You are on page 1of 11

Project Location

› MPO is in BGEN office in Southampton


› 8 desk assigned plus meeting room:
o 2 car parking spaces
› FT Exxon Project Engineer, Chris Bird assigned
› Additional:
o Mandatory Project and Office Induction
o KOM on 6/7th September
› Site Visits permits via XOM, standard PEP and
notification required.
Project Status
› Engineering
o Complete. However, Value Engineering expected in Phase 2

› Procurement
o Major equipment purchased. Large portion currently stored in
various global locations
o Bulks are approx. 60% delivered

› Modules
o Equipment and bulks procured, but not fabricated
o Modules fabrication an Optional Scope item

› Construction
o Some enabling works complete. Full bathtub excavation of
Block 36B
o Partial construction of temp. construction village and welfare
area
Substation
Substation - Structure
Substation - Foundation
Check 2.2mx2.2m 1.8mx1.8m 1.5mx1.5m

Bearing Pressure SLS Ratio: 0.43 Ratio: 0.60 Ratio: 0.85


Sliding SLS FoS: 10.06 FoS: 7.67 FoS: 6.2
Overturning Z SLS FoS: 92.5 FoS: 57.73 FoS: 38.86
Overturning X SLS FoS: 5.76 FoS: 3.6 FoS: 2.42
Sliding ULS FoS: 6.6 FoS: 4.99 FoS: 3.99
Overturning Z ULS FoS: 57.31 FoS: 35.42 FoS: 23.6
Overturning X ULS FoS: 3.79 FoS: 2.34 FoS: 1.56
Bearing Pressure 1 Ratio: 0.19 Ratio: 0.25 Ratio: 0.33
Bearing Pressure 2 Ratio: 0.29 Ratio: 0.39 Ratio: 0.52
Reinforcement 1005 mm/m2 (Min547) 1005 mm/m2 (Min547) 1005 mm/m2 (Min547)
Punching Shear Ratio: 0.18 Ratio: 0.44 Ratio: 0.32
Competitors

› Bid list:

› Altrad / Costain / Bilfinger / Bailey Alliance were selected by Exxon to compete in Phase 1.
Project Timeline

Note : Mid October interim review is a critical gate.


Client
› ExxonMobil
o IOC HQ out of Houston
o FAST Project Team
› ExxonMobil – main contacts:
o Chris Bailey: FAST Project – Procurement & Contracts Manager (UK)
• chris.m.bailey@exxonmobil.com
o Yuri Cordy: FAST Project – Project Manager
• yuri.cordy@exxonmobil.com
o Graham Lewis: FAST Project Lead
• graham.l.lewis@exxonmobil.com
o Chris Bird: FAST Project Engineer (Embedded)
• chris.m.bird@exxonmobil.com
Alliance Partners – Division of Responsibilities
› Alliance will be formed of four equal partners
o ExxonMobil – to be embedded in the Alliance Team..
o Kent plc
o Project Management
o Engineering & Procurement
o Completions and Commissioning
o Modules
o BGEN
o Construction Management
o Structural, Piping and Mechanical
o Electrical & Instrumentation
o Taylor Woodrow
o Construction Management
o Earthworks and Civils.
Project Management
Project Execution Strategy
› Key Personnel – Exxon Representative Chris Bird
Schedule

You might also like