Professional Documents
Culture Documents
1. OBJECTIVE
1. REFERENCE
2. PRE-REQUISITES
4. TEST EQUIPMENT
6. COMMISSIONING REPORT
1. OBJECTIVE
2. REFERENCE
HT Switchgear drawing
Make: Siemens India.
(Drawing Nos. refers to Siemens drawings)
5. TEST EQUIPMENT
3. Breaker truck should be removed with putting the panel number marking on
it. After this, another panel should to be installed in the same fashion. Side
bolts of the first panel are required to be removed. Second panel should be
placed very near to the first panel and aligned this on the foundation. It
should be matched with the side bolts hole of the first panel. Perfect
matching will take place only when the second panel is properly aligned on
the foundation and it is perfectly vertical. Sims may be used as per
requirement. Both the panel should be bolted. Install all HT panels by
following this sequence.
Before finalizing the welding, it is required to check that all the breakers can
be easily racked in and racked out, with the proper operation of shutter drive
mechanism and breaker earthing contact. Finalize the welding after
satisfactory rack in rack out operations.
5. Bus bars of the adjacent panels should be joined together using the bus
bars and hardware supplied. Bolts should be torque tightened. The support
insulators should be cleaned properly.
8. Ensure that HT cables are well supported with clamps so that the weight of
the cable should not be exerted on the cable terminal.
1. All the breakers should be checked for smooth rack-in, rack-out, locking
of transfer operating mechanism, proper fixing of interlocking plate, door
interlock during service position and cable compartment back cover
opening interlock. Bus bar and cable earthing trolley should also be
checked.
2. Insulation resistance of the breaker should be checked.
3. Contact resistance of each phase of the circuit breaker shall be measured
by micro ohmmeter.
4. Breaker operation (manual and electrical) should be checked. Tripping
should be checked through lock-out.
5.
5. Spring charging time should be measured with stopwatch.
6. Anti pumping operation should be checked.
7. Safety shutters operations should be checked.
8. Moving breaker earth continuity should be checked.
iv) HV test
High Voltage withstand test is required to be carried out at 16 kV for each
phase of the bus bar with respect to earth.
After carrying out high voltage test, it is required to measure the insulation
resistance of each phase bus bar with respect to earth and between the
phases to check the healthiness of bus bar support insulators during high
voltage test. It should be measured with 2.5 kV meggar.
Secondary injection test should be carried out for the protective relays.
Relay setting should be done as per co-ordination chart.
x) Operation check
Incomer-1/ Incomer-2 and Bus Coupler through ASCP and ABT panel.
Incomer breaker should be closed locally. Switchboard should be observed for any
abnormal humming sound. Bus PT and its phase sequence should be checked.
Ensure that other incomer breaker is racked-out. Bus coupler should be racked in
and closed locally. Observation should be continued for this portion of switchboard
also for any abnormal humming sound. Bus PT and its phase sequence should be
checked.
Ambient temp……….
Insulation HV Contact
Resistance TEST Resistance
Breaker
Sl. No. Feeder details
Ph Ph to
-Ph Earth
1
.
2
.
3
.
4
.
5
.
6
.
7
.
8
.
9
.
1
0
.
1
1
.
1
2
.
1
3
.
1
4
.
1
5
.
1
6
.
1
7
.
1
8
.
1
9
.
2
0
.
2
1
.
2
2
.
2
3
.
2
4
.
2
5
.
2
6
.
2
7
.
2
8
.
2
9
.
3
0
.
3
1
.
3
2
.
3
3. Insulation resistance of bus bar (Before H.V. test):
6. C.T. Testing:
Polarity Check
Ratio Test Pri. Sec. Pri. Sec. Pri. Sec.
Curr. Curr Curr Curr Curr Curr
Polarity Check
Ratio Test Pri. Sec. Pri. Sec. Pri. Sec.
Volt. Volt. Volt. Volt. Volt. Volt.
Table: 1
( I - Current.)
Check Operation of output contacts : …………………………………
Table: 5
Table: 1
NOTE: Recheck the settings in all the service codes and configuration of output
relays. It should be as per the application and schematic drawing.
Disconnect CT inputs from the relay.
Set the earth fault trip time settings (Code-32) to minimum. Keep the other
protection settings high so that it should not disturb the protection under test.
Inject single-phase current into each of the phase and earth fault inputs, in turn.
Slowly increase the current until the trip LED glows. Check the output relay contact
on which this protection id configured. Record the pick-up current. Reduce the
current until the trip contact drops off. Record the drop off level.
Original time setting should be resumed.
Operating time should be measured by injecting 2 times the set current into the
relay.
This test checks the accuracy of the thermal characteristics and that the relay has
been correctly set. The relay should be fully programmed to the calculated settings,
output relays mapped to the protection scheme being used for this test.
Code-10 and 22 is to be set for required thermal setting. Code-18 to be set as
1111. Code-26 to be set at 06. Code-24 to be set as OFF. Code-46 is to be
selected as 56. Before testing and during consecutive tests at different values,
thermal content is to be cleared.
Thermal characteristic is to be tested for 1.5 times and 3 times the setting.
When the single-phase current is injected, it gets split into one-third magnitude of
positive and negative sequence current. So to inject a thermal equivalent current,
the single phase current required is 3XIeq/ sqrt 7
Keep the other protection settings high so that it should not disturb the protection
under test.
Hot running condition of motor is envisaged when service code-56 shows 100. Hot
operating characteristic is verified by calculating the time the relay takes to trip from
100% thermal content.
Current is injected higher than the thermal setting and thermal content is allowed to
build up above 100%. Current is switched off without reducing the level. Current
injection is restarted the moment thermal content reaches 100% and the time is
calculated from this moment to tripping moment.
The relationship between single phase current and Negative Phase sequence
current is Negative Phase seq. current= 1/3 ( I injected current)
Set the relay for recommended unbalance current (code-13). Set withstands time
(code-31) setting to 0.1 second. Also set NPS characteristic (code-30) as 1111 i.e.
definite time. Keep the other protection settings high so that it should not disturb the
protection under test.
Inject single-phase current into each of the phase, in turn. Slowly increase the
current until the trip LED glows. Check the output relay contact on which this
protection is configured. Record the pick-up current. Reduce the current until the
trip contact drops off. Record the drop off level.
Operating time should be measured by injecting at least 1.3 times the set current
into the relay.
Now set NPS characteristic (code-30) as 2222 i.e. inverse time. Inject the multiple
of NPS setting and measure the operating time.
D. Stalling Protection
Set the relay for recommended stalling current (code-12). Set stall withstand time
(code-28) setting to 1 second. Also set starting time (code-29) to 1 sec. Keep the
other protection settings high so that it should not disturb the protection under test.
Inject single-phase current into each of the phase, in turn. Slowly increase the
current until the trip LED glows. Check the output relay contact on which this
protection is configured. Record the pick-up current. Reduce the current until the
trip contact drops off. Record the drop off level.
Original time setting should be resumed.
Operating time should be measured by injecting at least 1.3 times the set current
into the relay.
Ensure that code-6 is set for 1111. Set the relay for recommended starting current
(code-16). Set starting time (code-29) 1 second. Set stall withstand time (code-28)
more than 1 sec. Keep the other protection settings high so that it should not
disturb the protection under test.
Inject single-phase current into each of the phase, in turn. Slowly increase the
current until the trip LED glows. Check the output relay contact on which this
protection is configured. Record the pick-up current. Reduce the current until the
trip contact drops off. Record the drop off level.
Original time setting should be resumed.
Operating time should be measured by injecting at least 1.3 times the set current
into the relay.
Successful start is considered when current is injected higher than starting current
setting and reduced gradually below 80% of the setting before the set time delay.
Without switching off, if the current is increased more than set starting current, for
the time more than starting time, relay should not operate.