Implementing Agency
Noted By:
3.0 Annexes
Annex “A” Project Bar Chart & S-Curve page 7-8
Extension of Time
: 0 Calendar Days
Revised Contract
Completion Date
PROJECT UPDATE
The following contract requirements are all submitted at BCDA Field Office located at
Capas, Tarlac:
- Construction Schedule and S-Curve;
- Manpower Schedule;
- Construction Schedule;
- Equipment Utilization Schedule;
- Construction Safety and Health, Sanitation and Security Program;
- PERT/CPM;
- Contractor’s All-Risk Insurance;
- Personal Accident Insurance; and
- Shop drawings
Pre-Construction Activity:
- Joint as stake survey.
- Establishment of centerline.
- Establishment of RROW limit.
- Establishment of drainage structures.
- Application of tree cutting permit.
- Joint Tree Inventory with CENRO.
General:
- Construction of Field Office
- Facilities for the engineer were provided.
Sub Base and The activity for this this period is as follows:
Surface Preparation
N/A
Drainage and Slope The activity for this this period is as follows:
Protection
N/A
Street Light and The activity for this this period is as follows:
Miscellaneous
Structures N/A
N/A
Most of the documentary requirements for the project like as-stake plans
schedules and other pertinent documents are already transmitted at BCDA
Site Office located at Capas, Tarlac.
As of April 07, 2021, the project is at 1.7790% versus the scheduled percent
accomplishment of 1.2310% which makes it advance by 0.5480%. Most of the
activities were for the facilities of engineers and other pre-construction activity
such as above-mentioned activity.
APRIL 2021
05-Apr-21 10-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21
ITEM NO. DESCRIPTION QTY UNIT % WT
01-Apr-21 06-Apr-21 11-Apr-21 16-Apr-21 21-Apr-21 26-Apr-21
85 90 95 100 105 110
A FACILITIES FOR THE ENGINEER 1.02%
Construction of Field Office for the Engineer (Minimum of 180 sq. m floor
1.00 l.s. 0.27% 0.02% 0.02%
area)
Provision of Living Quarters for the Engineer (2 units – Rental Basis) 30.00 mo. 0.06% 0.001% 0.001% 0.001% 0.001% 0.001% 0.001%
Provision of Furniture / Fixtures, Equipment, and Appliances for the Field
1.00 l.s. 0.07% 0.34% 0.034%
Office of the Engineer
Provision of Furniture / Fixtures, Equipment, and Appliances for the Living
1.00 l.s. 0.03% 0.013% 0.013%
Quarters of the Engineer
Operations and Maintenance of Field Office for the Engineer 15.00 mo. 0.15% 0.002% 0.002% 0.002% 0.002% 0.002% 0.002%
Operations and Maintenance of Living Quarters for the Engineer 15.00 mo. 0.076% 0.001% 0.001% 0.001% 0.001% 0.001% 0.001%
Provision of 2 units - 4x4 Pick-up Type Service Vehicle for the Engineer on
30.00 mo. 0.21% 0.002% 0.002% 0.002% 0.002% 0.002% 0.002%
Bare Rental Basis
Operations and Maintenance of 2 units – 4x4 Pick-up Type Service for
30.00 mo. 0.11% 0.001% 0.001% 0.001% 0.001% 0.001% 0.001%
the Engineer
Provision of Progress Photographs 15.00 mo. 0.02% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
Provision of Communication Facility for the Engineer 6.00 ea. 0.03% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
C EARTHWORKS 10.52%
Clearing and Grubbing 14.01 ha. 0.73% 0.060% 0.060% 0.060% 0.060% 0.060% 0.060%
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 15 | 102
M a r c h 2 0 2 1
Annex “E1”
Mobilized Equipment and
Tools Schedule
-O (OPERATIONAL)
- I (IDLE)
- B (BREAKDOWN)
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 19 | 102
M a r c h 2 0 2 1
Annex “E3”
List of Delivered Materials
2021.03.19 08:07
2021.03.19 09:51
2021.03.19 09:51
2021.03.19 09:51
2021.03.26 09:18
TRIAL MIX
RSB TESTING