Professional Documents
Culture Documents
CORROSION MATTERS
6-3-899/2, 2ND FLOOR , SWATHI PLAZA
RAJBHAVAN ROAD, SOMAJIGAUDA, HYDERABAD – 500082
EMAIL: kbswaroop@corrmatt.com
WEBSITE : www.corrmatt.com
Page 1 of 48
CORROSION MATTERS
COMPANY OVERVIEW
Corrosion Matters , this company has been founded by Corrosion and Electrochemical
Engineers in 2005 to cater to projects, related to corrosion prevention systems
For prevention of corrosion , our team of engineers , are having hands on experience in
handling time bound and critical projects of importance.
The company is actively engaged in Cathodic Protection related comprehensive design
and project management services for projects that are typically , cross country pipelines,
complex plant Underground piping, Onshore and Offshore facilities , City Gas and Water
mains, above ground storage tanks , concrete steel structures etc.
The company has been chosen to foresee and supervise construction projects and key
assets of National and International Importance in Oil and Gas sectors.
The Objective of the company is to provide services to the industry to the minute detail
and innovate user friendly methods of Cathodic Protection Applications which shall help
the industries world over in a long way.
REGARDS,
CORROSION MATTERS
Page 2 of 48
CORROSION MATTERS
CATHODIC PROTECTION SYSTEM FOR U/G PIPING ( CROSS-COUNTRY)
1. SCOPE OF WORK :
The scope of work covers the Design, Engineering, Supply of Materials, Installation, Testing &
Commissioning of Permanent cathodic protection system for external surface of under ground
pipeline including post commissioning surveys such as Coating Conductance Measurements ,CIPL
survey, Pearson detection followed by DCVG [for defect classification] at defect locations evinced.
Also getting specific approval for major activities like
Page 3 of 48
CORROSION MATTERS
Soil resistivity survey should be carried out at at minimum two plots for each proposed CP station
as option for selecting best location for construction. Soil resistivity will be carried out at different
depth and at all anode bed locations.
The locations of anode ground bed plot will be selected based on the land availability to avoid
problems during construction & keeping maintenance in view. However from the resistance
calculations it can be decided type of anode bed.
Land selection for anode ground bed has been taken base on following broad guidelines, however
final decision to be taken at site based on land availability.
1. site for shallow ground bed should have minimum 100 mtr perpendicular distance from
the pipeline.
3. Accessibility of location and route for laying of anode header cable shall be checked and
marked on plot plan drawing.
4. Anode bed shall not be situated below HT line and near electrical earthing.
5. Lowest resistivity location shall be considered over options available, for better anode
ground bed resistance option.
Page 4 of 48
CORROSION MATTERS
The intent of this section is to propose design data and criteria for the Permanent Cathodic Protection
System.
In accordance with the project specification, the Cathodic Protection system will be designed to have a
desired design life in years.
For Example :
The Pipeline external surface is coated with 3 Layer Polyethylene (3LPE) coating and the current density
considered for the design is as follows:
ii) For Polyethylene coated Pipeline (Salt pan Area) : 125 µA/m2
A safety margin of 1.3 i.e. 30% has been provided for the current calculations over and above the
specified protective current density.
The Cathodic protection systems shall be a MMO Lida anodes systems and shall be designed for Deepwell
and Horizontal type anode bed.
BS7361-Cathodic Protection-Part 1 Cathodic Protection –code of Practice for Land and Marine
Applications
CP_MANUAL.doc Page 5 of 48
CORROSION MATTERS
1. The pipe to Soil Potential measurements shall be in between (-) 0. 95V “Off ” and (-) 1.1.7V “Off ”
as measured between the pipe surface and a copper – copper sulphate reference electrode.
2. In rare circumstances a minimum polarization shift of (-) 100mV shall indicate adequate levels of
cathodic protection for the pipeline with the written permission from owner.
3. A positive potential swing of >20mV shall be considered as the criteria for presence of an
interaction situation requiring investigation and incorporation of mitigation measures.
CP_MANUAL.doc Page 6 of 48
CORROSION MATTERS
In line with the project specifications and design calculations, location and No. of CP Station shall be
proposed as under:-
1 (SV#1) CP#1
2 (SV#2) CP#2
3 (SV#3) CP#3
4 (SV#5) CP#4
The following Calculation shall be used for design the permanent cathodic protection system
i. Surface Area
Sa = Π x Dx L
Where :
Sa = Surface area of Pipeline m2
D = Diameter of pipeline m
L = length of pipeline m
Where
It = C.P. current requirement (Amp)
Sa = Surface area of Pipeline m2
Id = C.P. protective current density mA/m2
1.3 = Safety Margin
CP_MANUAL.doc Page 7 of 48
CORROSION MATTERS
CP station Area Classification Chainage Dia. Protection span Total Km Surface Protective Current
(Km) (mm) (Km) Area (m2) Current Required
Density (µA) (Amp.)
From TO
CP#1 (SV#
1)
CP#2 (SV#
2)
CP#3 (SV#
3)
CP#4 (SV#
5)
CP_MANUAL.doc Page 8 of 48
CORROSION MATTERS
Current
NA = It /Ia.
Where
NA = Total Anode Weight (Kg.)
Weight
W = It x Ct x L/Uf
Where
W = Total Anode weight (Kg)
Total current Out put current Type of Anode required Anode Number of
requirement as per of individual Anode as per current required as Anode
Location
design (Amps) anode (Amps) (Nos) per Weight proposed
(Nos.) (Nos)
CP#1 (SV#1)
CP#2 (SV#2)
CP#3 (SV#3)
CP#4 (SV#5)
CP_MANUAL.doc Page 9 of 48
CORROSION MATTERS
L DS L L
Where
Ps = Soil Resistivity in Ω - m
Ps = Soil Resistivity in Ω – m
where
Rbs = Individual Anode to backfill resistance in Ω
CP_MANUAL.doc Page 10 of 48
CORROSION MATTERS
Rtbs = Rbs/N
where
N = Number of Anodes
Rgb = Rs + Rtbs
Single core copper conductor Armoured cable of 10 sq.mm is selected as Anode Tail Cable as per tender
specification.
Ri = Li x R10
Where
CP_MANUAL.doc Page 11 of 48
CORROSION MATTERS
Single core copper conductor cable of 35 sq.mm is selected as Anode and Cathode Header cable .
CP_MANUAL.doc Page 12 of 48
CORROSION MATTERS
VE = ρxA/2xπxd
Where
ρ = Resistivity in Ohm- mtr
A = Current in Amps
VE = Voltage at Pipeline
Remote earth voltage shall be less than the Natural PSP i.e. -0.45V
CP_MANUAL.doc Page 13 of 48
CORROSION MATTERS
CP Average Soil Proposed No. of Anodes Installed Type of Size of Anode bed. Total Total Total out put Remote Distance
St’n. Resistivity (Ω
Ω- Anode Anode Bed Ground Total circuit required earth between
Locati mtr Type No current Active Dia / Width Distance bed cable R’tance Voltage Anode bed to
Rating (7) Amps Volts
on (1) (4) (Amps) (6) Depth Length (mm) (10) between R’tance - R’tance (Rtcr) (Volts) Pipeline
Considered (2) (3) (Amps) (mtr) (mtr) (9) Anode (It) (Vt)
(8) (11) Rab (Ω
Ω) (Rtc) (13) (14) (17) proposed
(5) (15) (16)
(12) (mtr) (1.7)
SV-1
SV-2
SV-3
SV-5
Note: If column (17) is less than pipeline Natural PSP , the distance of remoteness is sufficient.
CP_MANUAL.doc Page 14 of 48
CORROSION MATTERS
Ap = Π x t x ( D-t ) in m2
where
D = Diameter of Pipe
T = Thickness of pipe
Rs = ρs x l / A in Ω / km
where
Rl = Rp/Sakin Ω per km
where
Rp = Coating resistance in
Where
where
Lp = α) x Cosh-1(Edp/ Ed)
(1/α
01 Dia (mtr)
02 Thickness (mm)
08 Attenuation constant α
1.6 Sample Design Calculation for CP Station for Span Length from 0 to 28.9 Km
Sa = P x d x l d Dia 0.4534 m
l Length 28900 m
L Life 40 Years
ohm-
PS Soil Resistivity 36 mtr
ohm-
Rbs = 0.159 Pb/L Ln ( 8 L / d)-1 Pb Backfill Resistivity for Calcined Coke 0.5 mtr
1.6.9 Rgb = Rs + Rtbs Rgb Total Ground bed Resistance 0.853 Ohms
Ri = Li x R10
Li Length of Anode cable mtr
R1 & R5 = 8 x 0.001.73 = 0.015ohms
1.6.10
R2 & R6 = 15x0.001.73 = 0.028 ohms
R4 & R8 = 29x0.001.73 = 0.053 ohms R25 Resistance of 10 mm2 cable 0.00115 Ohm/Mtr
Rtotal = Rgb + Rtc Rgb Total Ground bed Resistance 0.853 Ohms
From above electrically remoteness calculations for Anode bed, it can observed that Voltage raise in earth with respect to remote earth at a distance 100 is
less than to pipeline Voltage to earth (ie 0.45V) & Remoteness of anode ground bed can be achieved
1.6.17 ohm/K
Rs Linear Resistance of pipeline 0.01.70 m
0.0000
s Resistivity of steel pipe 0022 ohm-mtr
Rs = s x l / Ap
I unit length of pipe 1000 mtr
1.6.1.7 ohm/K
Rl Coating Leakage Resistance for 3LPE 10.45 m
ohm-
Rl = Rp/Sa
Rp Coating Resistance 15000 mtr2
1435.7
Sa Surface area per Km 1 mtr2
P/s
Edp =P/s max - P/s nat max Least negative PSP at drain point -1.5 V
P/s
nat Natural PSP of pipeline -0.45 V
P/s
Ed =P/s min - P/s nat min Least negative PSP at end point -0.95 V
P/s
nat Natural PSP of pipeline -0.45 V
Purpose :
Test stations/ Junction box shall be provided along the pipeline ROW for monitoring the
performance of the Cathodic Protection system
Materials Required :
Detailed Procedure:
• The location of the test stations/junction box shall be marked on row as per
approved design with their connection scheme and other related information on
alignment sheet.
• The test stations/junction box shall be installed with the front of the test station
facing the pipeline.
• The overall dimensions of foundations shall be 600 mm(W) x 700 mm (H) X 500
mm (D).
• Place reinforcement properly and take TLP bend and place it properly in the
reinforcement.
• Fill annular space with RCC Mix. The mixture shall be constantly rammed for
proper compaction.
• Place the TLP boxes/Junction boxes on the studs of the bend cast in concrete
foundation and tighten the bolts.
• The bolts shall then be distorted by hitting with a heavy hammer to make the
installation vandal/theft proof
Precautions:
• Cable should be neatly dressed inside the trench and to be terminated inside test
station.
Documentation:
Inspection Reports shall be furnished as per the report formats attached below:
PROJECT
OWNER
CONTRACTOR
CP CONTRACTOR
REFERENCE DOCUMENT
PERSONAL RESPONSIBLE
2 CHECK LOCATION P W RM
LEGEND
A - APPROVAL / ACCEPTANCE; R - REVIEW OF RECORD; RM - RANDOM CHECK
OWNER
CONTRACTOR
CP CONTRACTOR
Signature
Date
SCOPE
This procedure covers installation of Deep ground bed as per standard drawing & design document.
MATERIALS REQUIRED
Sr.No Material/Tool Make Application/Purpose
10 Casing Pipe for Deep anode bed Standard Casing Pipe for Deep anode bed
• Start the drilling of borehole with suitable diameter drilling bit and drill a borehole of
suitable depth as per approved document.
• Lower the casing pipe (3mm) one length at a time and coupling various lengths with couplers
one after the other.
• After lowering MS casing pipe, a PVC shrouding pipe equal to the inactive length of the deep well
ground bed shall be lowered along the casing pipe from the top.
• Mark length equal to the required depth on the tail cables of anodes to avoid excessive lowering.
• Tie all MMO anodes with vent pipe and cables to gather, and also install the centralizers for each
anodes and End weight to last anode as per design approval.
• Anodes shall be lowered with suitable nylon rope. Nylon rope shall be binded with end weight.
• Fill the slurry coke breeze inside the bore well up to the active length and rest backfill with metal
gravel, this is to ensure proper filling of entire borehole.
• Backfilling to be done till overflowing from top of the pit, and than allow it to settle, fill the top of
pit as per approved drawing, with metal gravel after settling time of two-three days.
• Clamp / Tie the anode tail cable and lay up to anode junction box
• All the tail cables and Header cable shall be laid and terminated in anode junction box.
• Total depth of excavation in horizontal ground bed shall be as per design document.
• Cross section of bottom of the trench should be as per approved design document, as the same is
only considered for anode bed resistance calculation. The shape of excavated trench from top to
bottom need not be precise. Moreover, it shall depend on nature of soil at the site.
• Pour backRill into the trench and tamp it to a level corresponding to 0.150 m from bottom of
trench. Pour sufficient water on coke breeze and mix with wooden plank to prepare slurry.
• Mark the locations of individual canister anodes alongside the trench as spacing indicated in the
approved design package and place the individual anode horizontally within the trench on the
bed of the backfill prepared.
• Anode tail cables of individual anodes should be coiled and kept on ground adjoining the trench.
• Pour backfill into the trench and tamp it to a level corresponding to design requirement. (Take
care while tamping the coke breeze so that the anode connection or cable is not damaged). Again
pore sufficient water on top of the spread up coke breeze all over the anode so that slurry can be
achieved.
• Lay Tail cable & header cables and bring them up to proposed anode junction box location as per
standard drawing.
• PVC sleeve to be provided on all anode tail cables up to entry of anode junction box, for
mechanical protection.
• At 1.0 m depth all anode tail cable and anode header cable to be laid as per cable laying
procedure.
• Earth restoration work with proper compaction to be carried out at cable laying and anode bed
location.
• Layout of anode installation in anode bed shall be as detailed out in the drawing showing anode
installation.
PRECAUTIONS
• Lower anode carefully to avoid damage to tail cable, Canister anodes should never be handled by
cables, but rope to be used for the same.
• Tail cables and PVC conduits shall be of sufficient length so as to reach Anode Junction Box
without any joint and providing sufficient slack for future maintenance purpose.
• Each shallow anode bed shall contain anodes with canisters positioned in the soil with suitable
backfill at appropriate depth with due regards to type of configuration.
• Keep tail cable lengths sufficient so as to reach anode junction box without any joint and
providing sufficient slack for future maintenance purpose
PROJECT
OWNER
CONTRACTOR
CP CONTRACTOR
2 CHECK LOCATION P
W A
3 CHECK DEPTH P
W R
4 CHECK CASING PIPE LOWERING P
W R
5 CHECK ANODE LOWERING P W RM
LEGEND
A - APPROVAL / ACCEPTANCE; R - REVIEW OF RECORD; RM - RANDOM CHECK
PROJECT
OWNER
CONTRACTOR
CP CONTRACTOR
REFERENCE DOC.
LOCATION
ANODE RATING
Signature
Date
Scope
This procedure covers Thermit Weld for cable connection to pipeline for all type of cables related to
Cathodic Protection System.
Cable to Pipe connection during construction shall be done by Thermit welding method.
Materials Required
Procedure
• Excavate (wherever pipeline backfilled with soil) a pit over the pipeline to expose the pipeline
top surface at location of Thermit weld where cable to pipe connection is to be carry out as per
design document. Care should be taken not to damage the coating of buried pipeline. Only
manual excavation shall be carried out over pipeline.
• Mark where connection is to be carried out. If there are more than one connection as per design
document, consecutive marking shall be minimum 300 mm apart. Connection location shall be
minimum 300mm apart from other connection and Welding joint, Seam or Circumferential Weld
Joint of the pipeline. The location for cable to pipe connection shall be selected such that the pipe
joints and field-coated areas are avoided.
• Cut open the coating on the pipeline with care and without damaging the pipe for a size of
approximately 50 mm x 50 mm (suitable for thermit weld mould).
• Clean the surface of the pipeline to white metal finish using sand paper and cleaning with fine file
as required.
• Depending on the size of cable select the model of cad weld material i.e. CA-15 or CA-32 and
mould.
• Copper sleeve of suitable size shall be double Crimped on the cable (up to 10 sqmm cable).
• Place the mould on the exposed area and pour the cad weld material. Ignite using the gun and
wait for 2 minutes cool down period.The resistance of Cable to pipe at thermite connection point
shall not exceed 0.1Ω
• Test the connection by striking 0.5 Kg hammer directly over the connection. And if connection
fails, the above procedure shall be repeated after waiting time of approx.10min.to cool the
pipeline surface.
• Place a plastic funnel around the exposed area such that about 15mm wide coating remains in
side the plastic funnel. Apply mastic/Mseal around the plastic funnel to prevent leakage of
encapsulation materials.
• Mix proper quantity of epoxy-hardner and keep mixing with wooden rod till it gets heated, Fill up
the conical funnel from the top by pouring mix of Epoxy – Dobofil – 60 and hardener – 758 at
1:10 ratio. 3/4th of the cone to be Rilled with mix and remaining plastic cone to cut after setting of
the hardener.
• Allow the epoxy-hardener to set ensuring every metallic part of joint is completely insulated and
test the insulation level by a holiday detector at 25 KV.
• Cable shall be laid in accordance with approval cable laying drawings. Cable route shall be
carefully measured and cable cut to be required length from test station to pipe. A loop of approx
0.5mtr.of cable shall be kept at both pipe and Test Station end.
Precautions
a. Only Manual excavation to be done without damaging the coating.
c. Location of cable to pipe connection shall be minimum 300mm apart from other connection
and from Pipe weld joint, Seam or Circumferential Weld Joint
f. Maximum 15 grams Ignition powder shall be used for each connection. If one connection
fails, wait of approx 10 min for pipeline cooling and then repeat the procedure for
connection.
Hazard Identification and risk assessment will be carried out and Operational Control measures shall be
adopted for Anode Installation Activities.
PROJECT
OWNER
CONTRACTOR
CP CONTRACTOR
REFERENCE DOC.
1C x 6 SQMM Cable
1C x 10 SQMM Cable
1C x 25 SQMM Cable
Resistance of cable to pipe at thermit connection point Acceptable / Not Accebtable
Hammer Test
Holiday Test OK / NOT OK
1C x 6 SQMM Cable
1C x 10 SQMM Cable
1C x 25 SQMM Cable
Name
Date
Purpose
To describe the procedure for commissioning of Permanent cathodic protection system and provide
adequate quality assurance / control of workmanship and inspection at site.
Scope
This procedure will cover commissioning of the Impressed Current C.P system installed to protect under
ground pipeline from external corrosion.
Equipments
- Soil resistivity meter
- Digital multimeters
- Megger
Commissioning Procedure
• On completion of installation of anode beds and other systems as envisaged in the specification,
they shall be individually checked, tested and compared against the agreed specifications and
procedure.
• The CP commissioning shall be carried out with current interrupter provided in the output of the
CPPSM unit to measure CP “ON” & “OFF” potentials.
• Current dissipated by each anode shall be corrected through anode lead junction box.
• Electrical continuity of the entire pipeline shall be verified in conformity with design.
• Input resistance of the pipeline at all the drainage points shall be checked and recorded.
• Temporary protection facilities provided (if any) which do not form part of permanent CP shall
be disconnected from the sytem & removed unless agreed otherwise.
• The pipeline shall be allowed to depolarize for atleast 72 hours after switching ‘off’ the protection
(if any) of all other pipelines in the common R.O.W.
• Before the pipeline is put on charge by switching ‘on’ CP station, natural structure –to-electrolyte
potential values at all the test stations of the system shall be measured with respect to zinc
reference cell.
• CP station shall be energized so as to achieve a maximum pipe soil potential (PSP) as specified at
the test station nearest to the drainage point, and observations on either spread of protected
portion of pipeline under this CP station shall be taken for PSP values pipeline current values
across the cross section of the pipeline shall also be determined at all the intended test stations
influenced by this CP station.
• Another complete set of PSP observations shall be taken after lines have stayed on charge for
24/48 hours. If there are appreciable differences in these observations as compared to those of
earlier set, a third set of observations shall be taken after 72 hrs. Maximum drainage point
protective potentials shall not be allowed to go beyond the maximum PSP values as specified, in
any case.
• The output of CP Station shall then be so adjusted that the sites of occurrence of least negative
protective potentials are increased to (-) 1.00 V. A full set of observations shall again be taken 72
hrs. after the adjustment of potentials and the protection system shall be left in this state of
operation.
• Care shall be exercised to ensure that power supply remains uninterrupted during the period of
commissioning. In case of an interruption, the test in progress shall be repeated after allowing
time for polarization. More sets of observations may be advised to be taken by the
owner/owner’s representative in any of the above-mentioned steps.
• PSP values at each of the test stations of the existing pipelines shall be measured and plotted
where existing pipelines run in parallel to the new pipeline and mutual interference situations
between the pipelines shall be identified and necessary mitigation shall be carried out.
• Interference situations shall also be identified and mitigated by comparing different sets of
readings taken at same test stations at different intervals of time under identical conditions
where positive potential swing exceed 50 MV.
• Final records of testing and commissioning including graphical representation of final structure
to electrolyte potential readings shall be complied with interpretation in consolation with
owner/owner’s representative and submitted.
• If it is found during commissioning that the sites of occurrence of least negative or most negative
protective potentials are less negative than (-) 1.00V even after 72 hrs of operation, then the
drainage point potentials shall be adjusted depending upon anode ground bed currents in
consultation with Owner/Owner’s representative. In any case, the drainage point protective ‘ON’
potential values shall not exceed the PSP values as per specification and the pipe to soil ‘OFF’
potential shall not exceed a value more negative than (-) 1.20 V at any location on the pipeline.
• The current dissipated by the indiviual anodes shall be measured from the anode lead junction
box and corrected for equal dissipation to the extent possible keeping the total ground bed
current same.
PROJECT
OWNER
CONTRACTOR
CP CONTRACTOR
REFERENCE DOC
5 Submission Of Records P W A
LEGEND
PROJECT
OWNER
CONTRACTOR
CP CONTRACTOR
REFERENCE DOC.
LOCATION
DATE
SR NO ACTIVITY OBSERVATION
RE-2
REMARKS
Name:
Sign:
Date:
PROJECT
OWNER
CONTRACTOR
CP CONTRACTOR
REFERENCE DOC.
Date
CP Station No Location
6.0 Total Anode To Cathode Circuit Resistance (DC O/P Volts/Current) Ohms
A1 A6
A2 A7
A3 A8
A4 A9
A5 A10
Name:
Sign:
Date:
PROJECT
OWNER
CONTRACTOR
CP CONTRACTOR
REFERENCE DOC.
Report.No. Date:
TR Unit Parameters
Mode Auto/AVCC/Manual
REMARKS
Name:
Sign:
Date:
(Format 1 of 3)
PROJECT VCM PIPELINE PROJECT
Report.No. Date:
Chainage Casing
No Type Natural PSP AC PSP
(Km) PSP
Name:
Sign:
Date:
NSPECTION REPORT
PROJECT
OWNER
CONTRACTOR
CP ONTRACTOR
REFERENCE DOC.
Report.No. Date:
Chainage Casing
No Type `ON` PSP AC PSP
(Km) PSP
REMARKS : Setting of TR unit to be recorded in TR format with note for commissioning first set of readings
purpose.
Name:
Sign:
Date:
INSPECTION REPORT
PROJECT
OWNER
CONTRACTOR
CP ONTRACTOR
REFERENCE DOC.
Test station PSP Initial (-V) PSP 48 Hrs (-V) PSP After 72 Hrs (-V). Remarks
REMARKS
Name:
Sign:
Date:
CIPL SURVEY
Purpose
To define the procedure for the conduction of CIPL Survey on the commissioned Pipeline to evaluate the
CP system and to provide adequate quality assurance / control.
• Current interrupts with synchronized timer circuits and adjustable time settings
• Rodometer
Procedure
• Before commencing the survey, confirm that the cathodic protection system is operating
normally by checking the DC feeders, drain points, insulating joints with commissioning
results.
• Check the cathodic protection commissioning result to identify the area requiring special
attention during the CIPL survey.
• Locate the route of the pipeline using the pipeline locator and provide temporary markers
(Marking powder) on the route to enable the survey to walk-on the route of the pipeline for
carrying out the CIPL survey.
• Install current interrupter with synchronized timer in the DC negative output of the DC
power source (CP System) at the CP station of the section in which the survey is being
carried out.
• With the equipment connected and the pipeline located, move along the pipeline carrying the
mobile data collector and Zinc reference cell and measure and store the pipe to soil
potentials.
• Record distance traversed and physical features such as roads, as descriptors to assist
locating specific areas after processing the data.
• As each section between TLP connections is completed, real the fine wire for further use and
shift continuous chart records to the next section.
• Transfer the data from the simcorder to a computer for producing the data print outs and
plot of the PSP potential profiles.
OWNER
CONTRACTOR
CP
ONTRACTOR
REFERENCE DOCUMENT
CONTRACTOR/OWNER: INSPECTOR
Verification Records
S.NO ACTIVITY Performed By Verification By
By submission
CPC OWNER
CONTRACTOR by CPC
LEGEND
A - APPROVAL / ACCEPTANCE
R - REVIEW
RM - RANDOM CHECK
W - WITNESS
PROJECT
OWNER
CONTRACTOR
CP ONTRACTOR
REF. DOC : CPC-CONTRACTOR-VCM-DD-001 DATE
TRU Section
Name
Date
**********************