o Major equipment purchased. Large portion currently stored in
various global locations
o Bulks are approx. 60% delivered
› Modules
o Equipment and bulks procured, but not fabricated
o Modules fabrication an Optional Scope item
› Construction
o Some enabling works complete. Full bathtub excavation of
Block 36B
o Partial construction of temp. construction village and welfare
area
Substation
Substation - Structure
Substation - Foundation
Check 2.2mx2.2m 1.8mx1.8m 1.5mx1.5m
› Bid list:
› Altrad / Costain / Bilfinger / Bailey Alliance were selected by Exxon to compete in Phase 1.
Project Timeline