Professional Documents
Culture Documents
Revision History
Revision # Revision information Date
3
2
1 Issued For Approval 13-11-2023
0 Issued For Approval 14-08-2023
2. SCOPE ........................................................................................................................... 3
3. REFERENCES ................................................................................................................ 3
6. METHOD STATEMENT FOR H-BEAM INSTALLATION ALONG WITH CONCRETE PANELS ......... 5
7. MATERIAL..................................................................................................................... 6
7.2.2 TOLERANCE...................................................................................................................... 7
9. HSE: 8
11. ITP 11
As part of construction of B+G+2 Commercial Villas (10 Nos.) on Plot No. 6184126, 6184127, 6184128,
6184129, 6184130, 6184134, 6184135, 6184136, 6184143 and 6184144 at Nadd Al Shiba First,
Dubai. shoring works are required to support the excavation works.
Soiltec Piling and Foundation L.L.C (SPF) has been awarded the Shoring Works.
As per the IFC drawings, SPF has proposed a cantilever soldier pile system as a most feasible system for this
project.
The present document will be used as reference for execution to be made within the frame of the works,
but it can be completed with a specific technical note whenever any special problem appears or when
complementary information is updated
2. SCOPE
The objective of this document is to present the main information regarding the execution of the H-
Beam installation along with concrete panels as per the approved drawings.
3. REFERENCES
• Geotechnical Investigation Report No. SR/2304052-4 prepared by M/s Al Hai & Mukkadam.
• Drawing No. PJ2329-SPF-SH-A, B & C-01 Rev 01, “Shoring Layout & Section Details”
• BS 8110 Structure use of Concrete.
• BS 8004 Foundations.
• BS 5950 Structural use of steelwork in building.
• Service crane 50ton Capacity with Vibro-hammer or ABI machine according to availability.
• Spirit level and Plump Bob.
• “H” Beam – 457mm x 191mm, 67kg/m (12.0m Length)
• Pre-Cast Concrete Panels – 1m (Varies as per site condition) x 1.45m x 0.1m
• JCB or Excavator
5.1 RESPONSIBILITIES
Project Manager:
The Project Manager shall be responsible for the over-all directions, monitoring, coordination, control and
supply of required manpower & equipment’s etc. of all the construction activities and related to the shoring
works.
Construction Manager
The Construction Manager shall be responsible for the overall implementation and monitoring of all the
QA/QC Engineer
inspections and tests as per DEWA ITP and specification, involved in shoring works.
Site Engineer
The Site Supervisor shall be directly involved in the planning and execution of the activities involved in the
shoring works. He shall be responsible for the preparation of work plan, Safety Action Plan for work permits,
Foreman
The Foreman shall be responsible for the direct execution of works involved in shoring works processes
according to the approved method statement and drawings and shall directly control and give instruction to
the working personnel. He shall also ensure that works are performed with proper tools/equipment, PPE and
Safety Engineer
Safety Engineer shall review work hazards prior to the start of the work and prepare Safe Work Plan and
work permit, if required, prior to submittal to client that must be implemented and observed during shoring
works. He must observe compliance of all safety requirements as per works procedures and HSE plan,
during shoring works
The method statement provides the basis of the method by which we may carry out the shoring works. This
document will describe the execution method, materials used, resources, and schedule and design basis.
The present document will be used as reference for execution to be made within the frame of the works, but
it can be completed with a specific technical note whenever any special problem appears or when
complementary information is updated.
7.1.1 H-BEAM
lengths.
7.2 EXECUTION
7.2.1 GENERAL
b) Setting out of shoring location providing a reasonable space for handling and maneuvering.
c) Removal of any obstruction might conflict with the shoring wall (By China State).
d) H-Beams will be installed directly using API machine or Vibro hammer attached to crawler crane.
e) Pre-drilling at H-Beam locations might be required then installing the H-Beam using the ABI machine or Vibro
hammer attached to crawler crane.
h) H-Beams extraction.
7.2.2 TOLERANCE
The working platform will be prepared by the Main Contractor at H-Beam location. The working platform shall
be stable, above the water table, horizontal and be suitable for traffic of heavy equipment. The installation
operation at shoring positions should be free from any buried service or utilities.
It is the responsibility of the main contractor to ensure that no interruption of utilities close to shoring
locations.
The installation of H-beams will be carried out using API machine, the beams will be left and installed at its
desired place. pre-drilling and installing the beam using vibro-hammer attached
to the ABI machine or crawler crane might be required based on the soil
condition.
forklift, service crane or any other equivalent equipment will be used to fix the
The execution of any type of shoring works requires careful supervision and
The following items shall be supervised and controlled during the various phases of as follows:
• Upon receiving instruction from the main contractor will mobilize the equipment’s (crane and vibro-
hammer or ABI machine). All equipment’s shall be allocated within the plot limits or main contractor to
obtain any other permission as required from relevant Authorities.
• Main contractor to provide proper access and required permission for equipment’s.
• H-Beam will be removed using ABI machine or mobile crane with attached vibro-hammer. Beams removal
will be proceeded after completion of structural works and backfilling activities in the shoring locations.
• During removal of steel beams, care to be taken towards the nearby property.
• After removal, beams to be taken away stored properly and housekeeping to be done.
9. HSE:
Contractor shall ensure abiding to all Safety rules and regulations and local governing bodies, approved HSE
plan and relevant codes. Contractor shall prepare and submit Risk Assessment prior starting works, to the
concerned authorities for review and approval. Few safety points’ needs to be adhered are as follows:
• Barricade/ Signs, solid working platform with toe board sufficiently secured and maintained during the
entire stage of construction, to protect all workmen and material falling from height.
• Prior to using any machines/ equipment at site, it shall be inspected and certified by qualified person.
• Wearing of the basic PPE shall be mandatory all time and shall be fully enforced.
• Main proper Permit to work system. Regular Inspection and Supervision. Engaging only skilled & trained
• Regularly check and maintain proper housekeeping for safe working condition.
• Implement and regular inspection of proper tag system, work permit and safety signage.
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
Eliminating the need of manual handling and Only physically fit and strong people to be
using equipment instead assigned this job
Provide mechanical aids where practicable No person to lift more than 20kg at once
If manual handling is necessary, the following Provide regular training in safe manual
safety procedures should be taken care of: handling techniques
Correct manual handling techniques to be Close supervision to the task by a
conveyed to involved people by conducting pre competent supervisor who will ensure that
task TBT which must cover the following points: all controls are in place.
1. Avoid awkward postures or repetitive tasks, or Emergency procedure mentioned in the
take frequent breaks. approved HSE plan to be communicated to
Manual handling Personal Injury 2. Keep the load close to your body all site staff through HSE Meetings and
Improper handling of Property damage
3. Check the load for stability and look out for TBTs
load sharp edges.
Health Issues Reporting procedure mentioned in the HSE
Falling of load 4. Don’t twist your body, use your feet to change Plan to be communicated to all site staff
2 Handling of load with
Labors Yes direction. 2 5 5 50 through HSE Meetings and TBTs so that 2 5 1 10
sharp texture/ edges Personnel shall not exceed their own lifting that near misses and minor incidents do
Slips, Trips and Falls capacity not go unrecorded
Where appropriate rotation and breaks of Violation and reward procedure mentioned
repetitive work. in the approved HSE plan to be
Encourage team lifting where appropriate communicated to all site staff through HSE
Housekeeping to be done on daily basis to avoid Meetings and TBTs
slips and trips during carrying the load Task Risk assessment mentioned in the
approved Risk Assessment to be
communicated to relevant site staff
through HSE Meetings and TBTs
All people must wear the required PPE
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
Lifting Operation, Elimination of the use of the mobile crane Weekly inspection to be carried out for
Loading/ Offloading of If elimination is not practical, follow the the crane by a competent mechanic in the
Materials to/ from the following procedures: presence of site engineer and inspect the
Trailer Ensure that a valid PTW is obtained for lifting crane parts. At minimum, the following
operation before the start of the work and the items to be checked:
Operation by comments on PTW are to be implemented Ropes for Main and Auxiliary Hooks
incompetent operator after the start of the work All Pins and bolts
Outriggers jacks
Incompetent lifting Only authorized crane to be used for lifting
Crane Display
supervisor purpose Safety Devices
Crane failure Only certified operator to operate the crane Alarms and Limit Switch
Unstable ground Personal Injury Only certified and color coded lifting tools/
condition Property damage accessories to be used Note: Items to check are not lmited to the
above mentioned items.
Unauthorized access to Soil Contamination Pre-use inspection to be carried out by
lifting area Fatalities operator before the start of shift and fill out
Constant supervision to ensure that all
Unidentified weight of the provided checklist
Riggers, Bank control measures are in place.
the load All lifting tools to be visually inspected by a
Operators shall not use mobile phones
Man, Lifting certified lifting supervisor before use
Incorrect rigging
Supervisor, All lifting activities to be planned by a certified 10 during operation
Damaged lifting Yes 2 10 5 Ensure that regular training is carried out 2 10 1 20
accessories
Labors, Visitors, lifting supervisor in consultation with site 0 for all operators involved
Operators, engineer and HSE
Swinging Load Ensure that operators are wearing
Management Staff The whole process to be carried out under the
High wind speed mandatory PPE including Hi-Visible vests
directions of a lifting supervisor
Rain Emergency procedure mentioned in the
Only a certified rigger to give directions to the
Fog approved HSE plan to be communicated to
crane operator
Falling of materials all site staff through HSE Meetings and
All lifting activities to be carried out in
from trailers, TBTs
accordance with the approved lifting plan
Accidents arising from Reporting procedure mentioned in the HSE
Weight of the load to be known to lifting
Vehicle impact, Plant Plan to be communicated to all site staff
supervisor and should be conveyed to operator
impact through HSE Meetings and TBTs so that
and other people involved
Falling of load during Lifting area to be cordoned off to prevent any
that near misses and minor incidents do
lifting not go unrecorded
unauthorized entry and warning signs to be
Load coming on the provided at its perimeters Violation and reward procedure mentioned
hands of rigger while All people to be strictly instructed about not to in the approved HSE plan to be
tying stand/ walk under suspended load and crane’s communicated to all site staff through HSE
Absence of daily boom Meetings and TBTs
inspection regime Task Risk assessment mentioned in the
Remember Hierarchy of Control:
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
Lifting supervisor to carry out TBT to his team approved Risk Assessment to be
in the presence of Site Engineer to talk about communicated to relevant site staff
the involved risk and the necessary safety through HSE Meetings and TBTs
measures to be taken
Clear Duties to be assigned to each person
involved in the process before start of the
lifting operation
Lifting supervisor to regularly monitor weather
condition and stop the activity in rain, fog and
high wind speeds
A certified banksman to be appointed for
assisting the movement of crane inside the site
Regular training shall be provided to all staff
involved in the lifting process
Crane to be sited on a level and stable ground
with its outriggers fully open
Crane shall not be sited on or near the edge of
any excavation or trenches
Works to be carried out in a methodical and
controlled manner as mentioned in the lifting
plan
Ensure trailer is parked on even and
compacted ground.
Operatives shall access the top of the trailer by
means of a properly tied and footed ladder.
Only pickup loads that can be handled, around
25kg or less or get the help of fellow workers.
Use of mechanical means to move materials is
preferred
All loads to be properly and adequately secured
on trailer bed to avoid falling off. Stand to one
side of load when un- securing straps.
Wheel stops shall be installed to prevent falling
of vehicles into the excavation.
Riggers to ensure that they don’t put hands
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
Eliminate the use of steel cage Regular training shall be provided to the
If elimination is not practical, use the following steel fixers and welders for the safe
procedure: execution of work
A valid PTW must be taken before carrying out Close supervision to the task to ensure
Hot Works that required procedures are followed
Ensure only competent people perform steel TBT to be conducted for all of the
fabrication work involved people; conveying the safe work
Ensure suitable materials are used for procedures and the risk in the job to be
Fabrication and lowering fabrication performed
of steel cage Personal Injury Ensure that during hot works, a calibrated fire Emergency procedure mentioned in the
Property damage extinguisher, fire blanket and necessary approved HSE plan to be communicated to
Cuts and bruises Fatalities warning signs are provided and the area is all site staff through HSE Meetings and
Riggers, Bank
resulting from contact cordoned off TBTs
Man, Lifting
of skin with steel The operative must have a valid third party Reporting procedure mentioned in the HSE
Supervisor,
Falling of steel cage competency certificate 10 Plan to be communicated to all site staff
Labors, Visitors, Yes 2 10 5 2 10 1 20
while lifting
Operators, Steel
Ensure that waste skips are provided at the 0 through HSE Meetings and TBTs so that
Disassembling of steel fabrication yard and the waste is daily dumped that near misses and minor incidents do
Fixers,
cage while lifting into those skips not go unrecorded
Management Staff
Accumulation of steel A competent person to Ensure that steel cage is Task Risk assessment mentioned in the
wires in the area well fabricated and all joints are satisfactory approved Risk Assessment to be
Collision of fabricated before commencing with lifting communicated to relevant site staff
steel cage with people Ensure that regular housekeeping of the area is through HSE Meetings and TBTs
conducted All operatives to wear the mandatory PPE
Before lifting, the area is to be cordoned off to at all times inside the site
avoid any unauthorized entry
The crane, operator and lifting tools used must
have valid third party certificates
Ensure that rigging of the steel cage is done by
a certified rigger
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
Elimination of refueling process inside the Always have a spill containment tray in your
site hand when moving the fuelling pipe to and
If elimination is impractical, apply the from the vehicle to be refuelled
following control measures: Do not use a lighter or any other ignition
Movement of vehicle inside the site to be source in the vicinity of fuelling operation
regulated by a certified banksman Firmly tight the fuel cap on the vehicle after
Fuel truck should be parked at a safe fuelling
location with functional parking brake Keep fuel away from your eyes and skin
Fuel truck to be parked no less than 3 feet Regular training to people for the safe
near to the vehicle/machine to be filled execution of their task
Driver to shutoff the engine and all other Emergency procedure mentioned in the
Refueling of Vehicles
Personal Injury ignition sources and leave the vehicle approved HSE plan to be communicated to
Property damage before commencing with fuel operation all site staff through HSE Meetings and TBTs
Fire Driver, Labors, Yes
Explosion Fatalities Visitors,
and return until the filling is done Reporting procedure mentioned in the HSE
Spilling of oil Health disorders Operators,
Ensure that the fuelling area is well
10 Plan to be communicated to all site staff
Static Electricity resulting Soil Contamination ventilated 2 10 5 through HSE Meetings and TBTs so that that 2 10 1 20
Management Staf
Do not refuel a vehicle if there is any 0 near misses and minor incidents do not go
in fire
source of ignition in the immediate vicinity unrecorded
Collisions
Do not smoke in the vicinity of refuelling Task Risk assessment mentioned in the
operation approved Risk Assessment to be
Switch off your phones in the vicinity of communicated to relevant site staff through
refuelling operation HSE Meetings and TBTs
After putting the pipe inside the nozzle, People shall always wear the required PPE
stay away from the fuelling jet for the task they will perform
Do not get distracted while fuelling
In dry and cold weather, touch the vehicle
body with your hands before gripping
fuelling jet in your hand and starting with
the fuelling operation
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
Eliminate the use of Chemicals Close supervision to the task to ensure that
Substitute it with the similar chemical that is less all controls are in place
hazardous Regular trainings to all people on the safe
Storage and Handling Personal Injury If substitution is not practical, follow the following handling and storage procedures of
of Chemicals Labors, Visitors,
Property damage YES controls: chemicals
(Bentonite) Operators,
Health disorders Supervisor,
Ensure chemical bags are properly stacked Emergency procedure mentioned in the
Soil Contamination Management Staf
Ensure all chemical bags are stacked over wooden approved HSE plan to be communicated to
Inhalation of chemicals pallets all site staff through HSE Meetings and TBTs
Spreading of chemicals Chemical stack shall be covered with a plastic Reporting procedure mentioned in the HSE
on ground sheet at all times Plan to be communicated to all site staff
Improper stacking Storage shall not affect the walkways through HSE Meetings and TBTs so that that
Contact of chemicals with Enough distance to be kept between the stakes for near misses and minor incidents do not go
skin the easy movement of people and vehicles across 2 5 5 50 unrecorded 2 5 1 10
Leakage of hoses No two chemicals are to be stored together Task Risk assessment mentioned in the
Ensure all people dealing chemicals are wearing approved Risk Assessment to be
suitable masks, glasses and gloves communicated to relevant site staff through
Ensure all torn bags are removed from the site to HSE Meetings and TBTs
avoid spreading of the powder People shall always wear the required PPE
Stacking height should be no more than 6 feet for the task they will perform
Ensure that all people are given slip resistant shoes
who work in chemical area
Ensure the hoses are in good condition before
commencing with work
Ensure the provision of MSDS in chemical storage
and application area
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
Elimination of the use of electrical power Regular training to be conducted for all
tools operatives on the safe use of tools
Substituting them portable power tools Emergency procedure mentioned in the
Use right tool for the job approved HSE plan to be communicated to
Using of electrical Personal Injury Ensure the use of 110 V power tools fitted all site staff through HSE Meetings and TBTs
Labors, Visitors,
power tools Property damage YES with dead man switch. Reporting procedure mentioned in the HSE
Operators,
Health disorders Supervisor, Carry out pre-use inspection and fill out Plan to be communicated to all site staff
Over load of
Fatalities Management Staf the relevant checklist through HSE Meetings and TBTs so that that
electricity Ensure all power tools are in good near misses and minor incidents do not go
Fire condition with insulation. unrecorded
Electric Shock Only trained and authorized person to use Task Risk assessment mentioned in the
Trips and Falls power tools. 10 approved Risk Assessment to be
Proper cable management shall be 2 10 5 communicated to relevant site staff through 2 10 1 20
maintained to avoid slip, trip, fall and
0 HSE Meetings and TBTs
damage to cable. People shall always wear the required PPE
Ensure regular inspection and color coding for the task they will perform
of all equiqment.
Damage tools to be removed from service.
Ensure appropriate PPE’s shall be used.
To Carry out a work safely the final Risk Rating should be reduced to 20 or below. Exemption: Work covered by Permit to Work (PTW) and Vehicle Driving.
Risk Rating Final Risk Rating
Legal
Requiremen Existing Control Measure(s) with Additional Control Measure(s) with
Likelihood
Likelihood
Final Risk
Person(s) at
Severity
Severity
Number
Number
SI. No. Hazard(s) Hazard Effect ts to be Mechanism from hierarchy of Control for Mechanism from hierarchy of Control
Risk
Risk
complied each identified Hazard for each identified Hazard
(Yes / No)
Risk rating
Action to be taken
score
Likely hood of
No of people affected Severity of injury accident Less than 10 Risk acceptable unless the cost or effort to control the risk further is very low.
occurrences
1- 5 10-19 Risk is low; action is required to reduce the risk, although low priority, time,
1 Negligible 1 Improbable 0.5
persons effort and cost should be proportional to the risk.
6-50 persons 2 Minor 2 Remote 1
50 + persons 3 Major 5 Possible 5 20-49 Risk is medium, action required soon to control risk, interim measures
required in the short term,
Public/
Vulnerable Likely 50-99 Risk is High, Action required urgently to control the risk, interim measures
3 Fatal 10 10
persons affected certain required in the short term, significant effort, time, etc.. May have to be control
the risk.
100+ Risk totally unacceptable, immediate action to be taken required before work
activity can continue, risk assessments to be reviewed at regular intervals to
ensure that risk is being properly controlled. Control measures may have to
involve some considerable effort and time to control.
____________________________
Assessor Signature Reviewer Signature Project Manager Signature
Project - API RACECOURSE VILLAS A, B, C, D, E, F, G, H, J & K AT NADD AL SHIBA FIRST, DUBAI, UAE.
Test/ type
of Format Responsibility
Sl.
Activity / Process Controlling Document Inspection Acceptance criteria of
No.
Required Record SPF CSC A&D
1.Documents
Shoring layout & Sections Details Approved Shoring Drawings Concerned government
Document
1.1 authority requirements &
verification H R R, A
Contract Specifications.
Shoring Method statement Approved Shoring method Concerned authority
Document
1.2 statement. Requirement & Contract
verification H R R, A
specifications
2. Shoring Execution
Shoring Points Location Approved Shoring drawings Total Approved Shoring drawings.
2.1 H W H
station
Pre-drilling (If required) Approved Shoring drawings & Approved method statement
2.2 Spirit Level H W H
Method Statement
Beams Installation Approved Shoring drawings & Approved Shoring drawings
2.3 Visual H W S
Method Statement & Method Statement.
2.4 Point Verticality Approved Method Statement. Spirit Level Approved Method Statement. H W S
Concrete Panel Installation Approved Shoring drawings & Approved Shoring drawings
2.5 Visual H W S
Method Statement & Method Statement.
Inspection for Shoring Works Approved Shoring drawings & Approved Shoring drawings
2.6 Visual H W I
Method Statement & Method Statement.
QA/QC Engineer.
Project - API RACECOURSE VILLAS A, B, C, D, E, F, G, H, J & K AT NADD AL SHIBA FIRST, DUBAI, UAE.
Project - API RACECOURSE VILLAS A, B, C, D, E, F, G, H, J & K AT NADD AL SHIBA FIRST, DUBAI, UAE.
Sign: Sign:
Date: Date: