Professional Documents
Culture Documents
METHOD OF STATEMENT
FOR PAINTING WORKS
Remarks/
Checked and
Revision Description of
Date Prepared By Approved By Main Review By WSHO
Number Revision/ Status
Contractor
R0 07-07-2016 1st - Submission Ragu
Contract ER437:
Proposed Lift Shafts to Existing Pedestrian Overhead Bridge
1.0 OBJECTIVE
The objective of this method of statement is to describe the sequence of works and
other imminent measures involved in painting. Works shall be carried out in compliance
with the drawings, project specifications and materials.
4.0 EQUIPMENT/TOOLS
1. Primer/Paints
2. Pail
3. Abrasive paper
4. Painting Roller.
References
1. Scope of works or specification
2. Manufacturer Data sheet
3. Approved drawing
2
Contract ER437:
Proposed Lift Shafts to Existing Pedestrian Overhead Bridge
Preparation
Hardware materials which are already fixed and not to be painted shall be
removed. Removal if not possible, it shall be covered/protected appropriately
before surface preparation and painting will commence.
Clean and prepare steel surface to be painted. Efflorescence, chalk, dust, dirt,
grease and oils shall be removed.
a. Paint Application:
One coat of shop applied coating would be applied. Each coat shall have an
interval time of 4 hours for curing. Before the application of further coatings,
sanding would be done for cleaning and removing of splattered, blemishes
and stains on the painted surface.
Then two coats of shop applied coating would be applied as per the approved
specification and color.
3
Contract ER437:
Proposed Lift Shafts to Existing Pedestrian Overhead Bridge
7.0 PLANNING
4
Contract ER437:
Proposed Lift Shafts to Existing Pedestrian Overhead Bridge