You are on page 1of 22

Client :

JABATAN PENGAIRAN DAN SALIRAN


MALAYSIA
Project :

RANCANGAN TEBATAN BANJIR SUNGAI PENDANG :


MENAIKTARAF TERUSAN SELATAN, SUNGAI PENDANG DAN
STRUKTUR-STRUKTUR SERTA KERJA-KERJA BERKAITAN.

Document Title :
METHODS STATEMENT
Construction of Rip Rap at Bridge
(Revision 0)
Contractor :
PERTAMA MAKMUR SDN BHD
20-13 Menara K1, Lorong 3/137C,
Off Jalan Klang Lama,
58000 Kuala Lumpur.
TEL : 03-77733899

Consultant :
RPM Engineers Sdn Bhd
NO. 24-2, JALAN PEKAKA 8/4,
SEKSYEN 8, KOTA DAMANSARA,
47810, PETALING JAYA, SELANGOR

Doc. No : PMSB/JPS/PMSB/Construction of Rip rap /06.23 Date : June 2023


Prepared by : Review by : Approval by :
PERTAMA MAKMUR SDN BHD RPM ENGINEERS SDN BHD JPS MALAYSIA
TABLE OF CONTENTS PAGE

1.0 Introduction 3

2.0 Scope of Works 5

3.0 References 7

4.0 Equipment & Tools 9

5.0 Responsibilities 11

6.0 Construction of Riprap 13

7.0 Safety & Health 15

8.0 QA/QC 17

9.0 Appendix 19

Page 2 of 25
1.0 INTRODUCTION

Page 3 of 25
1.0 INTRODUCTION

Sungai Pendang Flood Mitigation Project has been proposed at Terusan Selatan (Southern
Canal) to lower casualties cause by flood event and at the meantime to improve systematic
agricultural controlling water level alongside the canal.
This method statement is produced to outline the sequence of activities, method, resources
required and safety precautions to execute the constructions works for bridge works. Such
shall cover 19 numbers and the type of bridge for structure as stated below:
i. Bridge type 1 (5 Nos)
ii. Bridge type 2 (14 Nos)

Page 4 of 25
2.0 SCOPE OF WORKS

Page 5 of 25
2.0 SCOPE OF WORKS

This work method statement outlines the associate works for bridge that covers in the
Construction Drawings by Consultant, RPM Engineers Sdn Bhd and Project Specifications.
Bridge works consist of construction substructure and superstructure. Substructure included
abutment and pier head. Superstructure comprise of beam, deck slab, curtain wall, approach
slab and kerb.
The scope of construction activities also will be covering several work procedures which are:
➢ Setting out
▪ To be set up the actual position and limitation area of work using the peg so
that construction can be carried out exactly accordingly to the plan.

➢ Excavation and filling


▪ To excavate soil until the level required.

➢ Lay the stone


▪ To lay riprap stone to the slope as mentioned in the construction drawing.

Page 6 of 25
3.0 REFERENCES

Page 7 of 25
3.0 REFERENCES

➢ Project Specifications
▪ The project specification inside TENDER NO. : JPS/IP/PB/10/2020 to be used
as reference is :
E4- EARTHWORK, EMBANKMENT & MISCELLANEOUS FILL
E20 – BRIDGE

➢ Construction Drawings
▪ Bridge :
• SP/RPM/PC/C/D/BR/01
• SP/RPM/PC/C/D/BR/02
• SP/RPM/PC/C/D/BR/03 (Rev 01)
• SP/RPM/PC/C/D/BR/04 (Rev 01)
• SP/RPM/PC/C/D/BR/05

Page 8 of 25
4.0 EQUIPMENT & TOOLS

Page 9 of 25
4.0 EQUIPMENT & TOOLS
4.1 Materials
The main materials used for this construction of Rip rap works shall be approved by
consultant prior to delivery and used on site.
i) Riprap stone
ii) Non- woven geotextile

4.2 Plant Machinery and Equipment


(a) Details of plant and machinery proposed to be used to perform work

Item Plant and Machinery Qty Purpose

1 Excavator 1 Major Excavation works i.e. drainage


crossing, sumps, wingwall etc.

2 1 tonne lorry 1 To transfer materials such as riprap


and non-woven geotextile.

(b) Detail of equipment proposed to be used to perform work

Item Plant and Machinery Qty Purpose

1 Dumpy level 1 Mark level


2 Measuring tape 3 Measure length

3 Spirit level 2 Check vertically

Plant machinery and equipments will be increased to meet the schedule time.

4.3 Manpower

Item Plant and Machinery Qty Responsibilities

1 Project Engineer / Site Supervisor 1 Provide technical consultation to the


workers

2 Excavator Operator 1 Operating Excavator

3 Skilled Workers 1 To make sure riprap arrange


according to construction drawing.

4 General Worker 2 Assist the skilled workers

Page 10 of 25
5.0 RESPONSIBILITIES

Page 11 of 25
5.0 RESPONSIBILITIES

1. Project Manager is responsible for overall project execution, quality and safety. Adopt
a leading role with respect to Contractor’s quality and safety procedures. The PM is
responsible for the overall implementation of this method of statement. The Project
Manager shall ensure that the key personnel are well aware of the specifications and
method of statement.

2. CM / Project Engineer shall arrange all materials, equipment, safety related items
and manpower and direct the Site Engineers & Foremen to resort appropriate action
for the smooth execution of the works.

3. Safety personnel shall be responsible for safe working environment, conditions and
take precautions the piling operations in accordance with the requirements of the
relevant laws and bylaws. Coordinate with Site Engineer to identify potential hazards
before works and advise methods of safe working from new developments.

4. Surveyor shall be responsible for setting out for levels, layout and lines and establish
top levels. Ensuring setting out books are properly maintained and filed when
completed. To coordinate with the Consultant surveyor in determining coordinates,
levels and limits. The pile position shall be marked with suitable identifying pin, peg
or marker.

5. QA/QC Engineer shall be responsible for ensuring that execution of works is


complying with approved method statement, specifications and ensure Work
Inspection Request (WIR) form are submitted based on ITP requirements.

6. Site Engineer shall ensure that all works are carried out according construction
drawing. He shall direct the surveyor for the setting out lines and levels in
concurrence from the Construction Manager / Senior Civil Engineer.

7. Specially qualified foremen shall maintain at site together with the necessary gangs
of trained labour experienced in the installation of piles.

Page 12 of 25
6.0 CONSTRUCTION

Page 13 of 25
6.2 CONSTRUCTION

6.21 Rip -rap construction


a. The slope will be trimmed in accordance to drawing. The level of laying rip rap
marked at the pile by surveyor.
b. A layer of geotextile layered on the trimmed slope and rip rap stone placed on it as
per construction drawing and specification.
c. Start by placing the largest rocks at the base of the slope of the river, ensuring the
rock interlock securely to provide stability.
d. Continue placing smaller rocks and fill in the gaps between the larger rocks, creating
a tightly packed and interlocking configuration.
e. Start by placing the largest rocks at the base of the slope or bank, ensuring they
interlock securely to provide stability.
f. Continue placing smaller rocks and fill in the gaps between the larger rocks, creating
a tightly packed and interlocking configuration.

Page 14 of 25
7.0 SAFETY & HEALTH

Page 15 of 25
9.0 SAFETY & HEALTH

Consultant HSE guidelines and management plan shall be strictly adhered during the
substructure and superstructure works.

Safety of the personnel and properties is to be given prime importance and all the works to
be carried out without causing any accidents or property damages.

Adequate access and egress should be provided to the site for work. All the personnel
should wear basic personnel protective equipment. All the equipment, tools and tackles
being used for the work should be in good working condition and maintained. All the
personnel will be provided with toolbox talk on the procedures to execute the work safely.

Necessary risk assessment of the activities is reflected in the enclosed risk assessment.

Page 16 of 25
8.0 QA/QC

Page 17 of 25
8.0 QA/QC
Quality controls that are apply in bridge works are :
a) To check the validity of calibration certificate for related instruments us

b) To check the materials used are approved and in good condition before works
started.

c) To conduct inspection with Client / Consultant using request for inspection using
Works Inspection Request (WIR).

Page 18 of 25
9.0 APPENDIX

Page 19 of 25
CONSTRUCTION
DRAWING
CPM FOR BRIDGE
WORKS
QAQC FORMS

You might also like