1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
1. Contract Details 1
2. Contract
2.1 NOA & NTP 2&3
2.2 Contract Agreement 4
2.3 P.O./J.O. - Not Applicable
2.4 Bill of Quantities (BOQ) 5
2.5 GCC - Not Applicable
3. Relationship Chart 6
B. MAIN PROJECT EXECUTION PLAN
1. Work Schedule
1.1 Construction Schedule with S- Curve 7
1.2 Manpower Loading 8
1.3 Equipment Loading 9
1.4 Material Delivery Schedule 10
1.5 Subcon Schedule 11
1.6 Table of Organization 12
1.7 Material Submittal Schedule 13
1.8 Hauling Schedule - Applicable to Excavation Group
1.9 Work Breakdown Schedule (WBS) 14
2. Quality Management/EHS Requirements
2.1 Construction Methodology 15
2.2 Quality Plan 16
2.2.1 Test Results, etc. 17
2.3 Safety Plan
2.3.1 PPE Schedule w/ Projected Cost 18
2.3.2 First Aide Requirements 19
1
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
NOTICE OF AWARD
Prepared by:
Checked by:
Noted by:
2
Prepared by:
Checked by:
2
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
NOTICE TO PROCEED
Prepared by:
Checked by:
Noted by:
3
16
Prepared by:
Checked by:
Noted by:
3
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
CONTRACT AGREEMENT
Prepared by:
Checked by:
Noted by:
4
Prepared by:
Checked by:
Noted by:
4
Prepared by:
Checked by:
Noted by:
4
Prepared by:
Checked by:
Noted by:
4
Prepared by:
Checked by:
Noted by:
4
Prepared by:
Checked by:
Noted by:
4
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
Prepared by:
Checked by:
BACKFILL AND COMPACTION OF EMBANKMENT BED, SUB-BASE & BASE COURSE OF ROAD PAVEMENT
CONCRETING OF PCCP
15
CONCRETING OF CAST IN PLACE CONCRETE( DITCH, BOX CULVERT)
1 Side forming on chair using phenolic forms brace with aluma beam, good lumber, pipes or metal panel with tie-rod.
2 Fixed base chair, level and align to carry 1m size pre-cast concrete gutter and curb.
3 Check sections size, dimension and height of forms with provision of corner champer.
4 Check rebar details, size and number according to design and shop drawing.
5 Direct pouring of RMC 3000 psi using chute, pails or boom truck, properly compact with concrete vibrator.
6 Use 3/8 size aggregates, admixture on concrete mix.
7 Use float and trowel to spread and level the concrete roughly finish.
8 Curing period for 28th days prior of use.
9 Remove side forms after 2-days after pouring.
10 Transfer pre-cast to designated stockpile area using boom truck.
11 Quality control review, compressive strength, mixture, slump, temperature and air content.
RC PIPE
1 Establish layout and level control points by survey Instrument.
2 Check excavation bottom for slope, invert and stabilty of soil.
3 Spread sand 100mm thk in the trench, spread and allign.
4 Layed RCP 1220mm using backhoe or boom truck.
5 Provide collar in each joint inside and outside of RCP.
6 Check invert and slope prior to backfill by balling or flow.
SHEET PILING
1 Establish layout and level control points by survey Instrument.
2 Provide access road for crane and truck positioning for sheet piling operation
3 Driving of sheet pile up to design elevation
B. WORK SEQUENCE:
1 TOPOGRAPHIC SURVEY, STAKING AND LAYOUT OF SITE AREA.
2 CLEARING, REMOVAL OF ROAD PAVEMENT ON STAGGERED SECTION.
a PROVIDE TEMPORARY ACCESS FOR DUMPTRUCK HAULER AND WATER SPRAYER.
3 EXCAVATION FOR RIPRAP BASE BY SEGMENT.
4 MANUAL RIPRAPPING OF BOULDERS ON CONCRETE BASE AND PROVIDE RMC BINDER AT EV. 3 LAYERS
5 BACKFILLING OF APPROVED SUBBASE COURSE PLACED AT EVERY 200mm LAYER.
6 COMPACTION WITH VIBRATORY 10T ROLLER, TESTING ABOVE (95% MDD) FDT PASS.
7 PLACE BASECOURSE AND COMPACTION UP TO 98% MDD, FDT PASS
8 PROFILE AND TOPOGRAPHIC SURVEY ON TOP OF THE COMPACTED LAYER, STRAIGHT EDGE TEST.
9 SHEET PILING INSTALLATION
10 PIPE AND BOX CULVERT INSTALLATION
11 PLACED CONCRETE PAVEMENT DIRECTLY FROM RMC TRUCK
12 U-DITCH CAST IN PLACE AND BACKFILL
13 SLOPE TRIMMING AND SODDING
14 METAL BARRICADE, STREET SIGN INSTALLATION
15 CONCRETE CUTTING, ASPHALT JOINT FILLER AND PAINTING
15
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon & Kauswagan, Cagayan de Oro City
BACKFILL AND COMPACTION OF EMBANKMENT BED, SUB-BASE & BASE COURSE OF ROAD PAVEMENT
RC PIPE
1 Establish layout and level control points by survey Instrument.
2 Check excavation bottom for slope, invert and stabilty of soil.
3 Spread sand 100mm thk in the trench, spread and allign.
4 Layed RCP 1220mm using backhoe or boom truck.
5 Provide collar in each joint inside and outside of RCP.
6 Check invert and slope prior to backfill by balling or flow.
15
GRAVEL SERVICE ROAD
1 Establish layout and level control points by survey Instrument.
2 Spread 3/4 gravel 100mm thk along the line of road.
3 Check profile and slope of the road +/-50nn deviation
4 Compaction using 3t roller
B. WORK SEQUENCE:
1 TOPOGRAPHIC SURVEY, STAKING AND LAYOUT OF SITE AREA.
2 CLEARING, REMOVAL OF TREES, VEGETATION AND OBSTRUCTIONS
a PROVIDE TEMPORARY ACCESS FOR DUMPTRUCK HAULER AND WATER SPRAYER.
b. PROVIDE TEMPORARY STOCKPILE AREA FOR TREES AND DEBRIS.
3 EXCAVATION FOR RIPRAP BASE BY SEGMENT.
4 MANUAL RIPRAPPING OF BOULDERS ON CONCRETE BASE AND PROVIDE RMC BINDER AT EV. 3 LAYERS
5 BACKFILLING OF APPROVED SUBBASE COURSE PLACED AT EVERY 200mm LAYER.
6 COMPACTION WITH VIBRATORY 10T ROLLER, TESTING ABOVE (95% MDD) FDT PASS.
7 PLACE BASECOURSE AND COMPACTION UP TO 98% MDD, FDT PASS
8 PROFILE AND TOPOGRAPHIC SURVEY ON TOP OF THE COMPACTED LAYER, STRAIGHT EDGE TEST.
9 PIPE AND BOX CULVERT INSTALLATION
10 U-DITCH CAST IN PLACE AND BACKFILL
11 SLOPE TRIMMING AND SODDING
12 METAL BARRICADE, STREET SIGN INSTALLATION
15
NAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
gy. Bonbon & Kauswagan, Cagayan de Oro City
boulder (150-300mm) counted according to the number of boulder to be layed in each section.
15
OULDERS ON CONCRETE BASE AND PROVIDE RMC BINDER AT EV. 3 LAYERS
15
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon & Kauswagan, Cagayan de Oro City
BACKFILL AND COMPACTION OF EMBANKMENT BED, SUB-BASE & BASE COURSE OF ROAD PAVEMENT
15
CONCRETING OF CAST IN PLACE CONCRETE( DITCH, BOX CULVERT)
1 Side forming on chair using phenolic forms brace with aluma beam, good lumber, pipes or metal panel with tie-rod.
2 Fixed base chair, level and align to carry 1m size pre-cast concrete gutter and curb.
3 Check sections size, dimension and height of forms with provision of corner champer.
4 Check rebar details, size and number according to design and shop drawing.
5 Direct pouring of RMC 3000 psi using chute, pails or boom truck, properly compact with concrete vibrator.
6 Use 3/8 size aggregates, admixture on concrete mix.
7 Use float and trowel to spread and level the concrete roughly finish.
8 Curing period for 28th days prior of use.
9 Remove side forms after 2-days after pouring.
10 Transfer pre-cast to designated stockpile area using boom truck.
11 Quality control review, compressive strength, mixture, slump, temperature and air content.
RC PIPE
1 Establish layout and level control points by survey Instrument.
2 Check excavation bottom for slope, invert and stabilty of soil.
3 Spread sand 100mm thk in the trench, spread and allign.
4 Layed RCP 1220mm using backhoe or boom truck.
5 Provide collar in each joint inside and outside of RCP.
6 Check invert and slope prior to backfill by balling or flow.
B. WORK SEQUENCE:
1 TOPOGRAPHIC SURVEY, STAKING AND LAYOUT OF SITE AREA.
2 CLEARING, REMOVAL OF TREES, VEGETATION AND OBSTRUCTIONS
a PROVIDE TEMPORARY ACCESS FOR DUMPTRUCK HAULER AND WATER SPRAYER.
b. PROVIDE TEMPORARY STOCKPILE AREA FOR TREES AND DEBRIS.
3 EXCAVATION FOR RIPRAP BASE BY SEGMENT.
4 MANUAL RIPRAPPING OF BOULDERS ON CONCRETE BASE AND PROVIDE RMC BINDER AT EV. 3 LAYERS
5 BACKFILLING OF APPROVED SUBBASE COURSE PLACED AT EVERY 200mm LAYER.
6 COMPACTION WITH VIBRATORY 10T ROLLER, TESTING ABOVE (95% MDD) FDT PASS.
7 PLACE BASECOURSE AND COMPACTION UP TO 98% MDD, FDT PASS
8 PROFILE AND TOPOGRAPHIC SURVEY ON TOP OF THE COMPACTED LAYER, STRAIGHT EDGE TEST.
9 PIPE AND BOX CULVERT INSTALLATION
10 U-DITCH CAST IN PLACE AND BACKFILL
11 SLOPE TRIMMING AND SODDING
15
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
BILL OF QUANTITIES
Prepared by:
Checked by:
5
Prepared by:
Checked by:
Noted by:
5
Prepared by:
Checked by:
Noted by:
5
Prepared by:
Checked by:
Noted by:
5
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
#REF!
TOTAL AMOUNT
ITEM NO. WORK DESCRIPTION QTY. UNIT UNIT COST
(Php)
5
1098 - FLOOD RISK MANAGEMENT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon and Kauswagan Cagayan De Oro, City
SUBCONTRACTOR
6
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
17
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
17
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
Prepared by:
Mario Tiongco
17
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
17
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
BILL OF QUANTITIES
TOTAL AMOUNT
ITEM NO. WORK DESCRIPTION QTY. UNIT UNIT COST
(Php)
311 PORT CEMENT CONCRETE PAVEMENT 0.2M 2,430.49 Sq.m 1,163.49 2,827,857.74
500-A PIPE CULVERT & STORM DRAIN (O.6M DIA.) 886.00 L.M 1,994.74 1,767,343.58
500-B PIPE CULVERT & STORM DRAIN (1.5M DIA.) 90.00 L.M 8,000.09 720,008.52
502-A CONCRETE MANHOLES; PMH1 (RCP 600MM) 51.00 UNITS 12,270.42 625,791.35
502-B CONCRETE MANHOLES; PMH2 (RCP 600MM) 17.00 UNITS 13,811.65 234,798.12
502-C CONCRETE MANHOLES; PMH3 (RCP 1500MM) 9.00 UNITS 29,633.94 266,705.46
SPL-3 R.C BOX DRAINAGE W/STEEL GRATED COVER 68.00 L.M 18,359.76 1,248,463.97
5
SPL-6 CONSTRUCTION SAFETY & HEALTH 1.00 L.S 76,367.47 76,367.47
5
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
16-May-16
23-May-16
30-May-16
15-Aug-16
22-Aug-16
29-Aug-16
12-Sep-16
19-Sep-16
26-Sep-16
14-Nov-16
21-Nov-16
28-Nov-16
12-Dec-16
19-Dec-16
26-Dec-16
13-Jun-16
20-Jun-16
27-Jun-16
16-Jan-17
23-Jan-17
11-Apr-16
18-Apr-16
25-Apr-16
10-Oct-16
17-Oct-16
24-Oct-16
31-Oct-16
2-May-16
9-May-16
11-Jul-16
18-Jul-16
25-Jul-16
1-Aug-16
8-Aug-16
5-Sep-16
7-Nov-16
5-Dec-16
6-Jun-16
2-Jan-17
9-Jan-17
4-Apr-16
3-Oct-16
4-Jul-16
ITEM DESCRIPTION
-
10-May-16
17-May-16
24-May-16
31-May-16
16-Aug-16
23-Aug-16
30-Aug-16
13-Sep-16
20-Sep-16
27-Sep-16
15-Nov-16
22-Nov-16
29-Nov-16
13-Dec-16
20-Dec-16
27-Dec-16
29-Mar-16
14-Jun-16
21-Jun-16
28-Jun-16
10-Jan-17
17-Jan-17
12-Apr-16
19-Apr-16
26-Apr-16
11-Oct-16
18-Oct-16
25-Oct-16
3-May-16
12-Jul-16
19-Jul-16
26-Jul-16
2-Aug-16
9-Aug-16
6-Sep-16
1-Nov-16
8-Nov-16
6-Dec-16
7-Jun-16
3-Jan-17
5-Apr-16
4-Oct-16
5-Jul-16
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10WEEK 11WEEK 12WEEK 13WEEK 14WEEK 15WEEK 16WEEK 17WEEK 18WEEK 19WEEK 20WEEK 21WEEK 22WEEK 23WEEK 24WEEK 25WEEK 26WEEK 27WEEK 28WEEK 29WEEK 30WEEK 31WEEK 32WEEK 33WEEK 34WEEK 35WEEK 36WEEK 37WEEK 38WEEK 39WEEK 40WEEK 41WEEK 42WEEK 42
Bulldozer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Backhoe (2) 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Vibratory Compactor 1 1 1 1 1 1 1 1 1 1 1 1 1
Dumptruck (2) 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1
Water Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Fuel Truck 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
C. SITE DEVELOPMENT
Backhoe (2) 1 1 1 1 1 1 1 1 1 1 1
Vibratory Compactor 1 1 1 1 1 1 1 1 1 1 1
Dumptruck (2) 1 1 1 1 1 1 1 1 1 1 1
Water Truck 1 1 1 1 1 1 1 1 1 1 1
Backhoe (2) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
TOTAL 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 1 0 0
6
IPM CONSTRUCTION and DEVELOPMENT CORPORATION
Brgy. Kapitolyo, Pasig City
OffIce
President
EDGARDO S. BARTOLOME
Area Manager
EDGAR CABASE
OrganIzatIon
Project Manager
Pjay Pajuayan
Project Engineer
QUALITY ASSURANCE
SAFETY & TRAFFIC
& QUALITY CONTROL OPERATIONS ENGINEERING ACCOUNTING SUPPORT GROUP
MANAGEMENT GROUP
GROUP
HERMEL
Heavy & Light Equipment Mechanic
GERMINO/FREDDIE MARIO TIONGCO Reygie Johnrad Pataueg VACANT Michael Villalobos
Project
12
1098 - FLOOD RISK MANAGEMENT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon and Kauswagan Cagayan De Oro City
SEGMENT C
0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16% 0.16%
1 FACILITIES FOR THE ENGINEER 5,399,569.92 1.46%
2 OTHER GENERAL REQUIREMENTS 14,671,668.07 3.95% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44%
7 DRAINAGE AND SLOPE PROTECTION STRUCTURES 87,474,568.34 23.57% 2.14% 2.14% 2.14% 2.14% 2.14% 2.14% 2.14% 2.14% 2.14% 2.14% 2.14%
SEGMENT A
0.19% 0.19% 0.19% 0.19% 0.19% 0.19%
1 FACILITIES FOR THE ENGINEER 4,161,096.29 1.12%
0.51% 0.51%
2 OTHER GENERAL REQUIREMENTS 11,306,497.45 3.05% 0.51% 0.51% 0.51% 0.51%
6 DRAINAGE AND SLOPE PROTECTION STRUCTURES 71,668,444.08 19.31% 2.41% 2.41% 2.41% 2.41% 2.41% 2.41% 2.41% 2.41%
SEGMENT B
0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14%
1 FACILITIES FOR THE ENGINEER 5,242,079.22 1.41%
0.38% 0.38% 0.38% 0.38%
2 OTHER GENERAL REQUIREMENTS 14,243,735.63 3.84% 0.38% 0.38% 0.38% 0.38% 0.38% 0.38%
0.33%
3 EARTHWORKS 6,162,542.99 1.66% 0.33% 0.33% 0.33% 0.33%
4 SUB-BASE AND BASE COURSE 4,244,533.12 1.14% 0.29% 0.29% 0.29% 0.29%
3.04%
6 DRAINAGE AND SLOPE PROTECTION STRUCTURES 90,286,702.34 24.33% 3.04% 3.04% 3.04% 3.04% 3.04% 3.04% 3.04%
TOTAL 371,066,673.84 100.00% 0.60% 0.60% 0.60% 2.74% 2.74% 2.74% 3.15% 3.15% 3.84% 6.35% 7.12% 7.12% 7.88% 6.94% 7.18% 6.31% 6.31% 4.96% 4.96% 4.63% 4.33% 4.13% 1.09% 0.53%
PROGRAMMED ACCOMPLISHMENT (%) 0.00% 0.60% 0.60% 0.60% 2.74% 2.74% 2.74% 3.15% 3.15% 3.84% 6.35% 7.12% 7.12% 7.88% 6.94% 7.18% 6.31% 6.31% 4.96% 4.96% 4.63% 4.33% 4.13% 1.09% 0.53%
CUMULATIVE ACCOMPLISHMENT (%) 0.00% 0.60% 1.20% 1.80% 4.55% 7.29% 10.04% 13.18% 16.33% 20.17% 26.52% 33.64% 40.76% 48.64% 55.59% 62.76% 69.08% 75.39% 80.35% 85.31% 89.93% 94.26% 98.39% 99.47% 100.00%
QUARTERLY ACCOMPLISHMENT 1.80% 8.23% 10.13% 20.59% 22.01% 17.58% 13.91% 5.74%
CUMULATIVE ACCOMPLISHMENT 1.80% 10.04% 20.17% 40.76% 62.76% 80.35% 94.26% 100.00%
QUARTERLY CASH FLOW 6,690,412.66 30,547,113.12 37,602,995.43 76,403,990.16 81,653,558.85 65,246,401.28 51,616,951.09 21,305,251.25
CUMULATIVE CASH FLOW 6,690,412.66 37,237,525.78 74,840,521.22 151,244,511.37 232,898,070.23 298,144,471.51 349,761,422.59 371,066,673.84
7
1098 - FLOOD RISK MANAGEMENT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon and Kauswagan Cagayan De Oro City
16.0 Project HR 1 1 1 1 1 1 1 1 1 1 1 1 1 1
17.0 Timekeeper 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
20.0 Warehouseman 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1
27.0 Watchman 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
28.0 Utility 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
8
1098 - FLOOD RISK MANAGEMENT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon and Kauswagan Cagayan De Oro City
1.0 Carpenter 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
2.0 Mason 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
3.0 Steelman 2 2 2 2 2 2 2 2 2 2
4.0 Welder 2 2 2
6.0 Laborer/Helper 10 10 10 30 35 40 45 50 55 55 55 50 50 45 45 45 45 45 35 20 10 10 10
8
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP CDOR) JICA LOAN AGREEMENT NO. PH-P259 CONTRACT PACKAGE NO. 1 (BONBON-KAUSWAGAN)
Brgy. Bon-bon - Kauswagan, Cagayan De Oro City
AUGUST 2019 SEPTEMBER 2019 ÓCTOBER 2019 NOVEMBER 2019 DECEMBER 2019 JANUARY 2020 FEBRUARY 2020 MARCH 2020 ÁPRIL 2020 MAY 2020 JUNE 2020 JULY 2020 ÁUGUST 2020 SEPTEMBER 2020 ÇOTOBER 2020 NOVE,BER 2020 DECEMBER 2020
ITEM DESCRIPTION QTY UNIT
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
PART C - EARTHWORKS
1.0 Embankment from Borrow 27,657.50 cu.m
1.10 Road raising (sub-base materials)
1.0 Sidewalk
1.10 Cement 1,980.00 bags
1.20 Sand 99.00 cu.m
1.30 Gravel 198.00 cu.m
1.40 Formworks 198.00 sq.m
3/4"x4'x8' Phenolic Board 25.00 shts
2"x3"x8' Coco Lumber 500.00 len
Assorted Nails 75.00 kgs
2.0 Right of Way Monument
2.10 Right of Way Monument 29.00 ea.
2.30 Labor & Equipment Cost 29.00 ea.
10
1098 - FLOOD RISK MANAGEMENT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon and Kauswagan Cagayan De Oro City
TOTAL 0 0 0 0 9 15 15 17 17 16 16 16 16 16 16 16 16 16 16 15 13 13 0 0
9
TOTAL 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14 14
9
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP CDOR) JICA LOAN AGREEMENT NO. PH-P259 CONTRACT PACKAGE NO. 1 (BONBON KAUSWAGAN)
Brgy. Bonbon - Kauswagan, Cagayan De Oro City, Misamis Oriental
Item
WORK DESCRIPTION Quantity Unit AUGUST 2019 SEPTEMBER 2019 OCTOBER 2019 NOVEMBER 2019 DECEMBER 2019 JANUARY 2020 FEBRUARY 2020 MARCH 2020 APRIL 2020 MAY 2020 JUNE 2020 JULY 2020 ÁUGUST 2020 SEPTEMBER 2020 OCTOBER 2020 NOVEMBER 2020 DECEMBER 2020
No.
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
A STONE MASONRY
A.1 Stone Masonry
A.1.1 Stone Masonry (Labor Only) 9,315.00 cu.m
B DRAIN PIPE
B.1 Drain Pipe
B.1.1 Drain Pipe (Labor Only) 720.00 LM
C FILTER LAYER OF GRANULAR MATERIAL
C.1 Filter Layer of Granular Material
C.1.1 Filter Layer of Granular Material (Labor Only) 162.00 cu.m
D LIGHTING POST AND ACCESSORIES
11
Document No. Revision No.: 0
Issue No.
Page Number:
1
1 of SCHEDULE OF MATERIAL SUBMITTALS Date Revised:
Effective Date:
0
Project: FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE RO RIVER (FRIMP-CODR) PACKAGE 1 Owner: DPWH-UPMO Date Prepared: Record No:
Location: Cagayan de Oro City Designer: 31-Jul-19
EARTHWORKS
103(1)a IPM-CDC-1098-L1-050 3/18/2019 Embankment using Sub-base Materials x 3/18/2019 3/25/2019 B Sto. Niňo Aggregates Passed
SUBBASE AND BASE COURSE
200(1) IPM-CDC-1098-L1-050 3/18/2019 Aggregate Sub-base Course x 3/18/2019 3/25/2019 B Sto. Niňo Aggregates Passed
202(1) IPM-CDC-1098-L1-050 3/18/2019 Crushed Aggregate Base Course x 3/18/2019 3/25/2019 B Sto. Niňo Aggregates Passed
SUBBASE AND BASE COURSE
300(2) Crushed Aggregate Surface Course x Pending for sampling and Testing
311(1)f1 Portland Cement Concrete Pavement
IPM-CDC-1098-L1-088 5/6/2019 PCCP Design Mix, 3500 PSI x 5/7/2019 5/29/2019 B LYL Batching Plant Found in Order
IPM-CDC-1098-L1-120 7/11/2019 PCCP Trial Mix x x 7/12/2019 7/23/2019 B LYL Batching Plant Complying to Project Specification
BRIDGE CONSTRUCTION
404(1)a IPM-CDC-1098-L1-101 5/29/2019 Reinforcing Steel (Grade 40) x 5/29/2019 Steel Asia For Approval
405(1)a3 Structural Concrete (U-ditch)
IPM-CDC-1098-L1-088 5/6/2019 Structural Concrete Design Mix, 3000 PSI x 5/7/2019 5/29/2019 B LYL Batching Plant Found in Order
IPM-CDC-1098-L1-120 7/11/2019 Structural Concrete Trial Mix x x 7/12/2019 7/23/2019 B LYL Batching Plant Complying to Project Specification
407(8) Lean Concrete
IPM-CDC-1098-L1-088 5/6/2019 Structural Concrete Design Mix, 2500 PSI x 5/7/2019 5/29/2019 B LYL Batching Plant Found in Order
IPM-CDC-1098-L1-120 7/11/2019 Structural Concrete Trial Mix x x 7/12/2019 7/23/2019 B LYL Batching Plant Complying to Project Specification
DRAINAGE AND SLOPE PROTECTION
500(1)b5 IPM-CDC-1098-L1-096 5/16/2019 Pipe Culverts (1220mmØ) x 5/16/2019 5/27/2019 B Sto. Niňo Aggregates Complying to Project Specification
506(1) Stone Masonry
IPM-CDC-1098-L1-050 3/18/2019 Holcim Cement Type I Portland Cement x 3/18/2019 3/25/2019 A Holcim Cement Corporation Passed
IPM-CDC-1098-L1-086 5/2/2019 Ha Long Portland Type I Cement x 5/3/2019 5/28/2019 A Ha Long Cement JSC Complying to Project Specification
IPM-CDC-1098-L1-033 2/28/2019 Boulders/Stone (Balulang Quarry) x 3/1/2019 3/19/2019 A Sto. Niňo Aggregates Complying to Project Specification
IPM-CDC-1098-L1-086 5/2/2019 Boulders/Stone (Balingasag Quarry) x 5/2/2019 5/28/2019 A Basoy Minerocks Corp. Complying to Project Specification
IPM-CDC-1098-L1-050 3/8/2019 Fine Aggregates x 3/18/2019 3/25/2019 A Sto. Niňo Aggregates Passed
IPM-CDC-1098-L1-035 2/28/2019 Filter Cloth, 250 GSM x x 3/1/2019 3/7/2019 B FABRIMETRICS PHILS., INC Interposes no objection
IPM-CDC-1098-L1-035 2/28/2019 PVC Pipe, 100mmØ x x 3/1/2019 3/7/2019 B Cagayan RSO Hardware Inc. Interposes no objection
1704(1)b Embankment
IPM-CDC-1098-L1-086 5/2/2019 Borrow Materials x 4/8/2019 5/28/2019 B Pagatpat/Canitoan Quarry Acceptable
IPM-CDC-1098-L1-122 7/15/2019 Trial Embankment x 7/15/2019 Pagatpat/Canitoan Quarry For Evaluation and Approval
1710(1)c Riprap
IPM-CDC-1098-L1-033 2/28/2019 Class "C"Stones (Balulang Quarry) x 3/1/2019 3/19/2019 A Sto. Niňo Aggregates Complying to Project Specification
IPM-CDC-1098-L1-086 5/2/2019 Class "C"Stones (Balingasag Quarry) x 5/2/2019 5/28/2019 A Basoy Minerocks Corp. Complying to Project Specification
1710(3) IPM-CDC-1098-L1-050 3/18/2019 Filter Layer of Granular Materials x 3/18/2019 3/25/2019 B Sto. Niňo Aggregates Passed
1717(5)a2 IPM-CDC-1098-L1-039 3/7/2019 Steel Sheet Piles x 3/7/2019 3/14/2019 B Xingda Construction Supply Found In Order & Acceptable
MISCELLANEOUS STRUCTURES
603(1)a Metal Guardrails Including Post No proposed Supplier yet
603(4)a Metal Beam End Piece x x No proposed Supplier yet
606(1)a1 Pavement Marking (White) x x x No proposed Supplier yet
606(1)a1 Pavement Marking (Yellow) x x x No proposed Supplier yet
631(1) IPM-CDC-1098-L1-130 7/22/2019 Epoxy Anchoring Adhesive x x 7/22/2019 SIKA/RC NEW CHEM INC. For Evaluation and Approval
ACTION CODES:
A Approved
B Approved as Noted
C Revised & Resubmit (Work may not proceed)
D Disapproved
13
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER (FRIMP CDOR) JICA LOAN AGREEMENT NO. PH-P259 CONTRACT PACKAGE NO. 1 (BONBON KAUSWAGAN)
Brgy. Bonbon - Kauswagan, Cagayan De Oro City, Misamis Oriental
Contract Amount
Item No. WBS CODE Level B.Elem. Item Cat. Description Gross Net of VAT
16 IF.001098.07.16 2 WKN FURNISHED AND DRIVEN STEEL SHEET PILE 7,457,273.28 6,658,279.71
10 IF.001098.09.10 LABOR
APPROVED INTERIM
BUDGET
4,550,000.00
500,000.00
300,000.00
200,000.00
500,000.00
100,000.00
150,000.00
300,000.00
300,000.00
200,000.00
1,500,000.00
500,000.00
3,200,000.00
200,000.00
700,000.00
20,000.00
500,000.00
500,000.00
500,000.00
500,000.00
280,000.00
2,670,000.00
550,000.00
120,000.00
2,000,000.00
1,000,000.00
500,000.00
500,000.00
1,000,000.00
500,000.00
500,000.00
-
15,580,000.00
1,930,000.00
3,220,000.00
1,650,000.00
1,500,000.00
350,000.00
200,000.00
130,000.00
300,000.00
3,000,000.00
750,000.00
550,000.00
2,000,000.00
9,850,000.00
2,000,000.00
1,000,000.00
1,000,000.00
1,000,000.00
3,200,000.00
500,000.00
500,000.00
400,000.00
50,000.00
200,000.00
2,000,000.00
37,850,000.00
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
11
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
11
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
2.0 MATERIAL RECOVERY FACILITY (15m x 20m) 300.00 sq.m 20,822.67 6,246,801.00 3,200,000.00 300,000.00 420,000.00 - 3,920,000.00 4,390,400.00 #REF! #REF!
WEIGHING BRIDGE & FACILITIES / MONITORING OFFICE
3.0 1.00 lot 3,297,633.84 3,297,633.84 2,000,000.00 150,000.00 120,000.00 - 2,270,000.00 2,542,400.00 #REF! #REF!
(2m x 2m)
Project Management (see separate breakdown) #REF! #REF!
OCM (7)% 2,579,846.67 3,517,001.60 3,517,001.60
Other Cost 8,000,000.00 8,000,000.00
TOTAL 85,994,888.88 19,620,000.00 5,156,880.00 21,266,000.00 - #REF! #REF! #REF! #REF!
46,042,880.00
Profit (Net of VAT) #REF! #REF!
11
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon and Kauswagan, Cagayan De Oro City
SCHEDULED BUDGET %
• Equipment
• Provision for GAO - 5% of Direct Cost (Contract), NET OF VAT 14,339,060.58 4.33%
Checked / Verified:
Josephine A. Marquez
Manager, PMO
Recommending Approval:
Date: _____________________
Reviewed By:
Isabelita P. Mercado
President
IPM Group of Companies
Date: ____________________
27
IPM CONSTRUCTION & DEVELOPMENT CORPORATION SCHEDULED BUDGET
No.10 Brixton Street Brgy. Kapitolyo Pasig City
1098
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER FLOODRISK MGT. SYSTEM
Brgy. Bonbon and Kauswagan, Cagayan De Oro City Date: May 15, 2020
DIRECT WORKS
Other COST
Dayworks 5,205,422.42 4,647,698.59 3,116,724.97 1,530,973.63
Provisional Sum 27,424,593.94 24,486,244.59 16,420,361.25 8,065,883.35
Sub-Total 32,630,016.37 29,133,943.19 19,537,086.22 9,596,856.97
PART C EARTHWORKS
Materials 6,772,283.10 6,046,681.34 6,084,650.00 (37,968.66)
Equipment 4,988,437.65 4,453,962.19 4,405,598.86 48,363.33
Direct Manpower - - - -
Subcon - - - -
Sub-Total (Earthworks) 11,760,720.75 10,500,643.53 10,490,248.86 10,394.67
Prepared by:
GINA B. CASIS
QS Supv. - PMO
SCHEDULED BUDGET
PROJECTED PROFIT
%
18.32%
18.32%
-42.37%
-18.67%
18.32%
29.99%
-426.45%
-41.57%
22.99%
-2.64%
18.32%
18.32%
-219.98%
16.34%
94.55%
60.62%
28.83%
68.68%
9.34%
8.34%
32.94%
32.94%
32.94%
-0.63%
1.09%
0.09%
41.77%
-40.49%
27.72%
19.66%
-779.40%
59.85%
14.48%
5.40%
-115.06%
-10.50%
34.07%
-52.12%
-115.06%
21.27%
19.14%
4.92%
-184.07%
-115.06%
33.85%
16.87%
19.71%
30.67%
22.99%
-115.06%
27.36%
-48.42%
32.94%
-41.57%
68.68%
9.34%
19.71%
3.02%
Project Name : Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
Contract Amount: (JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
371,066,673.84
Duration : 720 Calendar Days
0.23% 0.92% 0.92% 0.92% 2.89% 10.80% 11.17% 11.17% 13.14% 14.42% 14.84% 14.84% 3.71% 100.00%
Project Duration
Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Net Release TOTAL
Accomplishment 11,124,119.12 10,739,992.16 40,091,222.11 41,455,351.79 41,455,351.79 48,748,964.03 53,510,898.62 55,080,685.33 55,080,685.33 13,779,403.57 371,066,673.84
VAT 10.71 7,951,428.73 - - - - 1,639,808.35 3,006,841.66 3,109,151.38 3,109,151.38 3,656,172.30 4,013,317.40 4,131,051.40 4,131,051.40 5,009,169.63 - - 39,757,143.63
Profit (before tax) 0.61 366,097,030.89
99.81
Net Cash Flow 64,455,955.50 (812,021.95) (812,021.95) (1,456,352.83) (9,582,090.88) (20,985,197.51) (11,841,355.45) (11,231,260.26) (16,469,281.62) (7,616,773.29) 2,660,281.35 (26,253,281.02) (3,546,582.53) 41,116,934.05 - - (2,373,048.40)
Cumulative Cash Flow 64,455,955.50 63,643,933.54 62,831,911.59 61,375,558.76 51,793,467.88 30,808,270.37 18,966,914.92 7,735,654.65 (8,733,626.97) (16,350,400.26) (13,690,118.90) (39,943,399.92) (43,489,982.45) (2,373,048.40) (2,373,048.40)
Note: 1 Schedule of payment for progress billing should be the expected release of payment base from contract.
2 Cash out or payment for materials is from payment terms obtained from procurement schedule/planned material delivery.
3 Update and revise cash flow based from validated cash out and cash in schedule when necessary.
4 Leveling of activities should always be considered to avoid or minimized negative cumulative cash flow.
5 If after leveling of activities, a negative cumulative cash flow is still obtained (minimum result), then it will make IPM management to become aware when and how much is the additional cash outlay.
Prepared by:
GINA B. CASIS
QS Supv. - PMO
26
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
#REF!
#REF!
TOTAL 4,796,542.38
###
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
#REF!
TOTAL 1,199,135.60
Profit (Net of VA
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
#REF!
1.00 1220mm diameter RCPC 347.00 lm 8,912.99 3,092,808.58 7,958.03 2,761,436.23 336.00 lm 9,553.57 3,209,999.52
2.00 Cement 1,041.00 bags 269.35 280,391.99 240.49 250,349.99 504.00 bags 186.00 93,744.00
3.00 Sand - Delivered 70.00 cu.m 954.96 66,847.45 852.65 59,685.22 70.00 cum. 670.00 46,900.00
4.00 Gravel Bedding - Delivered 141.12 cu.m 1,199.83 169,319.44 1,071.27 151,178.07 141.00 cum. 750.00 105,750.00
22
1717 (5)a2 Furnished and Driven Steel Sheet Piles 6,815,165.17 6,084,968.90 3,370,768.00
1.00 Steel Sheet Pile 78,535.20 kgs 82.27 6,461,387.91 73.46 5,769,096.35 52,012.80 5.00% kg. 60.00 3,120,768.00
2.00 Miscellaneous Materials (see detailed breakdown below) 1.00 lot 353,777.26 353,777.26 315,872.56 315,872.56 1.00 lot 250,000.00 250,000.00
Oxy-Ace 0.00 0.00 0.00 0.00
Welding Rod 0.00 0.00 0.00 0.00
1719 (6)a2 Rectangular Aluminum Flap Gate (1700 x 1700 mm.) 7,713,167.05 6,886,756.29 5,620,000.00
1.00 Flood Gates 9.00 sets 822,737.82 7,404,640.36 734,587.34 6,611,286.04 9.00 set 600,000.00 5,400,000.00
2.00 Miscellaneous Materials (see detailed breakdown below) 1.00 lot 308,526.68 308,526.68 275,470.25 275,470.25 1.00 lot 220,000.00 220,000.00
603 (3)a1 Metal Guard Rail (Metal Beam) Including Post 0.00 0.00 373,442.43
1.00 Metal Guard Rail 1,240.00 lm 3,428.07 subcon 3,060.78 subcon 1,240.00 ln.m subcon
2.00 Cement 496.00 bags 186.00 92,256.00
3.00 Sand - Delivered 24.80 cum. 670.00 16,616.00
4.00 Gravel Bedding - Delivered 49.60 cum. 750.00 37,200.00
5.00 3/4"x4'x8' Phenolic Board 20.00 shts 1,200.00 24,000.00
6.00 2"x3"x8' Coco Lumber 400.00 len 90.00 36,000.00
7.00 Assorted Nails 60.00 kgs 75.00 4,500.00
8.00 12.0mm x 6.0m RSb Grade 40 414.00 pcs 195.00 80,730.00
9.00 10.0mm x 6.0m RSb Grade 40 570.00 pcs 134.00 76,380.00
10.00 G.I Tie Wire #16 85.98 kgs 67.00 5,760.43
201,488,891.70 171,293,447.43
-9,640,230.58 34,452.15
10,005,069.00 26.00
QS Supv. - PMO
22
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
Cagayan de Oro City
n
o
A - CONTRACT / SELLING B- PROJECT BUDGET
o
ITEM DESCRIPTION A - NET OF VAT f
QTY UNIT UNIT COST AMOUNT (GROSS) QTY (actual) UNIT UNIT COST AMOUNT (NET)
e
UNIT COST AMOUNT q
u
i
HEAVY & LIGHT EQUIPMENT p
t
PART C - EARTHWORKS
101(3)b4 Removal of Actual Structures / Obstructions 9,520.00 m2 246.82 2,349,739.21 220.38 2,097,981.44 1,300,000.00###
1.00 Backhoe with Breaker (380m2/day) 200.00 hr 2,750.00 550,000.00
###
2.00 Backhoe with Bucket (380m2/day) 200.00 hr 2,100.00 420,000.00
###
3.00 Dumptruck (380m2/day) 200.00 mo. 1,650.00 330,000.00
###
103(1)a Structure Excavation 617.00 cu.m 342.81 211,512.18 306.08 188,850.16 112,500.00###
1.00 Backhoe with Bucket (200m3/day) 30.00 hr 2,100.00 63,000.00
###
2.00 Dumptruck (200m3/day) 30.00 hr 1,650.00 49,500.00
###
104(2)a Embankment from Borrow 22,126.00 cu.m 109.70 2,427,186.26 97.94 2,167,130.59 2,941,056.00###
1.00 Grader (300 m3/day) 590.03 hr 2,700.00 1,593,072.00
###
2.00 Roller (300 m3/day) 590.03 hr 1,900.00 1,121,050.67
###
3.00 Water Truck (300m3/day) 2.84 mo. 80,000.00 226,933.33
###
202 (1) Crushed Agregate Base Course 2,786.25 cu.m 109.70 305,647.10 97.94 272,899.20 555,535.38###
1.00 Grader (200 m3/day) 111.45 hr 2,700.00 300,915.00
###
2.00 Roller (200 m3/day) 111.45 hr 1,900.00 211,755.00
###
3.00 Water Truck (200m3/day) 0.54 mo. 80,000.00 42,865.38
###
311(1)f1 Portland Cement Concrete Pavement Unreinforced 300mm 506,497.97 452,230.33 - ###
Concrete Vibrator by subcon 2.00
Bar Cutter 2.00 units 253,248.98 506,497.97 226,115.16 452,230.33 included to support equipment units
506 (1) Stone Masonry 9,315.00 cu.m 34.28 319,325.12 30.61 285,111.71 1,619,720.00###
1.00 Backhoe with Bucket (200 cum/day) 745.20 hr 2,100.00 1,564,920.00
###
2.00 One Bagger Mixer (100m3/day) ###
3.00 Water Truck (100m3/day) 0.19 0 80,000.00 15,200.00
###
4.0 Dumptruck 24.00 0 1,650.00 39,600.00
1700 (1) Cleaning and Grubbing 49,460.00 m2 27.42 1,356,420.42 24.49 1,211,089.66 1,000,800.00###
1.00 Backhoe (2750m2/day) 144.00 hr 2,100.00 302,400.00
###
2.00 Bulldozer (2750m2/day) 144.00 hr 3,200.00 460,800.00
###
3.00 Dumptruck (2750m2/day) 144.00 hr. 1,650.00 237,600.00
###
1700 (3)a1 Individual Removal of Trees (150-300 mm dia.) 54.00 each 2,056.84 111,069.61 1,836.47 99,169.29 90,000.00###
1.00 Backhoe with Bucket 24.00 hr 2,100.00 50,400.00
###
2.00 Dumptruck 24.00 hr 1,650.00 39,600.00
###
1700 (3)a2 Individual Removal of Trees (301-500 mm dia.) 37.00 each 2,742.46 101,471.00 2,448.62 90,599.10 75,000.00###
1.00 Backhoe with Bucket 20.00 hr 2,100.00 42,000.00
###
2.00 Dumptruck 20.00 hr 1,650.00 33,000.00
###
1700 (3)a3 Individual Removal of Trees (501-750 mm dia.) 6.00 each 3,428.07 20,568.45 3,060.78 18,364.68 15,000.00###
1.00 Backhoe with Bucket 4.00 hr 2,100.00 8,400.00
###
2.00 Dumptruck 4.00 hr 1,650.00 6,600.00
###
1700 (3)a4 Individual Removal of Trees (751-900 mm dia.) 3.00 each 5,142.11 15,426.33 4,591.17 13,773.51 15,000.00###
1.00 Backhoe with Bucket 4.00 hr 2,100.00 8,400.00
###
2.00 Dumptruck 4.00 hr 1,650.00 6,600.00
###
1700 (4) Individual Removal of Trees (above 900mm dia.) 2.00 each 7,884.57 15,769.14 7,039.80 14,079.59 15,000.00###
1.00 Backhoe with Bucket 4.00 hr 2,100.00 8,400.00
###
2.00 Dumptruck 4.00 hr 1,650.00 6,600.00
###
1701 (1) Unsuitable Excavation 1,535.00 cu.m 137.12 210,483.76 122.43 187,931.93 230,250.00###
1.00 Backhoe with Bucket (300 cum/day) 61.40 hr 2,100.00 128,940.00
###
2.00 Dumptruck (300 cum/day) 61.40 hr 1,650.00 101,310.00
###
1702 (1)a Structure Excavation 6,304.00 cu.m 342.81 2,161,058.00 306.08 1,929,516.07 945,600.00###
1.00 Backhoe with Bucket (200 cum/day) 252.16 hr 2,100.00 529,536.00
###
2.00 Dumptruck (200 cum/day) 252.16 hr 1,650.00 416,064.00
###
1704 (1)b Embankment 150,771.00 cu.m 109.70 16,539,333.81 97.94 14,767,262.33 20,040,945.23###
1.00 Grader (300 m3/day) 4,020.56 hr 2,700.00 10,855,512.00
###
2.00 Roller (300 m3/day) 4,020.56 hr 1,900.00 7,639,064.00
###
3.00 Water Truck (300m3/day) 19.33 mo. 80,000.00 1,546,369.23
###
1705 (1) Fill and Backfill 4,617.00 cu.m 109.70 506,477.40 97.94 452,211.97 613,705.85###
1.00 Grader (300 m3/day) 123.12 hr 2,700.00 332,424.00
###
2.00 Roller (300 m3/day) 123.12 hr 1,900.00 233,928.00
###
3.00 Water Truck (300m3/day) 0.59 mo. 80,000.00 47,353.85
###
1705 (2) Backfill 2,118.00 cu.m 109.70 232,341.16 97.94 207,447.46 411,435.08###
1.00 Grader (200 m3/day) 84.72 hr 2,700.00 228,744.00
###
2.00 Roller (200 m3/day) 84.72 hr 1,900.00 160,968.00
###
3.00 Water Truck (300m3/day) 0.27 mo. 80,000.00 21,723.08
###
17010 (1)c Riprap 20,432.00 cu.m 34.28 700,424.13 30.61 625,378.69 2,451,792.00###
1.00 Backhoe with Bucket (200 cum/day) 1,167.52 hr 2,100.00 2,451,792.00
###
One Bagger Mixer (200 cum/day) ###
Water Truck (200 m3/day) ###
17010 (3) Filter Layer of Granular Material 3,811.00 cu.m 109.70 418,060.51 97.94 373,268.31 759,854.77###
1.00 Grader (200 m3/day) 152.44 hr 2,700.00 411,588.00
###
2.00 Roller (200 m3/day) 152.44 hr 1,900.00 289,636.00
###
3.00 Water Truck (200m3/day) 0.73 mo. 80,000.00 58,630.77
###
Prepared by:
GINA B. CASIS
QS Supv. - PMO
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
Cagayan de Oro City
Support Equipment
1.00 Walk Behind Compactor 1.00 1,040.00 hrs 2.00 40.18 83,571.43
2.00 Tamping Rammer 1.00 520.00 hrs 1.20 40.18 25,071.43
3.00 Service Vehicle 2.00 1,092.00 hrs 6.00 40.18 526,500.00
4.00 Concrete Vibrator 1.00 832.00 hrs 0.45 40.18 15,042.86
5.00 Water Pump 1.00 832.00 hrs 0.45 40.18 15,042.86
6.00 Concrete Cutter 1.00 832.00 hrs 0.45 40.18 15,042.86
7.00 Scrader Machine 1.00 832.00 hrs 0.45 40.18 15,042.86
-
TOTAL FUEL & SUPPORT EQUIPMENT VAT EXCLUSIVE, Php 808,682.71 722,038.14 4,076,814.29
808,682.71
-
GINA B. CASIS
QS Supv. - PMO
24
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
B.7 (1) Occupational Safety and Health Program 918,723.90 - 820,289.19 642,240.00###
First Aide Facilities & Equipment (Rental) 425,081.21 425,081.21 379,536.79 379,536.79 ###
1.00 lot 1.00 lot 534,240.00 534,240.00
PPE's ###
Medical Supplies, Sanitation 24.00 20,568.45 493,642.69 18,364.68 440,752.40 1.00 lot 108,000.00 108,000.00###
###
Safety Officer (1) 24.00 mos 40,382.71 36,056.00 ###
Safety Aide - - Transfered to Indirect - ###
Transfered to Indirect Manpower
Project Nurse (1) 24.00 mos 32,840.95 Manpower 29,322.28 ###
Security Guard (2) 24.00 mos 34,280.74 30,607.81
Lowbed / Flatbed Trailer Truck - mobilization (actual: Heavy & Light Equipment) ###
CHECKING>>>> 12,810,171.44
Prepared by:
GINA B. CASIS
QS Supv. - PMO
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
Cagayan de Oro City
CHECKING>>>> 21,246,581.26
CHECKING>>>>
Selling / Contract 55,534,846.36 28,887,150.51 27,713,675.01
Variance 23,181,237.79 - (8,176,588.79)
Prepared by:
GINA B. CASIS
QS Supv. - PMO
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
Cagayan de Oro City
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) - 1,810,023.20 - 1,616,092.14 960,000.00
Field Office 200 sq.m 8,227.38 1,645,475.64 7,345.87 1,469,174.68 24.00 month 40,000.00 960,000.00
Parking Area 60 sq.m 2,742.46 164,547.56 2,448.62 146,917.47 - -
-
A.1.1 (9) Provision of Field Laboratory for the Engineer (Rental Basis) - 658,190.25 - 587,669.87 528,000.00
Field Laboratory 80 sq.m 8,227.38 658,190.25 7,345.87 587,669.87 24.00 month 22,000.00 528,000.00
-
A.1.1 (10) Provision of Living Quarters for the Engineer (Rental Basis) - 658,190.25 - 587,669.87 360,000.00
Living Quarters 80 sq.m 8,227.38 658,190.25 7,345.87 587,669.87 24.00 month 15,000.00 360,000.00
-
-
A.1.1 (11) Provision of Furnitures/Fixtures, Equipment & Appliances for the Field Office of the Engineer - 1,777,113.69 - 1,586,708.65 1,188,500.00
Sofa Set 1.00 set 27,424.59 27,424.59 24,486.24 24,486.24 1.00 set 13,500.00 13,500.00
Desk, 1.50 m x 0.70 m x 0.75 m 7.00 set 6,856.15 47,993.04 6,121.56 42,850.93 7.00 set 3,000.00 21,000.00
Conference Table, W240 x D100 x H750 1.00 set 21,939.68 21,939.68 19,589.00 19,589.00 1.00 set 14,000.00 14,000.00
Chairs for Conference and Reference Table 14.00 set 4,799.30 67,190.26 4,285.09 59,991.30 14.00 set 2,000.00 28,000.00
6-drawer Plan Cabinet 1.00 set 20,568.45 20,568.45 18,364.68 18,364.68 1.00 set 25,000.00 25,000.00
Lockable 3-drawer Filing Cabinet 2.00 set 13,712.30 27,424.59 12,243.12 24,486.24 2.00 set 9,000.00 18,000.00
Cupboard with Shelves 1.00 set 6,856.15 6,856.15 6,121.56 6,121.56 1.00 set 4,000.00 4,000.00
Whiteboard, Wall Type, 1.20 m x 1.80 m 1.00 set 4,799.30 4,799.30 4,285.09 4,285.09 1.00 set 2,500.00 2,500.00
Total Station (350 m Reflectorless and Accessories 1.00 set 479,930.39 479,930.39 428,509.28 428,509.28 1.00 set 250,000.00 250,000.00
Level Automatic, AT-B4 A Topcon 1.00 set 68,561.48 68,561.48 61,215.61 61,215.61 1.00 set 18,500.00 18,500.00
Tape Steel (Nylon Coated) 100 m - XBR 100 XBOE 1.00 set 13,712.30 13,712.30 12,243.12 12,243.12 1.00 set 4,500.00 4,500.00
Photocopy Machine with Printer and Scanner complete with Sorter and Accessories 1.00 set 54,849.19 54,849.19 48,972.49 48,972.49 1.00 set 115,000.00 115,000.00
Desktop Computer with 2TB Hard Disk, 4GB Memory and 2GB Video Card 5.00 set 82,273.78 411,368.91 73,458.73 367,293.67 5.00 set 55,500.00 277,500.00
Digital Camera 1.00 each 34,280.74 34,280.74 30,607.81 30,607.81 1.00 each 45,000.00 45,000.00
Air Conditioner Window Type 1.5 Hp 5.00 set 41,136.89 205,684.45 36,729.37 183,646.83 5.00 set 25,000.00 125,000.00
Electric Fan (Stand Type) 3.00 each 2,056.84 6,170.53 1,836.47 5,509.41 3.00 each 1,500.00 4,500.00
Refrigerator (16 cu.ft.) 1.00 unit 54,849.19 54,849.19 48,972.49 48,972.49 1.00 unit 31,000.00 31,000.00
Wall Clock 2.00 set 1,371.23 2,742.46 1,224.31 2,448.62 2.00 set 1,500.00 3,000.00
Fax Machine 1.00 set 10,969.84 10,969.84 9,794.50 9,794.50 1.00 set 8,000.00 8,000.00
Television Set (40-in. LED) 1.00 set 27,424.59 27,424.59 24,486.24 24,486.24 1.00 set 18,000.00 18,000.00
Water Dispenser / Water Cooler 1.00 set 6,856.15 6,856.15 6,121.56 6,121.56 1.00 set 6,500.00 6,500.00
Coffee Set 1.00 set 4,113.69 4,113.69 3,672.94 3,672.94 1.00 set 1,000.00 1,000.00
A4 Paper 100.00 reams 274.25 27,424.59 244.86 24,486.24 100.00 reams 300.00 30,000.00
A3 paper 50.00 reams 685.61 34,280.74 612.16 30,607.81 50.00 reams 900.00 45,000.00
Toner of Photocopy Machine 10.00 set 10,969.84 109,698.38 9,794.50 97,944.98 10.00 set 8,000.00 80,000.00
A.1.1 (13) Provision of Furnitures/Fixtures, Equipment & Appliances for the Living Quarters of the Engineer - 323,610.21 - 288,937.69 215,000.00
Sofa Set 1.00 set 27,424.59 27,424.59 24,486.24 24,486.24 1.00 set 13,500.00 13,500.00
Dining Table (8-Seater) 1.00 set 34,280.74 34,280.74 30,607.81 30,607.81 1.00 set 35,000.00 35,000.00
Air Conditioner Window Type 1.5 Hp 2.00 set 41,136.89 82,273.78 36,729.37 73,458.73 2.00 set 17,000.00 34,000.00
Electric Fan (Stand Type) 3.00 each 2,056.84 6,170.53 1,836.47 5,509.41 3.00 each 1,500.00 4,500.00
Refrigerator (16 cu.ft.) 1.00 Nos. 54,849.19 54,849.19 48,972.49 48,972.49 1.00 Nos. 31,000.00 31,000.00
Television Set (40-in. LED) 1.00 set 27,424.59 27,424.59 24,486.24 24,486.24 1.00 set 18,000.00 18,000.00
LPG Gas, 11kg/tank 24.00 month 1,371.23 32,909.51 1,224.31 29,383.49 24.00 month 1,500.00 36,000.00
Water Dispenser / Water Cooler 1.00 set 6,856.15 6,856.15 6,121.56 6,121.56 1.00 set 6,500.00 6,500.00
Gas Stove (2-Burner with Accessories) 1.00 set 3,428.07 3,428.07 3,060.78 3,060.78 1.00 set 2,500.00 2,500.00
Coffee Set 1.00 set 4,113.69 4,113.69 3,672.94 3,672.94 1.00 set 1,000.00 1,000.00
Wall Clock 2.00 set 1,371.23 2,742.46 1,224.31 2,448.62 2.00 set 1,500.00 3,000.00
King Size Bed 2.00 each 20,568.45 41,136.89 18,364.68 36,729.37 2.00 each 15,000.00 30,000.00
A.1.1 (14) Provision of Laboratory Testing Equipment, Apparatus and Publications for the Engineer - 342,807.42 - 306,078.06 700,000.00
Laboratory Testing Equipment, Apparatus 1.00 lot 342,807.42 342,807.42 306,078.06 306,078.06 1.00 lot 700,000.00 700,000.00
& Publications
A.1.1 (16) Operation and Maintenance of Field Office for the Engineer - 987,285.38 - 881,504.81 2,040,000.00
Water Consumption 24.00 mos 6,856.15 164,547.56 6,121.56 146,917.47 24.00 month 20,000.00 480,000.00
Power Consumption 24.00 mos 20,568.45 493,642.69 18,364.68 440,752.40 24.00 month 35,000.00 840,000.00
Maintenance Cost 24.00 mos 13,712.30 329,095.13 12,243.12 293,834.94 24.00 month 30,000.00 720,000.00
- - - -
Security Guard - - -
Utility Man - - - - -
A.1.1 (17) Operation and Maintenance of Laboratory Building for the Engineer - 822,737.82 - 734,587.34 780,000.00
Water Consumption 24.00 mos 6,856.15 164,547.56 6,121.56 146,917.47 24.00 month 5,500.00 132,000.00
Power Consumption 24.00 mos 13,712.30 329,095.13 12,243.12 293,834.94 24.00 month 21,500.00 516,000.00
Maintenance Cost 24.00 mos 13,712.30 329,095.13 12,243.12 293,834.94 24.00 month 5,500.00 132,000.00
- - - -
Utility Man - - -
- - - -
- - - -
A.1.1 (18) Operation and Maintenance of Living Quarters for the Engineer - 658,190.25 - 587,669.87 667,200.00
Water Consumption 24.00 mos 6,856.15 164,547.56 6,121.56 146,917.47 24.00 month 8,100.00 194,400.00
Power Consumption 24.00 mos 6,856.15 164,547.56 6,121.56 146,917.47 24.00 month 16,200.00 388,800.00
Maintenance Cost 24.00 mos 13,712.30 329,095.13 12,243.12 293,834.94 24.00 month 3,500.00 84,000.00
- - - -
Utility Man - - -
A.1.2 (1) Provision of 4x4 Pick Up Type Service Vehicles for the Engineer - 4,113,689.09 - 3,672,936.69 2,800,000.00
4x4 Pick Up Type Service Vehicle 2.00 each 2,056,844.55 4,113,689.09 1,836,468.34 3,672,936.69 2.00 unit 1,400,000.00 2,800,000.00
-
A.1.2 (5) Operation and Maintenance of 4x4 Pick Up Type Service Vehicles for the Engineer - 2,148,662.09 - 1,918,448.29 1,440,000.00
Maintenance Cost 24.00 mos 13,712.30 329,095.13 12,243.12 293,834.94 24.00 mos. 20,000.00 480,000.00
Fuel (Diesel) Consumption (200 liters each per month) 9,600.00 liters 61.71 592,371.23 55.09 528,902.88 24.00 mos. 40,000.00 960,000.00
- - - -
Driver 24.00 mos 45,250.58 1,086,013.92 40,402.30 969,655.29 -
a.) 13th Month, SSS, Pag-ibig, Philhealth, etc. (13%) 1.00 lot 141,181.81 141,181.81 126,055.19 126,055.19
TOTAL FACILITIES OF THE ENGR. VAT EXCLUSIVE, Php 14,465,047.23 12,915,220.74 11,837,100.00
CHECKING>>>>
Prepared by:
GINA B. CASIS
QS Supv. - PMO
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
Cagayan de Oro City
Direct - -
a.) Foreman (2) 24.00 mos. 25,642.00 22,894.64
b.) Warehouseman (1) 24.00 mos. 22,625.29 20,201.15
c.) Time Keeper (1) 24.00 mos. 22,625.29 20,201.15
d.) Utility / Messenger (2) 24.00 mos. 19,128.65 17,079.16
e.) Service Driver (1) 24.00 mos. 22,625.29 20,201.15
f.) Assistant Warehouseman (2) 24.00 mos. 19,128.65 17,079.16
g.) 13th Month, SSS, Pag-ibig, Philhealth, etc. (13%) 1.00 lot 610,504.37 545,093.19
Communication Expenses 24.00 mos. 3,428.07 82,273.78 3,060.78 73,458.73 24.00 mos 10,000.00 240,000.00
Courier and Postage 24.00 mos 25,000.00 600,000.00
Transportation Expenses 24.00 mos. 6,856.15 164,547.56 6,121.56 146,917.47 24.00 mos 75,000.00 1,800,000.00
Site Meetings and Representation 24.00 mos. 13,712.30 329,095.13 12,243.12 293,834.94 24.00 mos 170,000.00 4,080,000.00
Facilitation of Billing Representation 12.00 mos 50,000.00 600,000.00
Personnel Accident Insurance 100.00 men 685.61 68,561.48 612.16 61,215.61 100.00 men 500.00 50,000.00
Key Personnel Health Benefits 20.00 men 49,364.27 987,285.38 44,075.24 881,504.81 20.00 men 15,000.00 300,000.00
Checking>>>. 14,722,377.95
-
CHECKING>>>>
Selling / Contract 32,979,970.78 29,446,402.48
Variance (0.01) (0.01)
GINA B. CASIS
QS Supv. - PMO
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
Cagayan de Oro City
Prepared by:
GINA B. CASIS
QS Supv. - PMO
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
Cagayan de Oro City
CHECKING>>>
Prepared by:
QS Supv. - PMO
Flood Risk Management Project for Cagayan de Oro River (FRIMP-CDOR)
(JICA Loan Agreement No. PH-P259) Contract Package 1 (Bonbon-Kauswagan)
Cagayan de Oro City
SUBCONTRACT ITEMS
Prepared by:
GINA B. CASIS
QS Supv. - PMO
DIRECT MANPOWER BUDGET
BASIC RATE
No. of Project Duration GRAND TOTAL
No. Designation Qty Unit 13th Month SSS SSS PHILHEALTH PHILHEALTH PAG-IBIG PAG-IBIG
Manpower (Months) (Vat Ex)
MONTHLY DAILY TOTAL
1.00 Carpenter 6.00 21.00 3,276.00 Mandays 9,880.00 380.00 1,244,880.00 103,740.00 810.00 102,060.00 137.50 17,325.00 100.00 12,600.00 1,480,605.00
2.00 Mason 10.00 22.00 5,720.00 Mandays 9,880.00 380.00 2,173,600.00 181,133.33 810.00 178,200.00 137.50 30,250.00 100.00 22,000.00 2,585,183.33
3.00 Steelman 4.00 10.00 1,040.00 Mandays 9,880.00 380.00 395,200.00 32,933.33 810.00 32,400.00 137.50 5,500.00 100.00 4,000.00 470,033.33
4.00 Welder 2.00 3.00 156.00 Mandays 9,880.00 380.00 59,280.00 4,940.00 810.00 4,860.00 137.50 825.00 100.00 600.00 70,505.00
5.00 RCP Installer/Fitter 2.00 8.00 416.00 Mandays 9,880.00 380.00 158,080.00 13,173.33 810.00 12,960.00 137.50 2,200.00 100.00 1,600.00 188,013.33
6.00 Laborer/Helper 35.00 23.00 20,930.00 Mandays 9,490.00 365.00 7,639,450.00 636,620.83 770.00 619,850.00 137.50 110,687.50 100.00 80,500.00 9,087,108.33
TOTAL AMOUNT, Php 59.00 11,670,490.00 972,540.83 950,330.00 166,787.50 121,300.00 13,881,448.33
INDIRECT MANPOWER BUDGET
Project
No. of BASIC RATE
No. Designation Duration Qty Unit 13th Month SSS PHILHEALTH PAG-IBIG
Manpower
(Months)
MONTHLY DAILY TOTAL
1.00 Project Manager 1.00 24.00 624.00 Mandays 70,000.00 2,692.31 1,680,000.00 140,000.00 39,120.00 13,200.00 2,400.00
2.00 Project Engineer 1.00 23.00 598.00 Mandays 40,000.00 1,538.46 920,000.00 76,666.67 37,490.00 12,650.00 2,300.00
3.00 Field Engineer 2.00 23.00 1,196.00 Mandays 18,000.00 692.31 828,000.00 69,000.00 67,620.00 7,115.74 4,600.00
4.00 Safety Head 1.00 24.00 624.00 Mandays 18,000.00 692.31 432,000.00 36,000.00 35,280.00 3,712.56 2,400.00
5.00 Materials Engineer 1.00 24.00 624.00 Mandays 45,000.00 1,730.77 1,080,000.00 90,000.00 39,120.00 13,200.00 2,400.00
6.00 Survey Engineer 1.00 24.00 624.00 Mandays 25,000.00 961.54 600,000.00 50,000.00 39,120.00 3,712.56 2,400.00
7.00 Office Engineer I 1.00 23.00 598.00 Mandays 18,000.00 692.31 414,000.00 34,500.00 33,810.00 3,557.87 2,300.00
8.00 Office Engineer II 1.00 14.00 364.00 Mandays 24,250.00 932.69 339,500.00 28,291.67 22,820.00 2,165.66 1,400.00
9.00 Head - Office Engineer 1.00 4.00 104.00 Mandays 27,250.00 1,048.08 109,000.00 9,083.33 6,520.00 1,397.56 400.00
10.00 Safety Officer / Safety Engineer 1.00 16.00 416.00 Mandays 18,000.00 692.31 288,000.00 24,000.00 23,520.00 2,475.04 1,600.00
11.00 Autocad Operator 1.00 8.00 208.00 Mandays 14,000.00 538.46 112,000.00 9,333.33 9,040.00 1,237.52 800.00
12.00 QA/QC Aide 2.00 22.00 1,144.00 Mandays 14,000.00 538.46 616,000.00 51,333.33 49,720.00 6,806.36 4,400.00
13.00 Survey Aide 3.00 22.00 1,716.00 Mandays 14,000.00 538.46 924,000.00 77,000.00 74,580.00 10,209.54 6,600.00
14.00 Instrument Man 1.00 24.00 624.00 Mandays 14,000.00 538.46 336,000.00 28,000.00 27,120.00 3,712.56 2,400.00
15.00 Project Accountant 1.00 24.00 624.00 Mandays 17,000.00 653.85 408,000.00 34,000.00 33,360.00 3,712.56 2,400.00
16.00 Project HR 1.00 14.00 364.00 Mandays 15,000.00 576.92 210,000.00 17,500.00 17,220.00 2,165.66 1,400.00
17.00 Timekeeper 1.00 23.00 598.00 Mandays 11,000.00 423.08 253,000.00 21,083.33 20,470.00 3,162.50 2,300.00
18.00 Document Controller / Custodian 1.00 23.00 598.00 Mandays 15,000.00 576.92 345,000.00 28,750.00 28,290.00 3,557.87 2,300.00
19.00 Project Nurse 1.00 23.00 598.00 Mandays 14,000.00 538.46 322,000.00 26,833.33 25,990.00 3,557.87 2,300.00
20.00 Warehouseman 2.00 23.00 1,196.00 Mandays 15,000.00 576.92 690,000.00 57,500.00 56,580.00 7,115.74 4,600.00
21.00 Warehouseman Aide 1.00 23.00 598.00 Mandays 10,000.00 384.62 230,000.00 19,166.67 18,630.00 3,162.50 2,300.00
22.00 Gen. Foreman 1.00 20.00 520.00 Mandays 16,000.00 615.38 320,000.00 26,666.67 26,200.00 3,093.80 2,000.00
23.00 Foreman- Concrete Roads 1.00 12.00 312.00 Mandays 16,000.00 615.38 192,000.00 16,000.00 15,720.00 1,856.28 1,200.00
24.00 Leadman- Drainage/Slope 1.00 12.00 312.00 Mandays 15,600.00 600.00 187,200.00 15,600.00 14,760.00 1,856.28 1,200.00
25.00 Service Driver 3.00 22.00 1,716.00 Mandays 11,000.00 423.08 726,000.00 60,500.00 58,740.00 9,075.00 6,600.00
26.00 Traffic aide 6.00 22.00 3,432.00 Mandays 10,000.00 384.62 1,320,000.00 110,000.00 106,920.00 18,150.00 13,200.00
27.00 Watchman Office 2.00 18.00 936.00 Mandays 10,000.00 384.62 360,000.00 30,000.00 29,160.00 4,950.00 3,600.00
28.00 Watchman Pagatpat Quarry 1.00 16.00 416.00 Mandays 10,000.00 384.62 160,000.00 13,333.33 12,960.00 2,200.00 1,600.00
29.00 Watchman Canitoan Quarry 1.00 16.00 416.00 Mandays 10,000.00 384.62 160,000.00 13,333.33 12,960.00 2,200.00 1,600.00
30.00 Utility 1.00 19.00 494.00 Mandays 10,000.00 384.62 190,000.00 15,833.33 15,390.00 2,612.50 1,900.00
1,874,720.00
1,049,106.67
976,335.74
509,392.56
1,224,720.00
695,232.56
488,167.87
394,177.33
126,400.89
339,595.04
132,410.85
728,259.69
1,092,389.54
397,232.56
481,472.56
248,285.66
300,015.83
407,897.87
380,681.20
815,795.74
273,259.17
377,960.47
226,776.28
220,616.28
860,915.00
1,568,270.00
427,710.00
190,093.33
190,093.33
225,735.83
17,223,719.86
17,223,719.86
-
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon and Kauswagan, Cagayan De Oro City
ITEM NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL (VAT EX)
18
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO RIVER
Brgy. Bonbon and Kauswagan, Cagayan De Oro City
1,500,000.00
350,000.00
1,850,000.00
1098 - FLOOD RISK MANAGEMENT PROJECT FOR CAGAYAN DE ORO
RIVER
Brgy. Bonbon and Kauswagan, Cagayan De Oro City
ITEM NO. DESCRIPTION UNIT QUANTITY UNIT COST TOTAL (VAT EX)
19
SURETY BOND (Down Payment Bond)
Contract Amount 375,000,000.00
PERFORMANCE BOND
Contract Amount 375,000,000.00
GUARANTEE BOND
Contract Amount 375,000,000.00
CARI
Contract Amount 375,000,000.00
CGLI
Contract Amount 375,000,000.00
ANNEXES
Page 15 of 15
IPM CONSTRUCTION AND DEVELOPMENT CORPORATION
GUIMBA LANDFILL
Brgy. Lennec, Guimba Nueva Ecija
TABLE OF CONTENTS
- Page -
• Notice To Award - 1 -
• Notice To Proceed - 2 -
• Contract - 3-5 -
• Original Plan - 6 - 22 -
• Revised Plan - 23 - 41 -
Reference Subcon Budget
BUDGET
Item No. DESCRIPTION
QUANTITY UNIT Unit Price Amount (VAT Ex)
311(1)f1 Portland Cement Concrete Pavement Unreinforced 300mm
Supply of Labor for Formworks & Concreting 9,380.00 m2 60.00 562,800.00
Supply of Labor for bending of forms 1.00 lot 300,000.00 300,000.00
1710(1)c Riprap
Supply of Labor 14,594.00 m3 585.00 8,537,490.00
610(1) SODDING
Supply of Materials, Labor except top soil 23,090.00 m2 90.00 2,078,100.00