Professional Documents
Culture Documents
--------------------------------------------------------------------------------------------------------------------
Location: TOTAL GAZ D7, Village 5, Tan Thuan Dong Ward, District 7, Ho Chi Minh City,
VietNam
Revision: 01 Date:
30Jun202116Sep2022
Written: L.N.T.Van
Table of Contents
1 INTRODUCTION..................................................................................................................3
5.2 Requirement for Fire water buffer tank & water capacity.............................................11
--------------------------------------------------------------------------------------------------------------------
1
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
7 BIDDER’S CHECKLIST.....................................................................................................16
--------------------------------------------------------------------------------------------------------------------
2
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
1 INTRODUCTION
TOTALGAZ D7 (TGV D7), a LPG storage terminal and filling plant is located at Village 5, Tan
Thuan Dong Ward, District 7, Ho Chi Minh City. The plant was built and has been operating
since 1991 by TOTAL VietNam. With over 19.325 m 2 site area, the plant is designed into 05
main lots, including: LPG tank farm & piping, LPG Pumps & Compressors Area, LPG filling
hall, Tank-truck loading & unloading, Fire Fighting System, Generator Area and Workshop,
Canteen & Office Building.
The tank farm is equipped with 18 LPG tanks including: 14 x 150 m 3 bullet tanks; 04 x 330 m3
bullet tanks to meet the storage with max capacity 1600 MT. The Jetty is owned by the plant for
reception of LPG vessels with deadweight 3,000MT.
The filling hall with 01 Carousel 24 posts, 01 Carousel 36 posts for 12kg -12.5kg cylinders; 01
stationary filling line for big cylinders (39-45kgs) and 1 stationary filling line for 6kg cylinders.
Utility area is equipped with Air compressors, Power generators, Electrical system is able to
cover the demand of production & office.
Main fire water source is from Saigon river (brackish water during April to July). The Fire
Fighting & Fire Alarm system in TGV D7 Plant includes :
In this project, TOTAL shall upgrade the Fire Fighting System to comply with TOTAL’s new
HSE requirement and supply the cooling water for the current Fire scenarios of Plant.
--------------------------------------------------------------------------------------------------------------------
3
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
Therefore, TOTAL VietNam is looking for a suitable CONTRACTOR who has enough capacity
and experience for getting agreement with TOTAL Vietnam as a competent CONTRACTOR to
provide the service with scope of work to be defined hereunder.
--------------------------------------------------------------------------------------------------------------------
4
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
Any case of apparent conflict between those documents shall be brought to the notice of the
COMPANY by the CONTRACTOR. The CONTRACTOR are obliged to always check
that the applicable regulations, in particular regarding HEALTH, SAFETY,
ENVIRONMENT and QUALITY, do not impose more restrictive measures. Unless
otherwise agreed by the COMPANY, the more stringent requirements in the general order
of precedence shall apply.
--------------------------------------------------------------------------------------------------------------------
5
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
The latest edition of the following codes and standards below shall be applicable. The
CONTRACTOR may propose an equivalent alternative code compliance, in which case
the CONTRACTOR shall clearly identify the propose alternate in their proposal.
However, any proposed alternate shall be subject to The COMPANY approval.
NFPA 15 - Standard for Water Spray Fixed Systems for Fire Protection
NFPA 20 - Standard for the Installation of Stationary Pumps for Fire Protection
NFPA 22 - Standard for Water Tanks for Private Fire Protection
API RP 2030 - Application of Fixed Water Spray Systems for Fire Protection in
the Petroleum and Petrochemical Industries
API STD 2510 - Design and construction of LPG Installations
API PUBL 2510A - Fire Protection considerations for the Design and Operation
of Liquefied Petroleum Gas (LPG) Storage Facilities
The CONTRACTOR shall be responsible for ensuring compliance with all applicable
Vietnamese codes, standards, and regulations.
--------------------------------------------------------------------------------------------------------------------
6
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
The new fire scenarios and required flowrate might have a significant impact on the
existing firefighting system including pumps, valves and water network piping,
generator... Then the whole system must be upgraded follow then.
The layout of plant & other related technical information of existing Fire Fighting
System are available is Attachment 1: General Layout. All sizes and quantities indicated
shall be used as a guideline only. The CONTRACTOR shall re-measure and verify all
quantities/dimensions during Engineering Detailed Design and obtain Company's
approval thereon.
The Contractor shall provide manpower and tool/software to carry out Engineering of
the modification work and Cost Estimation for Procurement, Installation & Construction,
in accordance with the following requirement:
Conduct site survey, including but not limited to surveying the firefighting piping
and equipment and other related systems of the plant to study the possibility of
new installation / integration;
--------------------------------------------------------------------------------------------------------------------
7
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
Jetty 6 m2 3mx2m 1
--------------------------------------------------------------------------------------------------------------------
8
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
Dimension
150m3
--------------------------------------------------------------------------------------------------------------------
9
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
Place: TOTAL GAZ D7, Village 5, Tan Thuan Dong Ward, District 7, Ho Chi Minh
City, VietNam.
Fire Scenarios of Plant: Total discuss with contractor during the design;
Water flowrate: Contractor check with Local Authority the requirement of Water
flowrate (can keep 7.2 l/min/m2 for existing plant?) and confirm during Basic Design.
Due to the constraint of the existing Fire Pump House, the concept of adding new Fire
Pump is not feasible. Contractor study the concept of adding new submersible pumps
(number n+1), integrated into the existing main ring or the new ring, whatever feasible.
Water curtain can be used in this plant to minimize radiant heat and separate the fire
zone in sequence. Contractor study to install water curtain system along the pipe, in
front of the tank 1-11, 12-18.
Number of 02 Fixed Monitor those can cover equipment surface area in Pump House is
a requirement (including outskirt of at least 0.6m).
CONTRACTOR have a survey to evaluate & re-calculate then give out the Concept &
Detailed Design for Modification for upgrading existing system.
10
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
shall be safeguarded from fire by adequate separation distance from fire hazards,
or by fire proof enclosure, or by active fire protection – or a combination of
these;
shall be accessible in case of fire (operating devices);
shall be protected against unauthorized access (if indoors);
shall have suitable ventilation (if indoors);
shall not be installed in indoors areas which are used for flammable or
combustible storage and/or production;
shall have sufficient markings;
shall be safeguarded against mechanical damage.
Fire water source: Sai Gon River Water (Brackish water during April – July).
5.2 Requirement for Fire water buffer tank & water capacity
The fire water capacity shall be sized to cover the needs that are associated with a
credible over 4 hours.
The water capacity is always kept filled, the water level shall never be more than 10 cm
(4”) below the designed fire service level.
The fire water mains shall always be strictly independent of the other water networks
(process water, drinking water, etc.) and shall only be used for fire-fighting purposes.
New pipes, fittings, valves and accessories shall be in compliance with the requirements
provided in GS-MS-PVV-001 and GS-MS-PVV-002. Firefighting equipment and
pipelines shall be identified and painted according to GS-MS-COR-001. Those
documents are provided during execution.
Ball valves, in the fire water line to monitors, and butterfly valves shall be provided with
gear operators limiting its closure time to 10 to 15 seconds to avoid damage to piping by
water hammer.
--------------------------------------------------------------------------------------------------------------------
11
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
Maximum Water Demand: Contractor to calculate & confirm the new capacity based on
requirement on Table 1, with some derogation. Total will discuss in detail during the
engineering detail design.
--------------------------------------------------------------------------------------------------------------------
12
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------
13
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
Contractor restudy the control system and provide the new integrity concept to integrate
the new pumps into main control system.
Contractor study power supply for new pumps and capacity of generator.
Number of 02 Fixed Monitor those can cover equipment surface area in Pump House is
a requirement (including outskirt of at least 0.6m).
CONTRACTOR shall provide the Final Documentation (Design Deliverable) for both
documents/drawings for modification scope and updating existing drawing to comply
with the current status at site, including but not limited to:
Basic Design:
--------------------------------------------------------------------------------------------------------------------
14
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
UFD, PID;
Fire Fighting System Design Philosophy
Hydraulic Calculation for Fire Water System
Calculation Sheet for Fire Scenarios
Preliminary Datasheet, specification, MTO for main Equipmnet: Pump, Water
curtain, Fixed Monitor, Generator...
Cost Estimation Report
Response of Local Authority on the FF Basic Design.
Detail Design:
EMDR
UFD, P&ID
Fire Fighting System Design Philosophy
Calculation Sheet for Fire Scenarios
Datasheet, specification, MTO for FF Equipment’s
FF Equipment Layout & Escape Route
Hazardous Area Classification Drawing
Hydraulic Calculation for Fire Water System
Plot Plan, Piping General Arrangement, Isometric Drawings, Pipe Support, MTO
Mechanical Datasheet for new equipment: Pumps, Water curtain, Fixed
Monitor….
Calculation & Design Drawing (Mechanical & Civil), MTO for fire water tank
(if any)
Instrument Specification for Fire Fighting Control System
Datasheet for Valve & Instrumentation
Datasheet, Specification for Control System and Generator
Instrument Cable Routing Layout & Wiring Diagram
Instrument Hook up, Installation detail, Cable Schedule, MTO
Single line diagram for Fire water pump house
Earthling system layout
--------------------------------------------------------------------------------------------------------------------
15
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
CONTRACTOR have business license on Engineering Design for Fire Fighting System.
CONTRACTOR have experience with TOTAL in similar project will be added more
score in evaluation.
--------------------------------------------------------------------------------------------------------------------
16
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
7 BIDDER’S CHECKLIST
The BIDDERS are required to submit to COMPANY all the documents complied with
the following checklist packing in their technical proposals, but not limited to:
1 Company profile
6 Preliminary Schedule
--------------------------------------------------------------------------------------------------------------------
17
D7 LPG Plant _ Fire Fighting Upgrading Project
--------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------------------
18