Professional Documents
Culture Documents
Asphalt Works
Method statement
1
TABLE OF CONTENT
1- TITLE
3- HEALTH &SAFTY……………............................ 22
3.1- Safety …………………..…………………………………………… 22
3.3. Risk Assessment …………………………………………………… 24
2
1-Method statement of Asphalt
2.0. Scope of Work
3
2.1. Purpose
To ensure that the bituminous pavement layers are executed
safely and in accordance with the contract requirements and
that all quality assurance/ control activities are conducted in a
systematic manner, works are inspected and conformance is
verified and documented.
2.3. Responsibilities
2.3.1. Project Manager
-Responsible for accomplishing the stated project objectives
which include creating clear and attainable project objectives,
building the project requirements, and managing the
constraints of the project management triangle, which are cost,
time, scope, and quality.
4
2.3.2. Construction Manager
Responsible for overall construction activities ensuring
that all quality and safety procedures are implemented
and required approved permits are obtained.
5
Supervise the execution of works in the Site to ensure that
the work phase required and assigned by the Project
Manager is accomplished within the approved time, plan,
specification and standards.
Supervise and ensure all the works are carried out as per
the safest manner complying with the approved Project
HS&E plan requirements.
7
Ensure the quality and compliance during phases of
surveying works and the regular checking of the surveying
equipment or periodic calibration from third party.
2.4. Tools
Shovel
Spreader
Wheelbarrow
Air compressor/electric air blower
Drilling machine
Measuring tapes
Markers
Warning tape
Traffic Cones
Safety Barriers
8
Grading Stakes
Temporary Signages
2.5. Equipment
Paving Machine-Vogele
Pneumatic Tire Roller
Steel Roller
Plate Compactors
Skid Steer Loader/Bobcat
Road Brush Mounted Skid Loader
2.6. Materials
Aggregates: Course and fine gabbro aggregates will be from
approved sources.
9
In addition to an asphalt mix design submission, the
laboratories and standardization affairs (lsa) shall require a
copy of a valid calibration certificate.
The site team shall make sure that access roads are always
clear from any obstruction and the site is always accessible.
10
2.8. Site Clearance
Before commencing the work, the area shall be cleared of all
debris, materials, or other obstructions.
-HSSE
a. Approved safety plan procedures shall be strictly followed.
b. Where possible hazards may arise from filling activities, the
necessary safety measures will be taken to prevent accident or
injury at all times. This may include barriers, warning tape/ net,
signage, watchman, and proper lighting.
c. Where work upon existing services may be required, the
necessary work permits and safety equipment should be
obtained prior to the activity commencement.
d. HSSE will enforce that Personal Protective Equipment be
worn by site personnel at all times during construction
activities.
e. Provisions of adequate cool drinking water, shade, and salt
water tablets will be in place.
12
2.10. Prior Activities
a. The Surveyor will locate and mark all live services that are
present in the site (This includes above ground services as well
as buried services).
b. These services (Electric, Telephone, Gas, Oil, Chemical,
Water, Drainage, etc) will be clearly marked using stakes and
warning tapes. Near these services, special precautions will be
undertaken and coordination with the Engineer will be carried
out to avoid any damages during the filling and compaction
process.
c. Any existing service if exposed during previous excavation
will be clearly marked, protected, and properly supported
during all activities.
The tack coat shall be applied when the weather is not foggy,
rainy, windy; and stormy.
13
The tack coat shall be applied uniformly by using a Liquid
Bitumen Distributor. Application temperature shall be between
10°C-60°C and as per the consultant’s instruction.
Before the start of asphalt laying, the tack coat applied area
shall be protected from traffic movements
2.13. Metrology
2.13.1. Paving Plan for Asphalt
Wearing Course
The paving operations will be performed asphalt paving
machine equipped with multiplex ski beams on each side.
14
2.13.2. Procedure
1- Binder Layer (Asphaltic base course)
a- Prior to the placement of bituminous base course layer, the
sub-base course will be cleaned and prepared by removal of
dust and deleterious materials by air jetting or mechanically
sweeping or by any approved means. The cleaned course will
be afterwards lightly made wet prior to the application of the
prime coat
b- An approved priming coat of grade shall be applied to the
non-bituminous sub-base layer at the rate liters per
m2inaccordance with Technical specifications. Prime coat is a
cutback bitumen spray that shall be applied (50~70 oC) to all
surfaces of the crushed aggregate base course. Blotter sand is
used to correct areas with excess prime coat materials.
c- The Bitumen Distributor shall be calibrated before use. The
distributor shall be self-powered and full circulation spray bars
adjustable laterally and vertically. Heating and Mixing of
bituminous materials will be carryout accordance with T.S.
d- Sufficient time (48 Hour Min.) will be allowed for the curing
of the prime coats before placing the following bituminous
pavement layers.
15
The surfaces shall always be clean and free from any oil or
dilutes or any materials which may affect the properties of
asphalt mixtures. When necessary, the surfaces may be sprayed
with a thin layer of lubricant to prevent sticking the mixtures
with the surfaces. The transported asphaltic concrete materials
shall be covered at cold times or in case of the mixing plant is
far away from the project site to minimize the heat loss of the
mix.
16
i- Two separate equipped work teams will execute for asphalt
placement at adjacent lanes in echelon simultaneously.
18
2.13.4. Compaction
One rolling pass is defined as being the movement of a roller
from the start-point, to the asphalt-paver and back to the start-
point, noting that rollers must keep a five-meter safety
distance’ from any plant in the direction of travel.
The rolling shall start from the low side and to be progressing
toward the higher side in the longitudinal direction of the road.
The first pass for the breakdown rolling with steel wheel roller
will be a static-without vibration. Thereafter, there will be a
maximum number of 3 further passes with vibration.
The spray man must apply the spray with the roller direction of
travel moving away from – never with the roller moving
towards him.
21
2.14. Quality Assurance Requirements
Ensure that work is executed as per approved shop drawing,
method statement for asphalt, and records are generated
referring to approved ITP.
f. All working activity shall comply with the client’s safe work
method statement.
23
g. First aid material.
24
More specifically, distribution and sensitivity analyses illustrate
the factors that pose the greatest health risks caused by certain
VOCs.
The study calls for better health risk controls by targeting the
emission sources, propagating pathways, and individual
receptors of the VOCs to protect workers’ health
during pavement construction.
-Conclusions
VOCs are recognized as mixed harmful gases that can place
both people and the environment in jeopardy.
A considerable number of VOCs are generated during asphalt
pavement construction, and present negative effects on
workers’ health.
Only rarely have there been studies on the carcinogenic and
non-carcinogenic risks on these workers, making the health of
asphalt workers unprotected by laws or codes.
25
This paper studied the concentration of VOCs obtained by on-
site measurements.Risks
-Ergonomic –Repetitive Motion, Injuries, working from afixed
position for prolonged, periods of time.
-Training on how to avoid ergonomic risks. Ability to vary
workers position i.e. chair height, work surfaces angles etc.
Ability to take breaks as needed to alleviate stress
- Musculoskeletal From erecting hoardings, traffic barriers,
barricades and posting safety signage.
Workers assigned as material handlers.
-Risks
-TASK HAZARDS
- Lack of, or Improper, Training and Education
26
• Only trained and competent personnel are permitted to
perform maintenance
-Poor Housekeeping
• Keep a clean working area, remove any tripping hazards
• Ensure that tools are neatly and safely stowed on equipment
• Equipment / vehicles should be cleared daily of any garbage
so as not to obstruct brakes, accelerator pedals, etc.
- Lack of Spotter
• Signalers are required for backing vehicles when the
operator’s view of the path of travel is obstructed.
• Signalers are required when equipment is within the safe
limits of approach to overhead powerlines.
27
• Workers shall wear appropriate hearing protection where the
potential exposure of noise cannot be reduced.
- Asphalt Burns
• All personnel involved with paving equipment and asphalt
handling must wear long pants and shirts with sleeves.
28
• Wear appropriate PPE (i.e. gloves) when risk of burns.
- Lack of Inspection
• A pre-operational safety inspection is to be completed.
29