Republic of the Philippines

Office of the President


Bases Conversion and Development Authority
New Clark City Connecting Road Package 1

Implementing Agency

Progress Accomplishment Report


AS OF 07 APRIL 2021

CMS Consultant Contractor

Prepared by: Checked and Reviewed by:

Engr. Manolito Mañalac Engr. Edmundo Onias


Project Manager Team Leader / Project Manager
Positive Builders and Trading Urban Integrated Consultants Inc.

Noted By:

Engr. Ryan Pineda


Project Manager
BCDA
TABLE OF CONTENTS
1.0 Executive Summary page 3-4

2.0 Construction Progress Report page 5


2.1 Progress Status page 5
2.2 Construction Activity and Quantity of
Accomplished Work this Period page 5
2.3 Weather Chart page 5
2.4 Projected Work Activities page 5
2.5 Contractor’s Resources page 5
2.6 Materials Testing and Quality Control Activities page 5
2.7 Site Instructions page 6
2.8 Correspondence page 6
2.9 Minutes of the Meeting page 6
2.10 Progress Photographs page 6

3.0 Annexes
Annex “A” Project Bar Chart & S-Curve page 7-8

Annex “B” Statement of Work Accomplishment page 9-11

Annex “C” Monthly Weather Chart page 12-13

Annex “D” Projected Work Schedule page 14-15

Annex “E1” Mobilized Equipment and Tools Schedule page 16-17


Annex “E2” Utilized Manpower Schedule page 18-19
Annex “E3” List of Delivered Materials page 20-21

Annex “F” Submitted Materials Testing Reports page 22

Annex “G1” Site Instruction from BCDA page 23-26


Annex “G2” Site Instruction from CMS Consultant page 27

Annex “H1” Contractor Correspondence page 28


Annex “H2” CMS Consultant Correspondence page 29-39
Annex “H3” BCDA Correspondence page 40

Annex “I” Minutes of the Meeting page 41-61

Annex “J” Progress Photographs page 62-102

Progress Accomplishment Report P a g e 2 | 102


March 2021
1.0 Executive Summary

CONSTRUCTION OF NCC CONNECTING ROAD PACKAGE 1

PROJECT DATA CONTRACT STATUS

Source of Funds : General Appropriations Act Scheduled


Accomplishment to : 1.2310%
Implementing : Bases Conversion and Date
Agency Development Authority
Actual Accomplishment : 1.7790%
Project Manager : Engr. Ryan Pineda to Date

CMS Consultant : UICI Scheduled


Accomplishment for the : 0.9510%
Project Manager : Engr. Edmundo Onias Period

Contractor : Positive Builders and Trading Actual Accomplishment : 1.3990%


for the Period
Project Manager : Engr. Manolito Mañalac
Advance / (Slippage) to : (+) 0.4480%
Contract Amount : Php 965,807,314.26 Date

Contract Contract Elapsed Time : 87 Days


Duration : 450 Calendar Day
Percent Elapsed Time : 19.33%
Project Start Date : 11 January 2021
Accomplished Amount : Php 17,180,408.89
Suspension of
Time : 0 Calendar Days

Extension of Time
: 0 Calendar Days
Revised Contract
Completion Date

Date Completed : On Progress

PROJECT UPDATE

Majority of the Contractor’s Activity are as follows:

The following contract requirements are all submitted at BCDA Field Office located at
Capas, Tarlac:
- Construction Schedule and S-Curve;
- Manpower Schedule;
- Construction Schedule;
- Equipment Utilization Schedule;
- Construction Safety and Health, Sanitation and Security Program;
- PERT/CPM;
- Contractor’s All-Risk Insurance;
- Personal Accident Insurance; and
- Shop drawings

Progress Accomplishment Report P a g e 3 | 102


March 2021
PROJECT MILESTONE

Pre-Construction Activity:
- Joint as stake survey.
- Establishment of centerline.
- Establishment of RROW limit.
- Establishment of drainage structures.
- Application of tree cutting permit.
- Joint Tree Inventory with CENRO.

General:
- Construction of Field Office
- Facilities for the engineer were provided.

Earthworks The activities for this period are as follows:


1. Clearing and grubbing at Sta. 2+000 – 2+580
1.067% out of 10.518% of Road 1A.
“10.14% completed” 2. Clearing and grubbing at Sta. 0+000 – 0+520
of Road 2A.
3. Individual removal of trees of Road 1A and 2A
were 95% completed.
4. Roadway surplus common excavation at
Sta. 0+080 – Sta. 0+220 of Road 2A.

Sub Base and The activity for this this period is as follows:
Surface Preparation
N/A

Construction The activity for this this period is as follows:


of Bridge
N/A

Drainage and Slope The activity for this this period is as follows:
Protection
N/A

Street Light and The activity for this this period is as follows:
Miscellaneous
Structures N/A

Street Landscape The activity for this this period is as follows:

N/A

Progress Accomplishment Report P a g e 4 | 102


March 2021
2.0 CONSTRUCTION PROGRESS REPORT

2.1 Progress Status

Most of the documentary requirements for the project like as-stake plans
schedules and other pertinent documents are already transmitted at BCDA
Site Office located at Capas, Tarlac.

As of April 07, 2021, the project is at 1.7790% versus the scheduled percent
accomplishment of 1.2310% which makes it advance by 0.5480%. Most of the
activities were for the facilities of engineers and other pre-construction activity
such as above-mentioned activity.

Parallel with the above-mentioned activities, continuous materials testing and


site inspections are conducted before the start of each activity to ensure the
quality and/or suitability of materials used.

2.2 Construction Activity and Quantity of Work Accomplished this Period

Refer to Annex ”B”

2.3 Weather Chart

Refer to Annex “C” for the chart

2.4 Projected Activities for the Next Month

Refer to Annex “D”

2.5 Contractor’s Resources

Refer to Annex “E1”, “E2”, and “E3”

2.6 Materials Testing and Quality Control Activities

Refer to Annex “F” for the chart for the submitted


Materials Testing Reports

Progress Accomplishment Report P a g e 5 | 102


March 2021
2.7 Site Instructions

Refer to Annex “G1” and “G2”

2.8 Project Correspondence by BCDA PMO

Refer to Annex “H1”, “H2”, and “H3”

2.9 Minutes of Meeting

Refer to Annex “I”

2.10 Progress Photographs

Refer to Annex “J”

Progress Accomplishment Report P a g e 6 | 102


March 2021
Annex “A”
Project Bar Chart & S-Curve

Progress Accomplishment Report P a g e 7 | 102


March 2021
Progress Accomplishment Report P a g e 8 | 102
March 20 21
Annex “B”
Statement of Work Accomplishment

Progress Accomplishment Report P a g e 9 | 102


March 2021
Progress Accomplishment Report P a g e 10 | 102
March 20 21
Progress Accomplishment Report P a g e 11 | 102
March 20 21
Annex “C”
Monthly Weather Chart

Progress Accomplishment Report P a g e 12 | 102


March 2021
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 13 | 102
M a r c h 2 0 2 1
Annex “D”
Projected Work Schedule

Progress Accomplishment Report P a g e 14 | 102


March 2021
Contractor: POSITIVE BUILDERS AND TRADING
Project: CONSTRUCTION OF NEW CLARK CITY CONNECTING ROAD PACKAGE 1
Location: NEW CLARK CITY, CAPAS, TARLAC
Subject: PROJECTED WORK SCHEDULE
Duration: 450 C.D.

APRIL 2021
05-Apr-21 10-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21
ITEM NO. DESCRIPTION QTY UNIT % WT
01-Apr-21 06-Apr-21 11-Apr-21 16-Apr-21 21-Apr-21 26-Apr-21
85 90 95 100 105 110
A FACILITIES FOR THE ENGINEER 1.02%
Construction of Field Office for the Engineer (Minimum of 180 sq. m floor
1.00 l.s. 0.27% 0.02% 0.02%
area)
Provision of Living Quarters for the Engineer (2 units – Rental Basis) 30.00 mo. 0.06% 0.001% 0.001% 0.001% 0.001% 0.001% 0.001%
Provision of Furniture / Fixtures, Equipment, and Appliances for the Field
1.00 l.s. 0.07% 0.34% 0.034%
Office of the Engineer
Provision of Furniture / Fixtures, Equipment, and Appliances for the Living
1.00 l.s. 0.03% 0.013% 0.013%
Quarters of the Engineer
Operations and Maintenance of Field Office for the Engineer 15.00 mo. 0.15% 0.002% 0.002% 0.002% 0.002% 0.002% 0.002%
Operations and Maintenance of Living Quarters for the Engineer 15.00 mo. 0.076% 0.001% 0.001% 0.001% 0.001% 0.001% 0.001%
Provision of 2 units - 4x4 Pick-up Type Service Vehicle for the Engineer on
30.00 mo. 0.21% 0.002% 0.002% 0.002% 0.002% 0.002% 0.002%
Bare Rental Basis
Operations and Maintenance of 2 units – 4x4 Pick-up Type Service for
30.00 mo. 0.11% 0.001% 0.001% 0.001% 0.001% 0.001% 0.001%
the Engineer
Provision of Progress Photographs 15.00 mo. 0.02% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
Provision of Communication Facility for the Engineer 6.00 ea. 0.03% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%

B OTHER GENERAL REQUIREMENT 0.70%


Medical Room and First Aid Facilities 1.00 l.s 0.10%
Construction Survey and Staking 5.00 km. 0.02% 0.001% 0.001% 0.001% 0.001% 0.001% 0.001%
Permanent Monuments and Markers 25.00 ea. 0.04% 0.010% 0.010% 0.010% 0.010%
Construction Occupational Safety and Health Program 15.00 mo. 0.07% 0.001% 0.001% 0.001% 0.001% 0.001% 0.001%
Mobilization / Demobilization 1.00 l.s. 0.37% 0.004% 0.004% 0.004% 0.004% 0.004% 0.004%

C EARTHWORKS 10.52%
Clearing and Grubbing 14.01 ha. 0.73% 0.060% 0.060% 0.060% 0.060% 0.060% 0.060%

P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 15 | 102
M a r c h 2 0 2 1
Annex “E1”
Mobilized Equipment and
Tools Schedule

Progress Accomplishment Report P a g e 16 | 102


March 2021
Contractor: POSITIVEBUILDERSANDTRADING
Project: CONSTRUCTIONOFNEWCLARKCITYCONNECTINGROADPACKAGE1
Location: NEWCLARKCITY,CAPAS, TARLAC
Subject: TOOLSANDEQUIPMENTSCHEDULE
Date: MARCH2021

MARCH 2021 APRIL 2021


NO. PARTICULARS 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6
O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B O I B
1 Total Station 3 - - 3 - - 3 - - - 3 - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - - 3 - -
2 Real-Time Kinematic 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
3 Auto Level 2 - - 2 - - 2 - - - 2 - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - -
4 One Bagger Mixer 2 - - 2 - - 2 - - - 2 - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - -
5 Cut-Off Machine 2 - - 2 - - 2 - - - 2 - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - -
6 Bar Cutter 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
7 Grinder 2 - - 2 - - 2 - - - 2 - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - -
8 Electric Drill 5 - - 5 - - 5 - - - 5 - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 5 - - 4 - - 4 - - 5 - - 4 - - 4 - -
9 Welding Machine 4 - - 4 - - 4 - - - 4 - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - - 4 - -
10 Oxygen Tank 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
11 Acetylene Tank 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
12 Circular Saw 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
13 Chain Saw 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
14 Concrete V ibrator 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
15 Backhoe 12 - - 12 - - 12 - - - 12 - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - - 12 - -
16 Loader Truck 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
17 Bulldozer 2 - - 2 - - 2 - - - 2 - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - -
18 V ibratory Roller 2 - - 2 - - 2 - - - 2 - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - - 2 - -
19 Motor Grader 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -
20 Service V ehicle 1 - - 1 - - 1 - - - 1 - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - - 1 - -

-O (OPERATIONAL)
- I (IDLE)
- B (BREAKDOWN)

Progress Accomplishment Report P a g e 17 | 102


March 20 21
Annex “E2”
Utilized Manpower Schedule

Progress Accomplishment Report P a g e 18 | 102


March 2021
Contractor: POSITIVE BUILDERS AND TRADING
Project: CONSTRUCTION OF NEW CLARK CITY CONNECTING ROAD PACKAGE 1
Location: NEW CLARK CITY, CAPAS, TARLAC
Subject: MANPOWER SCHEDULE
Date: MARCH 2021

MARCH 2021 APRIL 2021


NO DESCRIPTION
04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06
01 Project Manager 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
02 Project-in-Charge 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
03 Project Engineer 2 2 2 - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 - - - - 2 2
04 QS Head 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
05 Quantity Surveyor 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
06 Architect 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
07 Geodetic Engineer 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
08 AutoCAD Operator 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
09 Instrument Man 3 3 3 - 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 - - - - 3 3
10 Survey Aide 6 6 6 - 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 - - - - 6 6
11 Safety Practitioner 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
12 Safety Officer 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
13 Admin Officer 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
14 Foreman 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
15 Carpenter 6 6 6 - 6 6 6 6 6 6 1 6 6 6 6 6 6 2 6 6 6 6 6 6 6 6 6 6 - - - - 6 6
16 Mason 8 8 8 - 8 8 8 8 8 8 2 8 8 8 8 8 8 2 8 8 8 8 8 8 8 8 8 8 - - - - 8 8
17 Steelman 2 2 2 - 2 2 2 2 2 2 1 2 2 2 2 2 2 4 2 2 2 2 2 2 2 2 2 2 - - - - 2 2
18 Welder 5 5 5 - 5 5 5 5 5 5 1 5 5 5 5 5 5 4 5 5 5 5 5 5 5 5 5 5 - - - - 5 5
19 Painter 1 1 1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 1 - - - - 1 1
20 Electrician 3 3 3 - 3 3 3 3 3 3 1 3 3 3 3 3 3 2 3 3 3 3 3 3 3 3 3 3 - - - - 3 3
21 Helper 9 8 8 - 8 8 9 9 9 9 2 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 - - - - 9 9
22 Equipment Operator 10 10 10 - 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 - - - - 2 2
23 Spotter - - - - - - - - - - - - - - - - - - - - - - 1 1 1 1 1 1 - - - - 4 4
24 Driver - - - - - - - - - - - - - - - - - - - - - - 4 4 4 4 4 4 - - - - 1 1

P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 19 | 102
M a r c h 2 0 2 1
Annex “E3”
List of Delivered Materials

Progress Accomplishment Report P a g e 20 | 102


March 2021
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 21 | 1 0 2
M a r c h 2 0 2 1
Annex “F”
Submitted Materials Testing Reports
(Quality Control & Testing Program)

Progress Accomplishment Report P a g e 22 | 102


March 2021
Annex “G1”
Site Instruction from BCDA

Progress Accomplishment Report P a g e 23 | 102


March 2021
Progress Accomplishment Report P a g e 24 | 102
March 2021
Progress Accomplishment Report P a g e 25 | 102
March 2021
Progress Accomplishment Report P a g e 26 | 102
March 2021
Annex “G2”
Site Instruction from CMS Consultant

Progress Accomplishment Report P a g e 27 | 102


March 2021
Annex “H1”
Contractor Correspondence

Progress Accomplishment Report P a g e 28 | 102


March 2021
Annex “H2”
CMS Consultant Correspondence

Progress Accomplishment Report P a g e 29 | 102


March 2021
Progress Accomplishment Report P a g e 30 | 102
March 2021
Progress Accomplishment Report P a g e 31 | 102
March 2021
Progress Accomplishment Report P a g e 32 | 102
March 2021
Progress Accomplishment Report P a g e 33 | 102
March 2021
Progress Accomplishment Report P a g e 34 | 102
March 2021
Progress Accomplishment Report P a g e 35 | 102
March 2021
Progress Accomplishment Report P a g e 36 | 102
March 2021
Progress Accomplishment Report P a g e 37 | 102
March 2021
Progress Accomplishment Report P a g e 38 | 102
March 2021
Progress Accomplishment Report P a g e 39 | 102
March 2021
Annex “H3”
BCDA Correspondence

Progress Accomplishment Report P a g e 40 | 102


March 2021
Annex “I”
Minutes of the Meeting

Progress Accomplishment Report P a g e 41 | 102


March 2021
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 42 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 43 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 44 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 45 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 46 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 47 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 48 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 49 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 50 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 51 | 1 0 2
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 52 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 53 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 54 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 55 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 56 | 10 2
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 57 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 58 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 59 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 60 | 102
M a r c h 2 0 2 1
P r o g r e s s A c c o m p l i s h m e n t R e p o r t P a g e 61 | 1 0 2
M a r c h 2 0 2 1
Annex “J”
Progress Photograph

Progress Accomplishment Report P a g e 62 | 102


March 2021
CONSTRUCTION OF BCDA SITE OFFICE

CONSTRUCTION OF BCDA SITE OFFICE

Progress Accomplishment Report P a g e 63 | 102


March 2021
CONSTRUCTION OF BCDA SITE OFFICE

CONSTRUCTION OF BCDA SITE OFFICE

Progress Accomplishment Report P a g e 64 | 102


March 2021
CONSTRUCTION OF STAFF HOUSE / QUARTERS

CONSTRUCTION OF STAFF HOUSE / QUARTERS

Progress Accomplishment Report P a g e 65 | 102


March 2021
PUBLIC ADVISORY FOR TREE CUTTING

COLLECTING OF SOIL SAMPLE

Progress Accomplishment Report P a g e 66 | 102


March 2021
REFLECTED KEYPLAN FOR CLEARING AND GRUBBING

Progress Accomplishment Report P a g e 67 | 102


March 2021
COLLECTING OF SOIL SAMPLE

COLLECTING OF SOIL SAMPLE

Progress Accomplishment Report P a g e 68 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 69 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 70 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 71 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 72 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 73 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 74 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 75 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 76 | 102


March 2021
CLEARING AND GRUBBING ACTIVITIES

CLEARING AND GRUBBING ACTIVITIES

Progress Accomplishment Report P a g e 77 | 102


March 2021
REFLECTED KEYPLAN FOR TREE CUTTING

Progress Accomplishment Report P a g e 78 | 102


March 2021
2021.03.26 14:47 2021.03.26 14:47

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 79 | 102


March 2021
2021.03.26 14:47 2021.03.26 14:47

2021.03.26 14:47 2021.03.26 14:47

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 80 | 102


March 2021
2021.03.26 14:47 2021.03.26 14:47

2021.03.26 14:47 2021.03.26 14:47

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 81 | 102


March 2021
TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 82 | 102


March 2021
TREE CUTTING ACTIVITIES

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 83 | 102


March 2021
TREE CUTTING ACTIVITIES

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 84 | 102


March 2021
Mar 30, 2021 1:38:48 PM

TREE CUTTING ACTIVITIES

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 85 | 102


March 2021
TREE CUTTING ACTIVITIES

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 86 | 102


March 2021
TREE CUTTING ACTIVITIES

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 87 | 102


March 2021
TREE CUTTING ACTIVITIES

2021.03.19 08:07

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 88 | 102


March 2021
2021.03.19 09:51

TREE CUTTING ACTIVITIES

2021.03.19 09:51

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 89 | 102


March 2021
2021.03.19 09:51

TREE CUTTING ACTIVITIES

2021.03.19 09:51

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 90 | 102


March 2021
2021.03.19 09:51

TREE CUTTING ACTIVITIES

2021.03.19 09:51

TREE CUTTING ACTIVITIES

Progress Accomplishment Report P a g e 91 | 102


March 2021
SOIL PENETRATION TESTING

STANDADRD PENETRATION TESTING

Progress Accomplishment Report P a g e 92 | 102


March 2021
Mar 25, 2021 10:35:16 AM

STANDADRD PENETRATION TESTING

Mar 25, 2021 10:35:16 AM

STANDADRD PENETRATION TESTING

Progress Accomplishment Report P a g e 93 | 102


March 2021
STANDADRD PENETRATION TESTING

STANDADRD PENETRATION TESTING

Progress Accomplishment Report P a g e 94 | 102


March 2021
STANDADRD PENETRATION TESTING

Mar 29, 2021 11:05:32 AM

STANDADRD PENETRATION TESTING

Progress Accomplishment Report P a g e 95 | 102


March 2021
REFLECTED KEYPLAN FOR CUT AREAS

Progress Accomplishment Report P a g e 96 | 102


March 2021
2021.03.26 09:18

CUT AND FILL ACTIVITIES

2021.03.26 09:18

CUT AND FILL ACTIVITIES

Progress Accomplishment Report P a g e 97 | 102


March 2021
CUT AND FILL ACTIVITIES

CUT AND FILL ACTIVITIES

Progress Accomplishment Report P a g e 98 | 102


March 2021
CUT AND FILL ACTIVITIES

CUT AND FILL ACTIVITIES

Progress Accomplishment Report P a g e 99 | 102


March 2021
SLUMP TEST FOR TRIAL MIX

TRIAL MIX

Progress Accomplishment Report P a g e 100 | 102


March 2021
COMPRESSIVE AND FLEXURAL TESTS

RSB TESTING

Progress Accomplishment Report P a g e 101 | 102


March 2021
COMPRESSIVE AND FLEXURAL TESTS

COMPRESSIVE AND FLEXURAL TESTS

Progress Accomplishment Report P a g e 102 | 102


March 2021