RECOMPLETION PROGRAM

BK-7
Name Position Signature Date
19 Aug 2023
Janico Zaverson M. Engineer Well
Prepared by :
O. Intervention

Sr Eng Petroleum Area


Prepared by : Hendro Vico
1

Sr Engineer Well
Prepared by : Hiban Hardanu
Intervention 19 Aug 2023

Reviewed by : Priantoro K.D.S. Sr. GGR Area 1

Assistant Manager
Reviewed by : -
Engineer WI

Assistant Manager
Reviewed by : Kristianto Wibowo
Operation WI 21 Aug 2023

Manager Well
Reviewed by : Budi Rivai Wijaya 21 Aug 2023
Intervention

Manager Subsurface
Reviewed by : Achmad Mansur
Development Area 1
Sr. Manager
Subsurface
Approved by : Ridwan Widijanto
Development &
Planning

Distribution:
Wirdan Arifin PHE ONWJ Production Senior Manager
Yan Heru H PHE ONWJ Sr Engineer Well Integrity Planning
Guspan H / Dwiputra K / S Zamroni / Company Man PHE ONWJ
Kadek P
Aziz Yandar Elnusa HWU Representative
Satriya Galih Wismawan Schlumberger Completion Representative
Alexander / Teddy Seik / Yahya Weatherford Fishing Tool & WBCO Representative
Hendro Mahambiro RDM Wellhead & X-Mas Tree Representative
Efrizal Nesitor Slickline Representative
Donny H / Arini M BDSI E-Line Representative
Cep N / Galih S.P / Yoel IKE Tubing Handling
Bobby Eka / Arizal Hallco Completion Representative
Raisya Maryam Hallco Coiled Tubing Unit / Cementing
Adi Lukminto Hallco Baroid Representative
BK-7 Operations File

BK-7 Recompletion Program Page 2 of 27 Juli, 2023


Table of Contents

LIST OF ATTACHMENTS............................................................................................... 4

1. GENERAL WELL INFORMATION ..................................................................... 5


1.1. BACKGROUND ................................................................................................. 5
1.2. OBJECTIVES ..................................................................................................... 5
1.3. KEY PERFORMANCE INDICATORS ................................................................ 5
1.4. WELL INFORMATION ....................................................................................... 5
1.5 WORKOVER OPERATION SUMMARY .......................................................... 10

2. DRILLING/WORKOVER ASSURANCE ........................................................... 18


2.1. SIMOPS ........................................................................................................... 18
2.2. PLATFORM HANDOVER ................................................................................ 18
2.3. PRE-JOB & RIG ACCEPTANCE ..................................................................... 19

3. TECHNICAL INFORMATION ........................................................................... 20


3.1. CASING DATA ................................................................................................. 20
3.3. WELLHEAD & TREE DATA ............................................................................. 20

4. WELL COMPLETION INFORMATION ............................................................ 23


4.1 WELL INFORMATION. .................................................................................... 23
4.2 WELL PROPERTIES. ...................................................................................... 23
4.3 PERFORATION PROGRAM. ........................................................................... 23
4.4 STIMULATION PROGRAM............................................................................. 23
4.5 FLUID PROGRAM. .......................................................................................... 24
4.6 DRAFT PROPOSED DIAGRAM ...................................................................... 26
4.7 TUBULAR TYPE. ............................................................................................. 24
4.8 COMPLETION DATA. ...................................................................................... 24
4.9 ESTIMATED MATERIAL REQUIREMENT. ..................................................... 24
4.10 POST COMPLETION. ...................................................................................... 25

BK-7 Recompletion Program Page 3 of 27 Juli, 2023


List of Attachments
1. Recompletion Program
2. Completion Program
3. Well Trajectory
4. Well Summary and History
5. Existing Completion installation report
6. Fishing tree diagram
7. Fluid program
8. E-line Program
9. Fracturing Program
10. Isolation Program
11. Wellhead and X-mas Tree program

BK-7 Recompletion Program Page 4 of 27 Juli, 2023


1. GENERAL WELL INFORMATION
1.1. BACKGROUND

BK-7 well was infill well that completed in October 1999 which initially
produce from B-58/59/60 with gas lift. Initial production for this well in November
1999 is 905 BFPD, 899 BOPD and WC 0.7%. In Dec 2019, B-58/59/60 were
isolated due to low performance and high watercut. Since then, BK-7 produced
from B-57A/B/C.

In April 2023, BK-7 well experience low production performance with well
test 163 BFPD, 8 BOPD, and WC 95%. Previously, in March 2023 this still
producing 2537 BFPD, 761 BOPD, and WC 70%. Based on the production
evaluation, tubing-casing communication depth are in GLM#2 & GLM#3. Several
effort to perform GLVR job has done but not success, KOT couldn’t latch to GLV
F/N. Downhole camera was run to identify the the current condition in GLM#2 &
GLM#3 depth, the result showed that those 2 GLM are in high side of tubing with
40 deg inclination. Concentric GL with Pack off were installed in GLM#2 &
GLM#3 but still tubing casing communication. The well BOL with lower rate, 790
BFPD, 71 BOPD, and WC 90%.

To return optimum production performance of BK-7 Well, need to deepening


gas lift Injection by Pulling out existing Completion (unset LSA) and Install 3-1/2”
Single String completion with new gaslift design.

1.2. OBJECTIVES
1.2.1. To perform Recompletion job without accidents, no harm to people, and
no damage to the environment as PHE ONWJ HSE Goals.
1.2.2. Cut Tubing and POOH Existing Completion
1.2.3. Wellbore Clean Out
1.2.4. Complete the well with new 3-1/2” single selective completion by Sting In
Overshot Guide into Existing tubing.

1.3. KEY PERFORMANCE INDICATORS


1.3.1. Operation meets PHE ONWJ HSSE goals.
1.3.2. Well completion days meet approval job days.
1.3.3. Operation cost meet approval job cost.

1.4. JOB INFORMATION


JOB TIME 9.65 days
JOB COST USD 1,200,503 (include tax 11%)
Intangible = USD 1,010,207

BK-7 Recompletion Program Page 5 of 27 Juli, 2023


Tangible = USD 190,297

1.5. WELL DATA

Well Depth (PBTD) 7,508 ft md

RKB Elevation 55.79 ft

Profile Directional Well

Max Inclination 43.2° at 3,514 ft md

Existing Completion Type Single gas lift completion

SCSSV Status Good Condition

Casing 9-5/8”, 47#, L-80, 8.681” ID, BTC


7”, 26#, L-80, 6.276” ID , BTC

Casing Shoe Depth 0 – 4981 ft md (9-5/8”)


4767 – 6794 ft md (7”)

Perforations B-57A 6963 - 6976 ft md

B-57B 7016 - 7032 ft md

B-57C 7040 - 7052 ft md

B-58 7102 - 7120 ft md

B-59A 7206 - 7212 ft md

B-60A 7384 - 7392 ft md

B-60B 7430 - 7445 ft md

1.5.1. Existing Completion Data & Diagram


NO DESCRIPTION MD (ft)
1 Elevation 55.79

BK-7 Recompletion Program Page 6 of 27 Juli, 2023


2 Tubing hanger 0
3 3-1/2” SCSSV 292
4 3-1/2” GLM #1 1,285
5 3-1/2” GLM #2 2,109
6 3-1/2” GLM #3 2,809
7 3-1/2” GLM #4 3,417
8 9-5/8” x 3-1/2” OTIS “MHS” Permanent Packer 4,728
9 3-1/2” X-Nipple 7,294
10 3-1/2” Float Collar 7,508
11 3-1/2” Float Shoe 7,569

1.5.2 Existing Well Diagram

BK-7 Recompletion Program Page 7 of 27 Juli, 2023


BK-7 Recompletion Program Page 8 of 27 Juli, 2023
BK-7 Recompletion Program Page 9 of 27 Juli, 2023
1.1. RECOMPLETION OPERATION SUMMARY

This Recompletion procedure is a guideline for the recompletion operations and


its related services. Personnel are expected to make adjustments as required by
the situation, to maintain safety and performance standards. Significant changes
to the procedure however must be justified in a management of change (MOC)
document.

Step DIMS Coding Description

1 Phase : - Preliminary Operation


Task : - WI team performed Intervention with results : (on 6 June 2023)
- SCSSV, good condition.
- Slickline Release T4 Type (Retrieved WRSV) covered by solid wax.
- SBHP final depth at 7000 ft
- Tubing Clearance to 4728 ft, Packer Depth ok
- Try to Tag SPM#2 & SPM#3 No Mark on IB
- Pack Off and Concentric Gas Lift Installation at SPM #3, Top of
Pack Off at 2810 ft MD, Bottom of Pack Off at 2798 ft MD
- Tubing Clearance Stop at 2800 ft MD (Top of Pack-Off SPM #3)
- Set AD2 Stopper SPM#2 at 2122 ft MD.
- Attempt to Set New 2.5” Receptacle + 10 ft Spacer + 3” G element,
Stopped at 2031 ft MD.
- Tubing Clearance stop at 2122 ft MD
- Running Wire Scratcher down to 2122 ft MD (Top of AD2 Stopper
SPM #2), ok.
- Pack Off and Concentric Gas Lift Installation at SPM #2, ok. Top
Pack Off at 2100 ft MD, Btm Pack Off at 2124 ft MD
- Set 3” T2-Type WRSV at 292 ft MD, ok. (indicated WRSV open at
60 psi

2 Phase: PRE Rig Move In & Install Scaffolding


Task : MOB ✓ Held pre job safety meeting.

✓ Boat and lift boat sails to EJ P/F, approaching EJ platform and


positioned.

✓ Jack up the lift boat and install gangway from lift boat to
platform.

✓ Inspect on platform and fill in well handover checklist.

✓ Install scaffolding to support job on top deck area (if needed)

Note:

• COMPANY’s representative shall involve in platform inspection.

• All finding should be recorded and declared to authority


department.

BK-7 Recompletion Program Page 10 of 27 Juli, 2023


Step DIMS Coding Description

3 Phase: INTERV Slickline Job prior Kill Well


Task : SLICK ✓ Held pre job safety meeting.

✓ Check and record SITP and SICP.

✓ R/U Slickline BOP and lubricator.

✓ Pressure test BOP and lubricator as per procedure.

✓ M/U & RIH GC for tubing clearance until SCSSV.

✓ RIH BTS to ensure SCSSV fully open.

✓ M/U and RIH GC for tubing clearance below SCSSV.

✓ Retrieve Concentric Gas Lift at SPM #2 & SPM #3

✓ Retrieve GLV at GLM #4 / as low as possible.

✓ Laydown Slickline, R/D Slickline BOP & Lubricator.

Note:

• COMPANY’s representative shall witness all testing and record


to Daily WORKOVER Report.

• Keep away from pressurized pipe during pumping.

• All activities should refer to Standard Operating Procedures.

• Any restriction during slickline job, shall follow PHE ONWJ SOP

• If Slickline tools unable to pass thru, prepare Macaroni Pipe as


contingency for clean out inside string as low as possible.

4 Phase: PRE Secure Well


Task : MOB ✓ Held pre job safety meeting.

✓ M/U pumping lines, pressure test lines from 300 psi to 5,000
psi.

✓ Check and record SITP and SICP.

✓ Mixing 8.6 ppg KCL Brine.

✓ Bleed off well pressure and secure the well by pumping down
killing fluid trough the tubing, annulus, and observes the well.

Note:

• COMPANY’s representative shall witness all testing and record


to Daily WORKOVER Report.

• Keep away from pressurized pipe during pumping.

• All activities should be refer to Standard Operating Procedures.

• Company Man onboard will decide actual Completion Fluid

BK-7 Recompletion Program Page 11 of 27 Juli, 2023


Step DIMS Coding Description
weight and volume based on actual well condition.

5 Phase: WHDTR Set BPV, N/D X-mas tree


Task : WHSU ✓ Held pre job safety meeting.

✓ Set BPV into tubing hanger.

✓ Losing all bolt and nut.

✓ N/D X-mas tree.

✓ Connect test Tbg Hgr Retrieving Tool onto Tubing Hanger or


Landing Joint to Tbg Hgr, make sure thread condition in good
condition

Note:

• COMPANY’s Representative shall witness all dismantling


process.

• Ensure isolation energy procedure has been performed before


dismantle X-Tree.

• All lifting equipment should be checked before used.

• Record all finding related of X-Mas tree.

6 Phase: DECOM N/U BOP


Task : RIGU ✓ Held pre job safety meeting.

✓ P/U and stack up mud cross, riser spool, single ram BOP,
annular BOP and bell nipple on the wellhead.

✓ Function test BOP.

Note:

✓ COMPANY’s Representative shall witness all testing and


record to Daily WORKOVER Report

7 Phase: DECOM R/U HWU & Pressure test BOP


Task : RIGU ✓ Held pre job safety meeting.

✓ P/U Work Window onto bell nipple and secure with sufficient
guy lines.

✓ P/U 340K Jack onto the Work Window, secure with sufficient
guy lines. P/U Work Basket, secure with sufficient guy lines.

✓ Connect all hydraulic hoses and lines, Function test same.

Pressure test BOP as per BOP test procedure.

Note:

BK-7 Recompletion Program Page 12 of 27 Juli, 2023


Step DIMS Coding Description

• COMPANY’s Representative shall witness all testing and


record to Daily WORKOVER Report

• KB Elevation 55.79 feet will be the corrected reference for all


reported well depths.

8 Phase: DECOM Unset Packer and POOH Existing Completion


Task : PULL ✓ Held pre job safety meeting.

✓ Unset & Retrieve LSA until 80% tensile 3-1/2” tubing L-80.
POOH & L/D Existing 3-1/2” 9.3# L-80 EUE tubing, 3-1/2”
SCSSV, 3-1/2” GLM, and 3-1/2” LSA to surface.

✓ Continue to step #11 (Perform WBCO)

✓ If LSA unable to be unset, continue to step #9 (Cut Tubing


above Packer)

Note:

• In case pulling weight close to tubing yield strength, assess and


discuss to overcome the problem and retry to unset tubing
hanger

• Keep fill up the well for well control.

• Avoid any material drop into the hole and observe for down
holes equipment damage while pulling out

• Re-tight tubing hanger screw after pulling out tubing hanger.

• Record all finding while POOH existing completion

9 Phase: DECOM Tubing Cut above Packer with E-line Mechanical Pipe Cutter (MPC) -
Task : PULL Contingency

✓ Held pre job safety meeting.

✓ R/U e-line unit and pressure test as per procedure.

✓ M/U and RIH MPC tools c/w GR - CCL on Existing String to


target cut 4725’ (Above Packer at 4728’)

✓ Perform cut tubing POOH.

✓ R/D E-line unit.

Note:

• Avoid any material drop into the hole and observe for down

BK-7 Recompletion Program Page 13 of 27 Juli, 2023


Step DIMS Coding Description
holes equipment damage while pulling out
• If MPC unable to reach plan cut point depth, contingency to run
Macaroni String assy for clean out inside string

10 Phase: DECOM POOH Existing Completion - Contingency


Task : PULL ✓ Held pre job safety meeting.

✓ POOH Cut Tubing until 80% tensile 3-1/2” tubing L-80. POOH
& L/D Existing 3-1/2” 9.3# L-80 EUE tubing, 3-1/2” SCSSV, 3-
1/2” GLM, and 3-1/2” Cut Tubing to surface.

✓ Continue to step #11 (Perform WBCO)

Note:

• In case pulling weight close to tubing yield strength, assess and


discuss to overcome the problem and retry to unset tubing
hanger

• Keep fill up the well for well control.

• Avoid any material drop into the hole and observe for down
holes equipment damage while pulling out

• Re-tight tubing hanger screw after pulling out tubing hanger.

• Record all finding while POOH existing completion

11 Phase: DECOM Well Bore clean out


Task : CLEAN ✓ Held pre job safety meeting.
✓ M/U 8-1/2” Rock Bit + 9-5/8” casing scraper + WBCO BHA.
✓ RIH Bit & Casing scrapper assy with 3-1/2” DP until tag top of
Cut Tubing (4725’).
✓ Perform reverse circulation min 1.5 hole cycle until got clean
return.
✓ POOH Bit & casing scraper assy with 3-1/2” DP to surface and
lay down.
✓ Reciprocate interval 4685’ - 4715’ (9-5/8” Packer depth plan at
+/- 4705’)

Note:

• In case pulling weight close to string yield strength, assess and


discuss to overcome the problem and retry to work on string.

• Optional to perform Milling, Casing Swage, Caliper, Downhole

BK-7 Recompletion Program Page 14 of 27 Juli, 2023


Step DIMS Coding Description
Camera if there is any anomaly on Casing or Well Bore during
WBCO.

• Keep fill up the well for well control.

• COMPANY’s Representative shall check all blades of casing


scrapper and record to Daily WORKOVER Report

12 Phase: RUNCM Run New Completion


Task : RUNCO ✓ Held pre job safety meeting.

✓ If Using LSA, M/U Single String Completion = LSA / Mule Shoe,


3-1/2” X-Nipple (Pre-set with Plug), 9-5/8” x 3-1/2” packer, 3-
1/2” SSD & 3-1/2” GLMs (valve installed as per gas lift valve
design).

✓ RIH completion jewelry on String 3-1/2” mod eue tubing.

✓ M/U 3-1/2” SCSSV connect ¼” control line and pressure up


control line to 3,000 psi, then function test the SCSSV. .

✓ RIH SCSSV with 3-1/2” mod eue tubing, continue RIH 3-1/2”
tubing before M/U tubing hanger.

✓ Space Out LSA / Mule Shoe and put mark.

✓ M/U and Land Tbg Hanger.

✓ If Using Overshot Guide, M/U Single String Completion =


Overshot Guide, 3-1/2” X-Nipple (Pre-set with Plug), 9-5/8” x 3-
1/2” packer, 3-1/2” SSD & 3-1/2” GLMs (valve installed as per
gas lift valve design).

✓ RIH completion jewelry on String 3-1/2” mod eue tubing.

✓ M/U 3-1/2” SCSSV connect ¼” control line and pressure up


control line to 3,000 psi, then function test the SCSSV. .

✓ RIH SCSSV with 3-1/2” mod eue tubing, continue RIH 3-1/2”
tubing before M/U tubing hanger.

✓ Allignment, Space Out Overshot Guide and put mark.

✓ M/U and Land Tbg Hanger, ensure Overshot Guide was


engaged properly.

✓ Check Allignment Overshot Guide by Slickline if possible

Notes:

• Ensure to run tubing drift each tubing before RIH.

• Perform integrity test to landing XN-Nipple, SSD, GLM,


SCSSV, and tubing hanger before RIH

• COMPANY’s Representative shall witness all testing and

BK-7 Recompletion Program Page 15 of 27 Juli, 2023


Step DIMS Coding Description
record to Daily WORKOVER Report

13 Phase: RUNCM Set Packer & Retrieve Plug


Task : RUNCO ✓ Held pre job safety meeting.

✓ M/U pumping line.

✓ Test pumping line or test line to 300 psi/5 minutes, increase to


5,000 psi/10 minutes. Bleed off.

✓ Pressure up tubing to 1,500 psi and increase to 2,500 – 3,500


psi to set packer.

✓ Perform backside test packer by pumping through annulus to


500 psi.

✓ Bleed off tubing pressure test to 2,000 psi. Close SCSSV,


perform inflow test in 10 minutes.
✓ R/U Slickline Unit, RIH Gauge Cutter ensure able to reach plug
depth at X-Nipple #1 (4715’), Retrieve Plug at 3-1/2” X-Nipple
#1 (4715’), R/D Slickline Unit.

Note:

✓ COMPANY’s Representative shall witness all testing and


record to Daily WORKOVER Report.

✓ Keep away from pressurized tubing during pressure testing.

14 Phase: POST R/D HWU and N/D BOP


Task : RIGD ✓ Hold pre job safety meeting.

✓ Set BPV on tubing hanger.

✓ R/D Work Basket, 340K Jack, and Work Window.

✓ N/D annular, ram BOPs, and mud cross.

15 Phase: POST N/U X-mas tree


Task : WHSU ✓ Hold pre job safety meeting.

✓ N/U X-mas tree.

✓ Perform cavity test to 1,500 psi.

✓ Set tree test plug and perform X-mas tree test to 3,000 psi.

Note:

✓ COMPANY’s Representative shall witness all testing and


record to Daily WORKOVER Report.

✓ Keep away from pressurized tubing during pressure testing.

BK-7 Recompletion Program Page 16 of 27 Juli, 2023


Step DIMS Coding Description

16 Phase: POST Rig Move out.


Task : DEMOB Clean up platform and handover platform to BK production. Move to
next well. (Final report)

Note :

PHE ONJW Company Man will take pictures / photographs of wellhead


and X-mas tree to be submitted as part of close out report to Engineer.
Please paint on wellhead / X-mas tree to identify well name.

BK-7 Recompletion Program Page 17 of 27 Juli, 2023


2. DRILLING/WORKOVER ASSURANCE

2.1. SIMOPS

Simultaneous operations (SIMOPS) represent one of the most significant


hazards while WORKOVER & Completion perform in this well. To reduce the
risks of incidents, all operations performed on the BK platform will be governed
by the East Java SIMOPS plan. The PHE ONWJ Company Man has been
designated as the Person in Charge (PIC) and will have the ultimate authority to
control simultaneous operations.

The condition of all existing wells on the BK platform has to be checked on a


daily basis by the Production Representative. The status of these checks shall be
reported on the PHE ONWJ Daily Drilling Report. The following information is
required: tubing, casing annulus pressures, status of the well (shut/flow).

The BK platform has active pipelines. Production from the platform will be
allowed to remain active without dispensation, but only during GREEN SIMOPS
activities. Specific precautions to be taken during the BK-7 Recompletion
program are documented in the SIMOPS Meeting Notes.

2.2. PLATFORM HANDOVER

An inspection of the BK platform will be conducted by WORKOVER and


Production Team. Outstanding issues from this inspection are documented in the
Well Handover Checklist. The Bravo Production Superintendent/OIM shall
ensure that the outstanding items are complete before HWU arrives on location.
Upon HWU arrival, both parties shall sign a Platform Handover Form indicating
the condition of the wells/jacket as a formal handover from Production Team to
Well Intervention Team.

Before releasing HWU from the BK platform, the HWU WSL and the Production
Representative shall recheck document and final condition of the wells in the
Platform Handover Form. The Bravo Production Representative / Offshore
Installation Manager shall inspect the wells and jacket (if required) and upon his
satisfaction both parties shall sign the Handover Form as a formal handover from
DWI Team to Production Team.

BK-7 Recompletion Program Page 18 of 27 Juli, 2023


2.3. PRE-JOB & RIG ACCEPTANCE

The following minimum acceptance checks shall be completed to the satisfaction


of PHE ONWJ’s Company Man prior to accepting the Hydraulic WORKOVER rig
on operating rate:

• Review of documentation, inspection records, and certification of all critical


HWU components.

• Visual inspection and function test of all critical HWU systems, particularly
the circulating system, fire fighting equipment and BOP accumulator.

• HWU inspection Checklist properly filled out.

• An emergency evacuation and medical drill will be held prior commencing


the job. The purpose of this drill is to check all emergency contact numbers
and response time.

• A pre job meeting will be conducted with all key persons.

• Filtration unit and filtered sea water (FSW) will be prepared, tested and
ready for use.

• BOP stacks (on test stump) and choke manifold successfully tested from
300 psi until 3,000 psi for 5 / 10 minutes with chart recording.

Note: The 13-5/8” BOP stack is installed on the wellhead, test to 3,000 psi.

• All high pressure pumping lines from mud pump to the stand pipe will be
tested to 300 psi until 5,000 psi.

• Ensure that Hot Work Permits for planned hot work outside designated safe
hot work areas are in process. These permits should be prepared in Jakarta,
approved by the PHE ONWJ GM and sent to HWU prior to any hot work
being initiated.

BK-7 Recompletion Program Page 19 of 27 Juli, 2023


3. TECHNICAL INFORMATION
3.1. CASING DATA

Casing Size Weight Grade / ID (inch) Cap (bbl/ft) Burst (psi) Collapse (psi)
(inch) (lb/ft) Conn.
9-5/8” 47# L-80 8.681 0.07321 6,870 4,760

7” 26# L-80 6.276 0.03826 7,240 5,410

3.2. TUBING DATA


Make
Tubing Weight Grade / ID Drift Burst Coll Tens up
Size (lb/ft) Conn. (inch) ID (psi) (psi) (lbs) Torque
(inch) (inch) Range
(ft/lbs)
L-80 mod
Existing 3-1/2” 9.3 2.992 2.797 9,080 10,180 207,000 3,000
EUE
L-80 mod
Proposed 3-1/2” 9.3 2.992 2.797 9,080 10,180 207,000 3,000
EUE

3.3. WELLHEAD & TREE DATA


Section Type Size Additional Features
A Well Head 13-5/8”-3K x 9 5/8 FMC

B Tubing Head 13-5/8”-3K x 11-3K FMC

C X-mas Tree Single Stack up Tree 3 1/8-3K with


single tubing hanger

BK-7 Recompletion Program Page 20 of 27 Juli, 2023


COMPLETION PROGRAM
BK-7
Name Position Signature Date
19 Aug 2023
Janico Zaverson M. Engineer Well
Prepared by :
O. Intervention

Sr Eng Petroleum Area


Prepared by : Hendro Vico
1

Sr Engineer Well
Prepared by : Hiban Hardanu
Intervention 19 Aug 2023

Reviewed by : Priantoro K.D.S. Sr. GGR Area 1

Assistant Manager
Reviewed by : -
Engineer WI

Assistant Manager
Reviewed by : Kristianto Wibowo
Operation WI 21 Aug 2023

Manager Well 21 Aug 2023


Reviewed by : Budi Rivai Wijaya
Intervention

Manager Subsurface
Reviewed by : Achmad Mansur
Development Area 1

Sr. Manager
Subsurface
Approved by : Ridwan Widijanto
Development &
Planning

Distribution:

Wirdan Arifin PHE ONWJ Production Senior Manager


Yan Heru H PHE ONWJ Sr Eng Well Integrity Planning
Guspan H / Dwiputra K / S Zamroni / Company Man PHE ONWJ
Kadek P
Aziz Yandar Elnusa WORKOVER Representative
Satriya Galih Wismawan Schlumberger Completion Representative
Alexander / Teddy Seik Weatherford Fishing Tool & WBCO Representative
Hendro Mahambiro RDM Wellhead & X-Mas Tree Representative

BK-7 Recompletion Program Page 21 of 27 Juli, 2023


Efrizal Nesitor Slickline Representative
Donny H / Arini M BDSI E-Line Representative
Cep N / Galih S.P / Yoel Indokaya Tubing Handling
Bobby Eka / Arizal Hallco Completion Representative
Raisya Maryam Hallco Coiled Tubing Unit / Cementing
Adi Lukmanto Hallco Baroid Representative
BK-7 Operations File

BK-7 Recompletion Program Page 22 of 27 Juli, 2023


4. Well Completion Information

4.1 Well Information

Proposed
Well Depth RKB Max Incl Isolate Zone
CIT

7508 ft md 55.79 43.2° - -

4.2 Well Properties

Current Temp Depth Depth


Zone Fluid Co2 %
Pr psia °F
Ft MD Ft TVD

B-57A Oil 1400 242 6963’ – 6976’ - -

B-57B Oil 1400 242 7016’ – 7032’ - -

B-57C Oil 1400 242 7040’ – 7052’ - -

B-58 Oil 1400 242 7102’ – 7120’ - -

B-59A Oil 1400 242 7206’ – 7212’ - -

B-60A Oil 1400 242 7384’ – 7392’ - -

B-60B Oil 1400 242 7430’ – 7445’ - -

4.3 Perforation Program


4.3.1 Perforation program
Zone Pay Net Perforation Hole
Depth, FtMD SPF Phasing
Target Zone, ft pay, ft gun size

- - - - - - - -

4.4 Stimulation Program


-

BK-7 Recompletion Program Page 23 of 27 Juli, 2023


4.5 Fluid Program
Hole Section Fluid System Additional Treatments

Completion Fluid 8.6 ppg Brine / FSW +


Lubricants

Loss fluid Brine + Calcium Carbonat

4.6 Tubular Type


OD ID Weight Burst Coll Yield
Tubular Grade Thread
Inch Inch Lbs psi Psi lbs
Tubing 3.500 2.992 9.30 L-80 EUE 6,990 7,400 207,000

4.7 Completion Data


PROPOSED
NO DESCRIPTION DEPTH
(ft md)
1. Tubing hanger 0
2. 3-1/2” SCSSV 400
3. 3-1/2” GLM #1
TBC
4. 3-1/2” GLM #2
TBC
5. 3-1/2” GLM #3
TBC
6. 3-1/2” GLM #4 TBC
7. 3-1/2” GLM #5 4690
9. 9-5/8” x 3-1/2" Retrievable Packer 4705
11. 3-1/2” X-Nipple #1 4715
12. 3-1/2” Overshot Guide / LSA 4725 / 4728
13. 9-5/8” x 3-1/2” OTIS “MHS” Permanent Packer 4728
14. 3-1/2” X-Nipple #2 7294
15. 3-1/2” Float Collar 7508
16. 3-1/2” Float Shoe 7569

4.8 Estimated Material Requirement


NO DESCRIPTION QTY UNIT REMARKS

1 3-1/8-3K Single Stack block X-mas tree 1 Set c/w Adjustable choke

2 13-3/8” x 3-1/2” tubing hanger 1 set

3 3-1/2” SCSSV + ¼” control line + fitting 1 set

4 3-1/2” Gas Lift Mandrel 5 ea

5 3-1/2” X-Nipple 1 ea

6 9-5/8” x 3-1/2” hydraulic retrievable 1 ea

BK-7 Recompletion Program Page 24 of 27 Juli, 2023


packer

7 Overshot Guide for inside 9-5/8” Csg 1 ea

8 Various Pup Joint 3-1/2” 30 ea

9 3-1/2” Mod EUE Tubing 160 Jts

Note:
• All material will be send completed with back up except X-mas tree & tubing
hanger.
• Record all material installed.
• Return and documented remain material to Warehouse.

4.9 Post Completion


• Report final measurements and direction of the outlet flange to the
Production OIM immediately so that final tie-in spool can be fabricated.

• Kick off well as per PHE ONWJ production procedure.

• Clean up BK platform.

• Document the final tree and well status on the Platform Handover Form and
in the Daily report, including: SCSSV position, connection type on top of
tubing hanger.

BK-7 Recompletion Program Page 25 of 27 Juli, 2023


4.10 Draft Proposed Diagram
BK-7 well will be completed by single selective completion type with gas lift.

PROPOSED DIAGRAM
Depth, ft MD
Diagram Accessories Notes
Top Bottom
NOT TO SCALE

3-1/2"
3-1/2" SCSSV
OTIS Wellstar SAFETY VALVE, 2.813" ID 292
400
(Replaced by H-Type)

3-1/2" McMurry GLM GLV


3-1/2" GLM #1 TBC

3-1/2"
3-1/2" GLM #2
McMurry GLM TBC GLV

3-1/2" GLM #3 TBC


3-1/2" McMurry GLM GLV
3-1/2" GLM #4 TBC
3-1/2" McMurry GLM GLV

3-1/2" GLM #5 4.690


9-5/8"
3-1/2" x 3-1/2"
McMurry GLMRetrievable Packer 4.705
4.690 SO 0.25"
3-1/2" X-Nipple #1 4.715
New packer
3-1/2" Overshot Guide 4.720
4.725
9-5/8" OTIS "MHS" Perm Packer 4.728

7" Top of Liner 4.767

9-5/8" Csg Shoe 4.981

7" Liner Shoe 6.794

B-57A Zone ( Pef Dec'19) 6.963 6.976 TARGET ZONE


B-57B Zone (Pef Dec'19) 7.016 7.032
B-57C Zone (Pef Dec'19) 7.040 7.052 TARGET ZONE
Set Kobe plug at 7079'md (Dec'19)
B-58 Zone 7.102 7.120

B-59A Zone 7.206 7.212

OTIS "X" Nipple, 2.813" ID 7.294

B-60A Zone 7.384 7.392

B-60B Zone 7.430 7.445

3-1/2" Float Collar 7.508

3-1/2" Float Shoe 7.569

RIH 2.75" GC down to 7518'MD

Updated by: Hendro Vico (Apr'23)

BK-7 Recompletion Program Page 26 of 27 Juli, 2023


4.11 Well Trajectory
Well Name: BK-7 KB (Feet) : PROJ.AZ:
`
No. M.D. Incl. Dir. Sect. T.V.D. S.S.D. X Y
1 0,00 0,00 0,00 0,00 0 0 0 0
2 296,00 0,50 43,00 0,94 296 -296 1 1
3 412,00 1,40 204,50 0,03 412 -412 1 0
4 502,00 4,60 229,60 -3,32 502 -502 -3 -3
5 593,00 7,80 234,40 -9,28 592 -592 -10 -9
6 683,00 11,00 242,90 -16,75 681 -681 -23 -17
7 774,00 14,40 247,70 -25,00 770 -770 -41 -25
8 864,00 18,20 246,70 -34,81 856 -856 -64 -35
9 955,00 21,90 244,70 -47,68 942 -942 -93 -48
10 1050,00 26,20 246,00 -63,79 1028 -1028 -128 -64
11 1145,00 30,90 246,20 -82,18 1112 -1112 -170 -82
12 1240,00 34,50 246,20 -103 1192 -1192 -217 -103
13 1335,00 38,30 246,70 -125 1268 -1268 -268 -125
14 1524,00 40,50 247,00 -173 1414 -1414 -378 -173
15 1809,00 39,00 246,70 -244 1633 -1633 -546 -244
16 1999,00 40,30 247,40 -291 1780 -1780 -658 -291
17 2190,00 40,40 247,10 -339 1925 -1925 -772 -339
18 2381,00 40,60 246,90 -388 2070 -2070 -886 -388
19 2572,00 40,60 247,60 -436 2215 -2215 -1001 -436
20 2759,00 41,70 248,40 -482 2356 -2356 -1115 -482
21 2948,00 42,10 248,70 -528 2497 -2497 -1232 -528
22 3136,00 41,20 248,40 -574 2637 -2637 -1348 -574
23 3325,00 42,00 248,50 -620 2779 -2779 -1465 -620
24 3514,00 43,20 247,70 -668 2918 -2918 -1584 -668
25 3703,00 43,10 247,50 -717 3056 -3056 -1703 -717
26 3891,00 42,10 247,20 -766 3194 -3194 -1821 -766
27 4079,00 42,10 247,50 -814 3334 -3334 -1937 -814
28 4269,00 42,20 247,90 -863 3475 -3475 -2055 -863
29 4457,00 42,30 247,40 -911 3614 -3614 -2172 -911
30 4645,00 42,60 246,10 -961 3752 -3752 -2289 -961
31 4833,00 42,40 246,90 -1012 3891 -3891 -2405 -1012
32 4905,00 42,30 247,00 -1031 3944 -3944 -2450 -1031
33 5026,00 41,90 246,80 -1062 4034 -4034 -2524 -1062
34 5215,00 41,00 247,10 -1111 4176 -4176 -2639 -1111
35 5404,00 41,80 246,90 -1160 4317 -4317 -2754 -1160
36 5592,00 42,10 246,60 -1210 4457 -4457 -2870 -1210
37 5780,00 42,20 246,70 -1260 4597 -4597 -2986 -1260
38 5971,00 42,40 246,80 -1311 4738 -4738 -3104 -1311
39 6161,00 42,40 246,70 -1361 4878 -4878 -3222 -1361
40 6349,00 42,20 247,30 -1411 5017 -5017 -3338 -1411
41 6632,00 40,90 249,40 -1480 5229 -5229 -3512 -1480
42 6725,00 40,50 248,90 -1501 5300 -5300 -3569 -1501
43 6965,00 37,20 250,40 -1554 5486 -5486 -3710 -1554
44 7156,00 40,40 246,90 -1597 5635 -5635 -3822 -1597
45 7345,00 39,70 246,60 -1645 5780 -5780 -3933 -1645
46 7503,00 40,70 246,20 -1686 5901 -5901 -4027 -1686
47 7575,00 40,70 246,20 -1705 5955 -5955 -4070 -1705

BK-7 Recompletion Program Page 27 of 27 Juli, 2023