MS-004
DESCRIPTION
FLOORING WORKS
SPECIFICATION & BOQ REF: LOCATION / USE: Unit B09-00-21, City Walk Avenue
Phase 2, Dubai
SUB CONTRACTOR / MANUFACTURER
PERSONNEL INVOLVED
NAME ROLE
DIFCI/FOSP COMMENTS
Not Reviewed
Signature
Date 07/02/2023
DOC. REF. NO. MS-004
Scope and This procedure defines the method used to ensure that the flooring works have been
Objective carried out as per the contract specification and relevant standards.
References Technical Submittals As per approved submittals
Construction drawings Flooring Layout
Project Manager has the overall responsibility of the project for execution, quality
and safety. He will maintain the planning progress and co-ordination of works.
Responsibilities & Supervisors / Foreman shall be directly responsible for the day-to-day job at site, for
Supervision coordinating of work with skilled and unskilled labor or any other staff assigned in his
area.
Marking the floor as per the approved shop drawings.
Provide reference lines for setting out point and finished floor level by fish strings etc.
Working area will be fenced off for installation.
Mix the sand cement mortar with clean water using drill mixing paddle.
Mortar mix shall be 1:3 (1 part Portland cement and 3 part sand)
Build up the semi dry mortar bed to the required thickness 20-25mm.
Start installing tiles in 1 direction alongside of the centerline / setting out start tile.
Floor tiles are to be set using thick wet mortar bedding.
Each tile is to be hammered to ensure bedding of tiles.
Procedure/Method
Check and adjust the levels and angles as required.
to Be Employed
Traffic to be prohibited from the installation time till 48hrs.
In wet areas provide slope to drains.
Install stone threshold as per approved shop drawing at location indicated.
Clean off all the joints to depth required to receive the approved grout.
Mix the grout powder with clean water according to the manufacturer instructions to
obtain a homogenous paste.
Apply the grout with a rubber trowel to fill the joints completely.
Wait for 10-20 minutes and clean off excess grout with slightly damped sponge.
Allow the grout to set for at least 24 hours before allowing foot traffic
Method of Access NA
and Egress to the
work area:
Fall Protection
Measures:
(Where work at height
cannot be eliminated –
consider both
Personnel & Materials)
1. Tape Measure
2. Drill & mixing paddle
3. Hammer
Material 4. Buckets
Requirement 5. Rubber Gloves
6. Carpenter’s square
7. Tile Cutter or Tile Saw
DOC. REF. NO. MS-004
Hazardous
Substances:
Attached MSDS if
Required: Very Toxic Harmful/ Corrosive Dangerous Oxidizing Highly Explosives
Irritant For the flammable
environment
Applicable: Y/N N N N N N N N
Control Measures:
Storage
To be agreed with client / Project Manager. Prior to works.
Arrangements:
Details of
N/A
Permit to Work:
Other:
1. Hi - Viz
Personal Protective 2. Face Mask
Equipment (PPE) 3.
Safety Boots Hard Hats Safety Gloves Hearing Eye Respiratory
Protection Protection Protection
Applicable: Y/N y Y Y N Y N Y
Emergency
Procedures:
First Aider On Site
First Aid Facilities: First Aid Location: On Site
Location of Nearest Hospital: TBC
DOC. REF. NO. MS-004
POLICE 999
AMBULANCE 998/999
Emergency FIRE 997
Numbers: ELECTRICITY 991
WATER 992
Other Information
& Comments
Risk Matrix
PROBABILITY
1 2 3 4 5
Acceptable level of risk. Risk is controlled
5 LOW MED HIGH HIGH HIGH LOW
as far as reasonably practicable. Existing
Controls to be continuously monitored.
4 LOW MED HIGH HIGH HIGH
CONSEQUENCE
3 LOW MED MED HIGH HIGH MED Should aim to reduce risk further to As
Low As is Reasonably Practicable. (ALARP)
2 LOW LOW MED MED MED
•The job may require unusual capability or Ensure operatives are physically fit for the task.
special information or training and Sufficient skills (competency) to complete the
5 Individual Capacity R • May endanger those with a health problem. required task. Adequate consultations with
3 3 9 3 1 3
– Task specific injuries due to inexperience, employees and competent supervisions. Planning
inadequate consultation or failure to provide for required equipment carried out. Improvisation
appropriate equipment. using an appropriate equipment.
MSDS should be available at site for all chemical
which are going to be used for tile fixing job.
Control measures as per MSDS should be discussed
6 Health Hazards R Chemical and cement use for tile fixing – Skin
3 2 6 with concerned group of workers who are 3 1 3
allergy and respiratory diseases.
responsible for tile fixing job. Adequate PPE as per
MSDS should be available at site and site supervisor
should be ensuring that PPE are used completely.
Notes:
R – Routine Activity N – Non Routine Activity E – Emergency Operation