Jabal Omar projects takes careful consideration
In accordance with NFPA 5000, Section 11.2.1.4.5, the door leaf operating forces required to fully open any door
of the architectural design of elevators. The passenger core elevators in the hotel tower will not be provided with
leaf manually in a means of egress will not exceed 67 N (15 lbf) to release the latch, 133 N (30 lbf) to set the door
elevator lobbies because they are open directly into the rated corridors, which act as lobbies. Furthermore, the
leaf in motion, and 67 N (15 lbf) to open the door leaf to the minimum required width, unless otherwise specified
corridors in the hotel towers will have a zoned smoke control system as discussed further on the report.
as follows:
The forces specified in 11.2.1.4.5 will be applied at the latch stile.
The core passenger elevator will be provided with elevator lobbies in the portion of the podium to separate the
Opening forces for interior side-hinged or pivoted swinging door leaves without closers will not be more than
elevator from other occupancies. Computer models have been developed to validate the proposed design and to
22N (5 lbf).
validate the performance of the pressurization of the elevators, stairs, and the zoned smoke control systems.
The opening forces for power-operated door leaves will be as provided in NFPA 5000, Section 11.2.1.9 as
follows:
GCC 4-6/5/6 requires elevator hoistway vents. NFPA 5000, Section 54.9 requires hoistways of elevators and
Where means of egress door leaves are operated by power upon the approach of a person, or are provided
dumbwaiters penetrating more than three stories to be provided with a means of venting smoke and hot gases to
with power-assisted manual operation, the design will be such that, in the event of power failure, the door
the outer air in case of fire. A separate mechanical ventilation to remove the smoke from the elevator hoistway as
leaves open manually to allow egress travel or close when necessary to safeguard the means of egress.
required by GCC will not be provided. The engineered smoke control system (Corridor Exhaust) is intended to
The forces required to manually open the door leaves specified in 11.2.1.9.1 will not exceed those required in
limit smoke spread into the elevator hoistway.
11.2.1.4.5, except that the force required to set the door leaf in motion will not exceed 50 lbf (222 N).
A separate mechanical ventilation to remove the smoke from the elevator hoistway as required by GCC will not 9.7.1 Zoned-Smoke Control Design Concept
be provided for the service elevator or the fire fighter’s elevator. Use of elevator lobbies and pressurization of the
elevator shaft will prevent smoke entering the elevator hoistway. In a zoned smoke control, a building is divided into multiple zones, each separated from others by barriers. In the
event of a fire, the zone with the fire is called the smoke zone, and the other zones are called the non-smoke The
GCC 4-6/5/6 requires elevator hoistway vents. NFPA 5000, Section 54.9 requires hoistways of elevators and methods to treat the smoke zone and the zones surrounding the smoke zone are mechanical exhaust and passive
dumbwaiters penetrating more than three stories to be provided with means of venting smoke and hot gases to smoke control using smoke barriers.
the outer air in case of fire. The fire fighter’s elevator serve the entire building will not have a vent on the top or
the vents (if provided) will be closed upon pressurization of the elevator hoistway in accordance with NFPA 5000, Typically, a mechanical pressurization of surrounding zones has a negative impact on the pressure differences
Section 54.9.3 across the stairwell doors. This is specially the case for tall buildings (over 10 stories). The reason for the
negative impact is because the exhaust of the smoke zone increases the pressure difference across pressurized
stairwell doors on the floor of the smoke zone. Also, pressurization of the surrounding zones decreases the
9.6.1 Computational Modeling Scenarios pressure difference across pressurized stairwell door on these floors. This complex pressure differences can lead
to a negative pressure difference on the floors that are pressurized. A negative pressure difference has the
The pressure difference criteria listed in Table 9.7.1 will be used, and these criteria are consistent with pressure potential for a system failure.
differences requirements in the NFPA 5000 and NFPA 92A. The minimum pressure difference criteria are
intended to prevent smoke flow into the elevator shafts and stairwells. The maximum pressure difference criteria The possibility of failure of the stair pressurization must be taken into consideration for high rise building when
for stairwells are intended to prevent excessive door opening forces. The maximum pressure difference criterion supplemental or enhanced smoke control protection is proposed. A complete computer analysis of a zoned smoke
for elevators is intended to prevent the elevator doors from jamming. control system working in balance with the stair pressurization, elevator lobby pressurization, and fire fighter’s
elevator and lobby pressurization must be performed. This analysis is required because all four pressurization
Table 9-5-1 Minimum Pressure Differentials systems in a building interact with each other. The overall pressure and flows can be very complex and extremely
difficult to balance during final testing and commissioning.
Active Smoke Control System Minimum Pa
(in. H2O) 9.8 Parking Garage Ventilation
Pressurized Elevators Shaft 12.5 (0.05) NFPA 5000, Section 30.8.5.2; NFPA 101, Section 42.8.3.1.1.3; and NFPA 88A, Section 5.3.2 requires all
enclosed parking structure be ventilated by a mechanical system. Specifically, the mechanical ventilation system
Pressurized Stairs 12.5 (0.05) must be capable of providing a minimum of 300 L/min per sq.ft. of floor area (1 cfm per sq.ft. of floor area) during
hours of normal operation.
Zoned Smoke Control (Corridor Exhaust) 12.5 (0.05)
The objective of the referenced NFPA Codes and Standards requirements is to avoid excessive carbon monoxide
The maximum allowable pressure difference shall not result in door-opening forces concentrations during normal operations only. Additional requirements for occupancy safety or post fire,
exceeding the requirements of NFPA 92A, Section 5.2.2 and Table A.5.2.2. A firefighting operations is not covered in the NFPA standards.
maximum door-opening force is specified at 30 lbf.
Table 11-7 in Part-1 of GCC Fire Code indicates that a ventilation system is required to conform with international The design team has opted to use mechanical cross ventilation using jet fans. A computer model has been
standards acceptable to Civil Defense. The design team has opted to use the British Standards to comply with the provided to verify that the proposed exhaust fan locations, location of makeup air fans, and the number of jet fans
ventilation requirements outlined in the GCC Fire Code. meet the design intent. Refer to Exhibit 2 for details of the jet fan computer models.
9.8.1 Car Park Ventilation Standards 9.9 Quality Assurance for Smoke Control Systems
The British Building Regulations Standards, regarding to the car parks, closely matches the specific requirements NFPA 5000, Section 40.6.1 requires a quality assurance program for the installation and operation of smoke
in the GCC Chapter 11, Section 6. Therefore, the design team has chosen to provide a smoke removal in control systems. This quality assurance program must be prepared by the mechanical engineer of record. Also,
accordance Approved Document B-2006 edition and Approved Document F. Section 40.6.1.1 requires special tests and inspection of smoke control systems.
The performance and calculation methods for the ventilation system will be in accordance with BS 7346-7. Also, The special inspections and testing must include testing during erection and prior to concealment of ductwork for
the specifications, performance acceptance, and handover of the mechanical ventilators in the car-park areas are the purposes of identifying leakage and recording the actuating device location. In accordance with Section
recommended to be in accordance with BS EN 12101-3. 40.6.2, the testing and inspection agents for smoke control systems will have expertise in fire protection
engineering and mechanical engineering and will be certified as air balancers.
9.8.2 Car Park Smoke Removal Design Criteria
The Approved Document B-2006 edition and Approved Document F-2010 edition of the British Building
Regulations provide specific design guidelines for ventilation of car parks. The Approved Document B, Section 10. Civil Defense Access
11.6 requires basement car parks and enclosed car parks be provided with mechanical ventilation. The
mechanical ventilation must comply with the following: 10.1 Civil Defense Road Access
The system will be independent of any other ventilation system (other than any system providing normal Approved Civil Defense fire access roads will be provided in accordance NFPA 5000, Section 7.1.5 and the GCC
ventilation to car park). The ventilation system must be designed to operate at 10 air changes per hour during Fire Code Part-1. Due to the topography of Makkah, there may be nonnegotiable grades and other conditions
fire condition as referenced in Approved Document F. where compliant fire access roads are not practical to construct. Therefore, the authority having jurisdiction shall
The system will be designed to run in two parts, each part capable of extracting 50% of the required rates and be consulted to determine if they require additional fire protection features for such areas.
designed to operate single or simultaneously.
Each part of the system will have independent power supply which will operate in the event of failure of the Makkah Civil Defense require access to more than a single facade of PH4 - S9 podium depending based on the
main power supply. height of the building as referenced in Section 1-5/6/1 in GCC Fire Code Part-1. This is necessary to ensure
Exhaust fans should be rated to run at 300οC for a minimum of 60 minutes and the ductwork and fixings must building access from a secondary point and in the event that access by a single road is impaired by vehicle
be constructed from materials having a melting point not less than 800οC. Further information on the hot congestion, condition of terrain, climatic conditions, or other factors that could limit access. Fire access roads shall
smoke removing equipment is referenced in BS EN 12101-3. have an unobstructed width of not less than 6.100 m and an unobstructed vertical clearance of not less than 4.5 m
in accordance with the NFPA 5000, Section 7.1.5.2.5 and section 1-5/6/1 in GCC Fire Code Part-1. NFPA 5000
The BS 7346-7, Section 4.1 outlines three design objectives: Section 6.1.5.2 requires access to the nearest building entry point to be within 15 meters of at least one exterior
door and the road access shall be provided such that any portion of the exterior wall of the first floor of the building
Clearance of smoke during the fire and after the fire has been suppressed, smoke removal to assist in is not more than 46 meters from the access road. Where the access roads pass through a tunnel or bridge a
checking for secondary seats of fire, as well as returning the building at its normal use. vertical clearance shall be permitted to be reduced, provided such reduction does not impair access by the fire
Creating and maintain a smoke-free route through the car park open space on the fire’s story for firefighters to apparatus. Approved signs are required to be installed and maintained indicating the established vertical
approach the car on fire, with the intention of facilitating manual fire suppression. clearance. The current and potential future type of fire apparatus in use in Makkah should be confirmed to ensure
Protection of escape routes for occupants within the same story as the car on fire, to reserve a smoke-free proper clearances are provided.
path to either the exterior of the building, or to a protected stairwell which leads to a final exit to a place of
safety. Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus up
to 40 ton per vehicle and shall be provided with an all-weather driving surface. The turning radius of a fire access
The design team has opted to select the first option: Clearance of smoke during the fire and after the fire has road shall be not less than 9 m (18 m diameters) in accordance with section 1-5/6/2/2 in GCC Fire Code Part-1.
been suppressed, smoke removal to assist in checking for secondary seats of fire, as well as returning Dead-end fire access roads in excess 46 m in length shall be provided with approved provisions for the fire
the building at its normal use. apparatus to turn around.
The BS 7346-7, Section 4.2 indicates that where the objective is to achieve clearance by horizontal cross flow
through the car park story one of the following may be used:
The standby power system is designed to have a capacity and rating sufficient to supply all required equipment.
Selective load pickup and load shedding are permitted. The standby power system is designed to provide 8 hours
of power supply to the following:
Electric fire pump
Jockey pump
Air compressor serving dry-pipe and pre-action systems.
Emergency command center equipment and lighting
Not less than one elevator serving all floors, with standby power transferable to any elevator
DIAGRAM 10.4: S9 Fire Command Center
Mechanical equipment for smokeproof enclosures
Additionally, below table provide additional details for emergency and standby power supply requirements for life The design team has elected to pressurize the fire fighter’s elevators hoistways serving the hotel as a strategy to
safety systems: comply with GCC Section 4-6/5/2. The fire firefighter’s elevator lobby will also be pressurized to comply with NFPA
5000, Section 54.12.2.4 and GCC 4-6/5/3.
Fire detection and Alarm Type O Class 24 Level 1
Emergency lighting system Type 10 Class 1.5 Level 1 11.2.3 Elevator Recall
The ANSI/ASME A17.1 Section 2.27.3.1 requires Phase 1 emergency recall operation, whether manually or
Emergency generators and a central battery system will provide the standby power for the required fire and life automatically, be activated by detectors at each floor served by the elevator. Only smoke detectors in the elevator
safety systems. lobbies must initiate the recall to a designated level. If the detector in the designated level activates, recall must
be to the alternate level. The designated level is typically the main floor or other floors level that best serves the
11.2 Passenger and Firefighter’s Elevators needs of emergency personnel for firefighting or rescue purposes identified by Civil Defense.
11.2.1 Passenger Elevators The core passenger elevator will have a Phase I recalled to an approved location. Elevator recall levels are
provided in Table 11.2.3 for coordination. However, the final recall elevator levels for both, passenger and fire
GCC Part-1, Chapter 4, Section 6/5/2 requires smoke and fire be prevented from entering the elevator hoistways fighter’s elevators will be coordinated with the elevator pressurization system and Civil Defense. The fire fighter’s
and spreading vertically to upper floors. GCC 4-6/5/3 requires elevators be provided with an elevator lobby elevator will have a Phase I recalled to the Main Entrance or Hotel lobby (Level 316). The elevator recall level will
separated from the rest of the building with resistance rating walls and doors. GCC 4-6/5/6 also requires have direct access to the fire command center and it will be easily accessible from the street level along Road A.
ventilation for elevator hoistways to dispose smoke in case of fire. Refer to Appendix C for Elevator Recall Levels Tables.
NFPA 5000 does not have requirements for elevator lobbies unless elevators are used as an evacuation system
(NFPA 5000, Section 54.12.2.3). The elevators in the hotel Towers for S07A, S07B, SR03 will not have a lobby. 12. Conclusion
The design team has elected to use a combination of rated elevator doors and corridor exhaust in the hotel portion
as a strategy to comply with Section 4-6/5/2.
This report summarizes the fire safety requirements for Jabal Omar Zone S9 and explains the strategy to achieve
the required fire and life safety level. The report compares the applicable provisions of NFPA Codes and
11.2.2 Fire Fighter’s Elevators Standards with GCC Fire Code requirements to assist Makkah Civil Defense in deciding about design acceptance
based on the conditions of the project. This document on its own is not sufficient to approve the Jabal Omar Zone
GCC Part-1, Chapter 8, Table 8-4C requires Residential buildings of Category (C), buildings consisting of rented S09. The information herein must be supported by the design review comments, the required fire strategy
or non-rented sleeping rooms such as hotels and furnished apartments, be provided with fire fighter’s elevators drawings, and the improved fire protection systems drawings to confirm the project compliance with the applicable
when the building height exceeded 6 floors or 20 meters or whichever less. For all buildings over 28 meters (92 requirements.
feet), GCC Chapter 4, Section 6/5/2 requires fire fighter’s elevators.
Aon Fire Protection Engineering Corporation
For high-rise buildings over 36.6 meters, NFPA 5000, Section 33.3.7 requires one fire fighter elevators. This
requirement is furthermore emphasized in NFPA 5000, Section 54.12.1 which requires every floor in a high-rise
building to be served by a fire fighter’s elevator. The lift capacity should be a minimum 1588 kg.
Gamal Ahmed, PhD
Note: Special requirement from Civil Defense for Phase 4, S09 requires two (2) dedicated firefighter
elevators. Thus, each hotel tower will have two elevators dedicated for Civil Defense Access.
Project Manager
Fire fighter’s elevator will have an elevator lobby in accordance with NFPA 5000, Section 54.12.2.1. Fire fighter’s
elevators will be installed in accordance with NFPA 5000 Chapter 54 and ASME A17.1, Safety Code for Elevators
and Escalators.
NFPA 5000, Section 54.12.2.4 requires fire fighter’s elevator lobbies to be enclosed with a smoke barrier having a
minimum 1-hour fire resistance rating. In accordance with Section 54.12.2.4, the elevator lobby door will have a Jaime Paucar, P.E.
fire protection rating of not less than a 3/4 hour (45 minutes) and will be self-closing or automatic closing.
However, the enclosed fire fighter’s elevator lobbies are not required at the street floor. Project Manager
A minimum of one of the fire fighter’s elevators shall be sized and arranged to accommodate a 610 mm × 1930
mm ambulance stretcher in the horizontal, open position for fire fighter emergency operation to all floors. The
Fire Safety Strategy Report – Phase 4, Zone S9, Appendix A 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page A
RECALL)
TAMPER
WATER FLOW
OPEN CIRCUIT
LOW BATTERY
RECALLFLOOR.
GROUND FAULT
FIRE PUMP RUN
AC POWER FAILURE
TELEPHONE LINE FAULT
OR ALTERNATE FLOOR.
KITCHEN HOOD SYSTEM
Makkah, Saudi Arabia
MANUAL PULL STATIONS
DUCT SMOKE DETECTORS
FIRE PUMP LOSE OF PHASE
Jabal Omar Development
FIRE PUMP PHASE REVERSAL
GUESTROOM SMOKE ALARMS
CARBON MONOXIDE DETECTORS
GENERAL MATRIX PREPARED BY
NOTIFICATION APPLIANCE SHORT CIRCUIT
AON FIRE PROTECTION ENGINEERING
CLEAN AGENT SYSTEMS ‐ GENERAL ALARM
REMOTE POWER SUPPLY TROUBLE CONTACT
(1) ONE HEAT DETECTOR OR SMOKE DETECTOR
SYSTEM INPUTS
HEAT DETECTORS IN ELEVATOR MACHINE ROOM AND SHAFT
FIREMAN'S ONE‐WAY COMMUNICATIONS MICROPHONE
THE ELEVATOR TO THE SECONDARY OR ALTERNATE RECALL FLOOR
TROUBLE CONDITION ON ALL SUPWEVISED SUPPRESSION SYSTEMS
THE ELEVATOR TO THE PRIMARY OR DESIGNATED RECALL FLOOR LEVEL], SMOKE
DETECTORS IN THE TOP OF SHAFT AND ELEVATOR MACHINE ROOM (SECONDARY
WHERE THE ELEVATOR MACHINE ROOM IS LOCATED ON THE GOUND FLOOR THEN
GROUND FLOOR LOBBY SMOKE DETECTORS FOR RESIDENTIAL TOWERS AND PODIUM
ELEVATORS WITHIN THE SAME ELEVATOR BANK ON THE GROUND LEVEL, SHALL RECALL
THE SAME ELEVATOR BANK ON ALL FLOORS EXCEPT THE GROUND LEVEL, SHALL RECALL
SYSTEM OUTPUTS
ELEVATORS OPERATED WITHIN THE MACHINE ROOM TO THE PRIMARY OR DESIGNATED
ACTIVIATION OF SUCH DEVICES SHALL RECALL THE ELEVATOR BANK TO THE SECONDARY
TWO (2) SMOKE DETECTORS OR ONE (1) HEAT DETECTOR AND ONE (1) SMOKE DETECTOR
LOBBY SMOKE DETECTORS FOR RESIDENTIAL TOWERS AND PODIUM ELEVATORS WITHIN
EXCEPTION: WHEN THE ELEVATOR MACHINE ROOM IS LOCATED ON THE GROUND LEVEL.
SMOKE DETECTORS IN THE TOP OF SHAFT AND ELEVATOR MACHINE ROOM SHALL RECALL
ACTIVATE GENERAL ALARM AUDIBLE/VISUAL SOUNDER/INDICATOR AT
FIRE ALARM CONTROL UNIT (FACU), THE COMMAND CENTER
X
X
X
X
X
X
X
X
X
MONITERING SYSTEM ROOM (CCMS), AND THE MAIN COMMAND
CONTROL CENTER (MCCC)
ACTIVATE SUPERVISORY ALARM AUDIBLE/VISUAL SOUNDER/INDICATOR
X
X
X
X
X
X
X
X
X
AT THE FACU, THE COMMAND CENTER MONITERING SYSTEM ROOM
(CCMS) AND THE MAIN COMMAND CONTROL CENTER (MCCC)
ACTIVATE TROUBLE ALARM AUDIBLE/VISUAL SOUNDER/INDICATOR AT
Fo
X
X
X
X
X
X
X
THE FACU, THE COMMAND CENTER MONITERING SYSTEM ROOM
(CCMS,) AND THE MAIN COMMAND CONTROL CENTER (MCCC)
ACTIVATE POINT INDENTIFICATION VISUAL INDICATOR AT THE FACU
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
rG
AND GRAPHIC USER INTERFACE (GUI) AND RECORD THE EVENT IN THE
SYSTEM MEMORY
X
ACTIVATE EXTERIOR SPRINKLER WATERFLOW ALARM
ui
ACTIVATE THE VISUAL AND AUDIBLE ALARM NOTIFICATION DEVICES ON
THE FIRE FLOOR, ONE (1) FLOOR ABOVE AND ONE (1) FLOOR BELOW
X
X
X
IMMEDIATELY. IN TOWERS UTILZING BOTH HORNS AND SPEAKERS,
da
HORNS SHALL BE SCHYNRONIZED SO THAT THEY DO NOT INTERFERE
WITH THE PRE‐RECORDED VOICE MESSAGE.
X
X
X
X
X
X
ACTIVATE POSITIVE ALARM SEQUENCE
nc
X
e ACTIVATE THE VISUAL AND AUDIBLE ALARM NOTIFICATION DEVICES ON
THE FIRE FLOOR AFTER POSITIVE ALARM SEQUENCE TIME OUT. N
X
TOWERS UTILZING BOTH HORNS AND SPEAKERS, HORNS SHALL BE
SCHYNRONIZED SO THAT THEY DO NOT INTERFERE WITH THE PRE‐
RECORDED VOICE MESSAGE.
O
TRANSMIT TROUBLE SIGNAL COMMAND CENTER MONITERING SYSTEM
CONCEPTUAL FIRE ALARM SEQUENCE OF OPERATION ‐ FOR SMOKE CONTROL SEQUENCE, REFER TO THE "RATIONAL ANALYSIS SMOKE CONTROL REPORT"
X
X
X
X
X
X
ROOM (CCMS) AND THE MAIN COMMAND CONTROL CENTER (MCCC)
nl
y
ACTIVATE THE DESIGNATED RELAY OUTPUT FOR ASSOCIATED AHU'S
X
X
X
X
X
X
X
AND FAHU'S IMMEDIATE SHUTDOWN
CLOSE ALL DESIGNATED DOORS AND DAMPERS ASSOCIATED WITH THE
X
X
X
X
X
X
FIRE FLOOR, ONE FLOOR ABOVE AND ONE FLOOR BELOW.
SHUTDOWN THE PUBLIC ADDRESS, AV AND MATV SYSTEMS AND
X
X
X
SEPRATE LOCAL SOUND SYSTEMS IN THE BUILDING
START SMOKE CONTROL SEQUENCE ‐ SEE SMOKE CONTROL SEQUENCE
X
X
X
X
X
X
MATRIX
ACTIVATE SOUNDER BASES ON ALL SMOKE ALARMS WITHIN THE SAME
X
GUESTROOM
X
ACTIVATE CARBON MONOXIDE AUDIBLE ALARM ON DEVICE.
X
ACTIVAT ELEVATOR SHUNT TRIP
X
SHUNT ALL HORNS DURING LIVE VOICE ANNOUNCEMENTS
X
ACTIVATE KITCHEN HOOD NOTIFICATION DEVICES
X
FOLLOW THE CLEAN AGENT SEQUENCE OF OPERATIONS
Appendix B – Elevator Recall Levels
Fire Safety Strategy Report – Phase 4, Zone S9, Appendix B 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page B
Jabal Omar Development (Phase VI) ‐ Elevator Recall
S07A, S07B, SR03
Fire Safety Strategy Report – Phase 4, Zone S9, Appendix C 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Makkah, Saudi Arabia Appendix C
:ĂďĂůKŵĂƌൟWŚĂƐĞϰൟŽŶĞƐ^Ϭϵൟ^ƚĂŝƌŝĂŐƌĂŵ
8SGDWHG'HFHPEHU
0& љ љ љ ї ([LWWRH[WHULRU
0& љ љ љ ј ([LWXSVWDLU
8SSHU7HFKQLFDO љ љ љ љ љ љ љ ([LWGRZQVWDLU
љ љ љ љ љ љ
љ љ љ љ љ љ
7\SLFDO)ORRU
љ љ љ љ љ љ
љ љ љ љ љ љ
7RZHU
љ љ љ љ љ љ
/RZHU7HFKQLFDO љ љ љ љ љ љ
&RPPHUFLDO љ љ љ љ љ љ љљ љ
&RPPHUFLDO љ љ љ љ љ љ љ љ
&RPPHUFLDO љ љ ї љљ ї љ љ љ
&RPPHUFLDO љ љ љ ј љ ј љ љ љ
*URXQG)ORRU ї ї ї ї ї ј ї ї ї
%DVHPHQW ј ј ј ј ј ј ј ј
%DVHPHQW ј ј ј ј ј ј
%DVHPHQW ј ј ј ј ј ј
6WDLU1R ϭ ϭϯ Ϯ ϱ ϰ ϯ ϲ ϳ ϴ ϵ
Appendix D – Firefighting Riser Diagrams (For Reference Only)
Fire Safety Strategy Report – Phase 4, Zone S9, Appendix D 9 March 2015
Jabal Omar Development Aon FPE No. 2814011-000
Makkah, Saudi Arabia Page D
NOTES:
rmc
Owner / Developer
Project Manager
Conceptual Designer
ATELIERS LION
ARCHITECTES URBANISTES
ARCHITECTS, URBAN DESIGNERS
INGEROP INTERNATIONAL
ENGINEER CONSULTANT
Main Consultant
Hotel ID Consultant
Project:
MAKKAH AL MUKARRAMAH
VOLUME = 225m³
VOLUME = 230m³
rmc
Owner / Developer
Project Manager
Conceptual Designer
ATELIERS LION
ARCHITECTES URBANISTES
ARCHITECTS, URBAN DESIGNERS
INGEROP INTERNATIONAL
ENGINEER CONSULTANT
Main Consultant
Hotel ID Consultant
Project:
MAKKAH AL MUKARRAMAH
rmc
Owner / Developer
Project Manager
Conceptual Designer
ATELIERS LION
ARCHITECTES URBANISTES
ARCHITECTS, URBAN DESIGNERS
INGEROP INTERNATIONAL
ENGINEER CONSULTANT
Main Consultant
Hotel ID Consultant
Project:
MAKKAH AL MUKARRAMAH
rmc
Owner / Developer
Project Manager
Conceptual Designer
ATELIERS LION
ARCHITECTES URBANISTES
ARCHITECTS, URBAN DESIGNERS
INGEROP INTERNATIONAL
ENGINEER CONSULTANT
Main Consultant
Hotel ID Consultant
Project:
MAKKAH AL MUKARRAMAH
Fire Safety Strategy Report – Phase 4, Zone S9, Appendix D 9 March 2015
Jabal Omar Development Aon FPE No. 2814011-000
Makkah, Saudi Arabia Page E
Page Left Intentionally Blank
Exhibit 1 – Smoke Control System
Rational Analysis and Technical
Report
Jabal Omar Development Project
9 March 2015
Submitted by:
t +9714.228.2841 |f +9714.228.2965
www.aonfpe.com
Prepared for:
Jabal Omar Development Company (Client)
Makkah, Kingdom of Saudi Arabia
14.3 Dampers 10
Table of Contents 15. Activation of System 10
15.1 Automatic Activation 10
1. Introduction 1
15.2 Manual Activation 10
2. Applicable Codes 1 16. Supervision 10
3. Project Description 1 17. Secondary Power 10
4. Proposed Design 2 18. Passive Smoke Barrier Construction 10
5. Exit Stair Enclosures 3 18.1 Visual Inspection 10
6. Smoke-Control Strategy 4 18.2 Leakage Testing 11
3. Project Description
The project consists of one zone contains 3 residential (hotel) high-rise towers consist of 22 levels (known as
S07A, S07B, SR03) which are located above a ten level podiums (consist of commercial areas and parking
areas).
Figure 1.1- Phase IV- S9 project location south side of Haram at Ibrahim Al-Khalil Street.
The requirements for the passive and active smoke control systems are based on the minimum prescriptive code
requirements from GCC, NFPA standards and additional international standards as required in Table 11-7 in Part- Tower Uses: Towers S07A, S07B and SR03 have 22 Levels. These consist of 19 floors of guestrooms, 2
1 of GCC Fire Code. technical floors and roof floors.
The following standards are referenced for this project, in addition to the smoke control requirements of the GCC The typical floor plates for Towers S07A, S07B and SR03 are essentially the same shape, size (approximately
code: 900 square meters) and orientation. Each tower is served by a common corridor with access to two exit stairs.
The general uses of the podium, starting at the lowest level, are as follows. The lowest three levels of the podium It is a well-established, code-supported principle of engineering that properly designed and installed automatic
is parking areas below the grade level. Above parking area will be the ground floor level as hotel entrance level sprinklers will limit smoke production in the event of a fire. While automatic sprinklers respond directly to the
above of it there are the 4 levels of commercial floors then the lower technical floor as podium floors to be as total source of the fire, the smoke management system must manage the smoke produced by the source. Smoke
number of floors 9 floors. management is therefore meant to be a combination of containment and removal if necessary.
Five of the twelve levels of the podium of Zone S9 are above grade, so the total height of the towers in Zone S9 is
31 stories. The lower grade around the base of the podium is at elevation +304.00. The main roof of the podium In the case of the Jabal Omar Zone S9, the building is compartmentalized into a series of primarily residential
is at +339.55, resulting in the podium height ranging from about 35 meters which is the “grade plane” as defined in occupancies in the hotel towers. The podium portion has multiple, separated, mixed occupancies consisting of
NFPA 5000, and is used in some (but not all) calculation requirements in NFPA. retail, storage (i.e. parking garage), and residential (Hotel guestrooms). All these occupancies are connected
vertically by exit stair enclosures and elevator shafts.
The proposed smoke control design seeks to take advantage of this compartmentalization by implementing a
smoke containment strategy. The overall smoke management strategy will utilize a combination of active and
passive components to contain hazardous amounts of smoke to the zone of fire origin. Table 1 provides a
summary of these active and passive elements.
The tower is divided into a series of compartments, or smoke zones (i.e.: separate floor levels), and sub-
compartments, or sub-zones (i.e. individual guestroom units). Typically, each smoke zone is enclosed on all sides
by walls, floors, and ceilings that are referred to as smoke barriers in the code because they are assigned
minimum requirements for tightness of construction as identified in NFPA 5000, Section 8.11.
Openings in these smoke barriers are also equipped with active and passive elements to limit the migration of
smoke. It is important to note that maintenance of a tenable environment within the smoke-control zone of fire
origin is not a requirement. Only walls, floors, and ceilings that are designated as separate smoke zones (not
sub-zones) within a building need to be constructed as smoke barriers. In the hotel towers, each guestroom will
be considered an individual smoke zone, separated from adjacent units and from adjacent floors by horizontal
assemblies and from stairwell and elevator shaft enclosures by fire barriers.
The high rise hotel will be designed to meet the smokeproof exit enclosure requirements of NFPA 5000, Section
33.3.3.1 and Section 11.2.3. Similarly, the GCC Section 3-4/2 requires emergency exit stairs be separated from
the rest of the building by barriers to prevent the spread of the fire and smoke. A minimum positive pressure
differential (12.5 Pa, per Section 5.2, NFPA 92A) will be provided between the alarm zone (smoke zone where the
fire alarm originated) and the exit stair. The resulting positive pressure differentials measured from the exit stair
enclosures to the alarm zone are intended to prevent smoke migration to multiple building levels via these
Figure 3.3: Vertical Distribution Of Uses In Jabal Omar S9 potential pathways.
The exit stair enclosures will be pressurized to provide a smoke-free exit route in the event of a building fire. A
secondary objective is to provide a smoke-free staging area for firefighters. Pressure differences will be
maintained across all interior stair and vestibule doors in the closed position. The minimum design pressure
difference across these barriers is +12.5 Pascals from the exit enclosure to the vestibule.
The maximum pressure difference allowed across these barriers is determined by NFPA 92A, Section 5.2.2 and
Table A.5.2.2, which limits door opening forces to a maximum of 30 pounds. Applied to the 3-foot wide by 7-foot
tall doors (0.9-meter wide by 2.1-meter tall) utilized in these exit stair enclosures, the corresponding maximum
pressure differential allowed may be calculated as shown in Equation 1.
Equation 1:
K d WAp
F Fcloser
2W d
Where:
A = door area (ft2)
d = distance from door handle to latch edge of door (ft)
F = total door opening force (lb)
Fcloser = force required to overcome closing device (lb)
Kd = 5.2
W = door width (ft)
∆p= design pressure difference (in. H2O)
By solving the above equation for ∆p, the maximum design pressure differential (where door opening forces do
not exceed 30 pounds) can be calculated:
Where:
∆p= design pressure difference (in. H2O)
A = door area (21 ft2)
d = distance from door handle to latch edge of door (3” or 0.25-ft)
F = total door opening force (30 lb)
Fcloser = force required to overcome closing device (5 lb)
Kd = 5.2
W = door width (3-ft)
For a total door opening force of 30 pounds and a force of 5 pounds to overcome a closing device, the maximum
pressure difference across a typical exit stair door within Zone S9 is 105 Pascals. Ultimately, testing will establish
this criteria for each required door, as door size and closure force will vary slightly between the doors. However, a
maximum pressure differential of approximately 105 Pascals is calculated in this design phase. The special
inspector will verify that all doors do not exceed the maximum 30-pound force during the commissioning of the
smoke control system.
Figure 6.1: Fire rated Elevator Doors (S07A, S07B and SR03)
Dedicated fans will be used for each pressurized stair. Centrifugal or vane-axial fans will be used to supply
pressurization to the stair enclosures. A shield around the intake will be provided to reduce adverse wind effects. As an enhanced smoke control design, the hotel corridors will be further separated using a zoned smoke control
Care must be taken to confirm proper installation as backward impeller rotation will result in reduced flow. Multiple system. The zoned smoke control system includes exhaust of the fire corridor.
injections points will be utilized to limit the air lost through open doors. It is recommended that multiple injection
points by way of a vertical duct located either in the stair enclosure or in a separate shaft be provided.
The supply air intake will be separated from other building exhaust outlets, such as toilet room exhaust, that might
expel smoke during a fire. The separation will be as great as is practically possible, to avoid recirculation of
contaminated air. A minimum of 6.1 meters (20ft) separation between the exhaust and makeup air inlets are
recommended.
6. Smoke-Control Strategy
Refer to the Fire Safety Strategy Report Chapter 6 for additional strategy discussion. The overall smoke control
strategy for S9 is based on a separation of floors into a number of smoke zones. The floor/ceiling assemblies, as
well as the stair shaft and elevator shaft walls, are considered smoke barriers. The inherent tightness of these
barriers will limit smoke migration into adjacent smoke zones. Each stairway will be pressurized.
The hotel towers will have passenger elevators without lobbies (open directly into the hotel corridor).
Essentially, the hotel corridor acts as a larger elevator lobby. The elevators connect the hotel tower floors to the
podium levels floors. Protection of elevator hoistways (smokeproof) will be provided using fire rated elevator
doors and a zone smoke control system (corridor exhaust system). The corridor exhaust system will keep the
corridor under negative pressure in relation to the elevator shaft (12.5 Pa) with the aid of the positive pressure
inside the shaft, thus preventing smoke from entering the elevator shafts. Figure 6.2: Corridor Exhaust and Elevator shaft Design Concept
The hotel towers S07A, S07B and SR03 and podiums will be provided with dedicated firefighting elevators. The
firefighting elevators will be provided with enclosed lobbies. The fire/smoke rated lobbies and lobby doors provide
protection to prevent smoke from entering into the firefighting elevator shafts. To further enhance the smoke
The active portion of the smoke-control system will consist of positive pressurization of the stair enclosures. 7.2.2 Fire Fighter’s Elevator Design Concept
Sufficient pressure will be provided to prevent smoke infiltration of the exit enclosure with all doors closed while
simultaneously keeping door operating forces below a prescribed limit of 30 pounds (NFPA 92A, Section 5.2.2 The fire fighter’s elevator serves the entire building. These elevators will be provided with an elevator lobby as
and Table A.5.2.2). required by GCC Chapter 4, Section 5. The design team has opted to use elevator pressurization to meet the
intent of preventing smoke and fire from entering the elevator hoistway to achieve minimum 12.5 Pa at the
7.1 Stair Pressurization elevator shaft doors.
All exit enclosures in the high-rise building are required to be smoke-proof enclosures or pressurized stairways in A separate mechanical ventilation to remove the smoke from the elevator hoistway will not be provided for the
accordance with NFPA 5000, Section 33.3.6. Each of the vertical exit enclosures will be maintained at elevated service elevator or the fire fighter’s elevator. Use of elevator lobbies and pressurization of the elevator hoistway
pressure relative to the building interior during a fire emergency. A minimum pressure difference of 12.5 Pascals will prevent smoke entering the elevator hoistway.
will be provided between the stair and its entrance vestibule. A maximum pressure difference across a door will
be based on door opening forces at or below 30 pounds (NFPA 92A, Section 5.2.2 and Table A.5.2.2). Refer to N.B. Pressure relief openings with dampers shall be provided at each fire lift lobby to discharge outside
Appendix D for CONTAM Floor Plans and Appendix E for Shaft Reports. building to relief excessive pressure caused by the hoistway fans.
In order to achieve the required pressure differentials, the minimum air capacities and inlet locations have been 7.2.3 Computational Modeling for Elevator Lobby Pressurization
calculated using computer modeling Contam. Refer to Appendix C for recommended fan sizes.
In recognition of both the complexity of the flow geometry and the multitude of driving forces that must be
NOTE: The capacities calculated are significantly lower than the original design. Thus, pressure relief considered in a high-rise building, the elevator hoistway pressurization system has been designed with the aid of a
vents are recommended for all stairs. computer model. Generally a network flow analysis is needed to determine if pressurized elevator lobbies and
pressurized stairwells are capable of being balanced to perform as intended. Also, assumptions regarding the
tightness of construction must be made both logically and conservatively so that the end result will increase in
7.2 Elevator Hoistway Pressurization
precision over very simplistic and ultimately inadequate hand calculations. The model software CONTAM1 is
designed by the National Institute of Standards and Technology with this purpose in mind.
The GCC Part-1, Chapter 4, Section 6/5/2 requires smoke and fire be prevented from entering the elevator
hoistways and spreading vertically to upper floors. GCC 4-6/5/6 also requires ventilation for elevator hoistways to
dispose smoke in case of fire. The Phase I or Phase II elevator recall levels for both, passenger and fire fighter’s 7.2.4 Computational Modeling Scenarios
elevators must be carefully analyzed when pressurization of elevator hoistways are provided.
The pressure difference criteria listed in Table 7.2.4 will be used, and these criteria are consistent with pressure
The requirement from GCC and NFPA 5000 are somewhat similar when it comes to providing fire fighter’s differences requirements in the NFPA 5000 and NFPA 92A. The minimum pressure difference criteria are
elevator protection. However, the requirements for passenger elevators between the NFPA 5000 and GCC do not intended to prevent smoke flow into the elevator hoistway and stairwells. The maximum pressure difference
agree. GCC 4-6/5/6 requires elevator hoistway vents. NFPA 5000, Section 54.9 requires hoistways of elevators criteria for stairwells and elevator hoistways are intended to prevent excessive door opening forces.
and dumbwaiters penetrating more than three stories to be provided with a means of venting smoke and hot
gases to the outer air in case of fire. The elevator hoistway pressurization system is intended to limit smoke Table 7.2.4 Minimum Pressure Differentials
spread from fire floor into the firefighter’s elevator hoistway.
Active Smoke Control System Minimum Pa (in. H2O)
7.2.1 Core Passenger Elevator Design Concept Pressurized Firefighter’s Elevator Hoistways 12.5 (0.05)
Elevator hoistways typically require a minimum positive pressure of 12.5 Pa (0.05 inches of water) and a Pressurized Stairs 12.5 (0.05)
maximum positive pressure will be determined based the door closing forces (NFPA 92A, Section 5.2). Whereas Zoned Smoke Control (Corridor Exhaust) in incident floor 12.5 (0.05)
the overall smoke control strategy for Jabal Omar projects takes careful consideration of the architectural design The max allowable pressure difference shall not result in door-opening forces exceeding the requirements
of elevators. The passenger core elevators in the hotel tower will not be provided with elevator lobbies because of NFPA 92A, Section 5.2.2 and Table A.5.2.2. A maximum door-opening force is specified at 30 lbf.
they are open directly into the rated corridors, which act as lobbies. Furthermore, the corridors in the hotel towers
will have a zoned smoke control system as discussed further on the report.
The core passenger elevator will be provided with elevator lobbies in the portion of the podium to separate the
elevator from other occupancies. Computer models have been developed to validate the proposed design and to 1
User Guide and Program Documentation, NISTIR 7251, National Institute of Standards and Technology, Gaithersburg, MD, 2010.
7.8 Response Time To meet the requirements of the Underwriter’s Laboratories (UL) requirements for smoke-control systems, the
detection and control system will be UUKL listed for smoke control. The activation control and status of the
smoke-control strategy will be performed by a combined system made up of the fire alarm detection system and
Smoke-control system activation will be initiated within 10 seconds after receipt of an appropriate automatic or
the firefighter’s control panel. The design team must provide a design/layout of the firefighter’s control panel for
manual activation command (NFPA 92A Section 6.4.3.6.1). Smoke-control systems will activate individual
review prior to fabrication.
components (such as dampers and fans) in the sequence necessary to prevent physical damage to the fans,
dampers, ducts and other equipment. NFPA 92A section 6.4.3.6.3
8. Passive Smoke Control
The time necessary for individual components to
Smoke-control systems are intended to provide a tenable environment for the evacuation and relocation of
achieve their desired state or operational mode once the component receives the signal shall not exceed the
occupants. All structural components that are defined as smoke barriers will be sealed to the maximum allowable
following time periods:
leakage area specifications of NFPA 5000 Section 8.11.6.6.1. Definitions, requirements, and assumptions for
these smoke barriers are provided herein.
(1) Fan operation at the desired state: 60 seconds
dampers within the building that are part of the smoke-control systems will be shown on the control panel (NFPA -3
Floors and Roofs 0.17x10
92A, Section 6.4.3.7). The firefighter’s control panel is required to be approved prior to fabrication.
Where:
7.9.1 Control capabilities
Control capabilities will include an “On – Auto – Off” control for each individual zone, which can activate and A = total leakage area, square feet
deactivate all necessary fans, open/close related dampers, and control all other operating smoke-control AW = unit wall, floor, or roof area of barrier, square feet (Section 909.5)
equipment that can also be controlled from other sources within the building, as a single unit. Note: Total leakage area of the barrier is the product of the smoke barrier gross area times the allowable
leakage area ratio.
The firefighter’s control panel will take highest priority over all other building sources. The controls and indicators
will be combined to control and indicate all elements of a single smoke zone as a unit (NFPA 92A, Section Passive barriers include the following building elements:
6.4.5.2).
Floor-ceiling assemblies
On the graphic zone panel, status lamps will be provided for the indication of operation of all smoke-control
Shafts
equipment within each smoke zone as a single unit as follows (NFPA 92A, Annex D):
Stair enclosures
Fans, dampers, and other operating equipment in normal mode – White.
Fans, dampers, and other operating equipment in smoke-control mode – Green.
Fans, dampers, and other operating equipment in fault mode – Yellow/Amber.
NFPA 5000 requires that systems or methods of construction to be used for smoke-control be based on a rational The operation of the HVAC systems on the transport of smoke was considered. These effects are considered
analysis in accordance with well-established principles of engineering. At a minimum, the analysis must address negligible because common area systems not used in smoke-control will be automatically shut down during
stack effect, temperature effects of fire, wind effect, HVAC system effects, and climatic effects. This section emergency operations.
describes these considerations. The rational analysis was performed using the computer model CONTAMW and
engineering judgment based on fire tests and historical data. Specifically, HVAC systems throughout the building will shut down. Dampers in shut down systems will operate to
prevent smoke from migrating floor to floor through HVAC duct work and create an effective smoke barrier
between smoke zones. Toilet exhaust does not generate a large enough pressure difference to impact smoke-
12.1 Stack Effect control systems and will not be controlled in the smoke-control sequence of operations.
The system must be designed such that the maximum probable normal or reverse stack effects will not adversely
interfere with the system’s capability. An evaluation of stack effect must consider altitude, elevation, weather 12.5 Climate
history, and interior temperatures. Smoke movement from a fire can be dominated by stack effect. During normal
stack effect, occurring when building interior temperatures are greater than exterior temperatures, there is Temperature data was obtained from the 2009 ASHRAE Handbook – Fundamentals, Chapter 27, Climatic Design
frequently an upward movement of air below the neutral plane within stair enclosures and shafts (sometimes Information for the input into the CONTAMW numerical model. This data is provided in Appendix A – Climatic
referred to the chimney effect). Conversely, during reverse stack effect (when it is hot outside and a building is Design Information.
air-conditioned); smoke above the neutral plane may flow downward via shafts and stair enclosures.
The effects of temperature considered the average of annual extreme maximum and minimum temperatures
Studies (Tamura and Wilson 1966, 1967) have shown that stack effect is significant for shafts but is negligible for recorded in Makkah. The temperature values are 45.1C and 17.2C, which were used as inputs to CONTAMW
floor to floor pressure differences. Stack effects related to altitude, elevation, weather, and interior temperature to predict climatic temperature effects.
are inputs to the computer model CONTAMW.
All of the factors necessary for a rational analysis as identified in NFPA 92A were considered and evaluated
o
The interior building temperature was assumed constant at 70 F and exterior temperature is adjusted to reflect through the use of CONTAMW and other well-established principles of engineering. The CONTAMW results
high and low temperature conditions for stack effect. Climate values are discussed in the “Climate” section of this confirm that adequate pressure differences will be provided to prevent smoke migration into the vestibules and
report. These values have been used as input data. stairs in either winter or summer conditions. Refer to Appendix E for computer modeling result for winter and
summer simulations.
In light of the degree of uncertainty surrounding the general characterization of the existing building construction, it This estimate for static pressure, coupled with an estimate for velocity pressure will then be used by the
is recommended that certain measures be taken to facilitate system balancing during the special inspection. Mechanical Engineer to predict air leakage from the smoke control ductwork. The air capacities specified in
These actions are the use of Variable Frequency Drives with all smoke control system pressurization fans as well this Rational Analysis and Technical Report do not take into account such air leakage estimates.
as the installation of adjustable door sweeps on all stairwell and vestibule doors, and high quality door closers.
Therefore, the Mechanical Engineer may choose to increase the air capacities in this report to compensate for
predicted ductwork leakage.
Leakage of pressurization air from smoke control ductwork will result in a reduced amount of air supplied to
pressurized smoke zones. Such leakage is determined by a combination of static pressure, duct openings and
2
Tamura, GT, and Shaw, CY; Air Leakage Data for the Design of Elevator and Stair Shaft Pressurization. Systems, ASHRAE
Transactions 82(Part II): 179-190.
3
Klote, Milke, Turnbull, Kashef, and Ferreira; Handbook of Smoke Control Engineering; ASHRAE; 2012. 4 rd
Gladstone, J. and W. Bevirt. HVAC Testing, Adjusting and Balancing Manual, 3 Edition. McGraw-Hill.
The construction and performance of smoke dampers under various conditions have been evaluated by 18.1 Visual Inspection
Underwriters Laboratories under the UL 555 S: Standard for Smoke Dampers8. During the special inspection, it is
important to confirm proper installation, ratings and listings such that the equipment is utilized in compliance with Passive barrier construction will be visually inspected to verify that leakage areas do not exceed those permitted
the standard. Such confirmation will be made during the special inspection by utilizing procedures that include but by smoke barrier construction. All ducts, vents and other orifices should be sealed prior to conducting the final
are not limited to those outlined in the referenced standard. acceptance test. Visual inspections will include, but not be limited to the following:
Pipes, conduits, bus ducts, cables, wires, air ducts, pneumatic tubes and ducts, and similar building service
15. Activation of System equipment that pass through smoke barriers will be inspected to verify that the space between the penetrating
item and the smoke barrier is filled with a material capable of maintaining smoke resistance or by an approved
The smoke-control system will be activated to test all appropriate smoke-control system components. device designed for the specific purpose.
Penetrating items that use a sleeve to penetrate the smoke barrier will be inspected to verify that the sleeve is
15.1 Automatic Activation solidly set in the barrier and that the space between the item and the sleeve is filled with a material capable of
maintaining smoke resistance or by an approved device designed for the specific purpose.
The system will be activated through automatic means to verify proper system operation. The fire alarm panel will Smoke barriers will be inspected to verify that the barrier is continuous throughout and that all barriers are
be verified for proper signal identification. The firefighter’s smoke-control panel will be verified for proper signal continuous through all concealed spaces.
identification and status indication.
Doors in smoke barriers will be inspected to verify that they close, leaving only the minimum clearance necessary
5
National Standards for Total System Balance. Associated Air Balance Council: Washington, D.C., 2002. Section 5.1.2. for proper operation, and will be without undercuts, louvers, or frills. In addition, self-closing or automatic-closing
6
National Standards for Total System Balance. Associated Air Balance Council: Washington, D.C., 2002. Section 5.2.2. functions will be tested.
7
National Standards for Total System Balance. Associated Air Balance Council: Washington, D.C., 2002. Section 6.4.
8 th
UL 555 S: Standard for Smoke Dampers, 4 edition: Underwriters Laboratories, Inc., 1999.
The passive smoke barriers will be tested to confirm that leakage does not exceed that estimated by NFPA 92A,
Table A.4.6.1. This will be accomplished by pressurizing at least one floor level through use of the HVAC system 19.1.6 Manual Activation
or door fans. The leakage will be calculated and compared to the NFPA 92A requirements.
The system will be activated manually through the use of the fire fighters control panel. The panel will be checked
to verify proper signal identification and status indication. In addition, the applicable smoke-control equipment will
19. Smoke-Control System Acceptance Test Criteria be checked to verify proper operation in accordance with the sequence of operation.
While the smoke-control system is in the automatic mode, it will be confirmed through manipulation of the
19.1 Smoke Control Special Inspections firefighter’s control panel controls that the panel can override all other signals and functions.
19.1.7 Smoke Control Special Inspections Procedures
An acceptance test of the smoke-control system will be necessary to confirm proper smoke-control system
activation and operation. This is accomplished through a combination of visual inspection of smoke-control system Testing and commissioning of the smoke control system requires special inspections. Refer to appendix F for a
components and measurement of pressure differentials and door opening forces while the system is in the active summary of requirements.
mode. Since confirmation of code compliance of minimum pressure differentials can be objectively accomplished
through pressure measurement equipment, a smoke test will not be required. Furthermore, the practice of using
cold smoke for such tests is inappropriate as a lack of buoyancy in the smoke would render the results of such a
20. Report
simulation entirely irrelevant9.
A complete smoke-control report of testing will be prepared by the required Special Inspector. The report will
CONTAMW is used as a tool to perform the calculations necessary to properly size the fans based upon the include identification of all devices by manufacturer nameplate data, design values, measured values and
rational analysis. A safety factor is used when sizing fans and it is expected that actual airflow will be adjusted identification tag or mark.
during air-balance to achieve proper pressure differences, while not exceeding door force requirements. Doors
must be set in motion when subjected to a 30 pound force and swing to a full-open position when subjected to a The report will be reviewed by the mechanical engineer of record, and when satisfied that the design intent has
15 pound force. The testing will establish this criteria for each required door, as door size and closure force will been achieved, the engineer of record will sign and date the report with the following statement:
vary slightly between the doors. The following inspections and tests should be conducted for proper confirmation.
"I have reviewed the report, and by personal knowledge and on-site observation, certify that the smoke-control
system is in substantial compliance with the design intent and, to the best of my understanding, complies with the
19.1.1 Smoke-Control Ductwork requirements of the code."
Smoke-control ductwork will be visually inspected to verify no damage has occurred during installation.
Smoke-control system ductwork will be leakage tested to 1.5 times its design pressure using the Leakage Test 21. Conclusion
Manual published by the Sheet Metal and Air Conditioning Contractors National Association, Inc. (SMACNA). The
test must conclude that the leakage does not exceed 5% of the design flow. The smoke-control system design documented in this report relies on a combination of passive and active
elements. This methodology results in a system that meets and exceeds requirements outlined in the fire strategy
19.1.2 Fans
report, while providing adequate tenability, as demonstrated by the CONTAM model.
Fans must be visually examined for proper rotation. Measurement of voltage, amperage, revolutions per minute
and belt tension (for belt driven fans) will be performed.
Aon Fire Protection Engineering Corporation
19.1.3 Dampers
Smoke-control system dampers will be visually inspected to confirm proper installation, proper rating and listings.
19.1.4 Activation of System
The smoke-control system will be activated to test all appropriate smoke-control system components.
19.1.5 Automatic Activation
The system will be activated through automatic means to verify proper system operation.
9
National Standards for Total System Balance. Associated Air Balance Council: Washington, D.C., 2002. Section 20.4.3.2.
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix A 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page A-1
Appendix B – Sequence of Operations
STAIR CASES AREA CORRIDOR Fire Lift Dampers
STAIR 3A
Tower S07A
Tower S07B
STAIR 1
STAIR 2
STAIR 4
STAIR 5
STAIR 6
STAIR 7
STAIR 8
STAIR 9
Tower S03
TOWERS SR 07A, 07B, 03
Fire Lift s
Fire Lift s
Fire Lift s
floor
area
System Input
1 Manual Pull station at any level in S07A X X
2 Manual Pull station at any level in S07B X X
3 Manual Pull station at any level in SR03 X X
4 Manual Pull station at any level in Podium Area X X X X X X X X X
Confirmed fire signal from typical floor (WFD OR 2 x Smoke detectors,
5 X X X X X X X
upon evacuation alarm) in S07A Tower
Confirmed fire signal from typical floor (WFD OR 2 x Smoke detectors,
6 X X X X X X X
upon evacuation alarm) in S07B Tower
Confirmed fire signal from typical floor (WFD OR 2 x Smoke detectors,
7 X X X X X X X
upon evacuation alarm) in SR03 Tower
Confirmed fire signal from typical floor (WFD OR 2 x Smoke detectors,
8 X X X X X X X X X X X X X X
upon evacuation alarm) in PODIUM AREA
Fire signal from Back of house service area (store, electrical room,
9 X X X
house keeping,…) Tower S07A
Fire signal from Back of house service area (store, electrical room,
10 X X X
house keeping,…) Tower S07B
Fire signal from Back of house service area (store, electrical room,
11 X X X
house keeping,…) Tower SR03
NOTES
ALL SMOKE CONTROL DAMPERS ARE MOTORIZED TYPE SET AT NORMAL CLOSED POSITION (0)
SMOKE DAMPERS LOCATED ON SMOKE EXHAUST DUCTS WILL OPERATE ONLY IN THE FIRE FLOOR
ALL HVAC MOTORISED SMOKE FIRE DAMPERS,HVAC SYSTEM SHOULD CLOSE UPON ACTIVATION OF ALARM
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix B 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page B-1
Appendix C – Fans Schedule and Minimum Air Capacities
It is recommended that the fan selection provide as wide a range of operation as practical and that
a method of fan speed adjustment (i.e. variable frequency drive) be considered to achieve the
necessary point of fan operation and to reduce field testing and balancing time.
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix C 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page C-1
Appendix D – CONTAM Floor Plans
Nomenclature
Stairwell
Elevators
Water tanks
Passengers Lifts
Commercial Area
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix D 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page D-1
Figure D.3- Basement 1 Floor Level +311.0
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix D 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page D-2
Figure D.9- Lower Technical Floor Level +339.5
Figure D.7- Commercial 3 Floor Level +329.5
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix D 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page D-3
Figure D.11- Upper Technical -1 Floor Level +413.6
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix D 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page D-4
Appendix E – Model Reports
E-1 Active Smoke Control
Stair Enclosure Pressure Differentials:
- Minimum pressure differentials of +12.5 Pa (+0.05 inches of water column) are required to be provided
between each stair enclosure and the adjacent fire floor area.
- Where vestibules are provided, they will not be considered an extension of the stair enclosure and pressure
differentials will be measured between the stair enclosure and the vestibule.
- The minimum pressure differential of +12.5 Pa (+0.05 inches of water column) is to be obtained with all
doors in the closed position.
- All stairs shall have pressure relief vents.
- Centrifugal or vane-axial fans will be used to supply pressurization to the stair enclosures. A shield around
the intake will be provided to reduce adverse effects of wind on fan performance. Propeller fans, which are
more susceptible to wind effects, will not be used.
- The supply air intake will be separated from other building exhaust outlets that might expel smoke during a
fire. The separation should be as great as is practically possible to avoid recirculation of contaminated air.
The supply air intake for the elevator hoistway pressurization is required to be from an outside,
uncontaminated source located a minimum distance of 20 feet from any air exhaust system or outlet.
- Fan motors are required to have a minimum service factor of 1.15. Belt-driven fans are required to be
provided with 1.5 times the required number of belts; a minimum of 2.
- Contam modeling/analysis indicates the air capacities identified in Appendix C should be used for sizing
purposes. These capacities should have a wide range of operation and shall have a method of fan speed
adjustment (i.e. variable frequency drive) to achieve the necessary point of fan operation and to reduce field
testing and balancing time.
- Minimum pressure differentials of +12.5 Pa (+0.05 inches of water column) are required to be provided
between the firefighter elevator and the adjacent elevator lobby or space.
- The minimum pressure differential of +12.5 Pa (+0.05 inches of water column) is to be obtained during
primary recall, secondary recall, and with all doors in the closed position.
- The minimum pressure differential is to be obtained on every floor.
- In order to achieve the required pressure differentials across the pressurized fire access elevators and
facilitate system commissioning, it is recommended the use of Variable Frequency Drives for all fans.
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-1
E-2 Scenario 1.A: Winter
– Model input parameters:
Value
Activation of Fire Alarm Manual Pull Station at any level in corridor Area in S07A: Parameter
Ambient Temperature 17.3 oC
Sequence of Operation: Interior Temperature 20 oC
Temperature of the protection area after pressurization system
Only the staircases pressurization fans in S07A will be activated, listed below: 17.3 oC
operation
Wind speed 6.3 m/s
CORRESPONDING Level 10 –
FAN FUNCTION Incident Floors
AREA S07A
PF-SR7A-MR1-01 Tower-S07A
Stair 2
PF-P09-LT-01 PODIUM Area – Modeling Result
Supply
PF-SR7A-MR1-02 Tower-S07A
Stair 5
PF-P09-C4-01 PODIUM Area Manual_Pull_station_at_any_level_in_S07A_Winters shaft report
Adjusted flows are the required flows to get the overall stair shafts within the acceptable differential pressures to level/zone [Pa] [sL/s] [Pa] [sL/s] zone
NFPA 92A.
+---------------------------+
CONTAM floor plan for incident floor:
UT-2/lobb 49.8 < 83.68 49.8 > 83.68 lobb
Level 10 was assumed as incident floor. The CONTAM floor plan during the modeling is shown as Figure __. |------ ------|
UT-1/corr 46.0 < 80.46 46.0 > 80.46 corr
|------ ------|
19th/corr 31.6 < 66.68 31.6 > 66.68 corr
|------ ------|
18th/corr 30.7 < 65.70 30.7 > 65.70 corr
|------ ------|
17th/corr 30.6 < 65.63 30.6 > 65.63 corr
|------ ------|
16th/corr 30.6 < 65.62 30.6 > 65.62 corr
|------ ------|
15th/corr 30.6 < 65.61 30.6 > 65.61 corr
|------ ------|
14th/corr 30.6 < 65.61 30.6 > 65.61 corr
|------ ------|
13th/corr 30.6 < 65.61 30.6 > 65.61 corr
|------ ------|
12th/corr 30.6 < 65.60 30.6 > 65.60 corr
|------ ------|
11th/corr 30.6 < 65.60 30.6 > 65.60 corr
|------ ------|
10th/corr 30.6 < 65.60 30.6 > 65.60 corr
|------ ------|
9th/corr 30.6 < 65.60 30.6 > 65.60 corr
|------ ------|
Figure- CONTAM Floor Plan of Tower Level 10 8th/corr 30.6 < 65.59 30.6 > 65.59 corr
|------ ------|
7th/corr 30.6 < 65.59 30.6 > 65.59 corr
|------ ------|
6th/corr 30.6 < 65.59 30.6 > 65.59 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-2
5th/corr 30.6 < 65.58 30.6 > 65.58 corr 14th/corr 34.8 < 70.00 34.8 > 70.00 corr
|------ ------| |------ ------|
4th/corr 30.6 < 65.58 30.6 > 65.58 corr 13th/corr 34.8 < 70.00 34.8 > 70.00 corr
|------ ------| |------ ------|
3rd/corr 30.6 < 65.57 30.6 > 65.57 corr 12th/corr 34.8 < 70.00 34.8 > 70.00 corr
|------ ------| |------ ------|
2nd/corr 30.5 < 65.51 30.5 > 65.51 corr 11th/corr 34.8 < 69.99 34.8 > 69.99 corr
|------ ------| |------ ------|
1st/corr 29.8 < 64.74 29.8 > 64.74 corr 10th/corr 34.8 < 69.99 34.8 > 69.99 corr
|------ ------| |------ ------|
LT/lobb 45.9 < 80.32 45.9 > 80.32 lobb 9th/corr 34.8 < 69.99 34.8 > 69.99 corr
|------ ------| |------ ------|
C4/exit 43.9 < 78.55 43.9 > 78.55 exit 8th/corr 34.8 < 69.98 34.8 > 69.98 corr
|------ ------| |------ ------|
C3/VST 30.8 < 65.81 30.8 > 65.81 VST 7th/corr 34.8 < 69.98 34.8 > 69.98 corr
|------ ------| |------ ------|
C2/exit 44.6 < 79.23 44.6 > 79.23 exit 6th/corr 34.8 < 69.98 34.8 > 69.98 corr
|------ ------| |------ ------|
C1/exit 44.8 < 79.39 44.8 > 79.39 exit 5th/corr 34.8 < 69.97 34.8 > 69.97 corr
|------ ------|
GRND/ 4th/corr 34.8 < 69.97 34.8 > 69.97 corr
|------ ------| |------ ------|
B1/serv 45.1 < 79.69 45.1 > 79.69 serv 3rd/corr 34.8 < 69.96 34.8 > 69.96 corr
+---------------------------+ |------ ------|
2nd/corr 34.8 < 69.96 34.8 > 69.96 corr
CONTAM Shaft Report at Stair 2 in S07A after simulation (Parameters in Pa & L/s) |------ ------|
1st/corr 34.8 < 69.98 34.8 > 69.98 corr
|------ ------|
LT/lobb 34.9 < 70.02 34.9 > 70.02 lobb
Manual_Pull_station_at_any_level_in_S07A_Winters shaft report |------ ------|
C4/serv 34.8 < 69.94 34.8 > 69.94 serv
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C3/serv 34.8 < 69.96 34.8 > 69.96 serv
+---------------------------+ |------ ------|
Roof/mach 33.1 < 68.23 33.1 > 68.23 mach C2/serv 34.9 < 70.07 34.9 > 70.07 serv
|------ ------| |------ ------|
MR-1/ C1/exit 34.3 < 69.45 34.3 > 69.45 exit
|------ ------| |------ ------|
UT-2/fire 34.6 < 69.77 34.6 > 69.77 fire GRND/exit 32.0 < 67.08 32.0 > 67.08 exit
|------ ------|
UT-1/fire 34.2 < 69.35 34.2 > 69.35 fire B1/fire 34.1 < 69.30 34.1 > 69.30 fire
|------ ------|
19th/corr 34.9 < 70.07 34.9 > 70.07 corr B2/fire 34.2 < 69.37 34.2 > 69.37 fire
|------ ------| |------ ------|
18th/corr 34.9 < 70.03 34.9 > 70.03 corr B3/fire 34.2 < 69.37 34.2 > 69.37 fire
|------ ------| +---------------------------+
17th/corr 34.9 < 70.02 34.9 > 70.02 corr
|------ ------| CONTAM Shaft Report at Stair 5 in S07A after simulation (Parameters in Pa & L/s)
16th/corr 34.8 < 70.01 34.8 > 70.01 corr
|------ ------|
15th/corr 34.8 < 70.01 34.8 > 70.01 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-3
Summer 5th/corr 36.2 < 71.37 36.2 > 71.37 corr
– Model input parameters: |------ ------|
4th/corr 36.3 < 71.42 36.3 > 71.42 corr
Value |------ ------|
Parameter
3rd/corr 36.3 < 71.46 36.3 > 71.46 corr
Ambient Temperature 45.1 oC |------ ------|
Interior Temperature 20 oC 2nd/corr 36.3 < 71.46 36.3 > 71.46 corr
Temperature of the protection area after pressurization system |------ ------|
45.1 oC
operation 1st/corr 35.6 < 70.72 35.6 > 70.72 corr
Wind speed 6.3 m/s
Level 10 – Lowe/lobb 56.0 < 88.75 56.0 > 88.75 lobb
Incident Floors
S07A |------ ------|
C4/exit 63.0 < 94.14 63.0 > 94.14 exit
– Modeling Result |------ ------|
C3/VST 44.5 < 79.10 44.5 > 79.10 VST
Manual_Pull_station_at_any_level_in_S07A_Summers shaft report |------ ------|
C2/exit 57.1 < 89.62 57.1 > 89.62 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C1/exit 62.0 < 93.36 62.0 > 93.36 exit
+---------------------------+ |------ ------|
UT-2/lobb 10.5 < 38.49 10.5 > 38.49 lobb GRND/
|------ ------| |------ ------|
UT-1/corr 48.4 < 82.54 48.4 > 82.54 corr B1/serv 61.5 < 93.01 61.5 > 93.01 serv
|------ ------| +---------------------------+
19th/corr 36.2 < 71.36 36.2 > 71.36 corr
|------ ------| CONTAM Shaft Report at Stair 2 in S07A after simulation (Parameters in Pa & L/s)
18th/corr 35.7 < 70.84 35.7 > 70.84 corr
|------ ------|
17th/corr 35.7 < 70.90 35.7 > 70.90 corr
|------ ------| Manual_Pull_station_at_any_level_in_S07A_Summers shaft report
16th/corr 35.8 < 70.96 35.8 > 70.96 corr
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
15th/corr 35.8 < 71.01 35.8 > 71.01 corr
|------ ------| +---------------------------+
14th/corr 35.9 < 71.04 35.9 > 71.04 corr Roof/mach 5.0 > 26.55 5.0 < 26.55 mach
|------ ------| |------ ------|
13th/corr 35.9 < 71.08 35.9 > 71.08 corr Mach/
|------ ------| |------ ------|
12th/corr 35.9 < 71.11 35.9 > 71.11 corr Uppe/fire 32.3 < 67.41 32.3 > 67.41 fire
|------ ------| |------ ------|
11th/corr 36.0 < 71.15 36.0 > 71.15 corr Uppe/fire 40.4 < 75.37 40.4 > 75.37 fire
|------ ------|
10th/corr 36.0 < 71.18 36.0 > 71.18 corr Floo/corr 44.3 < 78.95 44.3 > 78.95 corr
|------ ------| |------ ------|
9th/corr 36.1 < 71.21 36.1 > 71.21 corr Floo/corr 45.2 < 79.75 45.2 > 79.75 corr
|------ ------| |------ ------|
8th/corr 36.1 < 71.25 36.1 > 71.25 corr Floo/corr 45.5 < 80.00 45.5 > 80.00 corr
|------ ------| |------ ------|
7th/corr 36.1 < 71.29 36.1 > 71.29 corr Floo/corr 45.6 < 80.12 45.6 > 80.12 corr
|------ ------| |------ ------|
6th/corr 36.2 < 71.33 36.2 > 71.33 corr Floo/corr 45.7 < 80.20 45.7 > 80.20 corr
|------ ------| |------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-4
Floo/corr 45.8 < 80.27 45.8 > 80.27 corr
|------ ------|
E-2 Scenario 2.A:
Floo/corr 45.9 < 80.34 45.9 > 80.34 corr
|------ ------| Activation of Fire Alarm Manual Pull Station at any level in corridor Area in S07B:
Floo/corr 46.0 < 80.40 46.0 > 80.40 corr
|------ ------| Sequence of Operation:
Floo/corr 46.0 < 80.47 46.0 > 80.47 corr
|------ ------| Only the staircases pressurization fans in S07B will be activated, listed below:
Floo/corr 46.1 < 80.53 46.1 > 80.53 corr
|------ ------|
CORRESPONDING
Floo/corr 46.2 < 80.60 46.2 > 80.60 corr FAN FUNCTION
AREA
|------ ------| PF-SR7B-MR1-01 Tower-S07B
Floo/corr 46.3 < 80.68 46.3 > 80.68 corr Stair 3A
PF-P09-LT-02 PODIUM Area
|------ ------| Supply
PF-SR7B-MR1-02 Tower-S07B
Floo/corr 46.4 < 80.75 46.4 > 80.75 corr Stair 6
PF-P09-LT-04 PODIUM Area
|------ ------|
Floo/corr 46.5 < 80.84 46.5 > 80.84 corr Adjusted flows are the required flows to get the overall stair shafts within the acceptable differential pressures to
|------ ------| NFPA 92A.
Floo/corr 46.6 < 80.92 46.6 > 80.92 corr
|------ ------| CONTAM floor plan for incident floor:
Floo/corr 46.7 < 81.02 46.7 > 81.02 corr
|------ ------| Level 10 was assumed as incident floor. The CONTAM floor plan during the modeling is shown as Figure __.
Floo/corr 46.8 < 81.14 46.8 > 81.14 corr
|------ ------|
Floo/corr 47.0 < 81.28 47.0 > 81.28 corr
|------ ------|
Floo/corr 47.2 < 81.50 47.2 > 81.50 corr
|------ ------|
Lowe/lobb 48.0 < 82.18 48.0 > 82.18 lobb
|------ ------|
C4/serv 48.4 < 82.55 48.4 > 82.55 serv
|------ ------|
C3/serv 51.5 < 85.11 51.5 > 85.11 serv
|------ ------|
C2/serv 48.9 < 82.90 48.9 > 82.90 serv
|------ ------|
C1/exit 47.6 < 81.84 47.6 > 81.84 exit
|------ ------|
GRND/exit 44.2 < 78.89 44.2 > 78.89 exit
|------ ------|
B1/fire 44.2 < 78.84 44.2 > 78.84 fire
|------ ------|
B2/fire 44.6 < 79.23 44.6 > 79.23 fire
|------ ------|
B3/fire 44.8 < 79.36 44.8 > 79.36 fire
+---------------------------+
Figure- CONTAM Floor Plan of Tower Level 10
CONTAM Shaft Report at Stair 5 in S07A after simulation (Parameters in Pa & L/s)
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-5
Winter |------ ------|
– Model input parameters: Floo/corr 25.7 < 60.07 25.7 > 60.07 corr
|------ ------|
Value Floo/corr 25.6 < 60.07 25.6 > 60.07 corr
Parameter
|------ ------|
Ambient Temperature 17.3 oC Floo/corr 25.6 < 60.06 25.6 > 60.06 corr
Interior Temperature 20 oC |------ ------|
Temperature of the protection area after pressurization system Floo/corr 25.6 < 60.07 25.6 > 60.07 corr
17.3 oC
operation |------ ------|
Wind speed 6.3 m/s Lowe/stai 43.0 < 77.80 43.0 > 77.80 stai
Level 10 – |------ ------|
Incident Floors
S07B C4/exit 52.4 < 85.84 52.4 > 85.84 exit
|------ ------|
– Modeling Result C3/exit 55.4 < 88.30 55.4 > 88.30 exit
Manual_Pull_station_at_any_level_in_S07B_Winters shaft report |------ ------|
C2/exit 53.9 < 87.10 53.9 > 87.10 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone +---------------------------+
+---------------------------+ CONTAM Shaft Report at Stair 3A in S07B after simulation (Parameters in Pa & L/s)
Uppe/exit 39.1 < 74.20 39.1 > 74.20 exit
|------ ------|
Uppe/exit 35.7 < 70.85 35.7 > 70.85 exit Manual_Pull_station_at_any_level_in_S07B_Winters shaft report
|------ ------|
Floo/corr 25.7 < 60.12 25.7 > 60.12 corr level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------|
Floo/corr 25.7 < 60.09 25.7 > 60.09 corr +---------------------------+
|------ ------| Roof/mach 33.2 < 68.31 33.2 > 68.31 mach
Floo/corr 25.7 < 60.09 25.7 > 60.09 corr |------ ------|
|------ ------| Mach/
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Uppe/fire 32.5 < 67.62 32.5 > 67.62 fire
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Uppe/fire 31.5 < 66.62 31.5 > 66.62 fire
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Floo/corr 31.3 < 66.35 31.3 > 66.35 corr
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
Floo/corr 25.7 < 60.08 25.7 > 60.08 corr |------ ------|
|------ ------| Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
Floo/corr 25.7 < 60.07 25.7 > 60.07 corr |------ ------|
|------ ------| Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
Floo/corr 25.7 < 60.07 25.7 > 60.07 corr |------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-6
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr Summer
|------ ------| – Model input parameters:
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
|------ ------| Value
Parameter
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
|------ ------| Ambient Temperature 45.1 oC
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr Interior Temperature 20 oC
|------ ------| Temperature of the protection area after pressurization system
45.1 oC
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr operation
|------ ------| Wind speed 6.3 m/s
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr Level 10 –
Incident Floors
|------ ------| S07B
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr
|------ ------| – Modeling Result
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr Manual_Pull_station_at_any_level_in_S07B_Summers shaft report
|------ ------|
Floo/corr 31.2 < 66.29 31.2 > 66.29 corr level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------|
Floo/corr 31.3 < 66.30 31.3 > 66.30 corr +---------------------------+
|------ ------| UT-2/exit 20.0 < 53.00 20.0 > 53.00 exit
Lowe/lobb 32.5 < 67.59 32.5 > 67.59 lobb |------ ------|
|------ ------| UT-1/exit 28.8 < 63.62 28.8 > 63.62 exit
C4/exit 31.1 < 66.17 31.1 > 66.17 exit |------ ------|
|------ ------| 19th/corr 25.8 < 60.19 25.8 > 60.19 corr
C3/corr 31.8 < 66.90 31.8 > 66.90 corr |------ ------|
|------ ------| 18th/corr 25.9 < 60.39 25.9 > 60.39 corr
C2/exit 28.4 < 63.26 28.4 > 63.26 exit |------ ------|
|------ ------| 17th/corr 26.0 < 60.47 26.0 > 60.47 corr
C1/corr 32.1 < 67.17 32.1 > 67.17 corr |------ ------|
|------ ------| 16th/corr 26.0 < 60.52 26.0 > 60.52 corr
GRND/corr 32.4 < 67.53 32.4 > 67.53 corr |------ ------|
|------ ------| 15th/corr 26.1 < 60.56 26.1 > 60.56 corr
B1/fire 32.8 < 67.89 32.8 > 67.89 fire |------ ------|
|------ ------| 14th/corr 26.1 < 60.59 26.1 > 60.59 corr
B2/fire 33.1 < 68.23 33.1 > 68.23 fire |------ ------|
|------ ------| 13th/corr 26.1 < 60.63 26.1 > 60.63 corr
B3/fire 32.6 < 67.72 32.6 > 67.72 fire |------ ------|
+---------------------------+ 12th/corr 26.2 < 60.68 26.2 > 60.68 corr
|------ ------|
CONTAM Shaft Report at Stair 6 in S07B after simulation (Parameters in Pa & L/s) 11th/corr 26.2 < 60.74 26.2 > 60.74 corr
|------ ------|
10th/corr 26.3 < 60.82 26.3 > 60.82 corr
|------ ------|
9th/corr 26.3 < 60.84 26.3 > 60.84 corr
|------ ------|
8th/corr 26.3 < 60.84 26.3 > 60.84 corr
|------ ------|
7th/corr 26.3 < 60.85 26.3 > 60.85 corr
|------ ------|
6th/corr 26.3 < 60.85 26.3 > 60.85 corr
|------ ------|
5th/corr 26.3 < 60.85 26.3 > 60.85 corr
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-7
|------ ------| 10th/corr 34.4 < 69.56 34.4 > 69.56 corr
4th/corr 26.3 < 60.85 26.3 > 60.85 corr |------ ------|
|------ ------| 9th/corr 34.4 < 69.59 34.4 > 69.59 corr
3rd/corr 26.3 < 60.86 26.3 > 60.86 corr |------ ------|
|------ ------| 8th/corr 34.4 < 69.60 34.4 > 69.60 corr
2nd/corr 26.3 < 60.87 26.3 > 60.87 corr |------ ------|
|------ ------| 7th/corr 34.5 < 69.61 34.5 > 69.61 corr
1st/corr 26.4 < 60.90 26.4 > 60.90 corr |------ ------|
|------ ------| 6th/corr 34.5 < 69.62 34.5 > 69.62 corr
LT/stai 46.9 < 81.18 46.9 > 81.18 stai |------ ------|
|------ ------| 5th/corr 34.5 < 69.63 34.5 > 69.63 corr
C4/exit 77.0 < 104.11 77.0 > 104.11 exit |------ ------|
|------ ------| 4th/corr 34.5 < 69.65 34.5 > 69.65 corr
C3/exit 90.1 < 112.60 90.1 > 112.60 exit |------ ------|
|------ ------| 3rd/corr 34.5 < 69.67 34.5 > 69.67 corr
C2/exit 84.6 < 109.11 84.6 > 109.11 exit |------ ------|
+---------------------------+ 2nd/corr 34.5 < 69.70 34.5 > 69.70 corr
|------ ------|
CONTAM Shaft Report at Stair 3A in S07B after simulation (Parameters in Pa & L/s) 1st/corr 34.6 < 69.77 34.6 > 69.77 corr
|------ ------|
LT/lobb 40.9 < 75.85 40.9 > 75.85 lobb
Manual_Pull_station_at_any_level_in_S07B_Summers shaft report |------ ------|
C4/exit 40.0 < 74.98 40.0 > 74.98 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C3/corr 38.4 < 73.54 38.4 > 73.54 corr
+---------------------------+ |------ ------|
Roof/mach 0.5 < 8.36 0.5 > 8.36 mach C2/exit 48.1 < 82.26 48.1 > 82.26 exit
|------ ------| |------ ------|
MR-1/ C1/corr 40.5 < 75.51 40.5 > 75.51 corr
|------ ------| |------ ------|
UT-2/fire 30.6 < 65.61 30.6 > 65.61 fire GRND/corr 42.4 < 77.25 42.4 > 77.25 corr
|------ ------| |------ ------|
UT-1/fire 35.0 < 70.12 35.0 > 70.12 fire B1/fire 45.9 < 80.40 45.9 > 80.40 fire
|------ ------| |------ ------|
19th/corr 33.3 < 68.46 33.3 > 68.46 corr B2/fire 51.6 < 85.21 51.6 > 85.21 fire
|------ ------| |------ ------|
18th/corr 33.7 < 68.81 33.7 > 68.81 corr B3/fire 40.9 < 75.88 40.9 > 75.88 fire
|------ ------| +---------------------------+
17th/corr 33.8 < 68.95 33.8 > 68.95 corr
|------ ------| CONTAM Shaft Report at Stair 6 in S07B after simulation (Parameters in Pa & L/s)
16th/corr 33.9 < 69.03 33.9 > 69.03 corr
|------ ------|
15th/corr 33.9 < 69.09 33.9 > 69.09 corr
|------ ------|
14th/corr 34.0 < 69.15 34.0 > 69.15 corr
|------ ------|
13th/corr 34.1 < 69.22 34.1 > 69.22 corr
|------ ------|
12th/corr 34.1 < 69.30 34.1 > 69.30 corr
|------ ------|
11th/corr 34.3 < 69.41 34.3 > 69.41 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-8
E-2 Scenario 3.A: Winter
– Model input parameters:
Activation of Fire Alarm Manual Pull Station at any level in corridor Area in SR03:
Value
Parameter
Sequence of Operation:
Ambient Temperature 17.3 oC
Interior Temperature 20 oC
Only the staircases pressurization fans in SR03 will be activated, listed below:
Temperature of the protection area after pressurization system
17.3 oC
operation
CORRESPONDING Wind speed 6.3 m/s
FAN FUNCTION
AREA Level 10 –
Incident Floors
Stair 8 PF-P09- SR3-MR1-01 Tower-SR03 SR03
PF-P09-SR3-MR1-02 Tower-SR03 Supply
Stair 9
PF-P09-C1-01 PODIUM Area – Modeling Result
Adjusted flows are the required flows to get the overall stair shafts within the acceptable differential pressures to Manual_Pull_station_at_any_level_in_SR03_Winters shaft report
NFPA 92A.
Level 10 was assumed as incident floor. The CONTAM floor plan during the modeling is shown as Figure __. +---------------------------+
UT-2/lobb 47.2 < 81.47 47.2 > 81.47 lobb
|------ ------|
UT-1/corr 43.5 < 78.19 43.5 > 78.19 corr
|------ ------|
19th/corr 29.3 < 64.22 29.3 > 64.22 corr
|------ ------|
18th/corr 28.3 < 63.10 28.3 > 63.10 corr
|------ ------|
17th/corr 28.3 < 63.10 28.3 > 63.10 corr
|------ ------|
16th/corr 28.3 < 63.10 28.3 > 63.10 corr
|------ ------|
15th/corr 28.3 < 63.10 28.3 > 63.10 corr
|------ ------|
14th/corr 28.3 < 63.10 28.3 > 63.10 corr
|------ ------|
13th/corr 28.3 < 63.09 28.3 > 63.09 corr
|------ ------|
12th/corr 28.3 < 63.09 28.3 > 63.09 corr
|------ ------|
11th/corr 28.3 < 63.09 28.3 > 63.09 corr
|------ ------|
10th/corr 28.3 < 63.09 28.3 > 63.09 corr
|------ ------|
Figure- CONTAM Floor Plan of Tower Level 10 9th/corr 28.3 < 63.09 28.3 > 63.09 corr
|------ ------|
8th/corr 28.3 < 63.08 28.3 > 63.08 corr
|------ ------|
7th/corr 28.3 < 63.08 28.3 > 63.08 corr
|------ ------|
6th/corr 28.3 < 63.08 28.3 > 63.08 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-9
5th/corr28.3 < 63.08 28.3 > 63.08 corr 9th/corr 32.4 < 67.47 32.4 > 67.47 corr
|------ ------| |------ ------|
4th/corr 28.3 < 63.07 28.3 > 63.07 corr 8th/corr 32.4 < 67.47 32.4 > 67.47 corr
|------ ------| |------ ------|
3rd/corr 28.3 < 63.07 28.3 > 63.07 corr 7th/corr 32.4 < 67.46 32.4 > 67.46 corr
|------ ------| |------ ------|
2nd/corr 28.3 < 63.06 28.3 > 63.06 corr 6th/corr 32.4 < 67.46 32.4 > 67.46 corr
|------ ------| |------ ------|
1st/corr 28.3 < 63.06 28.3 > 63.06 corr 5th/corr 32.3 < 67.46 32.3 > 67.46 corr
|------ ------| |------ ------|
LT/stai 30.3 < 65.32 30.3 > 65.32 stai 4th/corr 32.3 < 67.45 32.3 > 67.45 corr
|------ ------| |------ ------|
C4/lobb 44.3 < 78.96 44.3 > 78.96 lobb 3rd/corr 32.3 < 67.44 32.3 > 67.44 corr
+---------------------------+ |------ ------|
2nd/corr 32.3 < 67.44 32.3 > 67.44 corr
|------ ------|
CONTAM Shaft Report at Stair 8 in SR03 after simulation (Parameters in Pa & L/s) 1st/corr 32.3 < 67.44 32.3 > 67.44 corr
|------ ------|
LT/lobb 32.5 < 67.62 32.5 > 67.62 lobb
Manual_Pull_station_at_any_level_in_SR03_Winters shaft report
C4/serv 32.5 < 67.58 32.5 > 67.58 serv
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C3/serv 32.5 < 67.57 32.5 > 67.57 serv
+---------------------------+ |------ ------|
Roof/mach 31.3 < 66.37 31.3 > 66.37 mach C2/exit 30.6 < 65.62 30.6 > 65.62 exit
|------ ------|
MR-1/ C1/exit 30.3 < 65.29 30.3 > 65.29 exit
|------ ------|
UT-2/fire 32.2 < 67.35 32.2 > 67.35 fire GRND/exit 28.5 < 63.35 28.5 > 63.35 exit
|------ ------|
UT-1/fire 31.9 < 66.95 31.9 > 66.95 fire B1/fire 57.5 < 89.97 57.5 > 89.97 fire
|------ ------| |------ ------|
19th/corr 32.4 < 67.53 32.4 > 67.53 corr B2/fire 57.1 < 89.65 57.1 > 89.65 fire
|------ ------| |------ ------|
18th/corr 32.4 < 67.51 32.4 > 67.51 corr B3/fire 57.1 < 89.59 57.1 > 89.59 fire
|------ ------| +---------------------------+
17th/corr 32.4 < 67.50 32.4 > 67.50 corr
|------ ------|
16th/corr 32.4 < 67.50 32.4 > 67.50 corr CONTAM Shaft Report at Stair 9 in SR03 after simulation (Parameters in Pa & L/s)
|------ ------|
15th/corr 32.4 < 67.49 32.4 > 67.49 corr
|------ ------|
14th/corr 32.4 < 67.49 32.4 > 67.49 corr
|------ ------|
13th/corr 32.4 < 67.49 32.4 > 67.49 corr
|------ ------|
12th/corr 32.4 < 67.48 32.4 > 67.48 corr
|------ ------|
11th/corr 32.4 < 67.48 32.4 > 67.48 corr
|------ ------|
10th/corr 32.4 < 67.47 32.4 > 67.47 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-10
Summer 5th/corr 34.3 < 69.46 34.3 > 69.46 corr
– Model input parameters: |------ ------|
4th/corr 34.3 < 69.50 34.3 > 69.50 corr
Value |------ ------|
Parameter
3rd/corr 34.4 < 69.53 34.4 > 69.53 corr
Ambient Temperature 45.1 oC |------ ------|
Interior Temperature 20 oC 2nd/corr 34.4 < 69.60 34.4 > 69.60 corr
Temperature of the protection area after pressurization system |------ ------|
45.1 oC
operation 1st/corr 34.6 < 69.74 34.6 > 69.74 corr
Wind speed 6.3 m/s |------ ------|
Level 10 – Lowe/stai 38.4 < 73.47 38.4 > 73.47 stai
Incident Floors
SR03 |------ ------|
C4/lobb 73.1 < 101.37 73.1 > 101.37 lobb
– Modeling Result +---------------------------+
Manual_Pull_station_at_any_level_in_SR03_Summers shaft report CONTAM Shaft Report at Stair 8 in SR03 after simulation (Parameters in Pa & L/s)
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-11
|------ ------|
8th/corr 42.9 < 77.69 42.9 > 77.69 corr
E-2 Scenario 4.A:
|------ ------| Activation of Fire Alarm Manual Pull Station at any level in Podium Area
7th/corr 43.0 < 77.75 43.0 > 77.75 corr Sequence of Operation:
|------ ------|
6th/corr 43.1 < 77.82 43.1 > 77.82 corr All the staircases pressurization fans will be activated, listed below:
|------ ------|
5th/corr 43.1 < 77.90 43.1 > 77.90 corr CORRESPONDING
FAN FUNCTION
|------ ------| AREA
4th/corr 43.2 < 77.98 43.2 > 77.98 corr Stair 1 PF-P09-G1-01 PODIUM Area
|------ ------| PF-P09-LT-01 PODIUM Area
Stair 2
3rd/corr 43.3 < 78.06 43.3 > 78.06 corr PF-SR7A-MR1-01 Tower-SR07A
|------ ------| PF-P09-LT-02 PODIUM Area
Stair 3A
2nd/corr 43.5 < 78.21 43.5 > 78.21 corr PF-SR7B-MR1-01 Tower-SR07B
|------ ------| Stair 3B PF-P09-LT-03 PODIUM Area
1st/corr 43.8 < 78.52 43.8 > 78.52 corr Stair 4 PF-P09-C3-01 PODIUM Area
PF-P09-C4-01 PODIUM Area
|------ ------| Stair 5 Supply
PF-SR7A-MR1-02 Tower-SR07A
Lowe/lobb 45.8 < 80.25 45.8 > 80.25 lobb
PF-P09-LT-04 PODIUM Area
Stair 6
PF-SR7B-MR1-02 Tower-SR07B
C4/serv 46.1 < 80.54 46.1 > 80.54 serv Stair 7 PF-P09-C4-02 PODIUM Area
|------ ------| Stair 8 PF-P09-LT-05 PODIUM Area
C3/serv 46.3 < 80.73 46.3 > 80.73 serv Stair 8A PF-P09- SR3-MR1-01 Tower-SR03
|------ ------| PF-P09-SR3-MR1-02 Tower-SR03
C2/exit 47.0 < 81.28 47.0 > 81.28 exit Stair 9
PF-P09-C1-01 PODIUM Area
|------ ------|
C1/exit 48.8 < 82.86 48.8 > 82.86 exit Adjusted flows are the required flows to get the overall stair shafts within the acceptable differential pressures to
|------ ------| NFPA 92A.
GRND/exit 49.3 < 83.27 49.3 > 83.27 exit
|------ ------| The CONTAM floor plan during the modeling is shown as Figure __.
B1/fire 55.9 < 88.66 55.9 > 88.66 fire
|------ ------|
B2/fire 52.5 < 85.97 52.5 > 85.97 fire
|------ ------|
B3/fire 51.7 < 85.31 51.7 > 85.31 fire
+---------------------------+
CONTAM Shaft Report at Stair 9 in SR03 after simulation (Parameters in Pa & L/s)
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-12
Winter
– Model input parameters: Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-13
C3/VST 30.8 < 65.81 30.8 > 65.81 VST |------ ------|
|------ ------| 3rd/corr 25.6 < 60.02 25.6 > 60.02 corr
C2/exit 44.6 < 79.19 44.6 > 79.19 exit |------ ------|
|------ ------| 2nd/corr 25.6 < 60.02 25.6 > 60.02 corr
C1/exit 44.8 < 79.36 44.8 > 79.36 exit |------ ------|
|------ ------| 1st/corr 25.6 < 60.03 25.6 > 60.03 corr
GRND/ |------ ------|
|------ ------| LT/stai 43.2 < 77.91 43.2 > 77.91 stai |-
B1/serv
45.2 < 79.72 45.2 > 79.72 serv ----- ------|
+---------------------------+ C4/exit 52.9 < 86.27 52.9 > 86.27 exit
CONTAM Shaft Report at Stair 2 after simulation (Parameters in Pa & L/s) |------ ------|
C3/exit 56.1 < 88.82 56.1 > 88.82 exit
|------ ------|
Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report C2/exit 47.9 < 82.06 47.9 > 82.06 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone +---------------------------+
CONTAM Shaft Report at Stair 3A after simulation (Parameters in Pa & L/s)
+---------------------------+
UT-2/exit 39.6 < 74.62 39.6 > 74.62 exit
|------ ------| Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report
UT-1/exit 35.8 < 70.95 35.8 > 70.95 exit level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------|
19th/corr 25.7 < 60.07 25.7 > 60.07 corr +---------------------------+
|------ ------| C2/exit 27.4 < 62.05 27.4 > 62.05 exit
18th/corr 25.6 < 60.04 25.6 > 60.04 corr |------ ------|
|------ ------| C1/elev 30.8 < 65.87 30.8 > 65.87 elev
17th/corr 25.6 < 60.04 25.6 > 60.04 corr |------ ------|
|------ ------| GRND/stai 29.8 < 64.79 29.8 > 64.79 stai
16th/corr 25.6 < 60.04 25.6 > 60.04 corr |------ ------|
|------ ------| B1/exit 27.1 < 61.72 27.1 > 61.72 exit
15th/corr 25.6 < 60.04 25.6 > 60.04 corr |------ ------|
|------ ------| B2/exit 23.5 < 57.45 23.5 > 57.45 exit
14th/corr 25.6 < 60.04 25.6 > 60.04 corr |------ ------|
|------ ------| B3/exit 23.3 < 57.30 23.3 > 57.30 exit
13th/corr 25.6 < 60.04 25.6 > 60.04 corr +---------------------------+
|------ ------| CONTAM Shaft Report at Stair 3B after simulation (Parameters in Pa & L/s)
12th/corr 25.6 < 60.04 25.6 > 60.04 corr
|------ ------|
11th/corr 25.6 < 60.04 25.6 > 60.04 corr Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
10th/corr 25.6 < 60.04 25.6 > 60.04 corr
|------ ------| +---------------------------+
9th/corr 25.6 < 60.04 25.6 > 60.04 corr C4/lobb 55.0 < 87.94 55.0 > 87.94 lobb
|------ ------| |------ ------|
8th/corr 25.6 < 60.03 25.6 > 60.03 corr C3/exit 43.5 < 78.23 43.5 > 78.23 exit
|------ ------| |------ ------|
7th/corr 25.6 < 60.03 25.6 > 60.03 corr C2/exit 41.6 < 76.51 41.6 > 76.51 exit
|------ ------| |------ ------|
6th/corr 25.6 < 60.03 25.6 > 60.03 corr C1/main 54.0 < 87.14 54.0 > 87.14 main
|------ ------| +---------------------------+
5th/corr 25.6 < 60.03 25.6 > 60.03 corr
|------ ------| CONTAM Shaft Report at Stair 4 after simulation (Parameters in Pa & L/s)
4th/corr 25.6 < 60.03 25.6 > 60.03 corr
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-14
LT/lobb 34.8 < 70.00 34.8 > 70.00 lobb
|------ ------|
Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report C4/serv 34.8 < 69.92 34.8 > 69.92 serv
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C3/serv 34.8 < 69.95 34.8 > 69.95 serv
+---------------------------+ |------ ------|
Roof/mach 33.2 < 68.32 33.2 > 68.32 mach C2/serv 34.9 < 70.04 34.9 > 70.04 serv
|------ ------| |------ ------|
MR-1/ C1/exit 34.2 < 69.38 34.2 > 69.38 exit
|------ ------| |------ ------|
UT-2/fire 34.6 < 69.75 34.6 > 69.75 fire GRND/exit 32.0 < 67.13 32.0 > 67.13 exit
|------ ------| |------ ------|
UT-1/fire 34.2 < 69.33 34.2 > 69.33 fire B1/fire 34.1 < 69.25 34.1 > 69.25 fire
|------ ------| |------ ------|
19th/corr 34.9 < 70.04 34.9 > 70.04 corr B2/fire 34.3 < 69.43 34.3 > 69.43 fire
|------ ------| |------ ------|
18th/corr 34.8 < 70.00 34.8 > 70.00 corr B3/fire 34.3 < 69.44 34.3 > 69.44 fire
|------ ------| +---------------------------+
17th/corr 34.8 < 69.99 34.8 > 69.99 corr CONTAM Shaft Report at Stair 5 after simulation (Parameters in Pa & L/s)
|------ ------|
16th/corr 34.8 < 69.98 34.8 > 69.98 corr
|------ ------|
15th/corr 34.8 < 69.98 34.8 > 69.98 corr Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
14th/corr 34.8 < 69.97 34.8 > 69.97 corr
|------ ------| +---------------------------+
13th/corr 34.8 < 69.97 34.8 > 69.97 corr Roof/mach 33.6 < 68.77 33.6 > 68.77 mach
|------ ------| |------ ------|
12th/corr 34.8 < 69.97 34.8 > 69.97 corr MR-1/
|------ ------| |------ ------|
11th/corr 34.8 < 69.96 34.8 > 69.96 corr UT-2/fire 32.6 < 67.71 32.6 > 67.71 fire
|------ ------| |------ ------|
10th/corr 34.8 < 69.96 34.8 > 69.96 corr UT-1/fire 31.4 < 66.46 31.4 > 66.46 fire
|------ ------| |------ ------|
9th/corr 34.8 < 69.96 34.8 > 69.96 corr 19th/corr 31.0 < 65.99 31.0 > 65.99 corr
|------ ------| |------ ------|
8th/corr 34.8 < 69.95 34.8 > 69.95 corr 18th/corr 30.9 < 65.94 30.9 > 65.94 corr
|------ ------| |------ ------|
7th/corr 34.8 < 69.95 34.8 > 69.95 corr 17th/corr 30.9 < 65.94 30.9 > 65.94 corr
|------ ------| |------ ------|
6th/corr 34.8 < 69.95 34.8 > 69.95 corr 16th/corr 30.9 < 65.94 30.9 > 65.94 corr
|------ ------| |------ ------|
5th/corr 34.8 < 69.94 34.8 > 69.94 corr 15th/corr 30.9 < 65.94 30.9 > 65.94 corr
|------ ------| |------ ------|
4th/corr 34.8 < 69.94 34.8 > 69.94 corr 14th/corr 30.9 < 65.94 30.9 > 65.94 corr
|------ ------| |------ ------|
3rd/corr 34.8 < 69.94 34.8 > 69.94 corr 13th/corr 30.9 < 65.94 30.9 > 65.94 corr
|------ ------| |------ ------|
2nd/corr 34.8 < 69.94 34.8 > 69.94 corr 12th/corr 30.9 < 65.94 30.9 > 65.94 corr
|------ ------| |------ ------|
1st/corr 34.8 < 69.95 34.8 > 69.95 corr 11th/corr 30.9 < 65.94 30.9 > 65.94 corr
|------ ------| |------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-15
10th/corr 30.9 < 65.94 30.9 > 65.94 corr Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report
|------ ------|
9th/corr 30.9 < 65.94 30.9 > 65.94 corr level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------|
8th/corr 30.9 < 65.93 30.9 > 65.93 corr +---------------------------+
|------ ------| C4/lobb 61.7 < 93.18 61.7 > 93.18 lobb
7th/corr 30.9 < 65.93 30.9 > 65.93 corr |------ ------|
|------ ------| C3/lobb 61.7 < 93.18 61.7 > 93.18 lobb
6th/corr 30.9 < 65.93 30.9 > 65.93 corr |------ ------|
|------ ------| C2/ambt 61.7 < 93.19 61.7 > 93.19 ambt
5th/corr 30.9 < 65.94 30.9 > 65.94 corr |------ ------|
|------ ------| C1/lobb 61.6 < 93.11 61.6 > 93.11 lobb
4th/corr 30.9 < 65.94 30.9 > 65.94 corr |------ ------|
|------ ------| GRND/ext_ 12.7 < 42.20 12.7 > 42.20 ext_
3rd/corr 30.9 < 65.94 30.9 > 65.94 corr |------ ------|
|------ ------| B1/exit 22.4 < 56.12 22.4 > 56.12 exit
2nd/corr 30.9 < 65.94 30.9 > 65.94 corr +---------------------------+
|------ ------|
1st/corr 30.9 < 65.96 30.9 > 65.96 corr CONTAM Shaft Report at Stair 7 after simulation (Parameters in Pa & L/s)
|------ ------|
LT/lobb 32.5 < 67.57 32.5 > 67.57 lobb
|------ ------|
C4/exit 31.0 < 66.01 31.0 > 66.01 exit Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
C3/corr 31.8 < 66.88 31.8 > 66.88 corr
|------ ------| +---------------------------+
C2/exit 28.9 < 63.71 28.9 > 63.71 exit C4/corr 16.9 < 48.78 16.9 > 48.78 corr
|------ ------| |------ ------|
C1/corr 32.1 < 67.25 32.1 > 67.25 corr C3/corr 19.2 < 51.94 19.2 > 51.94 corr
|------ ------| |------ ------|
GRND/corr 32.5 < 67.59 32.5 > 67.59 corr C2/corr 18.5 < 50.95 18.5 > 50.95 corr
|------ ------| |------ ------|
B1/fire 32.9 < 68.00 32.9 > 68.00 fire C1/exit 18.7 < 51.24 18.7 > 51.24 exit
|------ ------| |------ ------|
B2/fire 33.4 < 68.50 33.4 > 68.50 fire GRND/exit 57.9 < 90.21 57.9 > 90.21 exit
|------ ------| |------ ------|
B3/fire 32.7 < 67.85 32.7 > 67.85 fire B1/room 62.9 < 94.09 62.9 > 94.09 room
+---------------------------+ |------ ------|
B2/exit 32.0 < 67.06 32.0 > 67.06 exit
CONTAM Shaft Report at Stair 6 after simulation (Parameters in Pa & L/s) |------ ------|
B3/exit 48.5 < 82.56 48.5 > 82.56 exit
+---------------------------+
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-16
CONTAM Shaft Report at Stair 8A after simulation (Parameters in Pa & L/s)
Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report Manual_Pull_station_at_any_level_in_Podium_Area_Winters shaft report
level/zone [Pa] [sL/s] [Pa] [sL/s] zone
level/zone [Pa] [sL/s] [Pa] [sL/s] zone
+---------------------------+
UT-2/lobb 47.3 < 81.60 47.3 > 81.60 lobb +---------------------------+
|------ ------| Roof/mach 31.4 < 66.48 31.4 > 66.48 mach
UT-1/corr 43.5 < 78.21 43.5 > 78.21 corr |------ ------|
|------ ------| MR-1/
19th/corr 29.3 < 64.24 29.3 > 64.24 corr |------ ------|
|------ ------| UT-2/fire 32.2 < 67.34 32.2 > 67.34 fire
18th/corr 28.3 < 63.12 28.3 > 63.12 corr |------ ------|
|------ ------| UT-1/fire 31.8 < 66.93 31.8 > 66.93 fire
17th/corr 28.3 < 63.12 28.3 > 63.12 corr |------ ------|
|------ ------| 19th/corr 32.4 < 67.51 32.4 > 67.51 corr
16th/corr 28.3 < 63.11 28.3 > 63.11 corr |------ ------|
|------ ------| 18th/corr 32.4 < 67.49 32.4 > 67.49 corr
15th/corr 28.3 < 63.11 28.3 > 63.11 corr |------ ------|
|------ ------| 17th/corr 32.4 < 67.48 32.4 > 67.48 corr
14th/corr 28.3 < 63.11 28.3 > 63.11 corr |------ ------|
|------ ------| 16th/corr 32.4 < 67.48 32.4 > 67.48 corr
13th/corr 28.3 < 63.11 28.3 > 63.11 corr |------ ------|
|------ ------| 15th/corr 32.4 < 67.47 32.4 > 67.47 corr
12th/corr 28.3 < 63.11 28.3 > 63.11 corr |------ ------|
|------ ------| 14th/corr 32.4 < 67.47 32.4 > 67.47 corr
11th/corr 28.3 < 63.11 28.3 > 63.11 corr |------ ------|
|------ ------| 13th/corr 32.4 < 67.47 32.4 > 67.47 corr
10th/corr 28.3 < 63.10 28.3 > 63.10 corr |------ ------|
|------ ------| 12th/corr 32.4 < 67.46 32.4 > 67.46 corr
9th/corr 28.3 < 63.10 28.3 > 63.10 corr |------ ------|
|------ ------| 11th/corr 32.4 < 67.46 32.4 > 67.46 corr
8th/corr 28.3 < 63.10 28.3 > 63.10 corr |------ ------|
|------ ------| 10th/corr 32.3 < 67.46 32.3 > 67.46 corr
7th/corr 28.3 < 63.10 28.3 > 63.10 corr |------ ------|
|------ ------| 9th/corr 32.3 < 67.45 32.3 > 67.45 corr
6th/corr 28.3 < 63.10 28.3 > 63.10 corr |------ ------|
|------ ------| 8th/corr 32.3 < 67.45 32.3 > 67.45 corr
5th/corr 28.3 < 63.09 28.3 > 63.09 corr |------ ------|
|------ ------| 7th/corr 32.3 < 67.44 32.3 > 67.44 corr
4th/corr 28.3 < 63.09 28.3 > 63.09 corr |------ ------|
|------ ------| 6th/corr 32.3 < 67.44 32.3 > 67.44 corr
3rd/corr 28.3 < 63.08 28.3 > 63.08 corr |------ ------|
|------ ------| 5th/corr 32.3 < 67.44 32.3 > 67.44 corr
2nd/corr 28.3 < 63.08 28.3 > 63.08 corr |------ ------|
|------ ------| 4th/corr 32.3 < 67.43 32.3 > 67.43 corr
1st/corr 28.3 < 63.08 28.3 > 63.08 corr |------ ------|
|------ ------| 3rd/corr 32.3 < 67.42 32.3 > 67.42 corr
LT/stai 30.4 < 65.35 30.4 > 65.35 stai |------ ------|
|------ ------| 2nd/corr 32.3 < 67.42 32.3 > 67.42 corr
C4/lobb 44.4 < 79.04 44.4 > 79.04 lobb |------ ------|
+---------------------------+ 1st/corr 32.3 < 67.43 32.3 > 67.43 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-17
LT/lobb 32.5 < 67.62 32.5 > 67.62 lobb CONTAM Shaft Report at Stair 1 after simulation (Parameters in Pa & L/s)
|------ ------| Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report
C4/serv 32.4 < 67.56 32.4 > 67.56 serv
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
C3/serv 32.4 < 4.33 32.4 > 4.33
serv
|------ ------| +---------------------------+
C2/exit 30.4 < 4.20 30.4 > 4.20 exit UT-2/lobb 10.6 < 38.69 10.6 > 38.69 lobb
|------ ------| |------ ------|
C1/exit 30.2 < 65.20 30.2 > 65.20 exit UT-1/corr 48.4 < 82.50 48.4 > 82.50 corr
|------ ------| |------ ------|
GRND/exit 54.1 < 87.26 54.1 > 87.26 exit 19th/corr 36.2 < 71.31 36.2 > 71.31 corr
|------ ------|
B1/fire 57.4 < 89.89 57.4 > 89.89 fire 18th/corr 35.6 < 70.79 35.6 > 70.79 corr
|------ ------| |------ ------|
B2/fire 57.2 < 89.69 57.2 > 89.69 fire 17th/corr 35.7 < 70.84 35.7 > 70.84 corr
|------ ------| |------ ------|
B3/fire 57.1 < 89.59 57.1 > 89.59 fire 16th/corr 35.7 < 70.91 35.7 > 70.91 corr
+---------------------------+ |------ ------|
15th/corr 35.8 < 70.95 35.8 > 70.95 corr
CONTAM Shaft Report at Stair 9 after simulation (Parameters in Pa & L/s) |------ ------|
14th/corr 35.8 < 70.99 35.8 > 70.99 corr
|------ ------|
13th/corr 35.9 < 71.03 35.9 > 71.03 corr
Summer |------ ------|
– Model input parameters: 12th/corr 35.9 < 71.06 35.9 > 71.06 corr
|------ ------|
Value 11th/corr 35.9 < 71.09 35.9 > 71.09 corr
Parameter
|------ ------|
Ambient Temperature 45.1 oC 10th/corr 36.0 < 71.13 36.0 > 71.13 corr
Interior Temperature 20 oC |------ ------|
Temperature of the protection area after pressurization system 9th/corr 36.0 < 71.16 36.0 > 71.16 corr
45.1 oC
operation |------ ------|
Wind speed 6.3 m/s 8th/corr 36.0 < 71.20 36.0 > 71.20 corr
Level 10 – |------ ------|
Incident Floors
SR03 7th/corr 36.1 < 71.24 36.1 > 71.24 corr
|------ ------|
– Modeling Result 6th/corr 36.1 < 71.28 36.1 > 71.28 corr
|------ ------|
Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report 5th/corr 36.2 < 71.32 36.2 > 71.32 corr
|------ ------|
level/zone [Pa] [sL/s] [Pa] [sL/s] zone 4th/corr 36.2 < 71.37 36.2 > 71.37 corr
|------ ------|
+---------------------------+ 3rd/corr 36.3 < 71.41 36.3 > 71.41 corr
GRND/exit 38.1 < 73.22 38.1 > 73.22 exit |------ ------|
|------ ------| 2nd/corr 36.3 < 71.41 36.3 > 71.41 corr
B1/exit 30.8 < 65.87 30.8 > 65.87 exit |------ ------|
|------ ------| 1st/corr 35.5 < 70.68 35.5 > 70.68 corr
B2/exit 26.2 < 60.70 26.2 > 60.70 exit
|------ ------| LT/lobb 56.0 < 88.74 56.0 > 88.74 lobb
B3/exit 26.7 < 61.29 26.7 > 61.29 exit |------ ------|
+---------------------------+ C4/exit 62.9 < 94.05 62.9 > 94.05 exit
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-18
C3/VST 44.4 < 79.03 44.4 > 79.03 VST 5th/corr 26.2 < 60.71 26.2 > 60.71 corr
|------ ------| |------ ------|
C2/exit 57.0 < 89.52 57.0 > 89.52 exit 4th/corr 26.2 < 60.71 26.2 > 60.71 corr
|------ ------| |------ ------|
C1/exit 61.7 < 93.19 61.7 > 93.19 exit 3rd/corr 26.2 < 60.71 26.2 > 60.71 corr
|------ ------| |------ ------|
GRND/ 2nd/corr 26.2 < 60.72 26.2 > 60.72 corr
|------ ------| |------ ------|
B1/serv 61.4 < 92.92 61.4 > 92.92 serv 1st/corr 26.2 < 60.76 26.2 > 60.76 corr
+---------------------------+ |------ ------|
LT/stai 46.8 < 81.17 46.8 > 81.17 stai
CONTAM Shaft Report at Stair 2 after simulation (Parameters in Pa & L/s) |------ ------|
C4/exit 77.8 < 104.64 77.8 > 104.64 exit
|------ ------|
C3/exit 90.8 < 113.03 90.8 > 113.03 exit
Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report |------ ------|
C2/exit 76.7 < 103.88 76.7 > 103.88 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone +---------------------------+
+---------------------------+ CONTAM Shaft Report at Stair 3A after simulation (Parameters in Pa & L/s)
UT-2/exit 20.7 < 54.00 20.7 > 54.00 exit
|------ ------|
UT-1/exit 29.0 < 63.85 29.0 > 63.85 exit
|------ ------| Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report
19th/corr 25.7 < 60.09 25.7 > 60.09 corr
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
18th/corr 25.8 < 60.27 25.8 > 60.27 corr
|------ ------| +---------------------------+
17th/corr 25.9 < 60.35 25.9 > 60.35 corr C2/exit 35.4 < 70.57 35.4 > 70.57 exit
|------ ------| |------ ------|
16th/corr 25.9 < 60.40 25.9 > 60.40 corr C1/elev 12.8 < 42.44 12.8 > 42.44 elev
|------ ------| |------ ------|
15th/corr 26.0 < 60.44 26.0 > 60.44 corr GRND/stai 18.5 < 50.99 18.5 > 50.99 stai
|------ ------| |------ ------|
14th/corr 26.0 < 60.47 26.0 > 60.47 corr B1/exit 47.6 < 81.81 47.6 > 81.81 exit
|------ ------| |------ ------|
13th/corr 26.0 < 60.52 26.0 > 60.52 corr B2/exit 42.8 < 77.59 42.8 > 77.59 exit
|------ ------| |------ ------|
12th/corr 26.1 < 60.57 26.1 > 60.57 corr B3/exit 42.6 < 77.44 42.6 > 77.44 exit
|------ ------| +---------------------------+
11th/corr 26.2 < 60.67 26.2 > 60.67 corr
|------ ------|
10th/corr 26.2 < 60.69 26.2 > 60.69 corr CONTAM Shaft Report at Stair 3B after simulation (Parameters in Pa & L/s)
|------ ------|
9th/corr 26.2 < 60.70 26.2 > 60.70 corr
|------ ------|
8th/corr 26.2 < 60.70 26.2 > 60.70 corr
|------ ------|
7th/corr 26.2 < 60.70 26.2 > 60.70 corr
|------ ------|
6th/corr 26.2 < 60.70 26.2 > 60.70 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-19
7th/corr46.3 < 80.70 46.3 > 80.70 corr
Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report |------ ------|
level/zone [Pa] [sL/s] [Pa] [sL/s] zone 6th/corr 46.4 < 80.78 46.4 > 80.78 corr
+---------------------------+ |------ ------|
C4/lobb 53.9 < 87.06 53.9 > 87.06 lobb 5th/corr 46.5 < 80.87 46.5 > 80.87 corr
|------ ------| |------ ------|
C3/exit 43.4 < 78.11 43.4 > 78.11 exit 4th/corr 46.6 < 80.97 46.6 > 80.97 corr
|------ ------| |------ ------|
C2/exit 42.4 < 77.27 42.4 > 77.27 exit 3rd/corr 46.7 < 81.09 46.7 > 81.09 corr
|------ ------| |------ ------|
C1/main 53.8 < 87.00 53.8 > 87.00 main 2nd/corr 46.9 < 81.24 46.9 > 81.24 corr
+---------------------------+ |------ ------|
1st/corr 47.2 < 81.47 47.2 > 81.47 corr
CONTAM Shaft Report at Stair 4 after simulation (Parameters in Pa & L/s) |------ ------|
LT/lobb 48.0 < 82.18 48.0 > 82.18 lobb
|------ ------|
Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report C4/serv 48.4 < 82.49 48.4 > 82.49 serv
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C3/serv 51.4 < 85.05 51.4 > 85.05 serv
+---------------------------+ |------ ------|
Roof/mach 4.9 > 26.28 4.9 < 26.28 mach C2/serv 48.8 < 82.82 48.8 > 82.82 serv
|------ ------| |------ ------|
MR-1/ C1/exit 47.5 < 81.72 47.5 > 81.72 exit
|------ ------| |------ ------|
UT-2/fire 32.3 < 67.40 32.3 > 67.40 fire GRND/exit 44.2 < 78.87 44.2 > 78.87 exit
|------ ------| |------ ------|
UT-1/fire 40.3 < 75.34 40.3 > 75.34 fire B1/fire 44.1 < 78.76 44.1 > 78.76 fire
|------ ------| |------ ------|
19th/corr 44.3 < 78.90 44.3 > 78.90 corr B2/fire 44.6 < 79.19 44.6 > 79.19 fire
|------ ------| |------ ------|
18th/corr 45.1 < 79.69 45.1 > 79.69 corr B3/fire 44.7 < 79.33 44.7 > 79.33 fire
|------ ------| +---------------------------+
17th/corr 45.4 < 79.94 45.4 > 79.94 corr
|------ ------| CONTAM Shaft Report at Stair 5 after simulation (Parameters in Pa & L/s)
16th/corr 45.6 < 80.07 45.6 > 80.07 corr
|------ ------|
15th/corr 45.7 < 80.15 45.7 > 80.15 corr Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report
|------ ------|
14th/corr 45.7 < 80.22 45.7 > 80.22 corr level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------| +---------------------------+
13th/corr 45.8 < 80.28 45.8 > 80.28 corr Roof/mach 1.0 < 11.65 1.0 > 11.65 mach
|------ ------| |------ ------|
12th/corr 45.9 < 80.35 45.9 > 80.35 corr MR-1/
|------ ------| |------ ------|
11th/corr 46.0 < 80.41 46.0 > 80.41 corr UT-2/fire 30.7 < 65.69 30.7 > 65.69 fire
|------ ------| |------ ------|
10th/corr 46.0 < 80.48 46.0 > 80.48 corr UT-1/fire 34.8 < 69.99 34.8 > 69.99 fire
|------ ------| |------ ------|
9th/corr 46.1 < 80.55 46.1 > 80.55 corr 19th/corr 32.8 < 67.89 32.8 > 67.89 corr
|------ ------| |------ ------|
8th/corr 46.2 < 80.62 46.2 > 80.62 corr 18th/corr 33.1 < 68.22 33.1 > 68.22 corr
|------ ------| |------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-20
17th/corr 33.2 < 68.36 33.2 > 68.36 corr CONTAM Shaft Report at Stair 6 after simulation (Parameters in Pa & L/s)
|------ ------|
16th/corr 33.3 < 68.43 33.3 > 68.43 corr Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report
|------ ------|
15th/corr 33.4 < 68.50 33.4 > 68.50 corr level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------|
14th/corr 33.4 < 68.57 33.4 > 68.57 corr +---------------------------+
|------ ------| C4/lobb 61.4 < 92.95 61.4 > 92.95 lobb
13th/corr 33.5 < 68.64 33.5 > 68.64 corr |------ ------|
|------ ------| C3/lobb 61.4 < 92.97 61.4 > 92.97 lobb
12th/corr 33.6 < 68.74 33.6 > 68.74 corr |------ ------|
|------ ------| C2/ambt 64.2 < 95.00 64.2 > 95.00 ambt
11th/corr 33.8 < 68.91 33.8 > 68.91 corr |------ ------|
|------ ------| C1/lobb 61.1 < 92.70 61.1 > 92.70 lobb
10th/corr 33.8 < 68.95 33.8 > 68.95 corr |------ ------|
|------ ------| GRND/ext_ 9.8 < 37.18 9.8 > 37.18 ext_
9th/corr 33.8 < 68.97 33.8 > 68.97 corr |------ ------|
|------ ------| B1/exit 21.8 < 55.33 21.8 > 55.33 exit
8th/corr 33.8 < 68.98 33.8 > 68.98 corr +---------------------------+
|------ ------| CONTAM Shaft Report at Stair 7 after simulation (Parameters in Pa & L/s)
7th/corr 33.8 < 68.98 33.8 > 68.98 corr
|------ ------| Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report
6th/corr 33.8 < 68.99 33.8 > 68.99 corr
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
5th/corr 33.8 < 69.00 33.8 > 69.00 corr
|------ ------| +---------------------------+
4th/corr 33.9 < 69.02 33.9 > 69.02 corr C4/corr 13.3 < 43.19 13.3 > 43.19 corr
|------ ------| |------ ------|
3rd/corr 33.9 < 69.04 33.9 > 69.04 corr C3/corr 18.9 < 51.60 18.9 > 51.60 corr
|------ ------| |------ ------|
2nd/corr 33.9 < 69.06 33.9 > 69.06 corr C2/corr 14.5 < 45.21 14.5 > 45.21 corr
|------ ------| |------ ------|
1st/corr 34.0 < 69.15 34.0 > 69.15 corr C1/exit 19.3 < 52.04 19.3 > 52.04 exit
|------ ------| |------ ------|
LT/lobb 40.7 < 75.70 40.7 > 75.70 lobb GRND/exit 56.3 < 88.97 56.3 > 88.97 exit
|------ ------| |------ ------|
C4/exit 39.9 < 74.90 39.9 > 74.90 exit B1/room 59.0 < 91.12 59.0 > 91.12 room
|------ ------| |------ ------|
C3/corr 38.3 < 73.44 38.3 > 73.44 corr B2/exit 34.0 < 69.18 34.0 > 69.18 exit
|------ ------| |------ ------|
C2/exit 48.5 < 82.63 48.5 > 82.63 exit B3/exit 51.3 < 84.97 51.3 > 84.97 exit
|------ ------| +---------------------------+
C1/corr 40.5 < 75.44 40.5 > 75.44 corr
|------ ------| CONTAM Shaft Report at Stair 8 after simulation (Parameters in Pa & L/s)
GRND/corr 42.3 < 77.10 42.3 > 77.10 corr
|------ ------|
B1/fire 45.7 < 80.16 45.7 > 80.16 fire
|------ ------|
B2/fire 51.9 < 85.45 51.9 > 85.45 fire
|------ ------|
B3/fire 41.0 < 75.95 41.0 > 75.95 fire
+---------------------------+
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-21
Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report Manual_Pull_station_at_any_level_in_Podium_Area_Summers shaft report
level/zone [Pa] [sL/s] [Pa] [sL/s] zone
+---------------------------+ level/zone [Pa] [sL/s] [Pa] [sL/s] zone
UT-2/lobb 14.7 < 45.54 14.7 > 45.54 lobb
|------ ------| +---------------------------+
UT-1/corr 47.0 < 81.34 47.0 > 81.34 corr Roof/mach 3.6 > 22.51 3.6 < 22.51 mach
|------ ------| |------ ------|
19th/corr 34.7 < 69.85 34.7 > 69.85 corr MR-1/
|------ ------| |------ ------|
18th/corr 33.8 < 68.94 33.8 > 68.94 corr UT-2/fire 31.4 < 66.46 31.4 > 66.46 fire
|------ ------| |------ ------|
17th/corr 33.9 < 69.04 33.9 > 69.04 corr UT-1/fire 37.9 < 73.06 37.9 > 73.06 fire
|------ ------| |------ ------|
16th/corr 33.9 < 69.09 33.9 > 69.09 corr 19th/corr 41.3 < 76.19 41.3 > 76.19 corr
|------ ------| |------ ------|
15th/corr 34.0 < 69.13 34.0 > 69.13 corr 18th/corr 42.0 < 76.84 42.0 > 76.84 corr
|------ ------| |------ ------|
14th/corr 34.0 < 69.16 34.0 > 69.16 corr 17th/corr 42.2 < 77.05 42.2 > 77.05 corr
|------ ------| |------ ------|
13th/corr 34.0 < 69.18 34.0 > 69.18 corr 16th/corr 42.3 < 77.15 42.3 > 77.15 corr
|------ ------| |------ ------|
12th/corr 34.1 < 69.21 34.1 > 69.21 corr 15th/corr 42.4 < 77.22 42.4 > 77.22 corr
|------ ------| |------ ------|
11th/corr 34.1 < 69.24 34.1 > 69.24 corr 14th/corr 42.5 < 77.28 42.5 > 77.28 corr
|------ ------| |------ ------|
10th/corr 34.1 < 69.26 34.1 > 69.26 corr 13th/corr 42.5 < 77.34 42.5 > 77.34 corr
|------ ------| |------ ------|
9th/corr 34.1 < 69.29 34.1 > 69.29 corr 12th/corr 42.6 < 77.40 42.6 > 77.40 corr
|------ ------| |------ ------|
8th/corr 34.2 < 69.32 34.2 > 69.32 corr 11th/corr 42.6 < 77.45 42.6 > 77.45 corr
|------ ------| |------ ------|
7th/corr 34.2 < 69.35 34.2 > 69.35 corr 10th/corr 42.7 < 77.51 42.7 > 77.51 corr
|------ ------| |------ ------|
6th/corr 34.2 < 69.38 34.2 > 69.38 corr 9th/corr 42.8 < 77.57 42.8 > 77.57 corr
|------ ------| |------ ------|
5th/corr 34.3 < 69.42 34.3 > 69.42 corr 8th/corr 42.9 < 77.64 42.9 > 77.64 corr
|------ ------| |------ ------|
4th/corr 34.3 < 69.45 34.3 > 69.45 corr 7th/corr 42.9 < 77.71 42.9 > 77.71 corr
|------ ------| |------ ------|
3rd/corr 34.3 < 69.48 34.3 > 69.48 corr 6th/corr 43.0 < 77.78 43.0 > 77.78 corr
|------ ------| |------ ------|
2nd/corr 34.4 < 69.56 34.4 > 69.56 corr 5th/corr 43.1 < 77.85 43.1 > 77.85 corr
|------ ------| |------ ------|
1st/corr 34.5 < 69.69 34.5 > 69.69 corr 4th/corr 43.2 < 77.94 43.2 > 77.94 corr
|------ ------| |------ ------|
LT/stai 38.3 < 73.44 38.3 > 73.44 stai 3rd/corr 43.3 < 78.01 43.3 > 78.01 corr
|------ ------| |------ ------|
C4/lobb 73.0 < 101.33 73.0 > 101.33 lobb 2nd/corr 43.4 < 78.18 43.4 > 78.18 corr
+---------------------------+ |------ ------|
CONTAM Shaft Report at Stair 8A after simulation (Parameters in Pa & L/s) 1st/corr 43.8 < 78.48 43.8 > 78.48 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-22
LT/lobb 45.8 < 80.24 45.8 > 80.24 lobb
E-2 Scenario 1.B:
C4/serv 46.0 < 80.48 46.0 > 80.48 serv
|------ ------| Activation of Fire signal from Back of house service area in Tower S07A
C3/serv 46.2 < 80.65 46.2 > 80.65 serv
|------ ------| Sequence of Operation:
C2/exit 46.7 < 81.05 46.7 > 81.05 exit
Only the staircases and Fire Lift pressurization fans in S07A will be activated, listed below:
C1/exit 48.6 < 82.66 48.6 > 82.66 exit
|------ ------|
CORRESPONDING
GRND/exit 49.1 < 83.07 49.1 > 83.07 exit i FAN FUNCTION
AREA
PF-SR7A-MR1-01 Tower-S07A
B1/fire 55.7 < 88.50 55.7 > 88.50 fire Stair 2
PF-P09-LT-01 PODIUM Area
|------ ------| PF-SR7A-MR1-02 Tower-S07A
B2/fire 52.7 < 86.06 52.7 > 86.06 fire Stair 5
PF-P09-C4-01 PODIUM Area
|------ ------| Supply
Fire Lift PF-P9-SR7A-MR1-04-01 Tower-S07A
B3/fire 51.9 < 85.42 51.9 > 85.42 fire S07A-07 PODIUM Area
+---------------------------+ Fire Lift Tower-S07A
PF-P9-SR7A-MR1-04-02
S07A-08 PODIUM Area
CONTAM Shaft Report at Stair 9 after simulation (Parameters in Pa & L/s)
Adjusted flows are the required flows to get the overall stair shafts within the acceptable differential pressures to
NFPA 92A.
Level 10 was assumed as incident floor. The CONTAM floor plan during the modeling is shown as Figure __.
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-23
|------ ------|
6th/corr29.3 < 64.21 29.3 > 64.21 corr
Winter |------ ------|
– Model input parameters: 5th/corr 29.3 < 64.20 29.3 > 64.20 corr
|------ ------|
Value 4th/corr 29.3 < 64.20 29.3 > 64.20 corr
Parameter
|------ ------|
Ambient Temperature 17.3 oC 3rd/corr 29.3 < 64.19 29.3 > 64.19 corr
Interior Temperature 20 oC |------ ------|
Temperature of the protection area after pressurization system 2nd/corr 29.3 < 64.14 29.3 > 64.14 corr
17.3 oC
operation |------ ------|
Wind speed 6.3 m/s 1st/corr 28.6 < 63.46 28.6 > 63.46 corr
Level 10 – |------ ------|
Incident Floors
S07A LT/lobb 44.6 < 79.18 44.6 > 79.18 lobb
|------ ------|
– Modeling Result C4/exit 48.8 < 82.84 48.8 > 82.84 exit
|------ ------|
Fire_signal_from_Back_of_house_service_area_tower_S07A_Winters C3/VST 34.4 < 69.54 34.4 > 69.54 VST
shaft report |------ ------|
C2/exit 45.1 < 79.67 45.1 > 79.67 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C1/exit 45.7 < 80.21 45.7 > 80.21 exit
+---------------------------+ |------ ------|
UT-2/lobb 46.1 < 80.53 46.1 > 80.53 lobb GRND/exit 22.2 < 138.86 22.2 > 138.86 exit
|------ ------| |------ ------|
UT-1/corr 44.9 < 79.48 44.9 > 79.48 corr B1/serv 42.5 < 77.35 42.5 > 77.35 serv
|------ ------| +---------------------------+
19th/corr 30.4 < 65.35 30.4 > 65.35 corr
|------ ------| CONTAM Shaft Report at Stair 2 in S07A after simulation (Parameters in Pa & L/s)
18th/corr 29.5 < 64.37 29.5 > 64.37 corr
|------ ------|
17th/corr 29.4 < 64.29 29.4 > 64.29 corr Fire_signal_from_Back_of_house_service_area_tower_S07A_Winters shaft report
|------ ------|
16th/corr 29.4 < 64.27 29.4 > 64.27 corr
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
15th/corr 29.4 < 64.26 29.4 > 64.26 corr
|------ ------| +---------------------------+
14th/corr 29.3 < 64.25 29.3 > 64.25 corr Roof/mach 35.2 < 70.41 35.2 > 70.41 mach
|------ ------| |------ ------|
13th/corr 29.3 < 64.25 29.3 > 64.25 corr MR-1/ambt 69.8 < 99.07 69.8 > 99.07 ambt
|------ ------| |------ ------|
12th/corr 29.3 < 64.24 29.3 > 64.24 corr UT-2/fire 11.4 < 40.00 11.4 > 40.00 fire
|------ ------| |------ ------|
11th/corr 29.3 < 64.24 29.3 > 64.24 corr UT-1/fire 11.2 < 39.76 11.2 > 39.76 fire
|------ ------| |------ ------|
10th/corr 29.3 < 64.23 29.3 > 64.23 corr 19th/corr 51.4 < 85.02 51.4 > 85.02 corr
|------ ------| |------ ------|
9th/corr 29.3 < 64.22 29.3 > 64.22 corr 18th/corr 51.3 < 84.97 51.3 > 84.97 corr
|------ ------| |------ ------|
8th/corr 29.3 < 64.22 29.3 > 64.22 corr 17th/corr 51.3 < 84.94 51.3 > 84.94 corr
|------ ------| |------ ------|
7th/corr 29.3 < 64.21 29.3 > 64.21 corr 16th/corr 51.3 < 84.93 51.3 > 84.93 corr
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-24
|------ ------|
15th/corr 51.3 < 84.92 51.3 > 84.92 corr
|------ ------| Fire_signal_from_Back_of_house_service_area_tower_S07A_Winters shaft report
14th/corr 51.2 < 84.91 51.2 > 84.91 corr
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
13th/corr 51.2 < 84.90 51.2 > 84.90 corr
|------ ------| +---------------------------+
12th/corr 51.2 < 84.89 51.2 > 84.89 corr MR-1/mech 28.3 < 227.98 28.3 > 227.98 mech
|------ ------| |------ ------|
11th/corr 51.2 < 84.88 51.2 > 84.88 corr UT-2/fire 23.6 < 207.86 23.6 > 207.86 fire
|------ ------| |------ ------|
10th/corr 51.2 < 84.87 51.2 > 84.87 corr UT-1/fire 23.3 < 206.64 23.3 > 206.64 fire
|------ ------| |------ ------|
9th/corr 51.2 < 84.87 51.2 > 84.87 corr 19th/fire 23.4 < 207.00 23.4 > 207.00 fire
|------ ------| |------ ------|
8th/corr 51.2 < 84.86 51.2 > 84.86 corr 18th/fire 23.3 < 206.55 23.3 > 206.55 fire
|------ ------| |------ ------|
7th/corr 51.2 < 84.85 51.2 > 84.85 corr 17th/fire 23.2 < 206.21 23.2 > 206.21 fire
|------ ------| |------ ------|
6th/corr 51.2 < 84.85 51.2 > 84.85 corr 16th/fire 23.1 < 205.91 23.1 > 205.91 fire
|------ ------| |------ ------|
5th/corr 51.2 < 84.84 51.2 > 84.84 corr 15th/fire 23.0 < 205.62 23.0 > 205.62 fire
|------ ------| |------ ------|
4th/corr 51.2 < 84.84 51.2 > 84.84 corr 14th/fire 23.0 < 205.36 23.0 > 205.36 fire
|------ ------| |------ ------|
3rd/corr 51.2 < 84.84 51.2 > 84.84 corr 13th/fire 22.9 < 205.11 22.9 > 205.11 fire
|------ ------| |------ ------|
2nd/corr 51.2 < 84.87 51.2 > 84.87 corr 12th/fire 22.9 < 204.87 22.9 > 204.87 fire
|------ ------| |------ ------|
1st/corr 51.3 < 84.98 51.3 > 84.98 corr 11th/fire 22.8 < 204.66 22.8 > 204.66 fire
|------ ------| |------ ------|
LT/lobb 51.9 < 85.43 51.9 > 85.43 lobb 10th/fire 22.8 < 204.46 22.8 > 204.46 fire
|------ ------| |------ ------|
C4/serv 44.7 < 79.30 44.7 > 79.30 serv 9th/fire 22.7 < 204.27 22.7 > 204.27 fire
|------ ------| |------ ------|
C3/serv 46.4 < 80.76 46.4 > 80.76 serv 8th/fire 22.7 < 204.10 22.7 > 204.10 fire
|------ ------| |------ ------|
C2/serv 52.4 < 85.87 52.4 > 85.87 serv 7th/fire 22.7 < 203.94 22.7 > 203.94 fire
|------ ------| |------ ------|
C1/exit 33.6 < 68.72 33.6 > 68.72 exit 6th/fire 22.6 < 203.79 22.6 > 203.79 fire
|------ ------| |------ ------|
GRND/exit 21.3 < 54.75 21.3 > 54.75 exit 5th/fire 22.6 < 203.66 22.6 > 203.66 fire
|------ ------| |------ ------|
B1/fire 12.0 < 41.07 12.0 > 41.07 fire 4th/fire 22.6 < 203.54 22.6 > 203.54 fire
|------ ------| |------ ------|
B2/fire 11.8 < 40.79 11.8 > 40.79 fire 3rd/fire 22.6 < 203.44 22.6 > 203.44 fire
|------ ------| |------ ------|
B3/fire 11.8 < 40.73 11.8 > 40.73 fire 2nd/fire 22.5 < 203.35 22.5 > 203.35 fire
+---------------------------+ |------ ------|
1st/fire 22.5 < 203.36 22.5 > 203.36 fire
CONTAM Shaft Report at Stair 5 in S07A after simulation (Parameters in Pa & L/s) |------ ------|
LT/fire 22.9 < 205.04 22.9 > 205.04 fire
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-25
|------ ------| 16th/corr 33.0 < 68.10 33.0 > 68.10 corr
C4/fire22.5 < 203.09 22.5 > 203.09 fire |------ ------|
|------ ------| 15th/corr 33.1 < 68.19 33.1 > 68.19 corr
C3/fire 22.5 < 203.12 22.5 > 203.12 fire |------ ------|
|------ ------| 14th/corr 33.1 < 68.27 33.1 > 68.27 corr
C2/fire 22.7 < 204.14 22.7 > 204.14 fire |------ ------|
|------ ------| 13th/corr 33.2 < 68.35 33.2 > 68.35 corr
C1/fire 25.6 < 216.84 25.6 > 216.84 fire |------ ------|
|------ ------| 12th/corr 33.3 < 68.43 33.3 > 68.43 corr
GRND/fire 13.9 < 1721.08 13.9 > 1721.08 fire |------ ------|
|------ ------| 11th/corr 33.4 < 68.50 33.4 > 68.50 corr
B1/fire 22.8 < 204.69 22.8 > 204.69 fire |------ ------|
|------ ------| 10th/corr 33.4 < 68.58 33.4 > 68.58 corr
B2/fire 22.7 < 203.94 22.7 > 203.94 fire |------ ------|
|------ ------| 9th/corr 33.5 < 68.67 33.5 > 68.67 corr
B3/fire 22.6 < 203.79 22.6 > 203.79 fire |------ ------|
+---------------------------+ 8th/corr 33.6 < 68.76 33.6 > 68.76 corr
|------ ------|
7th/corr 33.7 < 68.87 33.7 > 68.87 corr
CONTAM Shaft Report at Elevator S07A-07 in S07A after simulation (Parameters in Pa & L/s) |------ ------|
6th/corr 33.9 < 69.01 33.9 > 69.01 corr
|------ ------|
Summer 5th/corr 34.0 < 69.20 34.0 > 69.20 corr
– Model input parameters:
|------ ------|
Value 4th/corr 34.3 < 69.48 34.3 > 69.48 corr
Parameter
|------ ------|
Ambient Temperature 45.1 oC 3rd/corr 34.5 < 69.66 34.5 > 69.66 corr
Interior Temperature 20 oC |------ ------|
Temperature of the protection area after pressurization system 2nd/corr 34.6 < 69.74 34.6 > 69.74 corr
45.1 oC |------ ------|
operation
Wind speed 6.3 m/s 1st/corr 34.0 < 69.12 34.0 > 69.12 corr
Level 10 – |------ ------|
Incident Floors LT/lobb 54.8 < 87.79 54.8 > 87.79 lobb
S07A
|------ ------|
– Modeling Result C4/exit 71.5 < 100.30 71.5 > 100.30 exit
|------ ------|
Fire_signal_from_Back_of_house_service_area_tower_S07A_Summers shaft report C3/VST 50.9 < 84.60 50.9 > 84.60 VST
|------ ------|
C2/exit 58.2 < 90.45 58.2 > 90.45 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C1/exit 64.8 < 95.49 64.8 > 95.49 exit
+---------------------------+ |------ ------|
UT-2/lobb 1.1 < 12.16 1.1 > 12.16 lobb GRND/exit 37.6 < 180.91 37.6 > 180.91 exit
|------ ------| |------ ------|
UT-1/corr 42.4 < 77.20 42.4 > 77.20 corr B1/serv 58.0 < 90.34 58.0 > 90.34 serv
|------ ------| +---------------------------+
19th/corr 32.7 < 67.81 32.7 > 67.81 corr
|------ ------|
18th/corr 32.6 < 67.77 32.6 > 67.77 corr CONTAM Shaft Report at Stair 2 in S07A after simulation (Parameters in Pa & L/s)
|------ ------|
17th/corr 32.8 < 67.97 32.8 > 67.97 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-26
|------ ------|
LT/lobb 65.4 < 95.93 65.4 > 95.93 lobb
Fire_signal_from_Back_of_house_service_area_tower_S07A_Summers shaft report |------ ------|
C4/serv 59.8 < 91.68 59.8 > 91.68 serv
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C3/serv 65.0 < 95.64 65.0 > 95.64 serv
+---------------------------+ |------ ------|
Roof/mach 0.1 < 4.14 0.1 > 4.14 mach C2/serv 65.9 < 96.30 65.9 > 96.30 serv
|------ ------| |------ ------|
MR-1/ambt 1.9 < 16.43 1.9 > 16.43 ambt C1/exit 47.5 < 81.70 47.5 > 81.70 exit
|------ ------| |------ ------|
UT-2/fire 6.3 < 29.68 6.3 > 29.68 fire GRND/exit 32.8 < 67.94 32.8 > 67.94 exit
|------ ------| |------ ------|
UT-1/fire 11.2 < 39.62 11.2 > 39.62 fire B1/fire 15.1 < 46.13 15.1 > 46.13 fire
|------ ------| |------ ------|
19th/corr 57.2 < 89.74 57.2 > 89.74 corr B2/fire 14.9 < 45.83 14.9 > 45.83 fire
|------ ------| |------ ------|
18th/corr 59.0 < 91.09 59.0 > 91.09 corr B3/fire 14.8 < 45.57 14.8 > 45.57 fire
|------ ------| +---------------------------+
17th/corr 59.5 < 91.47 59.5 > 91.47 corr
|------ ------|
16th/corr 59.7 < 91.68 59.7 > 91.68 corr CONTAM Shaft Report at Stair 5 in S07A after simulation (Parameters in Pa & L/s)
|------ ------|
15th/corr 59.9 < 91.82 59.9 > 91.82 corr Fire_signal_from_Back_of_house_service_area_tower_S07A_Summers shaft report
|------ ------|
14th/corr 60.1 < 91.94 60.1 > 91.94 corr level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------|
13th/corr 60.2 < 92.06 60.2 > 92.06 corr +---------------------------+
|------ ------| Mach/mech 13.5 < 157.60 13.5 > 157.60 mech
12th/corr 60.4 < 92.18 60.4 > 92.18 corr |------ ------|
|------ ------| Uppe/fire 16.9 < 175.85 16.9 > 175.85 fire
11th/corr 60.6 < 92.30 60.6 > 92.30 corr |------ ------|
|------ ------| Uppe/fire 21.6 < 199.11 21.6 > 199.11 fire
10th/corr 60.7 < 92.43 60.7 > 92.43 corr |------ ------|
|------ ------| Floo/fire 22.8 < 204.60 22.8 > 204.60 fire
9th/corr 60.9 < 92.57 60.9 > 92.57 corr |------ ------|
|------ ------| Floo/fire 22.9 < 204.77 22.9 > 204.77 fire
8th/corr 61.1 < 92.72 61.1 > 92.72 corr |------ ------|
|------ ------| Floo/fire 22.8 < 204.55 22.8 > 204.55 fire
7th/corr 61.4 < 92.90 61.4 > 92.90 corr |------ ------|
|------ ------| Floo/fire 22.8 < 204.30 22.8 > 204.30 fire
6th/corr 61.6 < 93.12 61.6 > 93.12 corr |------ ------|
|------ ------| Floo/fire 22.7 < 204.04 22.7 > 204.04 fire
5th/corr 62.0 < 93.42 62.0 > 93.42 corr |------ ------|
|------ ------| Floo/fire 22.6 < 203.80 22.6 > 203.80 fire
4th/corr 62.7 < 93.90 62.7 > 93.90 corr |------ ------|
|------ ------| Floo/fire 22.6 < 203.57 22.6 > 203.57 fire
3rd/corr 63.1 < 94.20 63.1 > 94.20 corr |------ ------|
|------ ------| Floo/fire 22.5 < 203.35 22.5 > 203.35 fire
2nd/corr 63.4 < 94.45 63.4 > 94.45 corr |------ ------|
|------ ------| Floo/fire 22.5 < 203.15 22.5 > 203.15 fire
1st/corr 63.9 < 94.81 63.9 > 94.81 corr |------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-27
Floo/fire 22.5 < 202.96 22.5 > 202.96 fire
|------ ------|
E-2 Scenario 2.B:
Floo/fire 22.4 < 202.79 22.4 > 202.79 fire Activation of Fire signal from Back of house service area in Tower S07B
|------ ------| Sequence of Operation:
Floo/fire 22.4 < 202.63 22.4 > 202.63 fire Only the staircases and fire lift pressurization fans in S07B will be activated, listed below:
|------ ------|
CORRESPONDING
Floo/fire 22.4 < 202.49 22.4 > 202.49 fire FAN
AREA
FUNCTION
|------ ------|
PF-SR7B-MR1-01 Tower-S07B
Floo/fire 22.3 < 202.36 22.3 > 202.36 fire Stair 3A
|------ ------| PF-P09-LT-02 PODIUM Area
Floo/fire 22.3 < 202.25 22.3 > 202.25 fire Stair 6
PF-SR7B-MR1-02 Tower-S07B
|------ ------| PF-P09-LT-04 PODIUM Area Supply
Floo/fire 22.3 < 202.16 22.3 > 202.16 fire Fire Lift PF-P9-SR7B-MR1-04-01 Tower-S07B
|------ ------| S07B-07 PODIUM Area
Floo/fire 22.3 < 202.07 22.3 > 202.07 fire Fire Lift Tower-S07B
|------ ------| PF-P9-SR7B-MR1-04-02
S07B-08 PODIUM Area
Floo/fire 22.2 < 201.98 22.2 > 201.98 fire
|------ ------| Adjusted flows are the required flows to get the overall stair shafts within the acceptable differential pressures to
Floo/fire 22.2 < 201.92 22.2 > 201.92 fire NFPA 92A.
|------ ------| CONTAM floor plan for incident floor:
Level 10 was assumed as incident floor. The CONTAM floor plan during the modeling is shown as Figure __.
Lowe/fire 23.2 < 206.32 23.2 > 206.32 fire
|------ ------|
C4/fire 22.3 < 202.19 22.3 > 202.19 fire
|------ ------|
C3/fire 22.4 < 202.48 22.4 > 202.48 fire
|------ ------|
C2/fire 22.5 < 203.24 22.5 > 203.24 fire
|------ ------|
C1/fire 29.9 < 234.24 29.9 > 234.24 fire
|------ ------|
GRND/fire 14.2 < 1736.26 14.2 > 1736.26 fire
|------ ------|
B1/fire 24.4 < 211.46 24.4 > 211.46 fire
|------ ------|
B2/fire 24.2 < 210.59 24.2 > 210.59 fire
|------ ------|
B3/fire 24.0 < 209.85 24.0 > 209.85 fire
+---------------------------+
CONTAM Shaft Report at Elevator S07A-07 in S07A after simulation (Parameters in Pa & L/s) Figure- CONTAM Floor Plan of Tower Level 10
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-28
Winter |------ ------|
– Model input parameters: 4th/corr 22.1 < 55.72 22.1 > 55.72 corr
|------ ------|
Value 3rd/corr 22.1 < 55.73 22.1 > 55.73 corr
Parameter
|------ ------|
Ambient Temperature 17.3 oC 2nd/corr 22.1 < 55.76 22.1 > 55.76 corr
Interior Temperature 20 oC |------ ------|
Temperature of the protection area after pressurization system 1st/corr 22.2 < 55.85 22.2 > 55.85 corr
17.3 oC
operation |------ ------|
Wind speed 6.3 m/s LT/stai 40.3 < 75.31 40.3 > 75.31 stai
Level 10 – |------ ------|
Incident Floors
S07B C4/exit 77.5 < 104.39 77.5 > 104.39 exit
– Modeling Result |------ ------|
C3/exit 91.8 < 113.66 91.8 > 113.66 exit
Fire_signal_from_Back_of_house_service_area_in_tower_S07B_Winters shaft report |------ ------|
C2/exit 83.6 < 108.47 83.6 > 108.47 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone +---------------------------+
+---------------------------+ CONTAM Shaft Report at Stair 3A in S07B after simulation (Parameters in Pa & L/s)
UT-2/exit 40.7 < 75.66 40.7 > 75.66 exit
|------ ------|
UT-1/exit 33.0 < 68.09 33.0 > 68.09 exit Fire_signal_from_Back_of_house_service_area_in_tower_S07B_Winters shaft report
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
19th/corr 22.1 < 55.82 22.1 > 55.82 corr
|------ ------| +---------------------------+
18th/corr 22.1 < 55.79 22.1 > 55.79 corr Roof/mach 60.6 < 92.30 60.6 > 92.30 mach
|------ ------| |------ ------|
17th/corr 22.1 < 55.76 22.1 > 55.76 corr MR-1/ambt 131.7 < 136.12 131.7 > 136.12 ambt
|------ ------| |------ ------|
16th/corr 22.1 < 55.75 22.1 > 55.75 corr UT-2/fire 1.1 < 12.50 1.1 > 12.50 fire
|------ ------| |------ ------|
15th/corr 22.1 < 55.74 22.1 > 55.74 corr UT-1/fire 0.4 > 7.34 0.4 < 7.34 fire
|------ ------| |------ ------|
14th/corr 22.1 < 55.74 22.1 > 55.74 corr 19th/corr 64.2 < 95.03 64.2 > 95.03 corr
|------ ------| |------ ------|
13th/corr 22.1 < 55.74 22.1 > 55.74 corr 18th/corr 64.2 < 95.00 64.2 > 95.00 corr
|------ ------| |------ ------|
12th/corr 22.1 < 55.74 22.1 > 55.74 corr 17th/corr 64.1 < 94.96 64.1 > 94.96 corr
|------ ------| |------ ------|
11th/corr 22.1 < 55.73 22.1 > 55.73 corr 16th/corr 64.1 < 94.95 64.1 > 94.95 corr
|------ ------| |------ ------|
10th/corr 22.1 < 55.73 22.1 > 55.73 corr 15th/corr 64.1 < 94.94 64.1 > 94.94 corr
|------ ------| |------ ------|
9th/corr 22.1 < 55.73 22.1 > 55.73 corr 14th/corr 64.1 < 94.94 64.1 > 94.94 corr
|------ ------| |------ ------|
8th/corr 22.1 < 55.73 22.1 > 55.73 corr 13th/corr 64.1 < 94.93 64.1 > 94.93 corr
|------ ------| |------ ------|
7th/corr 22.1 < 55.73 22.1 > 55.73 corr 12th/corr 64.1 < 94.93 64.1 > 94.93 corr
|------ ------| |------ ------|
6th/corr 22.1 < 55.72 22.1 > 55.72 corr 11th/corr 64.1 < 94.93 64.1 > 94.93 corr
|------ ------| |------ ------|
5th/corr 22.1 < 55.72 22.1 > 55.72 corr 10th/corr 64.1 < 94.93 64.1 > 94.93 corr
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-29
|------ ------| |------ ------|
9th/corr64.1 < 94.93 64.1 > 94.93 corr 18th/fire 17.7 < 179.96 17.7 > 179.96 fire
|------ ------| |------ ------|
8th/corr 64.1 < 94.93 64.1 > 94.93 corr 17th/fire 17.5 < 179.31 17.5 > 179.31 fire
|------ ------| |------ ------|
7th/corr 64.1 < 94.93 64.1 > 94.93 corr 16th/fire 17.5 < 178.93 17.5 > 178.93 fire
|------ ------| |------ ------|
6th/corr 64.1 < 94.93 64.1 > 94.93 corr 15th/fire 17.4 < 178.64 17.4 > 178.64 fire
|------ ------| |------ ------|
5th/corr 64.1 < 94.93 64.1 > 94.93 corr 14th/fire 17.3 < 178.37 17.3 > 178.37 fire
|------ ------| |------ ------|
4th/corr 64.1 < 94.93 64.1 > 94.93 corr 13th/fire 17.3 < 178.13 17.3 > 178.13 fire
|------ ------| |------ ------|
3rd/corr 64.1 < 94.95 64.1 > 94.95 corr 12th/fire 17.3 < 177.90 17.3 > 177.90 fire
|------ ------| |------ ------|
2nd/corr 64.1 < 94.99 64.1 > 94.99 corr 11th/fire 17.2 < 177.68 17.2 > 177.68 fire
|------ ------| |------ ------|
1st/corr 64.3 < 95.11 64.3 > 95.11 corr 10th/fire 17.2 < 177.48 17.2 > 177.48 fire
|------ ------| |------ ------|
LT/lobb 69.8 < 99.06 69.8 > 99.06 lobb 9th/fire 17.1 < 177.30 17.1 > 177.30 fire
|------ ------| |------ ------|
C4/exit 63.9 < 94.83 63.9 > 94.83 exit 8th/fire 17.1 < 177.12 17.1 > 177.12 fire
|------ ------| |------ ------|
C3/corr 44.8 < 79.41 44.8 > 79.41 corr 7th/fire 17.1 < 176.96 17.1 > 176.96 fire
|------ ------| |------ ------|
C2/exit 71.2 < 100.05 71.2 > 100.05 exit 6th/fire 17.0 < 176.81 17.0 > 176.81 fire
|------ ------| |------ ------|
C1/corr 42.2 < 77.01 42.2 > 77.01 corr 5th/fire 17.0 < 176.67 17.0 > 176.67 fire
|------ ------| |------ ------|
GRND/corr 46.0 < 80.47 46.0 > 80.47 corr 4th/fire 17.0 < 176.56 17.0 > 176.56 fire
|------ ------| |------ ------|
B1/fire 27.0 < 61.62 27.0 > 61.62 fire 3rd/fire 17.0 < 176.48 17.0 > 176.48 fire
|------ ------| |------ ------|
B2/fire 29.6 < 64.57 29.6 > 64.57 fire 2nd/fire 17.0 < 176.61 17.0 > 176.61 fire
|------ ------| |------ ------|
B3/fire 3.5 < 22.10 3.5 > 22.10 fire 1st/fire 17.4 < 178.87 17.4 > 178.87 fire
+---------------------------+ |------ ------|
LT/fire 29.0 < 230.58 29.0 > 230.58 fire
CONTAM Shaft Report at Stair 6 in S07B after simulation (Parameters in Pa & L/s) |------ ------|
C4/fire 27.5 < 224.73 27.5 > 224.73 fire
|------ ------|
Fire_signal_from_Back_of_house_service_area_tower_S07B_Winters shaft report C3/fire 27.3 < 223.84 27.3 > 223.84 fire
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C2/fire 27.2 < 223.28 27.2 > 223.28 fire
+---------------------------+ |------ ------|
MR-1/mech 40.2 < 271.42 40.2 > 271.42 mech C1/fire 29.3 < 231.75 29.3 > 231.75 fire
|------ ------| |------ ------|
UT-2/fire 30.5 < 236.35 30.5 > 236.35 fire GRND/fire 16.8 < 1888.06 16.8 > 1888.06 fire
|------ ------| |------ ------|
UT-1/fire 28.8 < 229.81 28.8 > 229.81 fire B1/fire 54.7 < 316.66 54.7 > 316.66 fire
|------ ------| |------ ------|
19th/fire 18.5 < 184.20 18.5 > 184.20 fire B2/fire 57.3 < 324.25 57.3 > 324.25 fire
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-30
|------ ------| |------ ------|
B3/fire 31.1 < 239.02 31.1 > 239.02 fire 10th/corr 22.7 < 56.46 22.7 > 56.46 corr
+---------------------------+ |------ ------|
9th/corr 22.7 < 56.47 22.7 > 56.47 corr
CONTAM Shaft Report at S07B-07 in S07B after simulation (Parameters in Pa & L/s) |------ ------|
8th/corr 22.7 < 56.49 22.7 > 56.49 corr
|------ ------|
7th/corr 22.7 < 56.50 22.7 > 56.50 corr
|------ ------|
6th/corr 22.7 < 56.51 22.7 > 56.51 corr
|------ ------|
Summer 5th/corr 22.7 < 56.52 22.7 > 56.52 corr
– Model input parameters: |------ ------|
4th/corr 22.7 < 56.53 22.7 > 56.53 corr
Value |------ ------|
Parameter
3rd/corr 22.7 < 56.55 22.7 > 56.55 corr
Ambient Temperature 45.1 oC |------ ------|
Interior Temperature 20 oC 2nd/corr 22.8 < 56.59 22.8 > 56.59 corr
Temperature of the protection area after pressurization system |------ ------|
45.1 oC
operation 1st/corr 22.8 < 56.66 22.8 > 56.66 corr
Wind speed 6.3 m/s |------ ------|
Level 10 – LT/stai 43.3 < 78.03 43.3 > 78.03 stai
Incident Floors
S07B |------ ------|
C4/exit 99.9 < 118.56 99.9 > 118.56 exit
– Modeling Result |------ ------|
C3/exit 121.7 < 130.86 121.7 > 130.86 exit
Fire_signal_from_Back_of_house_service_area_in_tower_S07B_Summers shaft report |------ ------|
C2/exit 110.9 < 124.89 110.9 > 124.89 exit
level/zone [Pa] [sL/s] [Pa] [sL/s] zone +---------------------------+
CONTAM Shaft Report at Stair 3A in S07B after simulation (Parameters in Pa & L/s)
+---------------------------+
UT-2/exit 25.3 < 59.67 25.3 > 59.67 exit
|------ ------|
UT-1/exit 29.5 < 64.41 29.5 > 64.41 exit Fire_signal_from_Back_of_house_service_area_in_tower_S07B_Summers shaft report
|------ ------|
19th/corr 22.4 < 56.13 22.4 > 56.13 corr level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------|
18th/corr 22.5 < 56.30 22.5 > 56.30 corr +---------------------------+
|------ ------| Roof/mach 28.6 < 63.39 28.6 > 63.39 mach
17th/corr 22.6 < 56.33 22.6 > 56.33 corr |------ ------|
|------ ------| MR-1/ambt 66.6 < 96.79 66.6 > 96.79 ambt
16th/corr 22.6 < 56.35 22.6 > 56.35 corr |------ ------|
|------ ------| UT-2/fire 0.7 < 9.64 0.7 > 9.64 fire
15th/corr 22.6 < 56.37 22.6 > 56.37 corr |------ ------|
|------ ------| UT-1/fire 0.4 < 7.95 0.4 > 7.95 fire
14th/corr 22.6 < 56.39 22.6 > 56.39 corr |------ ------|
|------ ------| 19th/corr 62.7 < 93.88 62.7 > 93.88 corr
13th/corr 22.6 < 56.41 22.6 > 56.41 corr |------ ------|
|------ ------| 18th/corr 62.9 < 94.08 62.9 > 94.08 corr
12th/corr 22.6 < 56.43 22.6 > 56.43 corr |------ ------|
|------ ------| 17th/corr 63.0 < 94.12 63.0 > 94.12 corr
11th/corr 22.7 < 56.45 22.7 > 56.45 corr |------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-31
16th/corr 63.0 < 94.14 63.0 > 94.14 corr CONTAM Shaft Report at Stair 6 in S07B after simulation (Parameters in Pa & L/s)
|------ ------|
15th/corr 63.0 < 94.17 63.0 > 94.17 corr
|------ ------|
14th/corr 63.1 < 94.19 63.1 > 94.19 corr
|------ ------|
13th/corr 63.1 < 94.21 63.1 > 94.21 corr
|------ ------|
12th/corr 63.1 < 94.23 63.1 > 94.23 corr
|------ ------|
11th/corr 63.2 < 94.25 63.2 > 94.25 corr
|------ ------| Fire_signal_from_Back_of_house_service_area_tower_S07B_Summer shaft report
10th/corr 63.2 < 94.27 63.2 > 94.27 corr
|------ ------| level/zone [Pa] [sL/s] [Pa] [sL/s] zone
9th/corr 63.2 < 94.29 63.2 > 94.29 corr
|------ ------| +---------------------------+
8th/corr 63.2 < 94.31 63.2 > 94.31 corr MR-1/mech 31.5 < 240.55 31.5 > 240.55 mech
|------ ------| |------ ------|
7th/corr 63.2 < 94.32 63.2 > 94.32 corr UT-2/fire 28.5 < 228.45 28.5 > 228.45 fire
|------ ------| |------ ------|
6th/corr 63.3 < 94.34 63.3 > 94.34 corr UT-1/fire 28.1 < 226.90 28.1 > 226.90 fire
|------ ------| |------ ------|
5th/corr 63.3 < 94.36 63.3 > 94.36 corr 19th/fire 17.9 < 181.31 17.9 > 181.31 fire
|------ ------| |------ ------|
4th/corr 63.3 < 94.38 63.3 > 94.38 corr 18th/fire 17.2 < 177.42 17.2 > 177.42 fire
|------ ------| |------ ------|
3rd/corr 63.4 < 94.41 63.4 > 94.41 corr 17th/fire 17.0 < 176.83 17.0 > 176.83 fire
|------ ------| |------ ------|
2nd/corr 63.5 < 94.48 63.5 > 94.48 corr 16th/fire 17.0 < 176.49 17.0 > 176.49 fire
|------ ------| |------ ------|
1st/corr 63.6 < 94.57 63.6 > 94.57 corr 15th/fire 16.9 < 176.24 16.9 > 176.24 fire
|------ ------| |------ ------|
LT/lobb 73.1 < 101.43 73.1 > 101.43 lobb 14th/fire 16.9 < 176.03 16.9 > 176.03 fire
|------ ------| |------ ------|
C4/exit 67.5 < 97.44 67.5 > 97.44 exit 13th/fire 16.9 < 175.82 16.9 > 175.82 fire
|------ ------| |------ ------|
C3/corr 49.6 < 83.52 49.6 > 83.52 corr 12th/fire 16.8 < 175.64 16.8 > 175.64 fire
|------ ------| |------ ------|
C2/exit 87.0 < 110.64 87.0 > 110.64 exit 11th/fire 16.8 < 175.46 16.8 > 175.46 fire
|------ ------| |------ ------|
C1/corr 49.4 < 83.37 49.4 > 83.37 corr 10th/fire 16.8 < 175.30 16.8 > 175.30 fire
|------ ------| |------ ------|
GRND/corr 54.4 < 87.45 54.4 > 87.45 corr 9th/fire 16.7 < 175.16 16.7 > 175.16 fire
|------ ------| |------ ------|
B1/fire 35.8 < 70.92 35.8 > 70.92 fire 8th/fire 16.7 < 175.03 16.7 > 175.03 fire
|------ ------| |------ ------|
B2/fire 43.4 < 78.18 43.4 > 78.18 fire 7th/fire 16.7 < 174.90 16.7 > 174.90 fire
|------ ------| |------ ------|
B3/fire 8.1 < 33.78 8.1 > 33.78 fire 6th/fire 16.7 < 174.80 16.7 > 174.80 fire
+---------------------------+ |------ ------|
5th/fire 16.6 < 174.70 16.6 > 174.70 fire
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-32
4th/fire 16.6 < 174.62 16.6 > 174.62 fire
|------ ------|
E-2 Scenario 3.B:
3rd/fire 16.6 < 174.58 16.6 > 174.58 fire
|------ ------| Scenario 3.C:
2nd/fire 16.6 < 174.75 16.6 > 174.75 fire
|------ ------|
Activation of Fire signal from Back of house service area in Tower SR03
1st/fire 17.1 < 177.08 17.1 > 177.08 fire
|------ ------|
LT/fire 28.9 < 230.27 28.9 > 230.27 fire Sequence of Operation:
|------ ------|
Only the staircases and fire lift pressurization fans in SR03 will be activated, listed below:
C4/fire 27.2 < 223.33 27.2 > 223.33 fire
|------ ------|
CORRESPONDING
C3/fire 27.1 < 222.76 27.1 > 222.76 fire FAN FUNCTION
AREA
|------ ------|
Stair 8A PF-SR3-MR1-01 PODIUM Area
C2/fire 26.9 < 221.99 26.9 > 221.99 fire
|------ ------| PF-P09-SR3-MR1-02 Tower-SR03
Stair 9
C1/fire 30.2 < 235.46 30.2 > 235.46 fire PF-P09-C1-01 PODIUM Area
Fire Lifts PF-P9-SR3-MR1-04-01 Tower-SR03 Supply
|------ ------|
SR03-07 PODIUM Area
GRND/fire 16.7 < 1887.49 16.7 > 1887.49 fire
Fire Lifts Tower-SR03
|------ ------| SR03-08
PF-P9-SR3-MR1-04-02
PODIUM Area Adjusted flows
B1/fire 61.9 < 336.87 61.9 > 336.87 fire
are the required flows to get the overall stair shafts within the acceptable differential pressures to NFPA 92A.
|------ ------|
B2/fire 69.6 < 357.19 69.6 > 357.19 fire CONTAM floor plan for incident floor:
|------ ------|
B3/fire 34.2 < 250.53 34.2 > 250.53 fire +---------------------------+ Level 10 was assumed as incident floor. The CONTAM floor plan during the modeling is shown as Figure __.
CONTAM Shaft Report at S07B-07 in S07B after simulation (Parameters in Pa & L/s)
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-33
Winter |------ ------|
– Model input parameters: Floo/corr 26.8 < 61.44 26.8 > 61.44 corr
|------ ------|
Value Floo/corr 26.8 < 61.44 26.8 > 61.44 corr
Parameter
|------ ------|
Ambient Temperature 17.3 oC Floo/corr 26.8 < 61.43 26.8 > 61.43 corr
Interior Temperature 20 oC |------ ------|
Temperature of the protection area after pressurization system Floo/corr 26.8 < 61.43 26.8 > 61.43 corr
17.3 oC
operation |------ ------|
Wind speed 6.3 m/s Floo/corr 26.9 < 61.47 26.9 > 61.47 corr
Level 10 – |------ ------|
Incident Floors
SR03 Lowe/
|------ ------|
– Modeling Result C4/lobb 55.0 < 87.96 55.0 > 87.96 lobb
+---------------------------+
Fire_signal_from_Back_of_house_service_area_tower_SR03_Winters_updated_5-12-14 shaft
report
CONTAM Shaft Report at Stair 8A in SR03 after simulation (Parameters in Pa & L/s)
level/zone [Pa] [sL/s] [Pa] [sL/s] zone
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-34
10th/corr 44.9 < 79.46 44.9 > 79.46 corr Fire_signal_from_Back_of_house_service_area_tower_SR03_Winters shaft report
|------ ------|
9th/corr 44.9 < 79.46 44.9 > 79.46 corr level/zone [Pa] [sL/s] [Pa] [sL/s] zone
|------ ------|
8th/corr 44.9 < 79.45 44.9 > 79.45 corr +---------------------------+
|------ ------| MR-1/mech 29.2 < 231.37 29.2 > 231.37 mech
7th/corr 44.9 < 79.45 44.9 > 79.45 corr |------ ------|
|------ ------| UT-2/fire 24.3 < 210.95 24.3 > 210.95 fire
6th/corr 44.9 < 79.44 44.9 > 79.44 corr |------ ------|
|------ ------| UT-1/fire 23.9 < 209.17 23.9 > 209.17 fire
5th/corr 44.9 < 79.44 44.9 > 79.44 corr |------ ------|
|------ ------| 19th/fire 23.9 < 209.25 23.9 > 209.25 fire
4th/corr 44.9 < 79.44 44.9 > 79.44 corr |------ ------|
|------ ------| 18th/fire 23.8 < 208.77 23.8 > 208.77 fire
3rd/corr 44.8 < 79.42 44.8 > 79.42 corr |------ ------|
|------ ------| 17th/fire 23.7 < 208.44 23.7 > 208.44 fire
2nd/corr 44.9 < 79.43 44.9 > 79.43 corr |------ ------|
|------ ------| 16th/fire 23.6 < 208.14 23.6 > 208.14 fire
1st/corr 44.9 < 79.50 44.9 > 79.50 corr |------ ------|
|------ ------| 15th/fire 23.6 < 207.86 23.6 > 207.86 fire
LT/lobb 46.0 < 80.47 46.0 > 80.47 lobb |------ ------|
|------ ------| 14th/fire 23.5 < 207.59 23.5 > 207.59 fire
C4/serv 45.2 < 79.71 45.2 > 79.71 serv |------ ------|
|------ ------| 13th/fire 23.4 < 207.35 23.4 > 207.35 fire
C3/serv 45.2 < 79.73 45.2 > 79.73 serv |------ ------|
|------ ------| 12th/fire 23.4 < 207.12 23.4 > 207.12 fire
C2/exit 45.2 < 79.77 45.2 > 79.77 exit |------ ------|
|------ ------| 11th/fire 23.3 < 206.91 23.3 > 206.91 fire
C1/exit 43.5 < 78.20 43.5 > 78.20 exit |------ ------|
|------ ------| 10th/fire 23.3 < 206.71 23.3 > 206.71 fire
GRND/exit 41.7 < 76.56 41.7 > 76.56 exit |------ ------|
|------ ------| 9th/fire 23.3 < 206.53 23.3 > 206.53 fire
B1/fire 50.5 < 84.31 50.5 > 84.31 fire |------ ------|
|------ ------| 8th/fire 23.2 < 206.36 23.2 > 206.36 fire
B2/fire 43.7 < 78.39 43.7 > 78.39 fire |------ ------|
|------ ------| 7th/fire 23.2 < 206.20 23.2 > 206.20 fire
B3/fire 41.1 < 76.01 41.1 > 76.01 fire |------ ------|
+---------------------------+ 6th/fire 23.1 < 206.06 23.1 > 206.06 fire
|------ ------|
CONTAM Shaft Report at Stair 9 in SR03 after simulation (Parameters in Pa & L/s) 5th/fire 23.1 < 205.92 23.1 > 205.92 fire
|------ ------|
4th/fire 23.1 < 205.81 23.1 > 205.81 fire
|------ ------|
3rd/fire 23.1 < 205.70 23.1 > 205.70 fire
|------ ------|
2nd/fire 23.0 < 205.61 23.0 > 205.61 fire
|------ ------|
1st/fire 23.0 < 205.62 23.0 > 205.62 fire
|------ ------|
LT/fire 23.5 < 207.53 23.5 > 207.53 fire
|------ ------|
C4/fire 28.0 < 226.61 28.0 > 226.61 fire
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-35
|------ ------|
C3/fire
28.5 < 228.58 28.5 > 228.58 fire
|------ ------|
Summer
– Model input parameters:
C2/fire 28.6 < 229.03 28.6 > 229.03 fire
|------ ------| Value
C1/fire 28.4 < 228.10 28.4 > 228.10 fire Parameter
|------ ------| Ambient Temperature 45.1 oC
GRND/fire 14.1 < 1729.20 14.1 > 1729.20 fire Interior Temperature 20 oC
|------ ------| Temperature of the protection area after pressurization system
B1/fire 29.0 < 230.46 29.0 > 230.46 fire 45.1 oC
operation
|------ ------| Wind speed 6.3 m/s
B2/fire 22.1 < 201.36 22.1 > 201.36 fire Level 10 –
|------ ------| Incident Floors
SR03
B3/fire 19.5 < 189.07 19.5 > 189.07 fire
+---------------------------+ – Modeling Result
CONTAM Shaft Report at SR03-07 in SR03 after simulation (Parameters in Pa & L/s) Fire_signal_from_Back_of_house_service_area_tower_SR03_Summers_updated_5-12-14 shaft
report
level/zone [Pa] [sL/s] [Pa] [sL/s] zone
+---------------------------+
Uppe/lobb 8.7 < 35.05 8.7 > 35.05 lobb
|------ ------|
Uppe/corr 40.7 < 75.67 40.7 > 75.67 corr
|------ ------|
Floo/corr 30.6 < 65.60 30.6 > 65.60 corr
|------ ------|
Floo/corr 30.2 < 65.14 30.2 > 65.14 corr
|------ ------|
Floo/corr 30.4 < 65.36 30.4 > 65.36 corr
|------ ------|
Floo/corr 30.5 < 65.48 30.5 > 65.48 corr
|------ ------|
Floo/corr 30.6 < 65.57 30.6 > 65.57 corr
|------ ------|
Floo/corr 30.6 < 65.65 30.6 > 65.65 corr
|------ ------|
Floo/corr 30.7 < 65.73 30.7 > 65.73 corr
|------ ------|
Floo/corr 30.8 < 65.81 30.8 > 65.81 corr
|------ ------|
Floo/corr 30.9 < 65.90 30.9 > 65.90 corr
|------ ------|
Floo/corr 31.0 < 66.02 31.0 > 66.02 corr
|------ ------|
Floo/corr 31.1 < 66.19 31.1 > 66.19 corr
|------ ------|
Floo/corr 31.3 < 66.36 31.3 > 66.36 corr
|------ ------|
Floo/corr 31.4 < 66.44 31.4 > 66.44 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-36
Floo/corr 31.4 < 66.48 31.4 > 66.48 corr 8th/corr 52.5 < 85.97 52.5 > 85.97 corr
|------ ------| |------ ------|
Floo/corr 31.4 < 66.49 31.4 > 66.49 corr 7th/corr 52.7 < 86.12 52.7 > 86.12 corr
|------ ------| |------ ------|
Floo/corr 31.4 < 66.50 31.4 > 66.50 corr 6th/corr 52.8 < 86.19 52.8 > 86.19 corr
|------ ------| |------ ------|
Floo/corr 31.4 < 66.50 31.4 > 66.50 corr 5th/corr 52.9 < 86.23 52.9 > 86.23 corr
|------ ------| |------ ------|
Floo/corr 31.4 < 66.51 31.4 > 66.51 corr 4th/corr 52.9 < 86.25 52.9 > 86.25 corr
|------ ------| |------ ------|
Floo/corr 31.6 < 66.62 31.6 > 66.62 corr 3rd/corr 52.9 < 86.26 52.9 > 86.26 corr
|------ ------| |------ ------|
Lowe/ 2nd/corr 52.9 < 86.28 52.9 > 86.28 corr
|------ ------| |------ ------|
C4/lobb 87.7 < 111.07 87.7 > 111.07 lobb 1st/corr 53.2 < 86.50 53.2 > 86.50 corr
+---------------------------+ |------ ------|
CONTAM Shaft Report at Stair 8A in SR03 after simulation (Parameters in Pa & L/s) LT/lobb 57.1 < 89.65 57.1 > 89.65 lobb
|------ ------|
C4/serv 55.0 < 87.97 55.0 > 87.97 serv
Fire_signal_from_Back_of_house_service_area_in_tower_SR03_Summers shaft report |------ ------|
level/zone [Pa] [sL/s] [Pa] [sL/s] zone C3/serv 55.5 < 88.38 55.5 > 88.38 serv
+---------------------------+ |------ ------|
Roof/mach 2.9 < 20.08 2.9 > 20.08 mach C2/exit 59.0 < 91.13 59.0 > 91.13 exit
|------ ------| |------ ------|
MR-1/ambt 5.8 < 28.49 5.8 > 28.49 ambt C1/exit 60.8 < 92.50 60.8 > 92.50 exit
|------ ------| |------ ------|
UT-2/fire 5.5 < 27.87 5.5 > 27.87 fire GRND/exit 61.1 < 92.73 61.1 > 92.73 exit
|------ ------| |------ ------|
UT-1/fire 8.9 < 35.43 8.9 > 35.43 fire B1/fire 50.5 < 84.24 50.5 > 84.24 fire
|------ ------| |------ ------|
19th/corr 48.4 < 82.54 48.4 > 82.54 corr B2/fire 36.4 < 71.57 36.4 > 71.57 fire
|------ ------| |------ ------|
18th/corr 49.9 < 83.76 49.9 > 83.76 corr B3/fire 34.7 < 69.82 34.7 > 69.82 fire
|------ ------| +---------------------------+
17th/corr 50.3 < 84.14 50.3 > 84.14 corr CONTAM Shaft Report at Stair 9 in SR03 after simulation (Parameters in Pa & L/s)
|------ ------|
16th/corr 50.6 < 84.34 50.6 > 84.34 corr
|------ ------|
15th/corr 50.8 < 84.50 50.8 > 84.50 corr
|------ ------|
14th/corr 50.9 < 84.64 50.9 > 84.64 corr
|------ ------|
13th/corr 51.1 < 84.79 51.1 > 84.79 corr
|------ ------|
12th/corr 51.3 < 84.94 51.3 > 84.94 corr
|------ ------|
11th/corr 51.5 < 85.11 51.5 > 85.11 corr
|------ ------|
10th/corr 51.8 < 85.32 51.8 > 85.32 corr
|------ ------|
9th/corr 52.1 < 85.63 52.1 > 85.63 corr
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-37
Fire_signal_from_Back_of_house_service_area_tower_SR03_Summers shaft report C3/fire 31.2 < 239.21 31.2 > 239.21 fire
level/zone [Pa] [sL/s] [Pa] [sL/s] zone |------ ------|
C2/fire 32.0 < 242.20 32.0 > 242.20 fire
+---------------------------+ |------ ------|
MR-1/mech 18.0 < 181.80 18.0 > 181.80 mech C1/fire 33.0 < 246.14 33.0 > 246.14 fire
|------ ------| |------ ------|
UT-2/fire 18.8 < 185.55 18.8 > 185.55 fire GRND/fire 14.1 < 1734.16 14.1 > 1734.16 fire
|------ ------| |------ ------|
UT-1/fire 22.0 < 201.05 22.0 > 201.05 fire B1/fire 37.5 < 262.40 37.5 > 262.40 fire
|------ ------| |------ ------|
19th/fire 22.9 < 205.16 22.9 > 205.16 fire B2/fire 23.5 < 207.59 23.5 > 207.59 fire
|------ ------| |------ ------|
18th/fire 23.0 < 205.36 23.0 > 205.36 fire B3/fire 21.7 < 199.68 21.7 > 199.68 fire
|------ ------| +---------------------------+
17th/fire 23.0 < 205.20 23.0 > 205.20 fire CONTAM Shaft Report at SR03-07 in SR03 after simulation (Parameters in Pa & L/s)
|------ ------|
16th/fire 22.9 < 205.00 22.9 > 205.00 fire
|------ ------|
15th/fire 22.9 < 204.78 22.9 > 204.78 fire
|------ ------|
14th/fire 22.8 < 204.58 22.8 > 204.58 fire
|------ ------|
13th/fire 22.8 < 204.39 22.8 > 204.39 fire
|------ ------|
12th/fire 22.7 < 204.21 22.7 > 204.21 fire
|------ ------|
11th/fire 22.7 < 204.06 22.7 > 204.06 fire
|------ ------|
10th/fire 22.7 < 203.92 22.7 > 203.92 fire
|------ ------|
9th/fire 22.6 < 203.83 22.6 > 203.83 fire
|------ ------|
8th/fire 22.6 < 203.74 22.6 > 203.74 fire
|------ ------|
7th/fire 22.6 < 203.63 22.6 > 203.63 fire
|------ ------|
6th/fire 22.6 < 203.51 22.6 > 203.51 fire
|------ ------|
5th/fire 22.6 < 203.39 22.6 > 203.39 fire
|------ ------|
4th/fire 22.5 < 203.28 22.5 > 203.28 fire
|------ ------|
3rd/fire 22.5 < 203.18 22.5 > 203.18 fire
|------ ------|
2nd/fire 22.5 < 203.10 22.5 > 203.10 fire
|------ ------|
1st/fire 22.5 < 203.13 22.5 > 203.13 fire
|------ ------|
LT/fire 23.0 < 205.37 23.0 > 205.37 fire
|------ ------|
C4/fire 30.3 < 235.65 30.3 > 235.65 fire
|------ ------|
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix E 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page E-38
C. Fusible link temperature if a fire damper or combination damper.
Appendix F – Special Inspection General Notes
D. Supervisory devices.
Acceptance testing of the smoke control systems is necessary to confirm proper activation and operation. The use
E. Dampers subject to close while fans are operating must be listed as dynamic dampers.
of chemical smoke (cold smoke), which has little or no buoyancy, should not be used in testing. Therefore,
acceptance testing of the project’s smoke control systems is to be without a fire. F. Verification of damper switch positions in both normal and smoke-control mode.
The special inspection will consist of equipment and construction inspections, as well as functional testing. The G. Supervision of wiring for smoke-control damper switches.
Special Inspector of Record will coordinate with the following trades: HVAC, Electrical, Fire Alarm, Automatic
Sprinkler, Energy/Building Management Systems, Door Contractor, etc. H. Location per control diagrams and numbering.
Confirming and verifying that the smoke control system components will function and operate as intended by The Special Inspector of Record will inspect doors and doorframes in smoke zone walls for the following:
the system design.
Measuring and balancing airflows, and verifying that the sequence of operation, component functions and A. Doors are properly rated for intended use.
controls of the smoke control systems comply with the system design.
B. Doors are capable of self-closing or automatically closing and latching under both passive and active
Accepted test and balance procedures to verify that pressure differences, where required, are being achieved.
A visual inspection of the smoke control system components. conditions.
Testing of equipment for sequence of operations, as well as providing a balance report by which future tests C. Doors are capable of automatically opening and latching under both passive and active conditions.
can be compared.
D. All doors located in smoke barriers have proper smoke seals and gaskets. Approval label followed by the
The special inspection will consist of equipment and construction inspections, as well as functional testing of the E. Doors are located as shown on the control diagrams.
following:
Fans
Smoke Barriers Fan performance to be performed and documented by a separate certified test and balance contractor. Proof of
certification and calibration certificates for all test equipment will be required for review prior to testing. The Special
Walls and all other smoke barrier construction will be visually inspected during construction and tested to ensure Inspector of Record will inspect fans functioning as part of the smoke-control system for the following:
that leakage areas do not exceed those permitted by smoke barrier construction. The Special Inspector of Record
will review all building walls forming smoke zones for the following:
A. Installation is in accordance with approved plans.
A. Location is consistent with smoke-control diagrams.
B. Listing or lab approval.
B. Walls are complete and without holes.
C. Duct detectors are installed if required.
C. Wall penetrations are sealed.
D. Supervisory devices are installed (i.e., current sensor or differential pressure switch).
D. Automatic smoke control activation is consistent with smoke zone boundaries where alarm initiates smoke-
E. Wiring is complete and within continuous raceways.
control.
F. Fan is labeled with unit number per drawing.
Dampers
G. Location per control diagrams and numbering.
The Special Inspector of Record will inspect dampers functioning as part of the smoke-control system for the
following:
Fire Alarm System
A. Installation is in accordance with manufacturers’ installation instructions. Components of the fire alarm system initiating smoke-control will be inspected as follows:
B. Listing or lab approval. A. Wiring for initiating devices used to activate smoke-control is installed within enclosed raceways.
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix F 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page F-1
B. System shall be UUKL listed.
C. Sequencing for smoke-control matches rational analysis report/design documents (programming). Duct Leakage Testing
D. Firefighter’s panel matches smoke zones and approved drawings. A. The Special Inspector of Record will witness duct leakage tests conducted by an approved air balance
company. Proof of certification and calibration certificates for all testing equipment will be required for review
Electrical prior to testing. Duct leakage testing should be performed during the construction phase while the ductwork
is exposed and accessible.
Components of the electrical system will be inspected as follows:
B. Ductwork to be tested:
A. Confirm appropriate equipment is on emergency power.
1. Smoke-control main distribution ductwork (if applicable).
B. Confirm stand-by source and its transfer switch are separated from the normal power transformers and switch
C. Test Criteria
gear.
1. Duct pressure tested at 1.5 times maximum design pressure. Fan operating pressure noted on
C. Confirm that stand-by power is transferred to the smoke-control equipment within 60 seconds. mechanical drawing fan schedule to be considered the maximum design pressure.
A. Test pressure differentials across smoke barriers separating adjacent smoke zones that include the 1. Combined leakage of all tested segments is not to exceed 5 percent of design flow. The Fan
following: volumes noted on the mechanical drawing equipment schedule is to be considered the design flow.
Fans
1. Pressure differentials measured from corridor to stairway vestibules.
A. Fan performance to be performed and documented by a separate certified test and balance contractor.
2. Pressure differentials measured from stairway vestibule to enclosed stairways. Proof of certification and calibration certificates for all test equipment will be required for review prior to
testing.
B. Minimum pressure difference test criteria.
B. Fan test / observation and passing criteria are as follows:
1. The minimum pressure difference across a smoke barrier shall be 0.05-inch water column.
Test / Observation Passing Criteria
C. Maximum pressure difference test criteria. Fan nameplate data Meets specification
Location Per control diagrams
1. The maximum air pressure difference across a zone barrier shall be determined by required door- Fan rotation Correct direction
opening forces. Motor voltage Does not exceed nameplate
Motor amperage Does not exceed nameplate
2. The door shall swing to the fully open position when an opening force not to exceed 15 pounds is Motor RPM Does not exceed nameplate
applied to the latch side of exits in active smoke-control zones. Service Factor Does not exceed nameplate
Belt Proper number / type / tension / no unusual noise
D. Small passive zones adjacent to an active pressurization zone may not maintain a 0.05 inch water column Fan volume Meets specification
pressure difference if the door is of tight construction. These rooms may be individually evaluated with Fan total pressure Review with volume results
room leakage tests.
C. Fans to be confirmed to operate in accordance with the approved sequence of operation / control diagrams.
Door Fan Testing
D. Confirm the variable frequency drive (VFD) are secondary to the smoke-control system and are not
A. The Special Inspector of Record will witness a door fan testing to verify that passive barrier construction overridden by the Building Management System or VFD is completely bypassed during smoke control
does not exceed the maximum allowable leakage areas. The maximum allowable leakage area shall be the operation (if installed).
aggregated areas calculated using leakage are rations as noted in the rational analysis report.
E. Confirm motor control center switches to be secondary to smoke-control system output and is overridden by
B. Fan door test will be performed in few selected rooms containing passive barriers to verify compliance with smoke control.
maximum allowable leakage.
F. Confirm fan ON / OFF supervision as follows:
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix F 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page F-2
1. Pressure differential switch: Confirm supervisory condition by turning fan OFF or ON to duplicate Firefighter’s Control Panel and Sequence Test
monitored positions.
A. Conduct testing of the manual system on the graphics panel.
2. Current sensing switch: Confirm supervisory condition by turning fan OFF or ON to duplicate
monitored positions. When Fan “ON” is a monitored position, the “OFF” position should also be B. Confirm that the portion of the smoke-control system functions in accordance with the switch position
tested under a no load condition (all fan belts off). tested (i.e., on, off, automatic, etc.)
G. Motors driving fan shall have a minimum service factor of 1.15. C. Confirm fans running or not running depending on switch position selected.
Active Smoke Control Dampers D. Confirm dampers open or closed depending on switch position selected.
A. Smoke dampers will be confirmed that they cycle open and closed. E. Confirm smoke graphic panel switches have priority over all other control actions.
B. Individual dampers may be picked and individually confirmed in order to confirm proper position is F. Document fan, door and damper conditions on test sheets.
annunciated at the control panel.
G. Tests to be conducted in an automatic alarm condition to confirm override priority status and in a manual,
C. Damper and end limit switches will be tested to confirm annunciation at the smoke graphic panel. Tests non-alarm condition.
include loss of power and individually picking dampers to the position in a sequence of operation test.
Acceptance Test
D. Check dampers for proper position per scenario and verify special pass / fail criteria in the approved rational
analysis report and smoke-control diagrams. A. Conduct an all systems pre-test of the smoke-control system.
Electrical B. Confirm scenarios all work in accordance with the smoke-control report.
A. Conduct shunt trip of building to shut off main power and activate emergency power. Initial test will be C. Confirm system functions under emergency power.
under normal power with smoke-control system activated.
Response Time
B. Confirm all smoke-control fans are on emergency power.
A. Smoke-control system activation will be initiated immediately after receipt of an appropriate automatic or
C. Confirm dampers that need to be open under automatic or manual operation are on emergency power. manual activation command. Smoke-control systems will activate individual components (such as
dampers and fans) in the sequence necessary to prevent physical damage to the fans, dampers, ducts
and other equipment. The total response time for individual components to achieve their desired
D. Confirm fire alarm and building management systems are on emergency and uninterruptible power
operating mode will not exceed the following:
sources for volatile memory if equipped.
E. Confirm emergency power transfers and all smoke-control equipment is operating within 60 seconds of Control air isolation valves Immediately
shunt. Smoke damper closing 15 seconds
Smoke damper opening 15 seconds maximum
F. Second test will include initiation of an alarm under emergency power conditions.
Fan starting (energizing) 15 seconds maximum
Initiation Devices Fan stopping (de-energizing) Immediately
Fan volume modulation 30 seconds maximum
A. Confirm all initiating devices activate smoke-control in accordance with the approved smoke-control report Pressure control modulation 15 seconds maximum
and the control diagrams.
Temperature control safety override Immediately
B. Test each type of initiating device to confirm that smoke-control is activated. Positive indication of status 15 seconds maximum
C. Verify all equipment is operating in accordance with the smoke-control report and control diagrams. All Systems Test
D. Verify proper indication on smoke graphics panel. A. Conduct an all systems test with the AHJ. The Special Inspector of Record will be present at the all
systems test by the AHJ.
E. Confirm all smoke-control equipment activates in accordance with the required response time.
B. Confirm scenarios function as written.
F. Document detectors function according to above on the smoke detector test sheet or utilize a device
printout to show list of detectors tested if available from the fire alarm system. C. Confirm system functions under emergency power.
Exhibit 1 - Smoke Control System Rational Analysis Report – Appendix F 9 March 2015
Jabal Omar Development Zones Ph 4, S09 Aon FPE No. 2814037-000
Makkah, Saudi Arabia Page F-3
Page Left Intentionally Blank
Exhibit 2 – Carpark Smoke Exhaust
CFD Report
Jabal Omar Development Project
9 March 2015
Submitted by:
Aon Fire Protection Engineering Corporation
Al Reem Tower, Al Maktoum Street, Suite 501 | Dubai, UAE
t +9714.228.2841 |f +9714.228.2965
www.aonfpe.com
Prepared for:
Jabal Omar Development Company
Table of Contents
1. Introduction 1
1.1. Emergency ventilation/Unsteady state Fire simulation 1
2. Computational Fluid Dynamics Analysis 1
2.1. Introduction 1
2.2. Processes involved in CFD 1
2.3. Governing Equations 2
2.3.1. Conservation of mass 2
2.3.2. Conservation of species 2
2.3.3. Momentum equation 2
2.3.4. Conservation of energy 2
2.4. Turbulence Modelling 3
2.4.1. LES Turbulence Model 3
2.4.2. Modeling Large Eddy Simulation Parameters 3
3. Fuel Load and Design Fires 3
4. Fire Mode Simulation 5
4.1. Design Criteria for Smoke (Fire) simulations 5
4.1.1. Simulation Parameters 5
5. Fire Simulation CFD Results 6
6. Conclusions 16
Appendix
Appendix A – Basement Level 1 A-1
Appendix B – Basement Level 3 B-1
Appendix C – Fans Schedule and C&E Matrix C-1
Fire Strategy – Phase 4, Zone S9 (Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page i
Basement 3 will have the same results output because it is similar to basement 2, however Appendix B will show
fans details and distribution.
1. Introduction
This report (Exhibit 2) provides an engineering analysis of the car park smoke removal system using a special
1.1. Emergency ventilation/Unsteady state Fire simulation
software tools complying with GCC and international standards. For an overall smoke control strategy for the
Fire safety in underground car parking is important, as accidental fires can be dangerous. When a fire breaks out
entire Phase 4 project, please refer to the Fire Safety Strategy Report, Chapter 9, Smoke Control System.
in a car park, a large amount of smoke is generated at high temperature leading to poor visibility and difficulty in
Specifically, the carpark smoke removal strategy is outlined in Section 9.9, Parking Garage Ventilation (Carpark)
evacuation. In most cases, the victims are poisoned or starved of oxygen by the smoke. In addition, the smoke
of that report.
also causes most of the damage to the vehicles. In the event of a fire, the first priority is to expel the smoke from
the car parking and the installed ventilation system must work efficiently. This shall ensure the quick and safe
The Zone S9 consists of three hotel towers which are on top of a 9-level podium, including the below grade levels.
evacuation of people from the car park and also provide smoke free area for fire fighters to control the fire.
The uses within the towers are primarily hotel guestrooms, while the podium contains mixed use functions. The
podium contains multiple uses on the various levels, including commercial (retail), both public and back-of-the-
The specific aim of the emergency ventilation study is to check whether it meets the temperature & visibility
house areas of the hotel; parking, and some residential.
tenability criteria in case of accidental fire inside the car park area, and also to check that the given location and
numbers of Jet fans are sufficient to push the hot smoke towards exhaust fans, without blocking the escaping
The podium contains 9 stories of multiple use commercial retail, restaurants, hotel front and back of the house
routes in the car parking area.
functions, offices, assembly spaces, parking areas, and residential units. The lowest three levels contain car
parking area. Level 4 is the Road B access to the hotel lobbies. Level 5 to 8 includes restaurants, lounges and
commercial area.
2. Computational Fluid Dynamics Analysis
The garage levels in the podium of Zone S9 are below grade. The general uses of the podium, starting at the
lowest level, are as follow:.
2.1. Introduction
Level (+304.6) “First Basement” = Storage (Parking)
Computational fluid dynamics (CFD) can simultaneously predict airflow, heat transfer and contaminant transport in
Level (+307.8) “Second Basement” = Storage (Parking), Retail, Business (offices)
Level (+311.0) “Third Basement ” = Storage (Parking), Business (offices). and around buildings. A CFD model is built upon fundamental physical equations of fluid flow and energy transfer.
Level (+316.0) “Ground Floor” = Hotel Lobby, Restaurant and Retail The technique is capable of providing time dependent and as well as steady state solutions to the coupled
Level (+320.65) “Commercial 1” = Retail, Assembly (Restaurants) differential equations that govern fluid flows. Its key benefits are; an ability to represent the effects of very complex
Level (+325.02) “Commercial 2” = Retail, Assembly (Restaurants) geometries coupled with a means to solve complex flow problems based on a more fundamental modeling of the
Level (+329.45) “Commercial 3” = Retail, Assembly (Restaurants) physics involved. It has since been developed and applied to an increasingly diverse range of problems, including
Level (+333.65) “Commercial 4” = Commercial Retail automotive, aerospace, nuclear engineering, turbo machinery, biomedical field, buildings, environment and fire
safety engineering.
The design of the smoke removal system is intended to clear the of smoke during the fire and after the fire
has been suppressed. The smoke removal will assist in checking for secondary seats of fire, as well as However, a number of assumptions and approximations are made throughout: both in formulating and
returning the building at its normal use. The design team has opted to use mechanical cross ventilation using constructing a CFD tool, as well as in its application to a particular flow problem. Also, compromises are often
jet fans required in order to achieve reasonable run-times. These all ultimately influence the reliance which can be placed
on results of CFD simulations. This section explains the basics of CFD as applied in fire safety engineering and
The objective of this report is to validate the design of the jet fan ventilation system and to verify the effectiveness presents the compromises that a CFD user often has to make. More information can be found in general books on
of jet fans and mechanical exhaust system in case of car fire using Computational Fluid Dynamics (CFD) analysis. CFD, for instance Ferziger and Peric (1996), Veersteg and Malalasekera (1995), Anderson (1995).
There are three parking levels in S9, as noted above. For additional details refer to the fire strategy drawings and
fire strategy report. CFD Simulation of fire spreading & smoke propagation inside a basement involves modeling of heat generation
by fire, effects of buoyancy due to temperature, smoke species concentrations, velocity and pressure variations
The CDF models and the report that follows have assumed the following naming nomenclature: caused by exhaust, fresh air and Jet fans in operation. CFD analysis provides a detailed picture of the smoke path
inside the basement and different parameters like smoke concentrations, smoke temperatures, visibility levels and
Basement Level 1 (Elevation +304.6) velocity profiles at different times and different positions inside the basement. This is difficult to obtain by
Basement Level 2 (Elevation +307.8) experiments, because experiments can be time consuming, costly and sometimes fire and smoke related
Basement Level 3 (Elevation +311.0) experiments inside the underground basements can be dangerous as well.
The Jet fan ventilation system is designed for the car parking for providing ventilation for car park area in normal
operating conditions as well emergency operating conditions. Basement 2 was selected as the worst case 2.2. Processes involved in CFD
location. Nevertheless, basement 1 level has been analyzed and is detailed in the Appendix A of this report.
When applying a CFD package to undertake a flow and thermal analysis, there are number of steps that involved
for completing the CFD process.
Fire Strategy – Phase 4, Zone S9 (Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 1
Defining the geometry and domain the terms for the inflow or outflow of species from the control volume due to diffusion and the production rate of
particular species within the control volume caused by chemical reaction.
Selecting physical sub-models
Specifying boundary conditions at the frontiers of the domains including walls, inlets, openings, supply fans, 2.3.3. Momentum equation
exhaust fans, Jet fans, fire location and burning material properties.
Discretizing the mathematical equations, which includes creating a mesh (which sub-divides the space into The equation for the conservation of momentum is derived by applying Newton’s second law of motion, which
small volumes), setting time steps (which divides the time into discrete steps) and selecting numerical sub- states that the rate of momentum of a fluid element is equal to the sum of the forces acting on it (Cox 1995). The
models equation is written as:
p v2
Where the first term describes the density changes with time and the second term defines the mass convection. E h
Where ‘u’ is the vector describing the velocity in the u, v and w directions.
2
Where sensible enthalpy ‘h’ is defined for ideal gases as
t T
Y j Is the mass fraction of species j and h j
Tref
c pj dT
Where the first term on the left side represents the accumulation of species due to change in density with time, the
second term is the inflow and outflow of species from the control volume due to convection. The right side gives
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 2
2.4. Turbulence Modelling 3. Fuel Load and Design Fires
Turbulence is the state of fluid motion which is characterized by apparently random and chaotic three-dimensional
vorticity. The most important physical consequence of turbulence is the enhancement of transport processes. In a The most influential factors for determining the heat release rate of a design fire are the type and quantity of the
turbulent flow, momentum, energy, and particle transport rates greatly exceed the corresponding molecular expected commodity. The heat content of the material, the burning rate, the exposed surface area, and how the
transport rates. Turbulent flows exhibit much more small-scale structure than their non-turbulent counterparts. commodity reacts to the application of water determine the protection requirements. The overall hazard of a
When turbulence is present, it usually dominates all other flow phenomena and results in increased energy commodity is a function of its heat release rate (expressed in kW), which is the product of its heat of combustion
dissipation, mixing, heat transfer, and drag. If there is no three-dimensional vorticity, there is no real turbulence. (expressed in kJ/kg) and burning rate (expressed in kg/sec).
The reason is ability to generate new vorticity from old vorticity that is essential to turbulence. And only in a three-
dimensional flow is the necessary stretching and turning of vorticity by the flow itself possible. An idealized fire model that is of considerable use is the t-squared fire. The heat release rate of this fire is
proportional to the square of time. This idealized heat release rate is expressed as:
Several scientists proposed their own definition to turbulence, in 1975, Hinze proposed the turbulence definition as
“Turbulent fluid motion is an irregular condition of flow in which the various quantities show a random variation (1)
Q = αt2
with time and space coordinates”.
Where: Q = heat release rate of fire (kW)
In 1937, Taylor and VonKermen proposed the following definition of turbulence: "Turbulence is an irregular motion α = fire intensity coefficient (kW/s2)
which in general makes its appearance in fluids, gaseous or liquid, when they flow past solid surfaces or even t = growth time (seconds)
when neighboring streams of the same fluid flow past or over one another." It is characterized by the presence of
a large range of excited length and time scales. The irregular nature of turbulence stands in contrast to laminar The growth time, t, is the interval between the time of effective ignition and the time when the heat release rate of
motion, because the fluid was imagined to flow in smooth layers. Virtually all flows of practical engineering interest the fire reaches 1,055 kW. For a medium growth fire, the fire growth rate follows the t-squared fire curve and
are turbulent. Turbulent flows always occur when the Reynolds number is large.
reaches 1,055 kW in 300 seconds(1).
Where Cs is an empirical constant & Δ is a length on the order of the size of a grid cell .
And other diffusive parameters, the thermal conductivity and material diffusivity are computed with following
equations:
2
Figure1. Fire Growth Rate Model (t )
1
In above equations the turbulent Prandtl number ‘Prt’ and the turbulent Schmidt number ‘Sct’ are constant values. th
Richard W. Bukowski., “Fire Hazard Analysis”, NFPA Fire Protection Handbook, 19 ed., A. E. Cote (Ed), National Fire Protection
Association, Quincy, MA, 2003, Vol. 1, pp. 3-107.
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 3
This “medium” growth design fire is selected to present a worst-case scenario, which will reach 4MW at 585 Sprinklers spacing : 3 meters (Ordinary hazard group I)
second and will remain constant for the duration of the simulation. Figure 1 illustrates typical t-squared medium
growth fire curve. Sprinklers temperature rating : 79 degrees
Based on the above criteria, sprinklers activate at 3.78 minutes at a heat release rate of 601 KW. A conservative
design would typically assume a sprinkler-controlled scenario. A conservative sprinkler-controlled fire curve, which
remains steady state at 1MW is illustrated in Figure 4.
2
Figure 2. Medium Growth Rate Curve (t )
The selection of a 4MW medium growth fire was based on full scale test data available for passenger vehicles.
Figure 3 shows a vehicle fire where the heat release rate peaks at 4MW and decays2). This decay is not cause by
sprinkler activation but due to fuel burnout. Figure 4. 1-MW Fire Medium Fire Growth Rate Curve
Rather than using the effectiveness of sprinkler-controlled fires, Aon FPE developed a conservative fire growth
curve that follows the full scale test data referenced in Figure 3, but it did not include a decay period. The design
fire reaches 4MW fire at 10 minutes and remains constant for the duration of the simulation (Refer to Figure 5).
This conservative design fire represents the worst-case scenario which was modeled to determine the effectives
of the jet fans system. In reality, the automatic sprinklers are assumed to control or even extinguished the fire.
Thus, the results of the fire simulations are extremely conservative.
2
Figure 3. Medium Growth Rate Curve (t )
The carpark areas will be provided with sprinkler system. The cooling effect of the sprinklers will control or even
extinguished the fire. To determine the fire growth prior to activation of sprinklers, the following calculations were
made using FPE tool software developed by NIST:
2
Shipp, M. and Spearpoint, M. (1995). “Measurements of the severity of fires Involving Private Motor Vehicles” Fire and Figure 5. 4 MW Fire Medium Growth Rate (Design Fire)
Materials, Vol.19, pp. 143-151.
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 4
The BS 7346-7, Section 4.2 indicates that where the objective is to achieve clearance by horizontal cross flow
4. Fire Mode Simulation through the car park story one of the following may be used:
Simulation of smoke propagation inside a car park involves modeling heat generation by fire, effects of buoyancy Natural cross ventilation specified as permanent openings in accordance with clause 7.
due to temperature and smoke species concentrations and the velocity and pressure variations caused by
mechanical ventilation system in operation. CFD analysis provides a detailed picture of the smoke path inside the Mechanical cross ventilation achieved using conventional ventilation in accordance with clause 8.
car park and different parameters like smoke concentrations, smoke temperatures and velocity profiles at different Mechanical cross ventilation using jet fans in accordance with clause 9.
times and different positions inside the building. This is difficult to obtain by experiments, because experiments
can be time consuming, costly and sometimes fire and smoke related experiments inside the buildings can be
The design team has opted to use mechanical cross ventilation using jet fans. A computer model has been
dangerous as well.
provided to verify that the proposed exhaust fan locations, location of makeup air fans, and the number of jet fans
meet the design intent.
In this analysis fire is modeled as combustion of polyurethane material in the car fire with a heat release rate of 4
MW medium t2 curve with convective & radiation effects. The fire simulation is carried out based on the below fire
curve with peak heat release rate of 4 MW with steady state beginning from 10 minutes which represents the 4.1.1. Simulation Parameters
worst case scenario. Refer to Graph (1). The fire source is represented as a rectangle block of length 4 m, width 2
m and height 1.25m situated in the car park area. During fire simulation, all the ventilation system runs in high The following tables summarize the modeling parameters:
speed and the Jet fans will activate after 2.5 minutes of delay. The delay is provided to allow occupants to exit the
area prior to turning the jet fans to high speed. Without a delay for occupant evacuation, occupants could be Table 1(Fire Details)
exposed to smoke and hot gases as they exit the carpark. Parameter Quantity
Fire size 4MW Car Fire
4.1. Design Criteria for Smoke (Fire) simulations Time to reach 4 MW fire as per medium fire
10 minutes
growth rate
Based on discussions with Civil Defense, the Approved Document BS7346-2006 edition and Approved Document
F-2010 edition of the British Building Regulations have been used to provide specific design guidelines for Total duration of fire 20 minutes duration
ventilation of car parks. The Approved Document B, Section 11.6 requires basement car parks and enclosed car Fire location As shown in the fig. 1(a)
parks be provided with mechanical ventilation. The mechanical ventilation must comply with the following:
Fire Material Polyurethane material in car
The system will be independent of any other ventilation system (other than any system providing normal Heat of Combustion of Petrol 28 KJ/g (Source: NFPA Handbook)
ventilation to car park). The ventilation system must be designed to operate at 10 air changes per hour during
fire condition as referenced in Approved Document BS7346-2006. Smoke yield of Petrol 0.104 (Source: NFPA Handbook)
Each part of the system will have independent power supply which will operate in the event of failure of the
main power supply. Table 2
Exhaust fans should be rated to run at 300οC for a minimum of 120 minutes and the ductwork and fixings Parameter Quantity
must be constructed from materials having a melting point not less than 800οC. Further information on the hot
No. of Exhaust Air Openings for Fire Point 4
smoke removing equipment is referenced in BS EN 12101-3.
No. of Supply Air Openings for Fire Point 3
The BS 7346-7, Section 4.1 outlines three design objectives:
Positions of Exhaust & Supply Openings As shown in Fig. 1 (a) & 1(b)
Clearance of smoke during the fire and after the fire has been suppressed, smoke removal to assist in
No. of Jet fans working for Fire Point 10
checking for secondary seats of fire, as well as returning the building at its normal use.
Location of Jet fans As shown in Fig. 1 (a) & 1 (b)
Creating and maintain a smoke-free route through the car park open space on the fire’s story for firefighters to
approach the car on fire, with the intention of facilitating manual fire suppression. Mode of Supply Air Inlet Natural & Mechanical
Protection of escape routes for occupants within the same story as the car on fire, to reserve a smoke-free Mode of Exhaust Air Outlet Mechanical
path to either the exterior of the building, or to a protected stairwell which leads to a final exit to a place of Mode of Exhaust Air Outlet
safety. Mechanical
The design team has opted to select the first option: Clearance of smoke during the fire and after the fire has
been suppressed, smoke removal to assist in checking for secondary seats of fire, as well as returning
the building at its normal use.
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 5
Table 3(a) 1) Following figures shows the geometric details, location of fire
Exhaust Air Opening Specifications source
Name Volume Flow Rate in CMS
Supply-1
Exhaust Air Louver Opening-1 7.14 Exhaust Air Fan opening (Red Object)
Exhaust Air Louver Opening-2 7.14
Exhaust Air Louver Opening-3 15.02 Supply-2
Table 3(c) Exhaust 1 Supply Air Fan & Ramp Openings (Green Object)
Jet fan Specifications
No. of Jet fans Volume Flow Rate in CMS
Type of Jet fan working for fire Fig. 1(a): Location of Jet Fans, Exhaust Air, Supply Air, Ramp openings & Fire location of “Jabal Omar
point Low speed High speed Phase-4-S9, Car park (level-2)”
31JT - 3LP-UBD- TB 10 0.6 1.2 Exhaust 4
Exhaust 3
The geometry of the car park and the results of the fire simulation for Basement 2 and basement 3 (basement 2 &
3 are identical) are summarized in the figures below.
Fig. 1(b): Location of Jet Fans, Exhaust Air, Supply Air, Ramp openings & Fire location in 3D view of
“Jabal Omar Phase-4-S9, Car park (level-2)”
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 6
2) Following figures shows the smoke generated from burning Car
inside the basement at different timings
Fig.2 (b) Contours of smoke from burning vehicle at 1.5minutes of time in Fig.2 (d) Contours of smoke from burning vehicle at 5 minute time in
“Jabal Omar Phase-4-S9, Car park (level-2)” “Jabal Omar Phase-4-S9, Car park (level-2)”
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 7
Fig.2 (e) Contours of smoke from burning vehicle at 10 minute time in Fig.2 (f) Contours of smoke from burning vehicle at 20 minute time in
“Jabal Omar Phase-4-S9, Car park (level-2)” “Jabal Omar Phase-4-S9, Car park (level-2)”
3) Following figures shows the Velocity contours of the air in the car
park area.
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 8
“Jabal Omar Phase-4-S9, Car park (level-2)” Fig.4 (a) Contours of Temperature in (°C) at starting of fire in
“Jabal Omar Phase-4-S9, Car park (level-2)”
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 9
“Jabal Omar Phase-4-S9, Car park (level-2)”
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 10
5) Following figures shows the Temperatures generated from burning
Car inside the basement in horizontal plane at 1.8 m height & at
different timings
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 11
Fig.5 (g) Contours of Temperature in (°C) at 20 minute time in
Fig.5 (e) Contours of Temperature in (°C) at 10 minute time in
“Jabal Omar Phase-4-S9, Car park (level-2)”
“Jabal Omar Phase-4-S9, Car park (level-2)”
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 12
Fig.6 (d) Contours of visibility levels in (meters) at 5 minute time in
Fig.6 (b) Contours of visibility levels in (meters) at 1.5 minute time in “Jabal Omar Phase-4-S9, Car park (level-2)”
“Jabal Omar Phase-4-S9, Car park (level-2)”
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 13
8) Following figures show the Visibility levels in (meters) in horizontal
plane at 1.8 m height & at different timings
Fig.6 (g) Contours of visibility levels in (meters) at 20 minute time in Fig.7 (b) Contours of visibility levels in (meters) at 1.5 minute time in
7) “Jabal Omar Phase-4-S9, Car park (level-2)” “Jabal Omar Phase-4-S9, Car park (level-2)”
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 14
Fig.7 (c) Contours of visibility levels in (meters) at 3 minute time in
“Jabal Omar Phase-4-S9, Car park (level-2)” Fig.7 (e) Contours of visibility levels in (meters) at 10 minute time in
“Jabal Omar Phase-4-S9, Car park (level-2)”
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 15
Fig.7 (g) Contours of visibility levels in (meters) at 20 minute time in
“Jabal Omar Phase-4-S9, Car park (level-2)”
6. Conclusions
The design objective for the Carpark smoke removal is to clear the smoke during the fire and after the fire has
been suppressed. A supplemental objective is to remove smoke to assist in checking for secondary seats of fire,
as well as returning the building at its normal use.
The fire simulation of the basement has been simulated for 20 minutes of duration with CFD; this work is carried
out to examine the proposed Jet fan ventilation system for given peak heat release rate (Convection + Radiation)
of 4 MW fire. The following conclusion can be reached after simulating the three basements levels:
The smoke is cleared within the fire area zone using the exhaust fans strategically located in the Carpark. The
remote civil defense access points (stairs) are maintained clear of smoke to allow Civil Defense access to
fight the fire.
The temperatures are less than 60 0C in the areas away from the fire, which give access to Civil Defense to
fight the fire (at all stairs access).
Visibility is maintained in the areas away from the fire (at least at one stair access), which give access to Civil
Defense to fight the fire.
The effectiveness of automatic sprinkler system was not accounted in the simulations. In reality, the sprinkler
system is assumed to control the fire, which will reduce the smoke production significantly.
Based on the results of the fire model, the jet fan system meets the intent of the code. The smoke removal of the
carpark areas will be detailed by the general contractor for integration with the building fire alarm.
Fire Strategy – Phase 4, Zone S9(Exhibit 2 – Carpark CDF Report) 9 March 2015
Jabal Omar Development Aon FPE No. 2814037-000
Mekkah, Saudi Arabia Page 16
Appendix A – Basement Level 1 Mode of Exhaust Air Outlet Mechanical
Table 3(a)
Exhaust Air Opening Specifications
Name Volume Flow Rate in CMS
Exhaust Air Louver Opening 25
Table 3(b)
Table 3(c)
Table 2
Parameter Quantity
No. of Exhaust Air Openings for Fire Point 1
No. of Supply Air Openings for Fire Point 1
Positions of Exhaust & Supply Openings As shown in Fig. 1 (a) & 1 (b)
No. of Jet fans working for Fire Point 6
Location of Jet fans As shown in Fig. 1 (a) & 1 (b)
Mode of Supply Air Inlet Natural & Mechanical
Fire Location
Exhaust
Supply Air Fan & Ramp Openings (Green Object) Fig.2 (a) Contours of smoke from burning vehicle at starting of fire in
“Jabal Omar Phase-1, Car park (level-1)”
Fig. 1(a): Location of Jet Fans, Exhaust Air, Supply Air, Ramp openings & Fire location in plan view of
“Jabal Omar Phase-4- S9, Car park (level-1)”
Supply 2
Supply 1
Fig.2 (f) Contours of smoke from burning vehicle at 20 minute time in (4) Following figures show the Temperatures generated from burning
“Jabal Omar Phase-4- S9, Car park (level-1)” Car inside the basement in different vertical planes & at different
timings
(3) Following figures shows the Velocity contours of the air in the car
park area.
Supply 2
Parameter Quantity
No. of Exhaust Air Openings for Fire Point 1
No. of Supply Air Openings for Fire Point 1
Supply 3
Positions of Exhaust & Supply Openings As shown in Fig. 1 (a) & 1 (b)
No. of Jet fans working for Fire Point 10
Location of Jet fans As shown in Fig. 1 (a) & 1 (b)
Jet Fan
Mode of Supply Air Inlet Natural & Mechanical
Mode of Exhaust Air Outlet Mechanical
Table 2(a)
Exhaust Air Opening Specifications
Exhaust 1
Name Volume Flow Rate in CMS
Exhaust Air Louver Opening-1 7.57
Exhaust Air Louver Opening-2 7.57
Exhaust 4
Exhaust Air Louver Opening-3 15.02
Exhaust Air Louver Opening-4 7.5
Exhaust 3
Table 2(b)
Supply Air Opening Specifications
Name Volume Flow Rate in CMS (each opening)
Exhaust 2
Supply Air Louver Opening - 1 6.68
Supply Air Louver Opening - 2 15.02
Supply Air Louver Opening - 3 6.68
Table 2(c)
Closed
Closed
Closed
PHASE 1-S2
Car Park Floors
System Input
1 Normal Ventilation condition X X X X X X X X
Note:
Motorized smoke dampers mention in table above shall be located at the Supply and exhaust fans at each parking Level for air control purposes.